X PEKERJAAN BONGKARAN :

1Bongkar dinding 1/2 batu M2pekerja 0.2org/hr


mandor 0.01org/hr

2Bongkar dinding 1/2 batu M3pekerja 2org/hr


mandor 0.1org/hr

3Bongkar batu kali M3pekerja 1.5org/hr


(tebal < 50 cm) mandor 0.075org/hr

4Bongkar batu kali M3pekerja 3org/hr


(tebal < 50 cm) mandor 0.15org/hr

5Bongkar beton M3tukang 1.2org/hr


kepala tukang 0.12org/hr
pekerja 6org/hr
mandor 0.3org/hr

6Bongkar beton bertulang M3tukang 1.6org/hr


kepala tukang 0.16org/hr
pekerja 8org/hr
mandor 0.4org/hr

7Bongkar lantai M2pekerja 0.1org/hr


mandor 0.01org/hr

8Bongkar plesteran M2pekerja 0.05org/hr


mandor 0.0025org/hr

9Bongkar atas genteng M2pekerja 0.02org/hr


mandor 0.01org/hr

10Bongkar karpusan atap genteng M2pekerja 0.03org/hr


mandor 0.015org/hr

11Bongkar atap seng/asbes M2tk. Besi 0.05org/hr


pekerja 0.01org/hr

12Bongkar kaso & reng kayu M2tk. Kayu 0.025org/hr


(kayu tidak dipakai lagi) ke. Tk. Kayu 0.0025org/hr
pekerja 0.1org/hr
mandor 0.005org/hr

13Bongkar rangka atap kuda-2 kayu M3tukang kayu 1org/hr


kepala tukang 0.2org/hr

14Bongkar plafond + rangka M2pekerja 0.04org/hr


mandor 0.02org/hr

15Bongkar lisplank M' pekerja 0.03org/hr

mandor 0.015org/hr
16Bongkar kusen pintu M3tukang 1org/hr
kepala tukang 0.1org/hr

17Bongkar daun pintu M2pekerja 0.02org/hr


mandor 0.001org/hr

18Bongkar kaca M2pekerja 0.03org/hr


mandor 0.003org/hr

19Bongkar rabat beton M2pekerja 0.05org/hr


mandor 0.0025org/hr

20Bongkar bak air teraso BHpekerja 0.3org/hr


mandor 0.015org/hr

Upah Borongan Pekerjaan Penutup Lantai dan Dinding

PEKERJAAN PENUTUP LANTAI DAN DINDING


1 m Pasang Lantai Ubin PC Abu - abu ukuran 40 x 40 cm 31,360.50
1 m Pasang Lantai Ubin PC Abu - abu ukuran 30 x 30 cm 32,636.25
1 m Pasang Lantai Ubin PC Abu - abu ukuran 20 x 20 cm 33,912.00
1 m Pasang Lantai Ubin Warna ukuran 40 x 40 cm 31,360.50
1 m Pasang Lantai Ubin Warna ukuran 30 x 30 cm 31,360.50
1 m Pasang Lantai Ubin Warna ukuran 20 x 20 cm 33,912.00
1 m Pasang Lantai Ubin Teraso ukuran 40 x 40 cm 31,360.50
1 m Pasang Lantai Ubin Teraso ukuran 30 x 30 cm 32,636.25
1 m Pasang Lantai Ubin Granito ukuran 40 x 40 cm 31,421.25
1 m Pasang Lantai Ubin Granito ukuran 30 x 30 cm 32,636.25
1 m Pasang Lantai Ubin Teralux Kerang ukuran 40 x 40 cm 31,360.50
1 m Pasang Lantai Ubin Teralux Kerang ukuran 30 x 30 cm 31,360.50
PEKERJAAN PENUTUP LANTAI DAN DINDING
1 m Pasang Lantai Ubin Teralux Marmer ukuran 60 x 60 cm 31,360.50
1 m Pasang Lantai Ubin Teralux Marmer ukuran 40 x 40 cm 73,791.00
1 m Pasang Lantai Ubin Teralux Marmer ukuran 30 x 30 cm 88,236.00

1 m Pasang Plint Ubin PC Abu - abu ukuran 15 x 20 cm 7,654.50


1 m Pasang Plint Ubin PC Abu - abu ukuran 10 x 30 cm 7,654.50
1 m Pasang Plint Ubin PC Abu - abu ukuran 10 x 40 cm 7,654.50
1 m Pasang Plint Ubin PC Warna ukuran 10 x 20 cm 7,654.50
1 m Pasang Plint Ubin PC Warna ukuran 10 x 30 cm 7,654.50
1 m Pasang Plint Ubin PC Warna ukuran 10 x 40 cm 10,206.00
1 m Pasang Plint Ubin Teraso ukuran 10 x 30 cm 10,206.00
1 m Pasang Plint Ubin Teraso ukuran 10 x 40 cm 10,206.00
1 m Pasang Plint Ubin Granito ukuran 10 x 40 cm 7,654.50
1 m Pasang Plint Ubin Granito ukuran 10 x 30 cm 70,956.00
1 m Pasang Plint Ubin Teralux Kerang ukuran 10 x 40 cm 70,956.00
1 m Pasang Plint Ubin Teralux Kerang ukuran 10 x 30 cm 70,956.00
1 m Pasang Plint Ubin Teralux Marmer ukuran 10 x 60 cm 70,956.00
1 m Pasang Plint Ubin Teralux Marmer ukuran 10 x 40 cm 70,956.00
1 m Pasang Plint Ubin Teralux Marmer ukuran 10 x 30 cm 70,956.00
1 m Pasang Teraso Cor ditempat 70,956.00
1 m Pasang Teralux Cor ditempat, tebal 3 cm 70,956.00
1 m Pasang Ubin Tahan Asam 36,045.00
1 m Pasang Lantai Keramik Artistik 10 x 20 cm 83,227.50
1 m' Pasang Plint Keramik Artistik ukuran 10 x 20 cm 16,281.00
1 m' Pasang Plint Keramik Artistik ukuran 10 x 10 cm 16,281.00
1 m' Pasang Plint Keramik Artistik ukuran 5 x 20 cm 16,281.00
1 m' Pasang Plint Vinyl tanpa adukan 14,472.00
1 m Pasang Lantai Keramik 10 x 20 cm 83,227.50
1 m Pasang Lantai Keramik 15 x 15 cm 83,227.50
1 m Pasang Lantai Keramik 20 x 20 cm 83,227.50
1 m Pasang Lantai Keramik 25 x 25 cm 83,227.50
1 m Pasang Lantai Keramik 15 x 20 cm 83,227.50
1 m Pasang Lantai Keramik 33 x 33 cm 83,227.50
PEKERJAAN PENUTUP LANTAI DAN DINDING
1 m Pasang Lantai Keramik 33 x 33 cm anti slip 83,227.50
1 m Pasang Lantai Keramik 10 x 33 cm 83,227.50
1 m Pasang Lantai Mozaik 30 x 30 cm, ex lokal 83,227.50
1 m Pasang Lantai Marmer 83,227.50
1 m Pasang Lantai Karpet 100% Wool 30,753.00
1 m Pasang Lantai Karpet 100% Wool, 20% Nylon 30,753.00
1 m Pasang Underlyer, tebal 6 mm 21,708.00
1 m Pasang Lantai Karpet 30,753.00
1 m Pasang Lantai Parquet Jati 85,590.00
1 m Pasang Dinding Porselen 11 x 11 cm, putih 99,225.00
1 m Pasang Dinding Porselen 11 x 11 cm, warna 99,225.00
1 m Pasang Dinding Porselen 15 x 15 cm, putih 92,542.50
1 m Pasang Dinding Porselen 15 x 15 cm, warna 92,542.50
1 m Pasang Dinding Porselen 10 x 20 cm, warna 92,542.50
1 m Pasang Dinding Porselen 20 x 20 cm, warna 92,542.50
1 m Pasang Dinding Keramik Artistik 10 x 20 cm, warna 92,542.50
1 m Pasang Dinding Keramik Artistik 5 x 20 cm, warna 92,542.50
1 m Pasang Dinding Keramik 10 x 20 cm 92,542.50
1 m Pasang Dinding Keramik 15 x 15 cm 92,542.50
1 m Pasang Dinding Keramik 20 x 20 cm 59,467.50
1 m Pasang Dinding Keramik 10 x 20 cm 57,881.25
1 m Pasang Dinding Marmer 122,647.50
1 m Pasang Dinding Bata Klinker 5 x 5 x 24 cm 83,227.50
1 m Pasang Dinding Batu Paros 83,227.50
1 m Pasang Dinding Batu Tempel Hitam 83,227.50
1 m Pasang Lantai Vinyl Karet 30 x 30 cm KL I 27,135.00
1 m Pasang Lantai Vinyl Karet 30 x 30 cm KL II 27,135.00
1 m Pasang Lantai Vinyl Asbes 30 x 30 cm 27,135.00
1 m Pasang Lantai Vinyl Motif Kembang 30 x 30 cm 27,135.00
1 m Pasang Wall Covering lebar 50 cm 69,903.00
1 m Floor Hardener Ferrovax 21,708.00
1 m Floor Hardener Mastercron 21,708.00
1 m Plint Kayu 2 x 10 cm 22,518.00
Analisa Pekerjaan Plesteran

VPEKERJAAN PLESTERAN

1Plesteran dinding 1:2 + acian M2semen 0.24zak


tebal 15 mm pasir pasang 0.02m3
tk. Batu 0.214org/hr
kepala tukang batu 0.021org/hr
pekerja 0.4org/hr
mandor 0.02org/hr

2Plesteran dinding 1:3 + acian M2semen 0.1632zak


tebal 15 mm pasir pasang 0.0194m3
tk. Batu 0.214org/hr
kepala tukang batu 0.021org/hr
pekerja 0.4org/hr
mandor 0.02org/hr

3Plesteran dinding 1:4 + acian M2semen 0.1302zak


tebal 15 mm pasir pasang 0.021m3
tk. Batu 0.214org/hr
kepala tukang batu 0.021org/hr
pekerja 0.4org/hr
mandor 0.02org/hr

4Acian PC M2semen 0.08zak


tk. Batu 0.11org/hr
kepala tukang batu 0.011org/hr
pekerja 0.14org/hr
mandor 0.01org/hr

5Brapen pondasi 1:4 M2semen 0.085zak


pasir pasang 0.17m3
tk. Batu 0.09org/hr
kepala tukang batu 0.009org/hr
pekerja 0.18org/hr
mandor 0.009org/hr

Upah Borangan Pekerjaan Persiapan

PEKERJAAN PERSIAPAN
1 m' Pagar Sementara dari Kayu tinggi 2 m 52,380.00

1 m' Pagar Sementara dari Seng Gelombang tinggi 2 m 52,380.00


PEKERJAAN PERSIAPAN

1 m' Pagar Sementara dari Kawat Duri tinggi 1.8 m 45,630.00

1 m' Pek. Pengukuran kembali (site) & Pemasangan Bowplank 18,765.00

1 m Pek. Kantor Direksi Keet , dengan lantai plesteran 475,200.00

1 m Pembuatan Gudang Semen dan Alat - alat 301,050.00

1 m Pembuatan Rumah Jaga / Konstruksi Kayu 244,350.00

Membersihkan Lapangan dan Perataan 13,500.00

1 m Pembuatan Bedeng Buruh 301,050.00

1 m Pembuatan Bak Adukan ( 40 x 50 x 20 ) cm 209,250.00

1 m Pembuatan Stegger dari Bambu, ( 40 x 50 x 20 ) cm 301,050.00

1 m Pembuatan Jalan Sementara 74,250.00

1 m Bongkaran Beton Bertulang 494,977.50

1 m Bongkaran Dinding Tembok Bata Merah 454,477.50

Upah Borongan Pekerjaan Pondasi

PEKERJAAN PONDASI
1 m' Pembuatan Tiang Pancang ( 35 x 35 ) cm, Beton Bertulang 112,725.00

1 m3 Pasangan Batu kali 1 Pc : 3Ps 175,365.00

1 m3 Pasangan Batu kali 1 Pc : 5Ps 175,365.00


1 m Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat
7,981.20
Penutup )
1 m Melabur Tembok dengan Kapur Sirih 10,562.40
1 m Melabur Tembok Lama dengan Kapur Sirih ( untuk pemeliharaan ) 3,537.00
1 m Pemasangan Wall Paper 19,480.50
1 m Pengecatan Permukaan Baja dengan Meni Besi 22,680.00
1 m Pengecatan Permukaan Baja dengan Meni Besi dan Perancah 40,365.00
PEKERJAAN PONDASI
1 m Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 4
4,677.75
Lapis Cat Konvensional, tebal 200 um
1 m Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 1
7,938.00
Lapis Cat Mutakhir, tebal 200 um
1 m Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Manual Sistem 3
167,400.00
Lapis Cat Konvensional, tebal 200 um
1 m Pengecatan Permukaan Baja Lapis Seng ( Galbani ) secara Semprot ( Airless
Spray ) dgn Sistem 1 Lapis Cat Mutakhir, tebal 200 um

Upah Borongan Pekerjaan Beton

PEKERJAAN BETON
1 m2 Membuat Lantai Kerja Beton Tumbuk 1 Pc : 3 Ps : 5 Kr 80,568.00

1 m Membuat Beton Tumbuk 1 Pc : 3 Ps : 5 Kr 148,837.50

1 m Membuat Beton Tumbuk 1 Pc : 3 Ps : 6 Kr 148,837.50

1 m Membuat Beton Tumbuk 1 Pc : 4 Ps : 6 Kr 148,837.50

1 m Membuat Beton 1 Pc : 2 Ps : 3 Kr 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 2 Ps : 4 Kr 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 2 Ps : 2.5 Kr 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 1.5 Ps : 3Kr 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 1.5 Ps : 2.5Kr 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 1 Ps : 2Kr 148,837.50

1 m Membuat Tiang Pancang Prestressed Beton 148,837.50

1 m Membuat Beton Bertulang 1 Pc : 2Ps : 3 Splt 307,327.50

1 m Membuat Beton Bertulang 1 Pc : 2Ps : 4 Splt 307,327.50

1 m Membuat Beton Bertulang 1 Pc : 1.5Ps : 3 Splt 307,327.50


PEKERJAAN BETON

1 m Membuat Beton Bertulang 1 Pc : 1.5Ps : 2.5 Splt 307,327.50

1 m Membuat Beton Bertulang 1 Pc : 1Ps : 1Splt 307,327.50

1 m Membuat Beton Kedap Air dengan Strorox - 100 307,327.50

1 m' Memasang PVC Waterstop lebar 150 mm 6,844.50

1 m' Memasang PVC Waterstop lebar 200 mm 6,905.25

1 m' Memasang PVC Waterstop lebar 230 mm 70,605.00

1 m' Memasang PVC Waterstop lebar 250 mm 70,605.00

1 m' Memasang PVC Waterstop lebar 300 mm 70,605.00

1 m' Memasang PVC Waterstop lebar 320 mm 70,605.00

1 Kg Pembesian dengan Besi Polos atau Besi Ulir 4,593.38

1 Kg Kabel Presstressed Polos / Strands 911.25

1 Kg Jaring Kawat Baja 4,556.25

1 m2 Pasang Bekisting 58,482.00

1 m2 Pasangan Stoot Werk 56,970.00

1 m2 Pasang Bekisting untuk Pondasi 50,409.00

1 m2 Pasang Bekisting untuk Sloof 50,409.00

1 m2 Pasang Bekisting untuk Kolom 58,482.00

1 m2 Pasang Bekisting untuk Balok 59,832.00

1 m2 Pasang Bekisting untuk Lantai 57,604.50

1 m2 Pasang Bekisting untuk Dinding 59,832.00


PEKERJAAN BETON

1 m2 Pasang Bekisting untuk Tangga 59,832.00

1 m Membuat Pondasi Beton Bertulang ( 150 Kg + bekisting ) 552,892.50

1 m Membuat Sloof Beton Bertulang ( 200 Kg + bekisting ) 713,866.50

1 m Membuat Kolom Beton Bertulang ( 300 Kg + bekisting ) 1,161,405.00

1 m Membuat Balok Beton Bertulang ( 200 Kg + bekisting ) 934,537.50

1 m Membuat Balok Beton Bertulang ( 150 Kg + bekisting ) 883,305.00

1 m Membuat Dinding Beton Bertulang ( 150 Kg + bekisting ) 852,255.00

1 m Membuat Tangga Beton Bertulang ( 200 Kg + bekisting ) 852,727.50


Bahan

1 m Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 10,989.00


Bahan

1 m Membuat Ring Balok Beton Bertulang (10 x 15) cm 46,284.75

Analisa Harga Satuan Biaya Bangunan

Posted on 12 Maret 2013 by Rani Plan Consultant

Sebelum anda menghitung Rencana Anggaran Biaya (RAB) anda terlebih dahulu harus
memahami dan menghitung terlebih dahulu Analisa Harga Satuan Pekerjaan dan sebaiknya
anda menggunakan Analisa Harga Satuan Pekerjaan yang sudah berlaku yaitu Analisa Harga
Satuan Pekerjaan berdasarkan Standart Nasional Indonesia (SNI), anda bisa Download disini.

Sebaiknya anda menggunakan Analisa Harga Satuan Pekerjaan SNI yang terbaru (SNI 2008)
terkecuali item pokok pekerjaan yang di SNI 2008 tidak tercantum misalnya PEKERJAAN
PERSIAPAN anda bisa menggunakan Analisa Satuan SNI 2002.

Kalau kita perhatikan dalam Analisa Satuan Pekerjaan berdasarkan SNI terbagi menjadi 14
item pokok pekerjaan dan dibagi lagi menjadi sub item pekerjaan, dengan uraian sebagai
berikut :

I. PEKERJAAN PERSIAPAN (terdiri dari 16 sub item pekerjaan) SNI 2002, dapat anda
Download disini.

No. Kode Kode Analis Uraian Pekerjaan


Bantu
SNI-
01 K010101 Pagar Sementara dari Kayu Tinggi 2 M (1 m)
02.01.01
Pagar Sementara dr Seng Gelombang Tinggi
02 K010201 SNI-02.01.02
=2m (1 m)
Pagar Sementara dari Kawat Duri Tinggi = 1,80
03 K010301 SNI-02.01.03
m (1 m;)
04 K010401 SNI-02.01.04 Pengukuran dan Pemasangan Bouplank (1 m)
Pembuatan Kantor Sementara, dengan lantai
05 K010501 SNI-02.01.05
plesteran. (1 m2)
Pembuatan Gudang Semen dan alat-alat (1
06 K010601 SNI-02.01.06
m2)
Pembuatan Rumah Jaga/Konstruksi Kayu (1
07 K010701 SNI-02.01.07
m2)
08 K010801 SNI-02.01.08 Pembersihan Lapangan dan Perataan (1 m2)
Pembuatan Stegger dari bambu, uk.
09 K010901 SNI-02.01.09
(40x50x20). (1 m2)
10 K011001 SNI-02.01.10 Pembuatan Bedeng Buruh (1 m2)
11 K011101 SNI-02.01.11 Pembuatan Bak Aduk uk. (40x50x20) (1 m2)
12 K011201 SNI-02.01.12 Pembuatan Jalan Sementara (1 m2)
13 K011301 SNI-02.01.13 Bongkar Beton Bertulang (1 m3)
14 K011401 SNI-02.01.14 Bongkar Dinding Tembok Bata Merah (1 m3)
Pasangan Pagar Kawat jaring Galvanis Panjang
15 K011501 SNI-02.01.15
1 cm (1 m2)
Pasangan Pagar Beton Pracetak (50x50x213)
16 K011601 SNI-02.01.16
cm (1 m)

Anda dapat memilih sub item mana yang akan anda gunakan sesuai dengan jenis item
pekerjaan anda.

No. : Merupakan Nomor sub item pekerjaan persiapan.

Kode Bantu : Digunakan untuk kode antar link dalam Rencana Anggaran Biaya (Harga
Satuan-Analisa-RAB)

Kode Analis : Digunakan sebagai parameter analis yang digunakan.

Anda silakan membuat kode sendiri yang menurut anda lebih mudah tidak harus sama
dengan yang saya buat.

Maksud kode Analis SNI-02.01.04 adalah : Digunakan SNI 2002 (SNI-02), Item Pekerjaan
Persiapan (01), Pekerjaan Pengukuran dan Pemasangan Bouplank (04).

II. PEKERJAAN TANAH (terdiri dari 15 sub item pekerjaan) SNI 2008, dapat anda
Download disini.

Kode
No. Kode Analis Uraian Pekerjaan
Bantu
SNI-
01 K020101 Menggali 1 m3 tanah biasa sedalam 1 m
08.02.01
SNI-
02 K020201 Menggali 1 m3 tanah biasa sedalam 2 m
08.02.02
SNI-
03 K020301 Menggali 1 m3 tanah biasa sedalam 3 m
08.02.03
SNI-
04 K020401 Menggali 1 m3 tanah Keras sedalam 1 m
08.02.04
SNI-
05 K020501 Menggali 1 m3 tanah Cadas sedalam 1 m
08.02.05
SNI-
06 K020601 Menggali 1 m3 tanah Lumpur sedalam 1 m
08.02.06
SNI-
07 K020701 Menggali 1 m3 tanah biasa sedalam 1 m
08.02.07
SNI-
08 K020801 Membuang 1 m3 tanah sejauh 30 m
08.02.08
SNI-
09 K020901 Mwngurug Kembali 1 m3 Galian
08.02.09
SNI-
10 K021001 Memadatkan 1 m3 tanah (per 20 cm)
08.02.10
SNI-
11 K021101 Mengurug 1 m3 Pasir
08.02.11
SNI- Memasang 1 m3 Lapisa Pudel campuran (1 KP
12 K021201
08.02.12 : 3 PP : 7 TL)
SNI- Memasang 1 m3 Lapisan Pudel campuran (1
13 K021301
08.02.13 KP : 5 TL)
SNI-
14 K021401 Memasang 1 m2 Lapisa ijuk tebal 10 cm
08.02.14
SNI- Mengurug 1 M3 sirtu padat untuk peninggian
15 K021501
08.02.15 lantai bangunan.

Selanjutnya anda dapat memilih sub item mana yang akan anda gunakan sesuai dengan jenis
item pekerjaan anda.
Maksud kode Analis SNI-08.02.04 adalah : Digunakan SNI 2008 (SNI-08), Item Pekerjaan
Tanah (02), Pekerjaan Menggali 1 m3 tanah Keras sedalam 1 m (04).

Demikian seterusnya sampai dengan 14 Item Pekerjaan

Penjelasan Tentang Koefisien Analisa Satuan Pekerjaan.

Kita ambil sebagai contoh; Analis Pekerjaan Persiapan dengan Kode Bantu (K010401) atau
Kode Analis (SNI-02.01.04) yaitu sub item pekerjaan Pengukuran dan Pemasangan
Bouplank. dengan koefisien analis sbb :

Pengukuran dan Pemasangan Bouplank (1 m)

0,0120 M3 Kayu 5/7


0,0200 Kg Paku

0,0070 Lbr Papan 3/20

0,1000 Oh Pekerja

0,0050 Oh Mandor

0,1000 Oh Tukang Kayu

0,0100 Oh Kepala Tukang

Sebagai acuan kita ambil koefien dengan nilai yang tekecil dari koefisien bahan maupun
tenaga kerja yakni : 0,005 (Mandor), selanjutnya masing- masing koefisien kita bagi dengan
nilai acuan 0,005 sehingga bentuk analis menjadi sbb:

Pengukuran dan Pemasangan Bouplank (200 m)

2,40 M3 Kayu 5/7

4,00 Kg Paku

1,40 Lbr Papan 3/20

20 Oh Pekerja

1 Oh Mandor

20 Oh Tukang Kayu

2 Oh Kepala Tukang

Jadi untuk mengukur dan memasang bouplank sepanjang 200 m memerlukan :

Bahan : 2,4 m3 Kayu 5/7, 4 Kg paku dan 1,4 Lbr Papan 3/20

Tenaga Kerja : 20 org Pekerja, 1 Org Mandor, 20 Org Tukang Kayu dan 2 Org Kepala
Tukang dalam 1 hari

atau sebaliknya.

Selanjutnya untuk mengetahu berapa Nilai (Harga) Satuan item Pekerjaan maka terlebih
dahulu kita harus mengetahui Harga Satuan Upah dan Bahan

Analisa Harga Satuan Pekerjaan Konstruksi - AHS SNI


Analisa Harga Satuan Pekerjaan (AHS-SNI) adalah pedoman baku alat untuk menghitung
harga standard satuan pekerjaan konstruksi. AHS-SNI diterbitkan oleh setiap instansi terkait
di setiap Pemerintah Daerah Kabupaten dan Kota Madya di seluruh wilayah Indonesia dalam
hal ini oleh Dinas Pekerjaan Umum Kab/Kodya. Yang dimaksud harga satuan pekerjaan
adalah harga satuan setiap pekerjaan dalam pekerjaan konstruksi. Ruang lingkup pekerjaan
konstruksi meliputi pekerjaan bangunan gedung, bangunan air, jalan, jembatan, galangan
kapal, bandara, bangunan konstruksi baja, ternasuk bangunan rumah tinggal.

Dalam setiap lingkup pekerjaan/proyek terdiri dari pekerjaan-pekerjaan tertentu. Dalam


lingkup pekerjaan bagunan gedung termasuk bangunan rumah tinggal terdiri dari pekerjaan-
pekerjaan : pekerjaan Persiapan; pekerjaan pondasi, pekerjaan beton; pekerjaan dinding,
pekerjaan atap, pekerjaan lantai, pekerjaan plapond, dst. Pada setiap pekerjaan tersebut masih
ada sub pekerjaan, misalnya pada pekerjaan pondasi : pekerjaan galian pondasi, pasangan
pondasi batu kali, pondasi tiang pancang, dst. Pada setiap pekerjaan atau sub pekerjaan terdiri
dari komponen bahan material, upah kerja, sewa alat dsb. Untuk menentukan harga satuan
pekerjaan tersebut maka harus menggunakan AHS SNI. Dalam AHS-SNI ukuran untuk
menentukan harga satuan pekerjaan, maka setiap bahan atau tenaga yang diperlukan diberi
angka koefisien. Angka koefisien inilah sebagai rumus atau pedoman yang dijadikan alat
pengali terhadap volume pekerjaan, harga material, dan upah kerja sehingga menhasilkan
harga satuan untuk setiap pekerjaan.

Yang biasa menggunakan AHS-SNI adalah para konsultan perencana, konsultan pengawas,
dan kontraktor pelaksana konstruksi dalam rangka melaksanakan kegiatan yang berkaitan
dengan bidang yang menjadi kewenangan masing- masing dalam melaksanakan pekerjaan
jasa konstruksi.

Analisa harga Satuan Pekerjaan Konstruksi (AHS-SNI) diterbitkan seiap tahun. Yang
berubah dari setiap terbitan AHS-SNI biasanya harga satuan bahan dan upah, sedangkan
koefisien AHS relatif tidak berubah. Jadi, apabila Anda sudah punya AHS-SNI tahun 2011
dalam bentuk file excel, maka untuk updatenya Anda hanya perlu mengedit harga satuan
material dan upah kerja. Biasanya para konsultan dan kontraktor hanya mendapatkan AHS-
SNI terbaru dari Dinas PU dalam bentuk cetakan, bukan bentuk file excel.

AHS-SNI aslinya dalam format file excel. AHS disimpan dalam sheet. Sheet-ssheet AHS
terdiri dari : Analisa Harga Satuan Pekerjaan, Harga Satuan Upah, harga Satuan Bahan, dan
Harga Satuan Pekerjaan. Analisa Harga Satuan terdiri dari uraian pekerjaan, volume
(koefiseien) pekerjaan, harga satuan upah, dan harga satuan bahan. gabungan hasil perkalian
antara koefisien/volume dengan harga satuan menjadi harga satuan pekerjaan. Harga bahan
material dan upah kerja merupakan standard harga yang ditetapkan oleh instansi terkait, dan
setiap tahun biasanya berubah sesuai perkembangan harga pasar. Harga satuan pekerjaan
adalah hasil perhitungan berdasarkan analisa harga satuan, harga satuan bahan, dan harga
satuan upah.

Setiap Analisa Harga Satuan Pekerjaan saya sajikan dalam halaman terpisah, silahkan klik
satu persatu halaman tersebut di bawah ini:

Halaman Analisa Harga Satuan AHS -SNI Tahun 2011:


1. Analisa Harga Satuan Pekerjaan Persiapan
2. Analisa Pekerjaan Tanah
3. Analisa Pekerjaan Pondasi
4. Analisa Pekerjaan Beton
5. Analisa Pekerjaan Dinding
6. Analisa Pekerjaan Plesteran-Acian
7. Analisa HArga Satuan Pekerjaan Penutup Atap
8. Analisa Harga Satuan Pekerjaan Tutup Plapond
9. Analisa Harga Satuan Pekerjaan Lantai
10. Analisa Harga Satuan Pekerjaan Kayu
11. Analisa Harga Satuan Pekerjaan Penutup Besi dan Alluminium
12. Analisa Harga Satuan Pekerjaan Kusen Aluminium
13. Analisa Harga Satuan Pekerjaan Kunci dan Kaca
14. Analisa Harga Satuan Pekerjaan Sanitasi
15. Analisa Harga Satuan Pekerjaan Pengecatan
16. Analisa Harga Satuan Pekerjaan Penanaman Pohon
17. Harga Satuan Pekerjaan Konstruksi
18. Harga Satuan Upah Kerja
19. Harga Satuan Bahan Material

Analisa Harga Satuan Pekerjaan Rangka Atap Baja Ringan (Bukan AHS-SNI)

Agar Analisa Satuan Pekerjaan tersebut menjadi satu kesatuan, maka Anda bisa menyimpannya
dalam satu file Excel. Caranya, sebagai berikut :

1. Buka excel Anda


2. Buat file baru dan beri nama AHS-SNI
3. Buat Sheet sebanyak link halaman di atas = 19 sheet
4. Ganti nama sheet mulai sheet1 dengan nama A1, A2,A3, dst.. sampai A19
5. Buka link no. 1, lalu copy paste ke Sheet A1; link no.2 ke sheet A2 , dst.
6. Setelah selesai ubah harga satuan bahan dan upah pada sheet A1 sd. A17 dengan
formula/rumus dengan menghubungkannya ke sheet terkait : sheet A17, sheet A18, dan
sheet A19

Harga satuan pekerjaan (sheet A17) merupakan hasil proses yang nantinya Anda gunakan
untuk membuat RAB. Selamat mencoba! Bagi Anda yang mau bertanya.. silahkan kontak
saya via email : ndkusman@yahoo.com (tidak melayani kontak via Ponsel
Analisa Harga Satuan Pekerjaan Persiapan

Diposkan : 31 Mei 2014


Oleh : Endang Kusman

HARGA
No. URAIAN SATUAN VOLUME HARGA
SATUAN
(Rp) (Rp)
A-
1 M' Pagar Sementara Dari Kayu Tinggi 2 m
01
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Residu Kg 0.4000 8,100.00 3,240.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 269,315.90
Dibulatkan 269,316.00
A-
1 M' Pagar Sementara Seng Gelombang Tinggi 2 m
02
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Seng Gelombang BJLS-30 Lbr 1.2000 62,900.00 75,480.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Kayu balok terentang M3 0.0720 2,640,000.00 190,080.00
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Meni Besi Kg 0.4500 30,400.00 13,680.00
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 355,235.90
Dibulatkan 355,236.00
A- 1 M' Pagar SementaraKawat Duri Tinggi
03 1,80 m
- Dolken Kayu 8-10 / 400 cm Btg 1.0000 28,000.00 28,000.00
- Semen Portland Kg 2.0000 1,406.00 2,812.00
- Kawat Duri Kg 2.5000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Paku Biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Pekerja Oh 0.3000 42,000.00 12,600.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0200 80,000.00 1,600.00
Jumlah 222,842.90
Dibulatkan 222,843.00
A-
1 M2 Pengukuran Dan Pasang Bouwplank
04
- Kayu kaso 5/7 M3 0.0120 1,870,500.00 22,446.00
- Paku Biasa 2" - 5" Kg 0.0200 23,400.00 468.00
- Kayu papan albasia M3 0.0070 2,071,700.00 14,501.90
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 49,265.90
Dibulatkan 49,266.00
A- 1 M2 Pembuatan Kantor Sementara dgn
05 Lantai Diplester
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Kayu Balok terentang M3 0.1800 2,640,000.00 475,200.00
- Paku Biasa Kg 0.8500 23,400.00 19,890.00
- Besi Strip Kg 1.1000 26,800.00 29,480.00
- Semen Portland Kg 35.0000 1,406.00 49,210.00
- Pasir Pasang M3 0.1500 233,400.00 35,010.00
- Pasir beton M3 0.1000 255,400.00 25,540.00
- Koral Beton2/3 M3 0.1500 211,100.00 31,665.00
- Bata Merah Bh 30.0000 775.00 23,250.00
- Seng Plat m' 0.2500 15,815.00 3,953.75
- Kawat harmonika M2 2.0000 35,900.00 71,800.00
- Kaca Polos 3mm M2 0.0800 87,400.00 6,992.00
- Kunci Tanam Bh 0.1500 94,500.00 14,175.00
- Plywood 120 x 240 x 0,4 cm Lbr 0.0600 140,000.00 8,400.00
- Pekerja Oh 2.0000 42,000.00 84,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Tukang Batu Oh 1.0000 65,000.00 65,000.00
- Kepala Tukang Oh 0.3000 75,000.00 22,500.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 1,135,065.75
Dibulatkan 1,135,066.00
A- 1 M2 Pembuatan Gudang Semen dan Alat-
06 alat
- Dolken Kayu 8-10 / 400 cm Btg 1.7000 28,000.00 47,600.00
- Kayu balok terentang M3 0.2100 2,640,000.00 554,400.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 10.5000 1,406.00 14,763.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 1.5000 62,900.00 94,350.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 927,350.00
Dibulatkan 927,350.00
A-
1 M2 Pembuatan Bedeng Buruh
07
- Dolken Kayu 8-10 / 400 cm Btg 1.2500 28,000.00 35,000.00
- Kayu balok terentang M3 0.1860 2,640,000.00 491,040.00
- Paku Biasa Kg 0.3000 23,400.00 7,020.00
- Semen Portland Kg 18.0000 1,406.00 25,308.00
- Pasir Beton M3 0.0300 255,400.00 7,662.00
- Koral Beton 2/3 M3 0.0500 211,100.00 10,555.00
- Seng Gelombang BJLS 30 Lbr 1.5000 62,900.00 94,350.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 861,935.00
Dibulatkan 861,935.00
A-
1 M2 Membersihkan Lapangan dan Perataan
08
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 8,200.00
Dibulatkan 8,200.00
A-
1M2 Pembuatan Jalan Sementara
09
- Batu Belah 15/20 M3 0.1500 205,500.00 30,825.00
- Batu Pecah 5/7 M3 0.0900 196,000.00 17,640.00
- Pasir Pasang M3 0.0100 233,400.00 2,334.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 96,799.00
Dibulatkan 96,799.00
A-
1 M3 Bongkaran Beton Bertulang
10
- Pekerja Oh 6.6670 42,000.00 280,014.00
- Mandor Oh 0.3330 80,000.00 26,640.00
Jumlah 306,654.00
Dibulatkan 306,654.00
A-
1 M3 Bongkaran Dinding Tembok Bata Merah
11
- Pekerja Oh 6.6670 42,000.00 280,014.00
- Mandor Oh 0.0330 80,000.00 2,640.00
Jumlah 282,654.00
Dibulatkan 282,654.00
A-
1 M Pagar beton Pracetak ( 5 x 50 x 213 ) cm
12
- Panel Beton Pracetak Lbr 0.9860 199,200.00 196,411.20
- Kolom Beton Pracetak Btg 0.5250 264,000.00 138,600.00
- Pasir Beton M3 0.0740 255,400.00 18,899.60
- Koral 2/3 M3 0.1460 211,100.00 30,820.60
- Semen abu - abu Kg 45.0000 1,406.00 63,270.00
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 474,296.40
Dibulatkan 474,296.00
A-
1 M Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
13
- Kawat ram ayam Lbr 0.4340 14,900.00 6,466.60
- Besi siku L 50.50.5 Kg 6.7860 18,300.00 124,183.80
- Besi pelat (1,2 x 3) mm Kg 0.0424 18,300.00 775.92
- Baut bh 4.0000 600.00 2,400.00
- Semen Portland Kg 2.5000 1,406.00 3,515.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 166,813.22
Dibulatkan 166,813.00
A-
1 M2 Pagar BRC lengkap dengan tiang
14
- BRC lengkap dengan tiang Lbr 0.4340 171,300.00 74,344.20
- Semen Portland Kg 2.0000 1,406.00 2,812.00
- Kawat Duri Kg 2.5000 63,500.00 158,750.00
- Pasir beton M3 0.0050 255,400.00 1,277.00
- Koral Beton 2/3 M3 0.0090 211,100.00 1,899.90
- Pekerja Oh 0.3750 42,000.00 15,750.00
- Tukang Batu Oh 0.1250 65,000.00 8,125.00
- Kepala Tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0190 80,000.00 1,520.00
Jumlah 265,378.10
Dibulatkan 265,378.00
A-
1 M2 Steiger Werk / perancah dari Bambu
15
- Bambu 6 - 10 (600) cm btng 1.0000 25,000.00 25,000.00
- Tali ijuk kg 0.2500 23,400.00 5,850.00
- Pekerja org 0.2500 42,000.00 10,500.00
- Tukang kayu org 0.0170 65,000.00 1,105.00
- Kepala tukang org 0.0020 75,000.00 150.00
- Mandor org 0.0130 80,000.00 1,040.00
Jumlah 43,645.00
Dibulatkan 43,645.00
A-
1 M' Cerucuk Bambu
16
- Bambu 7 -10 (400) cm btng 1.2500 25,000.00 31,250.00
- Pekerja org 0.5000 42,000.00 21,000.00
- Mandor org 0.0250 80,000.00 2,000.00
Jumlah 54,250.00
Dibulatkan 54,250.00

Kembali ke Analisa AHS SNI

Analisa Harga Satuan Pekerjaan Tanah

Berkut ini adalah contoh Analisa Harga Satuan (AHS) SNI tahun 2011 untuk pekerjaan tanah
yang sering digunakan untuk pekerjaan bangunan rumah.

B. ANALISA HARGA SATUAN PEKERJAAN TANAH


No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA
(Rp) (Rp)
B-01 1 M3 Galian Tanah Biasa sedalam 1 m
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 20,000.00
Dibulatkan 20,000.00
B-02 1 M3 Galian Tanah Biasa Sedalam 2 m
- Pekerja Oh 0.5260 42,000.00 22,092.00
- Mandor Oh 0.0520 80,000.00 4,160.00
Jumlah 26,252.00
Dibulatkan 26,252.00
B-03 1 M3 Galian Tanah Biasa Sedalam 3 m
- Pekerja Oh 0.7350 42,000.00 30,870.00
- Mandor Oh 0.0730 80,000.00 5,840.00
Jumlah 36,710.00
Dibulatkan 36,710.00
B-04 1 M3 Galian Tanah Keras Sedalam 1 m
- Pekerja Oh 0.6250 42,000.00 26,250.00
- Mandor Oh 0.0620 80,000.00 4,960.00
Jumlah 31,210.00
Dibulatkan 31,210.00
1 M3 Galian Tanah Lumpur Sedalam 1
B-05
m
- Pekerja Oh 0.8230 42,000.00 34,566.00
- Mandor Oh 0.0830 80,000.00 6,640.00
Jumlah 41,206.00
Dibulatkan 41,206.00

Materi TerAnalisa Harga Satuan Pekerjaan Pondasi (AHS SNI 2011)

Untuk menghitung biaya pekerjaan pondasi bagunan rumah Anda diperlukan Analisa Harga
Satuan Pekerjaaan Pondasi. Berikut adalah contoh analisa pekerjaan pondasi (AHS SNI tahun
2011). Pada dasarnya yang selalu berubah setiap tahun pada analisa harga satuan, adalah
harga bahan dan upah, sedangkan koefisien (volume pek.) tetap.

C. ANALISA HARGA SATUAN PEKERJAAN PONDASI


HARGA
No. URAIAN SATUANVOLUME HARGA
SATUAN
(Rp) (Rp)
C- 1 M3 Pasanag Pondasi batu Kali adk 1pc
01 : 3 ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
Semen
- Kg 202.0000 1,406.00 284,012.00
Portland
- Pasir Pasang M3 0.4850 233,400.00 113,199.00
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
Kepala
- Oh 0.0600 75,000.00 4,500.00
Tukang
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 735,761.00
Dibulatkan 735,761.00
C- 1 M3 Pasang Pondasi Batu kali adk 1pc :
02 4ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
Semen
- Kg 163.0000 1,406.00 229,178.00
Portland
- Pasir Pasang M3 0.5200 233,400.00 121,368.00
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
- Kepala Oh 0.0600 75,000.00 4,500.00
Tukang
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 689,096.00
Dibulatkan 689,096.00
C- 1 M3 Pasang Pondasi Batu kali adk 1pc :
03 5ps
- Batu Belah M3 1.1000 205,500.00 226,050.00
Semen
- Kg 136.0000 1,406.00 191,216.00
Portland
- Pasir Pasang M3 0.5440 233,400.00 126,969.60
- Pekerja Oh 1.5000 42,000.00 63,000.00
- Tukang Batu Oh 0.6000 65,000.00 39,000.00
Kepala
- Oh 0.0600 75,000.00 4,500.00
Tukang
- Mandor Oh 0.0750 80,000.00 6,000.00
Jumlah 656,735.60
Dibulatkan 656,736.00
C- 1 M3 Pasang Pondasi Batu Kosong
04 (aanstamping)
- Batu Belah M3 1.2000 205,500.00 246,600.00
- Pasir Urug M3 0.3000 175,300.00 52,590.00
- Pekerja Oh 0.7800 42,000.00 32,760.00
- Tukang Batu Oh 0.3900 65,000.00 25,350.00
Kepala
- Oh 0.0390 75,000.00 2,925.00
Tukang
- Mandor Oh 0.0390 80,000.00 3,120.00
Jumlah 363,345.00
Dibulatkan 363,345.00

kait :

Analisa Harga Satuan Pekerjaan Beton

NO URAIAN SAT VOLUME HRG.SAT JUMLAH


1 M3 Sloof Beton Tulang 15/20 (180 kg besi +
D-17r2
bekisting) 4dia. 12 ring 8-15
Kayu papan terentang M3 0.2700 2,850,000 769,500
Paku Biasa 2" - 5" Kg 2.0000 23,400 46,800
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 3.0000 27,700 83,100
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Pekerja Oh 4.8500 55,000 266,750
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 1.5600 70,000 109,200
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.3310 80,000 26,480
Mandor Oh 0.1700 85,000 14,450
Jumlah 5,069,380
Dibulatkan 5,069,380

1 M3 Kolom Beton Tulang 15/20 (180 kg besi +


bekisting) 4dia.12 8-15
Kayu papan terentang M3 0.4000 2,850,000 1,140,000
Paku Biasa 2" - 5" Kg 4.0000 23,400 93,600
Minyak Bekisting Ltr 40,500 -
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 1.8000 27,700 49,860
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1500 2,640,000 396,000
Dolken -8-10/4m Btg 20.0000 15,000 300,000
Pekerja Oh 7.3000 55,000 401,500
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 3.3000 70,000 231,000
Tukang Besi Oh 2.1000 70,000 147,000
Kepala Tukang Oh 0.5700 80,000 45,600
Mandor Oh 0.2500 85,000 21,250
Jumlah 6.480.910
Dibulatkan 6.481.000

1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk +


balok poratl (180 kg besi + bekisting) 4dia. 12, 8-15
Kayu papan terentang M3 0.3200 2,850,000 912,000
Paku Biasa 2" - 5" Kg 3.2000 23,400 74,880
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 2.2500 27,700 62,325
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1400 2,640,000 369,600
Dolken -8-10/4m Btg 16.0000 15,000 240,000
Pekerja Oh 5.9600 55,000 327,800
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 2.8000 70,000 196,000
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.4550 80,000 36,400
Mandor Oh 0.2080 85,000 17,680
Jumlah 6.412.865
Dibulatkan 6,413,000
D-29 1 M3 Tangga Beton Tulang (90 kg besi + bekisting)
Kayu papan terentang M3 0.2500 2,850,000 712,500
Paku Biasa 2" - 5" Kg 3.0000 23,400 70,200
Minyak Bekisting Ltr 1.2000 40,500 48,600
Besi Beton Kg 90.0000 16,500 1,485,000
Kawat Beton Kg 3.0000 27,700 83,100
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1050 2,640,000 277,200
Dolken -8-10/4m Btg 14.0000 15,000 210,000
Pekerja Oh 5.6000 55,000 308,000
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 2.3000 70,000 161,000
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.4050 80,000 32,400
Mandor Oh 0.2020 85,000 17,170
Jumlah 4,188,720
Dibulatkan 4,189,000
1 M3 Membuat Plat Lantai Tb. 10 Cm Beton
3
Bertulang ( 90 Kg Besi + Bekisting )
Kayu Terentang M3 0.4000 2,850,000 1,140,000
Paku Biasa 2" - 5" Kg 4.0000 23,400 93,600
Minyak Bekisting Ltr 2.0000 40,500 81,000
Besi Beton Polos Kg 90.0000 16,500 1,485,000
Kawat Beton Kg 3.0000 27,700 83,100
Kayu Balok Terentang M3 0.1050 151,100 15,866
Plywood Tebal 9 mm Lbr 3.5000 151,100 528,850
Dolken kayu Galam o - 8-10/4 m Btg 60.0000 15,000 900,000
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Pekerja Oh 5.2000 55,000 286,000
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 3.3000 70,000 231,000
Kepala Tukang Oh 0.3650 80,000 29,200
Mandor Oh 1.0600 85,000 90,100
Jumlah 5,648,816
Dibulatkan 5,649,000

Materi Terkait :

Analisa Harga Satuan Pekerjaan Beton


NO URAIAN SAT VOLUME HRG.SAT JUMLAH
1 M3 Sloof Beton Tulang 15/20 (180 kg besi +
D-17r2
bekisting) 4dia. 12 ring 8-15
Kayu papan terentang M3 0.2700 2,850,000 769,500
Paku Biasa 2" - 5" Kg 2.0000 23,400 46,800
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 3.0000 27,700 83,100
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Pekerja Oh 4.8500 55,000 266,750
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 1.5600 70,000 109,200
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.3310 80,000 26,480
Mandor Oh 0.1700 85,000 14,450
Jumlah 5,069,380
Dibulatkan 5,069,380

1 M3 Kolom Beton Tulang 15/20 (180 kg besi +


bekisting) 4dia.12 8-15
Kayu papan terentang M3 0.4000 2,850,000 1,140,000
Paku Biasa 2" - 5" Kg 4.0000 23,400 93,600
Minyak Bekisting Ltr 40,500 -
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 1.8000 27,700 49,860
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1500 2,640,000 396,000
Dolken -8-10/4m Btg 20.0000 15,000 300,000
Pekerja Oh 7.3000 55,000 401,500
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 3.3000 70,000 231,000
Tukang Besi Oh 2.1000 70,000 147,000
Kepala Tukang Oh 0.5700 80,000 45,600
Mandor Oh 0.2500 85,000 21,250
Jumlah 6.480.910
Dibulatkan 6.481.000

1 M3 Balok Beton Tulang 15/20 sofi-sofi, ring balk +


balok poratl (180 kg besi + bekisting) 4dia. 12, 8-15
Kayu papan terentang M3 0.3200 2,850,000 912,000
Paku Biasa 2" - 5" Kg 3.2000 23,400 74,880
Besi Beton Kg 180.0000 16,500 2,970,000
Kawat Beton Kg 2.2500 27,700 62,325
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1400 2,640,000 369,600
Dolken -8-10/4m Btg 16.0000 15,000 240,000
Pekerja Oh 5.9600 55,000 327,800
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 2.8000 70,000 196,000
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.4550 80,000 36,400
Mandor Oh 0.2080 85,000 17,680
Jumlah 6.412.865
Dibulatkan 6,413,000
D-29 1 M3 Tangga Beton Tulang (90 kg besi + bekisting)
Kayu papan terentang M3 0.2500 2,850,000 712,500
Paku Biasa 2" - 5" Kg 3.0000 23,400 70,200
Minyak Bekisting Ltr 1.2000 40,500 48,600
Besi Beton Kg 90.0000 16,500 1,485,000
Kawat Beton Kg 3.0000 27,700 83,100
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Kayu Balok Terentang M3 0.1050 2,640,000 277,200
Dolken -8-10/4m Btg 14.0000 15,000 210,000
Pekerja Oh 5.6000 55,000 308,000
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 2.3000 70,000 161,000
Tukang Besi Oh 1.4000 70,000 98,000
Kepala Tukang Oh 0.4050 80,000 32,400
Mandor Oh 0.2020 85,000 17,170
Jumlah 4,188,720
Dibulatkan 4,189,000
1 M3 Membuat Plat Lantai Tb. 10 Cm Beton
3
Bertulang ( 90 Kg Besi + Bekisting )
Kayu Terentang M3 0.4000 2,850,000 1,140,000
Paku Biasa 2" - 5" Kg 4.0000 23,400 93,600
Minyak Bekisting Ltr 2.0000 40,500 81,000
Besi Beton Polos Kg 90.0000 16,500 1,485,000
Kawat Beton Kg 3.0000 27,700 83,100
Kayu Balok Terentang M3 0.1050 151,100 15,866
Plywood Tebal 9 mm Lbr 3.5000 151,100 528,850
Dolken kayu Galam o - 8-10/4 m Btg 60.0000 15,000 900,000
Semen Portland Kg 323.0000 1,200 387,600
Pasir Beton M3 0.5200 225,000 117,000
Koral Beton 2/3 M3 0.7800 200,000 156,000
Pekerja Oh 5.2000 55,000 286,000
Tukang Batu Oh 0.3500 70,000 24,500
Tukang Kayu Oh 3.3000 70,000 231,000
Kepala Tukang Oh 0.3650 80,000 29,200
Mandor Oh 1.0600 85,000 90,100
Jumlah 5,648,816
Dibulatkan 5,649,000

Materi Terkait :

Analisa Harga Satuan Pekerjaan Dinding (AHS-SNI 2011)

Berikut adalah penggalan analisa harga satuan (AHS-SNI 2011) untuk pekerjaan dinding
yang biasa digunakan untuk menghitung biaya pekerjaan dinding pada rumah tinggal.
Keseluruhan analisa pekerjaan dinding untuk berbagai ukuran ketebalan dinding dan
komposisi adukan pada AHS-SNI ada sekitar 40 analisa.

E. ANALISA HARGA SATUAN PEKERJAAN DINDING


No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
E-
1 M2 Pasang Bata Merah Tebal 1 Bata, 1pc : 3ps
01
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 32.9500 1,406.00 46,327.70
- Pasir Pasang M3 0.0910 233,400.00 21,239.40
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 220,267.10
Dibulatkan 220,267.00
E- M2 Pasang Bata Merah Tebal 1 Bata, 1pc :
1
02 4ps
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 26.5500 1,406.00 37,329.30
- Pasir Pasang M3 0.0930 233,400.00 21,706.20
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 211,735.50
Dibulatkan 211,736.00
E- M2 Pasang Bata Merah Tebal 1 Bata, 1pc :
1
03 5ps
- Bata Merah Bh 140.0000 775.00 108,500.00
- Semen Portland Kg 22.2000 1,406.00 31,213.20
- Pasir Pasang M3 0.1020 233,400.00 23,806.80
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 207,720.00
Dibulatkan 207,720.00
E-
1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 3ps
04
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 14.3700 1,406.00 20,204.22
- Pasir Pasang M3 0.0400 233,400.00 9,336.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 105,680.22
Dibulatkan 105,680.00
E-
1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 4ps
05
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 11.5000 1,406.00 16,169.00
- Pasir Pasang M3 0.0430 233,400.00 10,036.20
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 102,345.20
Dibulatkan 102,345.00
E-
1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps
06
- Bata Merah Bh 70.0000 775.00 54,250.00
- Semen Portland Kg 9.6800 1,406.00 13,610.08
- Pasir Pasang M3 0.0450 233,400.00 10,503.00
- Pekerja Oh 0.3200 42,000.00 13,440.00
- Tukang Batu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0150 80,000.00 1,200.00
Jumlah 100,253.08
Dibulatkan 100,253.00

Analisa Harga Satuan Pekerjaan Plesteran (AHS SNI 2011)


Inilah penggalan analisa pekerjaan plesteran yang paling banyak digunakan untuk
menghitung biaya bangunan rumah tinggal.

F. ANALISA HARGA SATUAN PEKERJAAN PLESTERAN


No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
1 M2 Plesteran adk. 1pc : 2ps Tebal 15
F-01
mm
- Semen Portland Kg 8.5200 1,406.00 11,979.12
- Pasir Pasang M3 0.0170 233,400.00 3,967.80
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 36,021.92
Dibulatkan 36,022.00
1 M2 Plesteran adk. 1pc : 3ps Tebal 15
F-02
mm
- Semen Portland Kg 6.4800 1,406.00 9,110.88
- Pasir Pasang M3 0.0190 233,400.00 4,434.60
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 33,620.48
Dibulatkan 33,620.00
1 M2 Plesteran adk. 1pc : 4ps Tebal 15
F-03
mm
- Semen Portland Kg 5.2000 1,406.00 7,311.20
- Pasir Pasang M3 0.0200 233,400.00 4,668.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang Batu Oh 0.1500 65,000.00 9,750.00
- Kepala Tukang Oh 0.0150 75,000.00 1,125.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 32,054.20
Dibulatkan 32,054.00
1 M2 Plesteran adk. 1pc : 3ps Tebal 20
F-04
mm
- Semen Portland Kg 10.8000 1,406.00 15,184.80
- Pasir Pasang M3 0.0260 233,400.00 6,068.40
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 47,253.20
Dibulatkan 47,253.00
F-05 1 M2 Plesteran adk. 1pc : 4ps Tebal 20
mm
- Semen Portland Kg 8.6800 1,406.00 12,204.08
- Pasir Pasang M3 0.0280 233,400.00 6,535.20
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 44,739.28
Dibulatkan 44,739.00
1 M2 Plesteran adk. 1pc:5ps tebal 20
F-06
mm
- Semen Portland Kg 7.2900 1,406.00 10,249.74
- Pasir Pasang M3 0.0260 233,400.00 6,068.40
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang Batu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 42,318.14
Dibulatkan 42,318.00
F-11 1 M2 Acian Plesteran
- Semen Portland Kg 4.0000 1,406.00 5,624.00
- Pekerja Oh 0.1430 42,000.00 6,006.00
- Tukang batu Oh 0.1070 65,000.00 6,955.00
- Kepala Tukang Oh 0.0105 75,000.00 787.50
- Mandor Oh 0.0105 80,000.00 840.00
Jumlah 20,212.50
Dibulatkan 20,213.00

Materi Terkait :

Penggalan Analisa Harga Satuan Penutup Atap (AHS SNI 2011)

Untuk menghitung pekerjaan penutup atap seperti genting plentong, genting morando,
genting keramik, genting beton dll. diperlukan analisa harga satuan penutup atap. Berikut
adalah penggalan AHS SNI 2011 penutup atap yang biasa digunakan untuk menghitung RAB
Rumah tinggal.

G. ANALISA HARGA SATUAN PEKERJAAN PENUTUP ATAP


No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
G-011 M2 Pasang Atap Genteng Palentong
- Genteng palentong Bh 25.0000 1,900.00 47,500.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 59,915.00
Dibulatkan 59,915.00
G-021 M2 Pasang Genteng Bubung Palentong
- Genteng bubung palentong Bh 5.0000 6,000.00 30,000.00
- Semen Portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0320 233,400.00 7,468.80
- Pekerja Oh 0.4000 42,000.00 16,800.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0020 80,000.00 160.00
Jumlah 80,176.80
Dibulatkan 80,177.00
G-031 M2 Pasang Roof Light Fibreglass ( 180 x 90 ) cm
- Roof light fibreglass Lbr 0.6000 100,000.00 60,000.00
- Paku biasa " - 1" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 72,510.00
Dibulatkan 72,510.00
1 M2 Pasang Atap Asbes Gelombang ( 3,00 x 1,05 m ) x 4
G-04
mm
- Asbes gelombang Lbr 0.3500 80,000.00 28,000.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 42,371.00
Dibulatkan 42,371.00
G-051 M2 Pasang Atap Asbes Gelombang ( 2,70 x 1,05 m ) x 4 mm
- Asbes gelombang Lbr 0.4200 73,300.00 30,786.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 45,157.00
Dibulatkan 45,157.00
1 M2 Pasang Atap Asbes Gelombang ( 2,40 x 1,05 m ) x 4
G-06
mm
- Asbes gelombang Lbr 0.4400 65,900.00 28,996.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 43,172.00
Dibulatkan 43,172.00
M2 Pasang Atap Asbes Gelombang ( 2,10 x 1,05 m ) x 4
G-071
mm
- Asbes gelombang Lbr 0.5100 58,500.00 29,835.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 44,011.00
Dibulatkan 44,011.00
1 M2 Pasang Atap Asbes Gelombang ( 1,50 x 1,05 m ) x 4
G-08
mm
- Asbes gelombang Lbr 0.8000 42,300.00 33,840.00
- Paku seng Kg 0.1200 23,800.00 2,856.00
- Pekerja Oh 0.1400 42,000.00 5,880.00
- Tukang kayu Oh 0.0670 65,000.00 4,355.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0070 80,000.00 560.00
Jumlah 48,016.00
Dibulatkan 48,016.00
G-091 M Pasang Nok Stel Gelombang 1,05 m
- Nok stel gelombang Lbr 2.1000 38,100.00 80,010.00
- Paku sekrup 3,5" Bh 6.0000 800.00 4,800.00
- Pekerja Oh 0.0840 42,000.00 3,528.00
- Tukang kayu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0130 75,000.00 975.00
- Mandor Oh 0.0040 80,000.00 320.00
Jumlah 97,758.00
Dibulatkan 97,758.00
G-101 M2 Pasang Atap Genteng Beton
- Genteng beton bh 11.0000 8,500.00 93,500.00
- Paku biasa 2" - 5" Kg 0.0300 23,400.00 702.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 110,652.00
Dibulatkan 110,652.00
G-111 M2 Pasang Atap Genteng Murando Natural
- Genteng murando natural bh 18.0000 2,700.00 48,600.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 61,015.00
Dibulatkan 61,015.00
G-121 M2 Pasang Atap Genteng Murando Glazur
- Genteng murando glazur bh 18.0000 4,000.00 72,000.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0080 75,000.00 600.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 84,415.00
Dibulatkan 84,415.00

Materi Terkait :

Analisa Harga Satuan Pekerjaan Penutup Langit-langit (AHS SNI 2011)

Berikut ini adalah penggalan Analisa Harga Satuan Pekerjaan untuk menghitung biaya
pekerjaan langit-langit: asbes, akustik, tekwood, gypsum, dan GRC.

H. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANGIT-LANGIT


No. URAIAN SATUAN VOLUMEHARGA SATUAN HARGA
(Rp) (Rp)
(Rp) (Rp)
1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m,
H-01
tebal 5 mm
- Pelat asbes tebal 4 mm m2 1.1000 22,500.00 24,750.00
- Paku seng Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0015 80,000.00 120.00
Jumlah 31,443.00
Dibulatkan 31,443.00
1 M2 Langit-langit Asbes ( 1,00 x 1,00 ) m,
H-02
tebal 3,5 mm
- Pelat asbes tebal 3,5 mm Lbr 1.1000 19,500.00 21,450.00
- Paku seng Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang kayu Oh 0.0700 65,000.00 4,550.00
- Kepala tukang Oh 0.0070 75,000.00 525.00
- Mandor Oh 0.0015 80,000.00 120.00
Jumlah 28,143.00
Dibulatkan 28,143.00
H-031 M2 Langit-langit Akustik ( 60 x 120 ) cm
- Akustik 600 x 1200 Lbr 1.5000 132,800.00 199,200.00
- Paku Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 210,400.00
Dibulatkan 210,400.00
H-041 M2 Langit-langit Akustik ( 60 x 120 ) cm + Rangka Alluminium
- Profil Alluminium "T" M 3.6000 12,200.00 43,920.00
- Kawat f 4 mm Kg 0.1500 28,200.00 4,230.00
- Ramset / dina bolt Bh 1.0500 7,200.00 7,560.00
- Akustik 600 x 1200 Lbr 1.5000 132,800.00 199,200.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.5000 65,000.00 32,500.00
- Kepala tukang Oh 0.0500 75,000.00 3,750.00
- Mandor Oh 0.0075 80,000.00 600.00
Jumlah 298,060.00
Dibulatkan 298,060.00
H-051 M2 Langit-langit teakwood (60 x 120) cm, t = 4 mm + rangka kayu borneo super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Teakwood 120 cm x 240 cm x 0,4 cm Lbr 0.3900 131,700.00 51,363.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 154,907.00
Dibulatkan 154,907.00
H-061 M2 Langit-langit Teakwood 3 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,400.00 1,404.00
- Teakwood (120 x 240x 0,3) cm Lbr 0.3900 129,100.00 50,349.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 153,893.00
Dibulatkan 153,893.00
H-071 M2 Langit-langit Triplek 4 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
- Triplek 120 cm x 240 cm x 0,4 cm Lbr 0.3900 64,400.00 25,116.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 128,684.00
Dibulatkan 128,684.00
H-081 M2 Langit-langit Gypsum Board, tebal 9 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- Gypsum board ( 120 x 240 x 9 ) mm Lbr 0.3640 79,800.00 29,047.20
- Paku gypsum kg 0.1100 17,500.00 1,925.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 15,000.00 1,080.00
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 93,960.20
Dibulatkan 93,960.00
H-091 M2 Langit-langit GRC t = 4 mm + rangka besi hollow
- Hollow 4/4 Zincromate Btg 0.4150 29,200.00 12,118.00
- Hollow 2/4 Zincromate Btg 0.1500 22,600.00 3,390.00
- GRC ( 120 x 240 x 4 ) mm Lbr 0.3640 67,500.00 24,570.00
- Paku GRC kg 0.1100 35,000.00 3,850.00
- Ramset / dina bolt Bh 4.0000 7,200.00 28,800.00
- Cotton plaster Bh 0.0720 15,000.00 1,080.00
- Compoun Zak 0.1250 75,000.00 9,375.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 91,408.00
Dibulatkan 91,408.00
H-101 M2 Langit-langit gypsum t = 9 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
- Gypsum board ( 120 x 240 x 9 ) mm Lbr 0.3900 79,800.00 31,122.00
- Paku sekrup kg 0.1100 17,500.00 1,925.00
- Pekerja Oh 0.2700 42,000.00 11,340.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0400 75,000.00 3,000.00
- Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 136,615.00
Dibulatkan 136,615.00
H-111 M2 Langit-langit GRC t = 4 mm + Rangka Kayu Borneo Super
- Kayu Balok Borneo Super M3 0.0230 2,640,000.00 60,720.00
- Paku biasa 2" - 5" Kg 0.0600 23,800.00 1,428.00
-
GRC ( 120 x 240 x 4 ) mm Lbr 0.3900 67,500.00 26,325.00
-
Paku GRC kg 0.1100 35,000.00 3,850.00
-
Pekerja Oh 0.2700 42,000.00 11,340.00
-
Tukang kayu Oh 0.4000 65,000.00 26,000.00
-
Kepala tukang Oh 0.0400 75,000.00 3,000.00
-
Mandor Oh 0.0135 80,000.00 1,080.00
Jumlah 133,743.00
Dibulatkan 133,743.00
H-121 M List Langit-langit Kayu Profil 10 cm
- List Kayu profil M 1.0500 29,400.00 30,870.00
- Paku Kg 0.0100 23,800.00 238.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 37,073.00
Dibulatkan 37,073.00
H-131 M List Langit-langit Gypsum 10 cm
- List gypsum M 1.0500 8,500.00 8,925.00
- Tepung gypsum Kg 0.1500 12,500.00 1,875.00
- Pekerja Oh 0.0500 42,000.00 2,100.00
- Tukang kayu Oh 0.0500 65,000.00 3,250.00
- Kepala tukang Oh 0.0050 75,000.00 375.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 16,765.00
Dibulatkan 16,765.00

Materi Terkait :

Analisa Harga Satuan Pekerjaan Penutup Lantai dan Dinding (AHS SNI
2011)

Berikut adalah analisa harga satuan pekerjaan penutup landat dan dinding untuk menghitung
biaaya penutup lantai per meter persegi, seperti lantai keramik, lantai marmer dll.

HARGA
No. URAIAN SATUAN VOLUME HARGA
SATUAN
(Rp) (Rp)
1 M2 Lantai Ubin Granito ukuran 40 x 40 cm
I-01
Setara Essenza
- Granito 40 x 40 cm m2 1.0500 345,000.00 362,250.00
- Semen portland Kg 9.8000 1,406.00 13,778.80
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 1.3000 15,700.00 20,410.00
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 421,656.90
Dibulatkan 421,657.00
1 M2 Lantai Ubin Granito ukuran 30 x 30 cm
I-02
Setara Essenza
- Granito 30 x 30 cm m2 1.0500 322,800.00 338,940.00
- Semen portland Kg 10.0000 1,406.00 14,060.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 1.5000 15,700.00 23,550.00
- Pekerja Oh 0.2600 42,000.00 10,920.00
- Tukang batu Oh 0.1250 65,000.00 8,125.00
- Kepala tukang Oh 0.0125 75,000.00 937.50
- Mandor Oh 0.0130 80,000.00 1,040.00
Jumlah 402,590.60
Dibulatkan 402,591.00
1 M Plint Ubin Granito ukuran 10 x 40 cm Setara
I-03
Essenza
- Plint granito 10 x 40 cm Bh 2.6500 27,600.00 73,140.00
- Semen portland Kg 1.2000 1,406.00 1,687.20
- Pasir pasang M3 0.0030 233,400.00 700.20
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang batu Oh 0.0300 65,000.00 1,950.00
- Kepala tukang Oh 0.0030 75,000.00 225.00
- Mandor Oh 0.0030 80,000.00 240.00
Jumlah 82,032.40
Dibulatkan 82,032.00
1 M Plint Ubin Granito ukuran 10 x 30 cm Setara
I-04
Essenza
- Plint granito 10 x 30 cm Bh 3.3300 25,900.00 86,247.00
- Semen portland Kg 1.6500 1,406.00 2,319.90
- Pasir pasang M3 0.0032 233,400.00 746.88
- Semen warna Kg 0.1000 15,700.00 1,570.00
- Pekerja Oh 0.0900 42,000.00 3,780.00
- Tukang batu Oh 0.0900 65,000.00 5,850.00
- Kepala tukang Oh 0.0090 75,000.00 675.00
- Mandor Oh 0.0045 80,000.00 360.00
Jumlah 101,548.78
Dibulatkan 101,549.00
I-05 1 M2 Lantai Keramik Corak 10 x 20 cm setara Mulia
- Keramik corak 10 x 20 cm m2 1.0000 56,000.00 56,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 92,670.20
Dibulatkan 92,670.00
1 M2 Lantai Keramik corak 20 x 20 cm setara
I-06
Mulia
- Keramik corak 20 x 20 cm m2 1.0000 62,500.00 62,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 99,170.20
Dibulatkan 99,170.00
1 M2 Lantai Keramik polos 30 x 30 cm setara
I-07
Mulia
- Keramik polos 30 x 30 cm m2 1.0000 53,000.00 53,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 89,670.20
Dibulatkan 89,670.00
1 M2 Lantai Keramik corak 30 x 30 cm Setara
I-08
Mulia
- Keramik corak 30 x 30 cm m2 1.0000 58,000.00 58,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 94,670.20
Dibulatkan 94,670.00
1 M2 Lantai Keramik polos 40 x 40 cm Setara
I-09
Mulia
- Keramik polos 40 x 40 cm m2 1.0000 56,800.00 56,800.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 93,470.20
Dibulatkan 93,470.00
1 M2 Lantai Keramik corak 40 x 40 cm Setara
I-10
Mulia
- Keramik corak 40 x 40 cm m2 1.0000 65,500.00 65,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 102,170.20
Dibulatkan 102,170.00
I-11 1 M2 Lantai Keramik Corak 10 x 20 cm setara Roman
- Keramik corak 10 x 20 cm m2 1.0000 72,200.00 72,200.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 108,870.20
Dibulatkan 108,870.00
1 M2 Lantai Keramik corak 20 x 20 cm setara
I-12
Roman
- Keramik corak 20 x 20 cm m2 1.0000 75,200.00 75,200.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 111,870.20
Dibulatkan 111,870.00
1 M2 Lantai Keramik polos 30 x 30 cm setara
I-13
Roman
- Keramik polos 30 x 30 cm m2 1.0000 68,900.00 68,900.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 105,570.20
Dibulatkan 105,570.00
1 M2 Lantai Keramik corak 30 x 30 cm Setara
I-14
Roman
- Keramik corak 30 x 30 cm M2 1.0000 76,600.00 76,600.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,270.20
Dibulatkan 113,270.00
1 M2 Lantai Keramik polos 40 x 40 cm setara
I-15
Roman
- Keramik polos 40 x 40 cm m2 1.0000 72,500.00 72,500.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 109,170.20
Dibulatkan 109,170.00
1 M2 Lantai Keramik corak 40 x 40 cm Setara
I-16
Roman
- Keramik corak 40 x 40 cm m2 1.0000 77,000.00 77,000.00
- Semen portland Kg 8.0000 1,406.00 11,248.00
- Pasir pasang M3 0.0215 233,400.00 5,018.10
- Semen warna Kg 0.0130 15,700.00 204.10
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang batu Oh 0.1200 65,000.00 7,800.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0125 80,000.00 1,000.00
Jumlah 113,670.20
Dibulatkan 113,670.00
I-17 1 M2 Lantai Marmer
- Marmer m2 1.0600 550,000.00 583,000.00
-Semen portland Kg 8.1900 1,406.00 11,515.14
-Pasir pasang M3 0.0450 233,400.00 10,503.00
-Semen warna Kg 0.6500 15,700.00 10,205.00
-Pekerja Oh 0.7000 42,000.00 29,400.00
-Tukang batu Oh 0.3500 65,000.00 22,750.00
-Kepala tukang Oh 0.0350 75,000.00 2,625.00
-Mandor Oh 0.0350 80,000.00 2,800.00
Jumlah 672,798.14
Dibulatkan 672,798.00
I-18 1 M2 Lantai Parquet Jati
- Parquet jati M2 1.0500 375,400.00 394,170.00
- Lem vinyl Kg 0.6000 44,000.00 26,400.00
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0325 80,000.00 2,600.00
Jumlah 475,845.00
Dibulatkan 475,845.00

Materi Terkait :

Analisa Harga Satuan Pekerjaan Kayu - AHS SNI 2011

Berikut adalah penggalan analisa harga satuan pekerjaan kayu, untuk menghitung harga
satuan pekerjaan kayu per m3, seperti pekerjaan kusen dan jendela, pekerjaan plapond, dan
pekerjaan atap.

J. ANALISA HARGA SATUAN PEKERJAAN KAYU


HARGA
No. URAIAN SATUAN VOLUME HARGA
SATUAN
J-01 1 M3 Kusen Pintu & jendela kayu Kamper Samarinda
- Kayu Balok Kamper Samarinda m3 1.2000 8,633,700.00 10,360,440.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 11,956,440.00
Dibulatkan 11,956,440.00
J-02 1 M3 Kusen Pintu & jendela kayu Kamper Medan/Kruing
- Kayu Balok Kamper Medan M3 1.2000 5,692,600.00 6,831,120.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 8,427,120.00
Dibulatkan 8,427,120.00
J-03 1 M3 Kusen Pintu & jendela kayu Borneo Super
- Kayu Borneo Balok Super M3 1.2000 5,280,000.00 6,336,000.00
- Pekerja Oh 6.0000 42,000.00 252,000.00
- Tukang Kayu Oh 18.0000 65,000.00 1,170,000.00
- Kepala Tukang Oh 2.0000 75,000.00 150,000.00
- Mandor Oh 0.3000 80,000.00 24,000.00
Jumlah 7,932,000.00
Dibulatkan 7,932,000.00
J-04 1 M2 Pintu Panel Kayu Kamper Samarinda
- Kayu Papan Kamper Samarinda M3 0.0400 8,633,700.00 345,348.00
- Paku Biasa 2" - 5" Kg 0.0500 23,400.00 1,170.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 573,768.00
Dibulatkan 573,768.00
J-05 1 M2 Pintu Panel Kayu Kamper Medan/Kruing
- Kayu Papan Kamper Medan M3 0.0400 5,692,600.00 227,704.00
- Paku Biasa 2" - 5" Kg 0.0500 23,400.00 1,170.00
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0500 80,000.00 4,000.00
Jumlah 456,124.00
Dibulatkan 456,124.00
J-06 1 M2 Pintu & Jendela Kaca Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0350 5,692,600.00 199,241.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 381,041.00
Dibulatkan 381,041.00
J-07 1 M2 Pintu & Jendela Kaca Kayu Borneo
- Kayu Papan Borneo Super M3 0.0350 5,595,800.00 195,853.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 377,653.00
Dibulatkan 377,653.00
J-08 1 M2 Pintu & Jendela Jalusi Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0640 5,692,600.00 364,326.40
- Pekerja Oh 1.0000 42,000.00 42,000.00
- Tukang Kayu Oh 3.0000 65,000.00 195,000.00
- Kepala Tukang Oh 0.3000 75,000.00 22,500.00
- Mandor Oh 0.5000 80,000.00 40,000.00
Jumlah 663,826.40
Dibulatkan 663,826.00
M2 Pintu Triplek Rangkap, Rangka Tertutup Kayu Kamper
J-09 1
Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.0300 23,800.00 714.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 356,458.96
Dibulatkan 356,459.00
J-10 1 M2 Jalusi Mati Kusen Kayu kamper Medan
- Kayu Papan Kamper Medan M3 0.0600 5,692,600.00 341,556.00
- Paku Biasa " - 1" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.5000 42,000.00 21,000.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0250 80,000.00 2,000.00
Jumlah 513,126.00
Dibulatkan 513,126.00
J-11 1 M2 Pintu Triplek Rangkap, Rangka Kayu Borneo Super
- Kayu Papan Borneo Super M3 0.0196 5,595,800.00 109,677.68
- Paku Biasa " - 1" Kg 0.0300 23,800.00 714.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 354,561.68
Dibulatkan 354,562.00
J-12 1 M2 Pintu Teakwood Rangkap, rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.3000 23,900.00 7,170.00
- Teakwood 4 mm Lbr 1.0000 131,700.00 131,700.00
- Pekerja Oh 0.6000 42,000.00 25,200.00
- Tukang Kayu Oh 2.0000 65,000.00 130,000.00
- Kepala Tukang Oh 0.2000 75,000.00 15,000.00
- Mandor Oh 0.0300 80,000.00 2,400.00
Jumlah 430,184.96
Dibulatkan 430,185.00
J-13 1 M2 Pintu Triplek & Formika, Rangka Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.8000 23,900.00 19,120.00
- Triplek 120 x 240 x 0,4 cm Lbr 1.0000 64,400.00 64,400.00
- Formica 3" x 6" Lbr 0.5000 132,900.00 66,450.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 486,734.96
Dibulatkan 486,735.00
M2 Pintu Teakwood & Formika, Rangka Kayu Kamper
J-14 1
Medan (dipolitur)
- Kayu Papan Kamper Medan M3 0.0196 5,692,600.00 111,574.96
- Paku Biasa " - 1" Kg 0.3000 23,800.00 7,140.00
- Lem Kayu Ltr 0.8000 23,900.00 19,120.00
- Teakwood 120 x 240 x 0,4 cm Lbr 1.0000 131,700.00 131,700.00
- Formica 4" x 8" Lbr 0.5000 238,100.00 119,050.00
- Pekerja Oh 0.8000 42,000.00 33,600.00
- Tukang Kayu Oh 2.5000 65,000.00 162,500.00
- Kepala Tukang Oh 0.2500 75,000.00 18,750.00
- Mandor Oh 0.0400 80,000.00 3,200.00
Jumlah 606,634.96
Dibulatkan 606,635.00
J-15 1 M3 Kuda-kuda Kayu Kamper Medan
- Kayu Balok Kamper Medan M3 1.1000 5,692,600.00 6,261,860.00
- Besi Strip Kg 15.0000 26,800.00 402,000.00
- Paku Biasa 2" - 5" Kg 0.8000 23,800.00 19,040.00
- Pekerja Oh 4.0000 42,000.00 168,000.00
- Tukang Kayu Oh 12.0000 65,000.00 780,000.00
- Kepala Tukang Oh 1.2000 75,000.00 90,000.00
- Mandor Oh 0.2000 80,000.00 16,000.00
Jumlah 7,736,900.00
Dibulatkan 7,736,900.00
J-16 1 M3 Kuda-kuda Kayu Borneo Super
- Kayu balok Borneo super M3 1.1000 5,280,000.00 5,808,000.00
- Besi Strip Kg 15.0000 26,800.00 402,000.00
- Paku Biasa 2" - 5" Kg 0.8000 23,800.00 19,040.00
- Pekerja Oh 4.0000 42,000.00 168,000.00
- Tukang Kayu Oh 12.0000 65,000.00 780,000.00
- Kepala Tukang Oh 1.2000 75,000.00 90,000.00
- Mandor Oh 0.2000 80,000.00 16,000.00
Jumlah 7,283,040.00
Dibulatkan 7,283,040.00
J-17 1 M2 Kaso + Reng Genteng Plentong Kayu Borneo Super
- Kayu balok Borneo super m3 0.0120 5,280,000.00 63,360.00
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 78,780.00
Dibulatkan 78,780.00
J-18 1 M2 Kaso + Reng Genteng Beton Kayu Borneo Super
- Kayu balok Borneo super M3 0.0140 5,280,000.00 73,920.00
- Paku Biasa 2" - 5" Kg 0.1500 23,800.00 3,570.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.1000 65,000.00 6,500.00
- Kepala Tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 89,340.00
Dibulatkan 89,340.00
J-19 1 M' Lisplang uk (3x20)cm, Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0072 5,823,400.00 41,928.48
- Paku Biasa 2" - 5" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang Kayu Oh 0.2000 65,000.00 13,000.00
- Kepala Tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 62,218.48
Dibulatkan 62,218.00
J-20 1 M' Lisplang uk (3x30)cm, Kayu Kamper Medan
- Kayu Papan Kamper Medan M3 0.0110 5,692,600.00 62,618.60
- Paku Biasa 2" - 5" Kg 0.0500 23,800.00 1,190.00
- Pekerja Oh 0.1100 42,000.00 4,620.00
- Tukang Kayu Oh 0.2200 65,000.00 14,300.00
- Kepala Tukang Oh 0.0220 75,000.00 1,650.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 84,778.60
Dibulatkan 84,779.00
J-21 1 M List Plafond + kayu Profil 10 cm
- Kayu Profil 10 cm M' 1.0500 29,400.00 30,870.00
- Pekerja Oh 0.0210 42,000.00 882.00
- Tukang Kayu Oh 0.0210 65,000.00 1,365.00
- Kepala Tukang Oh 0.0020 75,000.00 150.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 33,347.00
Dibulatkan 33,347.00
Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium

Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium


Diposkan : 01 Juni 2014
Oleh : Endang Kusman

No. URAIAN SAT VOLUME HARGA SAT HARGA


(Rp) (Rp)
K-01 1 Kg Besi profil
- Besi profil WF Kg 1.1000 24,000.00 26,400.00
- Meni besi Kg 0.0800 30,400.00 2,432.00
- Pekerja Oh 0.0600 42,000.00 2,520.00
- Tukang besi Oh 0.0060 65,000.00 390.00
- Kepala tukang Oh 0.0060 75,000.00 450.00
- Mandor Oh 0.0003 80,000.00 24.00
Jumlah 32,216.00
Dibulatkan 32,216.00
K-02 1 Kg Perakitan baja
- Solar m' 0.0100 7,150.0000 71.50
- Minyak pelumas m' 0.0010 55,000.0000 55.00
- Sewa alat jam 0.0080 100,000.0000 800.00
- Pekerja Oh 0.0010 42,000.0000 42.00
- Tukang besi Oh 0.00001 65,000.0000 0.65
- Kepala tukang Oh 0.00001 75,000.0000 0.75
- Mandor Oh 0.00005 80,000.0000 4.00
Jumlah 973.90
Dibulatkan 974.00
K-03 1 Cm Pengelasan dengan las listrik
- kawat las kg 0.0400 23,600.00 944.00
- Solar ltr 0.0300 7,150.00 214.50
- Minyak pelumas ltr 0.0040 55,000.00 220.00
- Sewa alat jam 0.0170 100,000.00 1,700.00
- Pekerja org 0.0040 42,000.00 168.00
- Tukang org 0.0020 65,000.00 130.00
- Kepala Tukang org 0.0002 75,000.00 15.00
- Mandor org 0.0002 80,000.00 16.00
Jumlah 2,463.50
Dibulatkan 2,464.00
K-04 1 m2 Pintu Rolling Door
- Rolling door M2 1.0000 306,600.00 306,600.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang besi Oh 1.5000 65,000.00 97,500.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 456,491.00
Dibulatkan 456,491.00
K-05 1 m2 Pintu Alluminium Natural
- Pintu alluminium natural m2 1.0000 211,800.00 211,800.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang besi Oh 1.0500 65,000.00 68,250.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 332,441.00
Dibulatkan 332,441.00
K-06 1 m2 Terali Besi
- Besi strip 2 x 3 m' 11.5000 5,500.00 63,250.00
- Pekerja Oh 1.2000 42,000.00 50,400.00
- Tukang las Oh 1.2000 65,000.00 78,000.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0006 80,000.00 48.00
Jumlah 192,598.00
Dibulatkan 192,598.00
K-07 1 m2 Kawat Harmonika 4 cm
- Kawat harmonika M2 1.1000 35,900.00 39,490.00
- Paku biasa " - 1" kg 0.0200 23,800.00 476.00
- Papan kayu kamper M2 0.0018 5,692,600.00 10,246.68
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Tukang kayu Oh 0.1000 65,000.00 6,500.00
- Kepala tukang Oh 0.0100 75,000.00 750.00
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 62,062.68
Dibulatkan 62,063.00
K-08 1 m' Talang Datar, Seng BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.0150 23,800.00 357.00
- Kayu papan borneo super M3 0.0096 5,595,800.00 53,719.68
- Flincote / meni besi Kg 0.2500 30,400.00 7,600.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0013 80,000.00 104.00
Jumlah 117,796.73
Dibulatkan 117,797.00
K-09 1 m' Talang Miring, Seng BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.0150 23,800.00 357.00
- Kayu papan borneo super M3 0.0190 5,595,800.00 106,320.20
- Flincote / meni besi Kg 0.3000 30,400.00 9,120.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.4000 65,000.00 26,000.00
- Kepala tukang Oh 0.0250 75,000.00 1,875.00
- Mandor Oh 0.0013 80,000.00 100.00
Jumlah 174,013.25
Dibulatkan 174,013.00
1 m' Talang 1/2 lingkaran D-15 cm, seng pelat
K-10
BJLS 28 lebar 90 cm
- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05
- Paku biasa " - 1" Kg 0.1000 23,800.00 2,380.00
- Kayu papan borneo super kg 0.0190 5,595,800.00 106,320.20
- Besi strip Kg 0.5000 26,800.00 13,400.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Tukang kayu Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0080 80,000.00 640.00
Jumlah 172,631.25
Dibulatkan 172,631.00
1 m' Pasang kusen pintu/jendela alluminium
K-11
natural 4"
- Alumunium profil natural 4" m' 1.1000 151,100.00 166,210.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 179,301.50
Dibulatkan 179,302.00
1 m' Pasang kusen pintu/jendela alluminium
K-12
warna 4"
- Alumunium profil warna 4" m' 1.1000 163,000.00 179,300.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 192,391.50
Dibulatkan 192,392.00
1 m' Pasang kusen pintu/jendela alluminium
K-13
natural 3"
- Alumunium profil natural 3" m' 1.1000 81,000.00 89,100.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 102,191.50
Dibulatkan 102,192.00
1 m' Pasang kusen pintu/jendela alluminium
K-14
warna 3"
- Alumunium profil warna 3" m' 1.1000 102,000.00 112,200.00
- Skrup fixer bh 2.0000 250.00 500.00
- Sealant m' 1.0000 7,500.00 7,500.00
- Pekerja Oh 0.0430 42,000.00 1,806.00
- Tukang kayu Oh 0.0430 65,000.00 2,795.00
- Kepala tukang Oh 0.0043 75,000.00 322.50
- Mandor Oh 0.0021 80,000.00 168.00
Jumlah 125,291.50
Dibulatkan 125,292.00
K-15 1 m2 Pintu alluminium strip lebar 8 cm
- Alumunium profil 4" natural m' 4.4000 151,100.00 664,840.00
- Alumunium strip 6mm m2 1.0500 171,800.00 180,390.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0042 80,000.00 336.00
Jumlah 855,298.50
Dibulatkan 855,299.00
1 m2 Pintu/jendela kaca rangka alluminium
K-16
natural 4"
- Alumunium profil natural 4" m' 4.4000 151,100.00 664,840.00
- Profil alluminium T m' 4.5000 12,200.00 54,900.00
- Sealant tube 0.2700 7,500.00 2,025.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 731,897.50
Dibulatkan 731,898.00
1 m2 Pintu/jendela kaca rangka alluminium
K-17
warna 4"
- Alumunium profil warna 4" m' 4.4000 163,000.00 717,200.00
- Profil alluminium T m' 4.5000 12,200.00 54,900.00
- Sealant tube 0.2700 7,500.00 2,025.00
- Pekerja Oh 0.0850 42,000.00 3,570.00
- Tukang kayu Oh 0.0850 65,000.00 5,525.00
- Kepala tukang Oh 0.0085 75,000.00 637.50
- Mandor Oh 0.0050 80,000.00 400.00
Jumlah 784,257.50
Dibulatkan 784,258.00
K-18 1 m2 Jendela nako & teralis (10 klips)
- Jendela nako (rangka + kaca 5 mm) m2 1.1000 300,000.00 330,000.00
- Paku skrup 1cm - 2,5cm bh 10.0000 250.00 2,500.00
- Besi strip m' 7.0000 5,500.00 38,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 393,980.00
Dibulatkan 393,980.00
K-19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku
- Besi siku L 30.30.3 Kg 15.0000 24,000.00 360,000.00
- Baja pelat Kg 32.8000 24,000.00 787,200.00
- kawat las Kg 0.0500 23,600.00 1,180.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang kayu Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0010 80,000.00 80.00
Jumlah 1,171,360.00
Dibulatkan 1,171,360.00
1 m2 Rangka jendela besi square tube (5 x 5)
K-20
cm
- Besi square tube M 4.7600 7,300.00 34,748.00
- Besi lis kaca (1 x 1) cm Kg 4.5220 24,000.00 108,528.00
- Pengelasan Cm 20.0000 2,464.00 49,280.00
- Pekerja Oh 0.6500 42,000.00 27,300.00
- Tukang kayu Oh 0.6500 65,000.00 42,250.00
- Kepala tukang Oh 0.0650 75,000.00 4,875.00
- Mandor Oh 0.0320 80,000.00 2,560.00
Jumlah 269,541.00
Dibulatkan 269,541.00
K-21 1 m2 Pintu lipat (folding door) bahan besi
- Pintu lipat M2 1.0000 501,700.00 501,700.00
- Pekerja Oh 1.0500 42,000.00 44,100.00
- Tukang kayu Oh 1.0500 65,000.00 68,250.00
- Kepala tukang Oh 0.1050 75,000.00 7,875.00
- Mandor Oh 0.0052 80,000.00 416.00
Jumlah 622,341.00
Dibulatkan 622,341.00
K-22 1 m2 Tirai (venetions blinds and vertical blinds)
- Tirai M2 1.0000 537,300.00 537,300.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang kayu Oh 0.3500 65,000.00 22,750.00
- Kepala tukang Oh 0.0350 75,000.00 2,625.00
- Mandor Oh 0.0018 80,000.00 144.00
Jumlah 577,519.00
Dibulatkan 577,519.00
Kembali Ke Analisa AHS SNI

Analisa Harga Satuan Pekerjaan Sanitasi

Diposkan : 04 Juni 2014


Oleh : Endang Kusman

No. URAIAN SAT VOLUME HARGA SAT HARGA


(Rp) (Rp)
M-01 1 Buah Closet jongkok Porselen Standar
Closet jongkok bh 1.00 188,200.00 188,200.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukang batu org 1.5000 65,000.00 97,500.00
Kepala Tukang org 1.5000 75,000.00 112,500.00
Mandor org 0.1600 80,000.00 12,800.00
Jumlah 463,770.00
Dibulatkan 463,770.00
M-02 1 Buah Urinoir
Urinoir bh 1.00 1,773,400.00 1,773,400.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.0000 42,000.00 42,000.00
Tukang batu org 1.0000 65,000.00 65,000.00
Kepala Tukang org 0.1000 75,000.00 7,500.00
Mandor org 0.0010 80,000.00 80.00
Perlengkapan 30 % harga urinoir lot 0.3000 1,773,400.00 532,020.00
Jumlah 2,430,770.00
Dibulatkan 2,430,770.00
M-03 1 Buah Wastafel
wastafel standar unit 1.00 1,012,700.00 1,012,700.00
P.C (50 gk) Kg 6.00 1,406.00 8,436.00
Pasir pasang m3 0.01 233,400.00 2,334.00
Pekerja org 1.2000 42,000.00 50,400.00
Tukang batu org 1.4500 65,000.00 94,250.00
Kepala Tukang org 0.1500 75,000.00 11,250.00
Mandor org 0.1000 80,000.00 8,000.00
Perlengkapan 12 % harga wastafel lot 0.1200 1,773,400.00 212,808.00
Jumlah 1,400,178.00
Dibulatkan 1,400,178.00
M-04 1 Buah bak Mandi Fibreglass Volume 0,30 m3
Bak fibreglass 0.60m x 0.60m bh 1.00 255,300.00 255,300.00
Pekerja org 1.8000 42,000.00 75,600.00
Tukang batu org 2.7000 65,000.00 175,500.00
Kepala Tukang org 0.5400 75,000.00 40,500.00
Mandor org 0.1100 80,000.00 8,800.00
Perlengkapan 18 % harga bak lot 0.1800 255,300.00 45,954.00
Jumlah 601,654.00
Dibulatkan 601,654.00
M-05 1 M' Saluran Air Limbah Buis beton d = 30 cm - 60 cm
Buis beton 30 cm bh 1.10 61,700.00 67,870.00
Bata merah bh 25.00 775.00 19,375.00
P.C (50 gk) Kg 10.300 1,406.00 14,481.80
Pasir pasang m3 0.061 233,400.00 14,237.40
Pasir urug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukang batu org 0.1900 65,000.00 12,350.00
Kepala Tukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 159,314.90
Dibulatkan 159,315.00
M-06 1 Buah Bak Kontrol Pas Bata Merah Uk (60 x 60) cm
Bata merah bh 186.00 775.00 144,150.00
P.C (50 gk) Kg 114.000 1,406.00 160,284.00
Pasir pasang m3 0.184 233,400.00 42,945.60
Batu pecah 2/3 m3 0.033 211,100.00 6,966.30
Besi beton m3 4.850 16,500.00 80,025.00
Pasir beton m3 0.120 255,400.00 30,648.00
Pekerja org 2.1600 42,000.00 90,720.00
Tukang batu org 0.7200 65,000.00 46,800.00
Kepala Tukang org 0.0720 75,000.00 5,400.00
Mandor org 0.1080 80,000.00 8,640.00
Tukang gali org 0.1000 42,000.00 4,200.00
Jumlah 620,778.90
Dibulatkan 620,779.00
M-07 1 Buah Bak Kontrol Pas Bata Merah Uk (30 x 30) cm
Bata merah bh 53.00 775.00 41,075.00
P.C (50 gk) Kg 44.000 1,406.00 61,864.00
Pasir pasang m3 0.070 233,400.00 16,338.00
Batu pecah 2/3 m3 0.070 211,100.00 14,777.00
Besi beton m3 1.600 16,500.00 26,400.00
Pasir beton m3 0.060 255,400.00 15,324.00
Pekerja org 3.2000 42,000.00 134,400.00
Tukang batu org 1.0150 65,000.00 65,975.00
Kepala Tukang org 0.0015 75,000.00 112.50
Mandor org 0.0160 80,000.00 1,280.00
Jumlah 377,545.50
Dibulatkan 377,546.00
M-08 1 M' Pipa PVC 1/2" (AW)
Pipa pvc 1/2" m' 1.2000 10,025.00 12,030.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 12,030.00 4,210.50
Jumlah 22,246.50
Dibulatkan 22,247.00
M-09 1 M' Pipa PVC 1" (AW)
Pipa pvc 1" m' 1.2000 15,800.00 18,960.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 18,960.00 6,636.00
Jumlah 31,602.00
Dibulatkan 31,602.00
M-10 1 M' Pipa PVC 11/2" (AW)
Pipa pvc 11/2" m' 1.2000 26,475.00 31,770.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 31,770.00 11,119.50
Jumlah 48,895.50
Dibulatkan 48,896.00
M-11 1 M' Pipa PVC 2" (AW)
Pipa pvc 2" m' 1.2000 27,675.00 33,210.00
Pekerja org 0.0360 42,000.00 1,512.00
Tukang batu org 0.0600 65,000.00 3,900.00
Kepala Tukang org 0.0060 75,000.00 450.00
Mandor org 0.0018 80,000.00 144.00
Perlengkapan 35 % harga pipa lot 0.3500 31,770.00 11,119.50
Jumlah 50,335.50
Dibulatkan 50,336.00
M-12 1 M' Pipa PVC 4" (AW)
Pipa pvc 4" m' 1.2000 86,975.00 104,370.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukang batu org 0.1350 65,000.00 8,775.00
Kepala Tukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan 35 % harga pipa lot 0.3500 104,370.00 36,529.50
Jumlah 154,417.00
Dibulatkan 154,417.00
M-13 1 M' Pipa PVC 3/4" (AW)
Pipa pvc 3/4" m' 1.2000 13,050.00 15,660.00
Pekerja org 0.0810 42,000.00 3,402.00
Tukang batu org 0.1350 65,000.00 8,775.00
Kepala Tukang org 0.0135 75,000.00 1,012.50
Mandor org 0.0041 80,000.00 328.00
Perlengkapan 35 % harga pipa lot 0.3500 15,660.00 5,481.00
Jumlah 34,658.50
Dibulatkan 34,659.00
M-14 1 Buah Bak Cuci piring Stainless steel
Bak cuci stainless steel + asesoris lengkap bh 1.0000 397,800.00 397,800.00
Pekerja org 0.0300 42,000.00 1,260.00
Tukang batu org 0.3000 65,000.00 19,500.00
Kepala Tukang org 0.0300 75,000.00 2,250.00
Mandor org 0.0015 80,000.00 120.00
Jumlah 420,930.00
Dibulatkan 420,930.00
M-15 1 Buah Kran 1/2" - 3/4"
Kran air bh 1.0000 40,900.00 40,900.00
Seal tape bh 0.0250 4,200.00 105.00
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 49,075.00
Dibulatkan 49,075.00
M-16 1 Buah Floor Drain
Floor drain bh 1.0000 66,600.00 66,600.00
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 74,670.00
Dibulatkan 74,670.00
M-17 1 M' Grafel beton U 20 cm -60 cm
Pipa beton U bh 1.1000 44,300.00 48,730.00
Bata merah bh 12.0000 775.00 9,300.00
P.C (50 gk) zak 0.1030 1,406.00 144.82
Pasir pasang m3 0.0305 233,400.00 7,118.70
Pasir urug m3 0.0345 175,300.00 6,047.85
Pekerja org 0.0100 42,000.00 420.00
Tukang batu org 0.1000 65,000.00 6,500.00
Kepala Tukang org 0.0100 75,000.00 750.00
Mandor org 0.0050 80,000.00 400.00
Jumlah 79,411.37
Dibulatkan 79,411.00
M-18 1 M' Pasang Talang Plastik PVC U 15 cm (AW)
Talang plastik PVC m' 1.05000 60,000.00 63,000.00
Perlengkapan 35 % harga talang lot 0.3500 63,000.00 22,050.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukang batu org 0.4000 65,000.00 26,000.00
Kepala Tukang org 0.0250 75,000.00 1,875.00
Mandor org 0.0013 80,000.00 100.00
Jumlah 119,325.00
Dibulatkan 119,325.00
M-19 1 M' Saluran Air Limbah Buis Beton 60 cm
Buis beton 60 cm bh 1.10 130,900.00 143,990.00
Bata merah bh 25.00 775.00 19,375.00
P.C (50 gk) zak 0.206 1,406.00 289.64
Pasir pasang m3 0.061 233,400.00 14,237.40
Pasir urug m3 0.069 175,300.00 12,095.70
Pekerja org 0.3800 42,000.00 15,960.00
Tukang batu org 0.1900 65,000.00 12,350.00
Kepala Tukang org 0.0190 75,000.00 1,425.00
Mandor org 0.0190 80,000.00 1,520.00
Jumlah 221,242.74
Dibulatkan 221,243.00
M-20 1 M' Pasang Talang Seng Datar
Seng pelat 3" x 6" lbr 0.50000 20,801.00 10,400.50
Paku kg 0.01500 23,400.00 351.00
Kayu kelas II m3 0.00960 2,850,000.00 27,360.00
Meni besi kg 0.2500 30,400.00 7,600.00
Pekerja org 0.1500 42,000.00 6,300.00
Tukang batu org 0.4000 65,000.00 26,000.00
Kepala Tukang org 0.0250 75,000.00 1,875.00
Mandor org 0.0013 80,000.00 100.00
Jumlah 79,986.50
Dibulatkan 79,987.00
M-21 1 Buah Closet Duduk
Closet duduk bh 1.00 1,724,700.00 1,724,700.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukang batu org 1.1000 65,000.00 71,500.00
Kepala Tukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan 6 % harga closet lot 0.0600 1,724,700.00 103,482.00
Jumlah 2,051,157.00
Dibulatkan 2,051,157.00
M-22 1 Buah Tangki Air fibreglass Volume 1 m3
Bak fibreglass kapasitas 1 m3 bh 1.00 1,316,400.00 1,316,400.00
Pekerja org 3.3000 42,000.00 138,600.00
Tukang batu org 1.1000 65,000.00 71,500.00
Kepala Tukang org 0.0010 75,000.00 75.00
Mandor org 0.1600 80,000.00 12,800.00
Perlengkapan 6 % harga bak lot 0.0600 1,316,400.00 78,984.00
Jumlah 1,618,359.00
Dibulatkan 1,618,359.00
M-23 1 Unit Septictank 2x1,50x1,50 m + Rembesan
Galian tanah m3 4.500 26,252.00 118,134.00
Pasir urug m3 0.214 175,300.00 37,514.20
lantai kerja m3 2.250 716,798.00 1,612,795.50
Pas bata adk 1pc : 3ps m2 15.000 220,267.10 3,304,006.50
Pelat beton K-225 m3 0.300 6,438,864.00 1,931,659.20
Plesteran adk 1pc : 3ps m2 15.000 41,301.82 619,527.30
Pipa PVC 4" jenis AW m' 5.400 256,800.00 1,386,720.00
Pipa GIP 1 1/2" m' 5.000 46,750.00 233,750.00
Galian tanah untuk rembesan m3 3.375 20,000.00 67,500.00
Pas ijuk kg 5.400 23,400.00 126,360.00
Urugan kerikil 3/5 m3 1.050 205,000.00 215,250.00
Pipa PVC 4" berlubang jenis AW m' 9.000 36,700.00 330,300.00
Urugan dan perataan tanah m3 1.125 34,584.00 38,907.00
Jumlah 10,022,423.70
Dibulatkan 10,022,424.00
M-24 1 Unit Septictank 1x1,50x1,50 m + Rembesan
Galian tanah m3 2.250 20,000.00 45,000.00
Pasir urug m3 0.107 175,300.00 18,757.10
lantai kerja m3 1.125 716,798.00 806,397.75
Pas bata adk 1pc : 3ps m2 7.500 220,267.10 1,652,003.25
Pelat beton K-225 m3 0.150 6,438,864.00 965,829.60
Plesteran adk 1pc : 3ps m2 7.500 41,301.82 309,763.65
Pipa PVC 4" jenis AW m' 9.000 256,800.00 2,311,200.00
Pipa GIP 1 1/2" m' 2.500 46,750.00 116,875.00
Galian tanah untuk rembesan m3 1.688 20,000.00 33,760.00
Pas ijuk kg 2.700 23,400.00 63,180.00
Urugan kerikil 3/5 m3 0.525 205,000.00 107,625.00
Pipa PVC 4" berlubang jenis AW m' 9.000 36,700.00 330,300.00
Urugan dan perataan tanah m3 0.563 34,584.00 19,470.79
Jumlah 6,780,162.14
Dibulatkan 6,780,162.00

Kembali ke Analisa SNI

Analisa Harga Satuan Pekerjaan Pengecatan

Diposkan : 05 Juni 2014


Oleh : Endang Kusman

No. URAIAN SAT VOLUME HARGA SAT HARGA

N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama


- Soda api Kg 0.0500 35,600.00 1,780.00
- Pekerja Oh 0.1500 42,000.00 6,300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 8,280.00
Dibulatkan 8,280.00
N-02 1 M2 Mendempul Dan Menggosok Kayu
- Dempul Kg 0.0800 35,800.00 2,864.00
- Minyak cat Kg 0.0200 38,400.00 768.00
- Batu apung Kg 0.0100 29,600.00 296.00
- Pekerja Oh 0.0400 42,000.00 1,680.00
- Tukang cat Oh 0.0400 65,000.00 2,600.00
- Kepala tukang Oh 0.0040 75,000.00 300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 8,708.00
Dibulatkan 8,708.00
N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve
- Plamir Kg 0.1500 25,000.00 3,750.00
- Cat dasar Kg 0.1700 30,000.00 5,100.00
- Cat penutup setara sieve 2x Kg 0.1700 41,700.00 7,089.00
- Pekerja Oh 0.0700 42,000.00 2,940.00
- Tukang cat Oh 0.0750 65,000.00 4,875.00
- Kepala tukang Oh 0.0075 75,000.00 562.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 24,516.50
Dibulatkan 24,517.00
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve
- Cat meni Kg 0.2000 30,400.00 6,080.00
- Plamir Kg 0.1500 25,000.00 3,750.00
- Cat dasar Kg 0.1700 30,000.00 5,100.00
- Cat penutup 3x setara sieve Kg 0.3500 41,700.00 14,595.00
- Pekerja Oh 0.0700 42,000.00 2,940.00
- Tukang cat Oh 0.1050 65,000.00 6,825.00
- Kepala tukang Oh 0.0040 75,000.00 300.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 39,790.00
Dibulatkan 39,790.00
N-05 1 M2 Pelaburan Bidang Kayu dengan Politur
- Politur Ltr 0.1500 48,000.00 7,200.00
- Politur jadi Ltr 0.3720 112,700.00 41,924.40
- Ampelas Lbr 2.0000 5,000.00 10,000.00
- Tukang cat Oh 0.0600 65,000.00 3,900.00
- Kepala tukang Oh 0.0160 75,000.00 1,200.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 64,424.40
Dibulatkan 64,424.00
N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
- Residu atau ter Ltr 0.3500 8,100.00 2,835.00
- Pekerja Oh 0.1000 42,000.00 4,200.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 7,515.00
Dibulatkan 7,515.00
N-07 1 M2 Pengecatan Tembok Baru Setara ICI
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 2x setara ICI Kg 0.2600 75,000.00 19,500.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.0630 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 30,607.50
Dibulatkan 30,608.00
N-08 1 M2 Pengecatan Tembok Lama Setara ICI
- Cat dasar Kg 0.1200 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.1800 75,000.00 13,500.00
- Pekerja Oh 0.0280 42,000.00 1,176.00
- Tukang cat Oh 0.0420 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 21,521.00
Dibulatkan 21,521.00
N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI
- Cat tembok setara ICI Kg 0.2000 75,000.00 15,000.00
- Plamir tembok Kg 0.1600 25,000.00 4,000.00
- Rol cat Bh 0.0100 32,500.00 325.00
- Steger werk Ls 1.0000 1,000.00 1,000.00
- Ampelas Lbr 0.5000 5,000.00 2,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang cat Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 53,775.00
Dibulatkan 53,775.00
N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.2000 25,000.00 5,000.00
- Plamir tembok Kg 0.1600 25,000.00 4,000.00
- Rol cat Bh 0.0100 32,500.00 325.00
- Steger werk Ls 1.0000 1,000.00 1,000.00
- Ampelas Lbr 0.5000 5,000.00 2,500.00
- Pekerja Oh 0.2000 42,000.00 8,400.00
- Tukang cat Oh 0.3000 65,000.00 19,500.00
- Kepala tukang Oh 0.0300 75,000.00 2,250.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 43,775.00
Dibulatkan 43,775.00
N-10-r'1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.1300 25,000.00 3,250.00
- Plamir tembok Kg 0.1100 25,000.00 2,750.00
- Rol cat Bh 0.1000 32,500.00 3,250.00
- Steger werk Ls 0.6700 1,000.00 670.00
- Ampelas Lbr 0.3300 5,000.00 1,650.00
- Pekerja Oh 0.1300 42,000.00 5,460.00
- Tukang cat Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 32,330.00
Dibulatkan 32,330.00
N-11 1 M2 Memasang Wallpaper
- Wallpaper m2 1.2000 55,700.00 66,840.00
- Lem Perekat Kg 0.2500 35,700.00 8,925.00
- Pekerja Oh 0.3500 42,000.00 14,700.00
- Tukang cat Oh 0.1750 65,000.00 11,375.00
- Kepala tukang Oh 0.0170 75,000.00 1,275.00
- Mandor Oh 0.0017 80,000.00 136.00
Jumlah 103,251.00
Dibulatkan 103,251.00
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
- Meni besi Kg 0.1000 30,400.00 3,040.00
- Kuas 3" Bh 0.0100 16,000.00 160.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.2000 65,000.00 13,000.00
- Kepala tukang Oh 0.0200 75,000.00 1,500.00
- Mandor Oh 0.0100 80,000.00 800.00
Jumlah 19,340.00
Dibulatkan 19,340.00
N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah
- Meni besi Kg 0.1000 30,400.00 3,040.00
- Kuas 3" Bh 0.0100 16,000.00 160.00
- Kayu perancah m3 0.0020 2,069,800.00 4,139.60
- Pekerja Oh 0.2500 42,000.00 10,500.00
- Tukang cat Oh 0.2250 65,000.00 14,625.00
- Kepala tukang Oh 0.0225 75,000.00 1,687.50
- Mandor Oh 0.0075 80,000.00 600.00
Jumlah 34,752.10
Dibulatkan 34,752.00
N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um
- Cat besi setara ICI Kg 0.3000 67,700.00 20,310.00
- Pekerja Oh 0.0060 42,000.00 252.00
- Tukang cat Oh 0.0600 65,000.00 3,900.00
- Kepala tukang Oh 0.0120 75,000.00 900.00
- Mandor Oh 0.0060 80,000.00 480.00
Jumlah 25,842.00
Dibulatkan 25,842.00
N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 2x setara vinilex Kg 0.2600 25,000.00 6,500.00
- Pekerja Oh 0.0200 42,000.00 840.00
- Tukang cat Oh 0.0630 65,000.00 4,095.00
- Kepala tukang Oh 0.0063 75,000.00 472.50
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 17,607.50
Dibulatkan 17,608.00
N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
- Plamir tembok Kg 0.1000 25,000.00 2,500.00
- Cat dasar Kg 0.1000 30,000.00 3,000.00
- Cat penutup 3x setara vinilex Kg 0.3900 25,000.00 9,750.00
- Pekerja Oh 0.0300 42,000.00 1,260.00
- Tukang cat Oh 0.0945 65,000.00 6,142.50
- Kepala tukang Oh 0.0095 75,000.00 712.50
- Mandor Oh 0.0038 80,000.00 304.00
Jumlah 23,669.00
Dibulatkan 23,669.00
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex
- Cat dasar Kg 0.1200 30,000.00 3,600.00
- Cat penutup 2 x Kg 0.1800 25,000.00 4,500.00
- Pekerja Oh 0.0280 42,000.00 1,176.00
- Tukang cat Oh 0.0420 65,000.00 2,730.00
- Kepala tukang Oh 0.0042 75,000.00 315.00
- Mandor Oh 0.0025 80,000.00 200.00
Jumlah 12,521.00
Dibulatkan 12,521.00

Kembali ke AHS-SNI

Harga Satuan Upah Kerja Bangunan - AHS 2011

NO URAIAN SATUAN UPAH (Rp.)


1 Mandor Org/hr Rp 80,000.00
2 Kepala Tukang Batu Org/hr Rp 75,000.00
3 Kepala Tukang Kayu Org/hr Rp 75,000.00
4 Kepala Tukang Besi Org/hr Rp 75,000.00
5 Kepala Tukang Cat Org/hr Rp 75,000.00
6 Kepala Tukang Listrik Org/hr Rp 75,000.00
7 Kepala Tukang Org/hr Rp 75,000.00
8 Tukang Batu Org/hr Rp 65,000.00
9 Tukang Kayu Org/hr Rp 65,000.00
10 Tukang Besi/Baja Org/hr Rp 65,000.00
11 Tukang Cat Org/hr Rp 65,000.00
12 Tukang Listrik Org/hr Rp 65,000.00
13 Tukang Pipa Org/hr Rp 65,000.00
14 Tukang Plitur Org/hr Rp 65,000.00
15 Tukang Taman Org/hr Rp 65,000.00
16 Tukang Org/hr Rp 65,000.00
17 Pembantu Tukang Org/hr Rp 42,000.00
18 Pekerja Biasa Org/hr Rp 42,000.00
19 Penjaga Malam Org/hr Rp 42,000.00
20 Sopir Org/hr Rp 65,000.00
21 Operator Org/hr Rp 75,000.00
22 Mekanik Org/hr Rp 65,000.00
23 Pembantu Sopir Org/hr Rp 42,000.00
24 Pembantu Operator Org/hr Rp 50,000.00
25 Pembantu Mekanik Org/hr Rp 42,000.00
harga sudah termasuk PPN dan keuntungan

Harga Satuan Bahan Bangunan - AHS 2011

NO MATERIAL SAT HARGA (Rp)

A. AGREGAT KASAR,BAHAN PEREKAT & BAHAN JADINYA

1 Pasir Urug m3 175,300.00


2 Tanah Urug Pilihan m3 89,200.00
3 Sirtu m3 203,500.00
4 Pasir Teras m3 174,200.00
5 Pasir Pasang Kali m3 233,400.00
6 Pasir Beton m3 255,400.00
7 Abu Batu m3 259,000.00
8 Batu Gosok ( Apung ) kg 29,600.00
9 Batu Pecah Mesin 1/2 m3 223,600.00
10 Batu Pecah Mesin 2/3 m3 211,100.00
11 Batu Pecah Mesin 3/5 m3 205,000.00
12 Batu Pecah Mesin 5/7 m3 196,000.00
13 Batu Belah Pondasi m3 205,500.00
14 Batu Bronjol ( Untuk Bronjong ) m3 180,800.00
15 Batu Koral Beton Kali m3 172,600.00
16 Batu Tempel Hitam m3 96,600.00
17 Batu Pinggir Beton 10 x 20 x 35 bh 14,100.00
18 Batu Pinggir Beton 15 x 35 x 50 ( K-225 ) bh 73,700.00
19 Batu Telor m3 97,800.00
20 Batako Kecil 8 x 10 x 20 bh 2,000.00
21 Batako Besar 8 x 20 x 30 bh 2,400.00
22 Con Blok 8 x 20 x 40 bh 5,400.00
23 Bata Merah Bakar kelas I bh 775.00
24 Bata Merah Bakar kelas II bh 675.00
25 Bata Merah Oven ( Klingker ) bh 1,800.00
26 Roster Beton 20 x 20 bh 14,800.00
27 Roster Beton 30 x 30 bh 15,500.00
28 Grass Blok 20 x 20 bh 9,700.00
29 Grass Blok 30 x 30 bh 22,500.00
30 Paving Blok Natural 8 cm m2 81,100.00
31 Paving Blok Warna 8 cm m2 108,600.00
32 Paving Blok Natural 6 cm m2 76,000.00
33 Paving Blok Warna 6 cm m2 86,000.00
34 Canstin Paving Blok m1 34,900.00
35 Semen PC /50 kg zak 70,300.00
1,406.00
36 Semen Putih zak 92,700.00
37 Kanstin Jalan Ukuran Besar ( Bina Marga ) 1bh =60cm bh 58,900.00
38 Readymix Beton K500, Tanpa Pompa ( Selang ) m3 1,105,000.00
39 Readymix Beton K400, Tanpa Pompa ( Selang ) m3 903,500.00
40 Readymix Beton K350, Tanpa Pompa ( Selang ) m3 877,500.00
41 Readymix Beton K300, Tanpa Pompa ( Selang ) m3 925,000.00
42 Readymix Beton K225, Tanpa Pompa ( Selang ) m3 850,000.00
43 Readymix Beton K175, Tanpa Pompa ( Selang ) m3 825,000.00
44 Kapur Pasang / Kapur Tembok m3 353,300.00
45 Kapur Sirih kg 18,300.00
46 Semen Warna kg 15,700.00
47 Tanah liat m3 31,300.00
48 Air ltr 3.00
49 Formite/spacer bh 2,500.00
50 Hollow/Con Blok 8 x 20 x 40 bh 5,000.00
51 Hollow/Con Blok 8 x 15 x 40 bh 4,000.00
52 Hollow/Con Blok 8 x 10 x 40 bh 3,000.00

B LABURAN,PENGISI DAN ALATNYA


1 Plamir Tembok kg 25,000.00
2 Cat Tembok ICI Eksterior ( Beton ) lt 120,000.00
3 Cat Tembok ICI Interior ( Plafon Dan Dinding ) lt 75,000.00
4 Cat Tembok Vinilex kg 25,000.00
5 Cat Dasar ICI untuk Interior ( 2 Pelapis ) lt 75,000.00
6 Cat Tembok Sanlek kg 20,000.00
7 Cat Dasar kg 30,000.00
8 Cat Tahan Asam lt 40,000.00
9 Pelapis Alkali ICI ( Cat Dasar Beton Ekterior ) kg 90,000.00
10 Cat Marka / Spotlight kg 185,000.00
11 Water Profing Emulsion ml 70,000.00
12 Water Profing Membrance bh 62,500.00
13 Rool Cat Tembok bh 32,500.00
14 Kape Tembok bh 8,500.00
15 Kape Kayu 5 lt 10,000.00
16 Soligneum 1 Blek kg 25,000.00
17 Plincote m3 29,000.00
18 Penawetan Kayu m3 382,600.00
19 Pegopenan Kayu bh 370,000.00
20 Kwas 3" bh 16,000.00
21 Oker bks 22,000.00
22 Oyan bks 5,200.00
23 Oten ( Pewarna Plitur ) lt 5,500.00
24 Spirtus kg 15,000.00
25 Bahan Pelitur Kripik ( Sirlak India ) kg 110,000.00
26 Dempul Lilin kg 34,200.00
27 Dempul Plitur kg 37,700.00
28 Dempul Halus / Imfra ( Wood Filler ) lt 37,700.00
29 Dempul Jadi kg 35,800.00
30 Politur lt 48,000.00
31 Politur Jadi lt 112,700.00
32 Terpentin kg 19,500.00
33 Tiner A kg 23,900.00
34 Tiner B kg 21,400.00
35 Kumpon lbr 30,800.00
36 Melamik kg 52,500.00
37 Dempul Plastik kg 39,200.00
38 Dempul Duco kg 35,800.00
39 Ampelas lbr 5,000.00
40 Dempul Kayu Cap Kucing kg 24,400.00
41 Meni Kayu / Besi kg 30,400.00
42 Sincromat kg 40,900.00
43 Cat Kayu Sieve lt 41,700.00
44 Cat Besi lt 44,000.00
45 Cat Besi Duco Danaglos / ICI bh 76,300.00
46 Cat Bron kg 67,700.00
47 Karet lis bh 3,300.00
48 Minyak cat kg 38,400.00
49 Glass beet kg 50,100.00
50 Residu lt 8,100.00
C BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu 5 s.d 7 bt 17,700.00
2 Bambu 7 s.d 10 bt 25,000.00
3 Bambu Gombong bt 37,200.00
4 Kayu Kamper Singkil / Kapur ( Kayu Samarinda kls II ) m3 7,094,450.00
5 Kayu Balok Borneo Super m3 5,280,000.00
6 Kayu Papan Borneo Super m3 5,595,800.00
7 Kayu Balok Kamper Medan (Kruing ) m3 5,692,600.00
8 Kayu Papan Kamper Medan (Kruing ) m3 5,823,400.00
9 Kayu Balok Kamper Banjar m3 6,363,600.00
10 Kayu Papan Kamper Banjar m3 6,645,300.00
11 Kayu Balok Kamper Samarinda m3 8,633,700.00
12 Kayu Papan Kamper Samarinda m3 8,724,300.00
13 Kayu Balok Rasamala m3 2,658,000.00
14 Kayu Jati Jatim Tua dia. 40 cm m3 20,772,000.00
15 Kayu Jati Jateng Tua dia. 40 cm m3 22,188,400.00
16 Kayu Jati Jabar Tua dia. 40 cm m3 13,625,400.00
17 Kayu Jati Jabar Tua dia. 40 cm kebawah m3 12,736,100.00
18 Kayu Hutan Kelas I ( Segeng,Mahoni, Laban ) m3 2,069,800.00
19 Kayu Balok Albasia m3 1,870,500.00
20 Kayu Papan Albasia m3 2,071,700.00
21 Dolken 5 s/d 7 bt 22,600.00
22 Dolken 7 s/d 10 bt 28,000.00
23 List Profil Kamper 1 cm m1 8,900.00
24 List Profil Kamper 2 cm m1 10,000.00
25 List Profil Kamper 4 cm m1 14,300.00
26 List Profil Kamper 5 cm m1 17,200.00
27 List Profil Kamper 10 cm m1 29,400.00
28 Pegangan Tangga Profil Jati m1 160,100.00
29 Pegangan Tangga Profil Kamper m1 122,500.00
30 Kayu Kaso 4/6 m3 2,772,000.00
31 Kayu Kaso 5/7 Kamper Medan m3 3,356,800.00
32 Kayu Reng 2/3 Borneo Super m1 2,500.00
33 Kayu Reng 2/3 Kamper Banjar m1 3,300.00
34 Kayu Reng 3/4 Kamper Medan m3 4,000.00
35 Kayu Papan Terentang m3 2,850,000.00
36 Kayu Balok Terentang m3 2,640,000.00
37 Batang Kelapa bt 139,500.00
38 Tali Ijuk kg 23,400.00
39 lapisan Ijuk tebal 10 cm m2 22,000.00
40 Venetion Blind m2 537,300.00
41 Vertikal Blind m2 351,200.00

D BAHAN PENUTUP RANGKA PLAFOND


1 Plafond Enternit 4 mm m2 17,400.00
2 Plafond hardpleks 5 mm 120 x 240 lbr 62,400.00
3 Plafond Asbes Semen 5 mm m2 22,500.00
4 Plafond Asbes Semen 3,5 mm m2 19,500.00
5 Gypsum 120 x 240 t= 9 mm ex DN lbr 79,800.00
6 Gypsum 120 x 240 t= 9 mm ex Luar lbr 83,800.00
7 Tepung gypsum kg 12,500.00
8 Acustik Amstrong 60 x 120 lbr 132,800.00
9 Cotton Plester bh 15,000.00
10 GRC (120 x 240) cm, t = 4 mm lbr 67,500.00
11 Cornice Coumpound zak 75,000.00
12 List gypsum m' 8,500.00

E BAHAN KAYU LAPIS


1 Triplek 3 mm 120 x 240 lbr 61,700.00
2 Triplek 4 mm 120 x 240 lbr 64,400.00
3 Triplek 4 mm ukuran Pintu lbr 56,200.00
4 Triplek 6 mm 120 x 240 lbr 92,000.00
5 Triplek 9 mm 120 x 240 lbr 166,600.00
6 Jabar Wood 4 mm lbr 119,000.00
7 Bilik Bambu ( tanpa kulit ) m2 19,800.00
8 Bilik Bambu ( dengan kulit ) m2 22,700.00
9 Bilik Bambu Hitam Variasi m2 34,200.00
10 Wall paper m2 55,700.00
11 MultiPlek 9 mm 120 x 240 lbr 151,100.00
12 MultiPlek 12 mm 120 x 240 lbr 195,000.00
13 MultiPlek 18 mm 120 x 240 lbr 255,400.00
14 Ply Wood 18 mm 120 x 240 lbr 323,900.00
15 Ply Wood 9 mm 120 x 240 lbr 235,000.00
16 Ply Wood 4 mm 120 x 240 lbr 140,000.00
17 Teak Wood 3 mm 120 x 240 lbr 129,100.00
18 Teak Wood 4 mm 120 x 240 lbr 131,700.00
19 Teak Wood 3 mm 120 x 240 ukuran Pintu lbr 127,200.00
20 Teak Wood ukuran Pintu 4 mm lbr 114,700.00
21 Tacon ( Tahan Bakar ) m2 128,200.00
22 Supercon m2 57,900.00
23 Melamin 4 mm 120 x 240 lbr 89,200.00
24 Melamin TOK 4 mm lbr 133,400.00
25 Formika 120 x 240 lbr 170,000.00
26 Formika ukuran Pintu lbr 132,900.00
27 Formika Warna 4" x 8" lbr 238,100.00

F BAHAN LANTAI DAN PELAPIS DINDING


1 Tegel PC 20 x 20 bh 3,400.00
2 Plin Tegel PC 10 x 20 bh 2,400.00
3 Tegel PC 30 x 30 bh 3,400.00
4 Plin Tegel PC 15 x 30 bh 2,800.00
5 Tegel Warna 20 x 20 bh 3,600.00
6 Plin Tegel Warna 10 x 20 bh 3,400.00
7 Tegel Warna 30 x 30 bh 5,700.00
8 Plin Tegel Warna 15 x 30 bh 6,300.00
9 Tegel Wafel PC 20 x 20 bh 3,200.00
10 Tegel Wafel Warna 20 x 20 bh 2,500.00
11 Tegel Badak PC 30 x 30 bh 4,100.00
12 Poslin 11 x 11 Warna Standar DN m2 63,300.00
13 Poslin 11 x 11 Warna khusus DN m2 67,300.00
14 Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos Mulia m2 54,500.00
15 Keramik 10 x 20 KW I DN Corak/Warna/Anti Slip Mulia m2 56,000.00
16 Keramik 20 x 20 (KM) KW I DN Corak/Warna /Anti Slip Mulia m2 62,500.00
17 Keramik 20 x 20 (KM) KW I DN Putih Polos Mulia m2 54,500.00
18 Keramik 20 x 25 Dinding KM KW I DN Corak Mulia m2 62,500.00
19 Keramik 30 x 30 KWI DN Putih Polos Mulia m2 53,000.00
20 Keramik 30 x 30 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 58,000.00
21 Keramik 40 x 40 KWI DN Putih Polos Mulia m2 56,800.00
22 Keramik 40 x 40 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 65,500.00
23 Keramik 10 x 20 dan 20 x 20 KW I DN Putih / Polos Roman m2 64,400.00
24 Keramik 10 x 20 KW I DN Corak/Warna/Anti Slip Roman m2 72,200.00
25 Keramik 20 x 20 (KM) KW I DN Corak/Warna/Anti Slip Roman m2 75,200.00
26 Keramik 20 x 20 (KM) KW I DN Putih Polos Roman m2 72,900.00
27 Keramik 20 x 25 Dinding KM KW I DN Corak Roman m2 75,200.00
28 Keramik 20 x 25 KW I DN Putih Polos Roman m2 72,900.00
29 Keramik 30 x 30 KW I DN Polos Roman m2 68,900.00
30 Keramik 30 x 30 KW I DN Warna/Corak (ANTI SLIP) Roman m2 76,600.00
31 Keramik 40 x 40 KW I DN Polos Roman m2 72,500.00
32 Keramik 40 x 40 KW I DN Warna/Corak (ANTI SLIP) Roman m2 77,000.00
33 Vinyl Lantai Standar m2 56,000.00
34 Karpet Kelas Baik LN m2 1,025,500.00
35 Karpet Kelas Sedang LN m2 353,500.00
36 Parquet Jati m2 375,400.00
37 Stairnosing Keramik 10/20 bh 13,700.00
38 Stairnosing Fiber m 25,000.00
39 Taraso Kerang 30 x 30 m2 31,800.00
40 Plin Taraso 10 x 30 bh 13,500.00
41 Granit Alam LN Ukuran Besar m2 1,848,400.00
42 Granit Alam LN Ukuran Kecil m2 1,612,900.00
43 Granit Alam DN Ukuran Besar m2 1,331,100.00
44 Granit Alam DN Ukuran Kecil m2 1,299,400.00
45 Granito Tile Essenza Ukuran 40 x 40 Polis m2 345,000.00
46 Granito Tile Essenza Ukuran 30 x 30 m2 322,800.00
47 Granito Tile Essenza Ukuran 40 x 40 UnPolis m2 204,900.00
48 Marmer m2 550,000.00
49 Marmer Alam Lampung Ukuran Besar m2 550,200.00
50 Marmer Alam Lampung Ukuran kecil m2 345,700.00
51 Marmer Alam Citatah Ukuran Besar m2 340,800.00
52 Marmer Alam Citatah Ukuran Kecil m2 237,600.00
53 Marmer Sintetis m2 157,900.00
54 Granito Tile Essenza 60 x 60 Polis m2 358,100.00
55 Granito Tile Essenza 60 x 60 UnPolis m2 231,800.00
56 Batu Tempel Hitam m2 96,500.00
57 Bata Karawang bh 600.00
58 Campuran untuk Kedap Air ( AM ) ltr 37,600.00
59 Plint keramik 10 x 20 bh 3,000.00
60 Plint keramik 10 x 25 bh 3,250.00
61 Plint keramik 10 x 30 bh 3,500.00
62 Plint keramik 10 x 40 bh 4,000.00
63 Plint keramik 15 x 30 bh 4,500.00
64 Plint keramik 15 x 40 bh 5,250.00
65 Plint granito 10 x 30 bh 25,900.00
66 Plint granito 10 x 40 bh 27,600.00
67 Plint granito 15 x 30 bh 31,100.00
68 Plint granito 15 x 40 bh 41,300.00

G BAHAN SALURAN AIR KOTOR / BERSIH


1 Grafel U 20 cm' m1 44,300.00
2 Grafel U 30 cm' m1 56,400.00
3 Grafel U 40 cm' m1 74,200.00
4 Buis Beton 20 cm ( 1 M' ) m1 49,200.00
5 Buis Beton 30 cm ( 1 M' ) m1 61,700.00
6 Buis Beton 40 cm ( 1 M' ) m1 80,900.00
7 Buis Beton 50 cm ( 1 M' ) stk 94,300.00
8 Buis Beton 60 cm ( 1 M' ) stk 130,900.00
9 Buis Beton 100 cm ( 0.50 M' ) stk 299,800.00
10 Buis Beton 80 cm ( 0.50 M' ) stk 298,500.00
11 BuisTanah 10 cm ( 0.50 M' ) stk 9,600.00
12 BuisTanah 15 cm ( 0.50 M' ) stk 12,700.00
13 BuisTanah 20 cm ( 0.50 M' ) stk 16,800.00
14 BuisTanah 25 cm ( 0.50 M' ) stk 22,800.00
15 Injuk kg 17,400.00

H BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata kg 16,500.00
2 Besi Beton U-39 / U-32 Rata-rata kg 20,700.00
3 Pagar BRC lengkap tiang ( Tanpa Pondasi ) m2 171,300.00
4 Bondek m2 185,000.00
5 Besi WF Ex DN SII kg 24,000.00
6 Besi WF Ex Jepang kg 23,900.00
7 Besi Profil DN SII kg 18,300.00
8 Besi Profil Ex LN kg 21,600.00
9 Besi C Lip Chanel kg 19,200.00
10 Ongkos Galfanis Besi kg 10,600.00
11 Kawat Beton kg 27,700.00
12 Kawat Duri kg 63,500.00
13 Kawat Pengikat m1 1,000.00
14 Kawat Bronjong 4 mm kg 28,200.00
15 Kawat Tembaga kg 41,400.00
16 Ram Nyamuk Hijau m2 13,400.00
17 Ram Kawat 1 x 1 cm m2 15,300.00
18 Ram Ayam m2 14,900.00
19 Kawat Kasa 1 x 1 ( Putih ) m2 32,100.00
20 Kawat Harmonika 4 cm m2 35,900.00
21 Kawat Harmonika 2 cm m2 28,600.00
22 Kawat Las Listrik kg 23,600.00
23 Wiremesh M8 m2 51,900.00
24 Wiremesh M6 m2 38,700.00
25 Timah kg 46,300.00
26 Timah Hitam kg 43,300.00
27 Ram nyamuk Alumunium m2 32,400.00
28 Plat Srip 2 x 30 mm ( 6 m1 ) bt 33,000.00
29 Plat Srip 3 x 30 mm ( 6 m1 ) bt 33,100.00
30 Plat Strip bt 18,200.00
31 Besi Strip kg 26,800.00
32 Plat Alumunium 0.2 mm m2 89,800.00
33 Plat Alumunium 0.3 mm m2 110,500.00
34 Plat Alumunium 0.4 mm m2 141,400.00
35 Plat Alumunium 0.5 mm m2 143,100.00
36 Plat Alumunium 0.6 mm m2 171,800.00
37 Plat Alumunium 0.1 mm m2 56,300.00
38 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 4 " ) m1 151,100.00
39 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 4 " ) m1 163,000.00
40 Kusen Alumunium Natural 1.3 mm t= 1,3 mm ( 3 " ) m1 81,000.00
41 Kusen Alumunium Warna 1.3 mm t= 1,3 mm ( 3 " ) m1 102,000.00
42 Daun Jendela Alumunium Natural ( tanpa kaca dan accessories ) m2 98,800.00
43 Daun Jendela Alumunium Warna ( tanpa kaca dan accessories ) m2 148,800.00
44 Daun Pintu Alumunium Natural ( tanpa kaca dan accessories ) m2 211,800.00
45 Daun Pintu Alumunium Warna ( tanpa kaca dan accessories ) m2 207,500.00
46 Handle Alumunium ( Tarikan Pintu Alumunium ) bh 345,200.00
47 Kait Angin Alumunium ps 104,500.00
48 Karet Asisoris Kusen / Pintu Alumunium m1 7,500.00
49 Jalusi Alluminium m' 35,000.00
50 Sunscreen Almunium m2 380,200.00
51 Seng Plat BJLS 30 60 cm ( 100 m1 ) roll 1,581,500.00
52 Seng Plat BJLS 30 90 cm ( 100 m1 ) roll 2,080,100.00
53 Plat Besi Tipis 1 mm kg 16,800.00
54 Plat Besi Tipis 0.5 mm kg 17,700.00
55 Plat Besi 2 mm s/d 5 mm kg 14,100.00
56 Plat Besi 6 mms/d 10 mm kg 14,100.00
57 Plat Besi 10 mm keatas kg 14,700.00
58 Kabel presstressed polos kg 26,700.00
59 Jaring Kawat Baja kg 28,900.00
60 Lem Kuning ( Aibond ) kg 35,700.00
61 Lem Fox kg 23,900.00
62 Lem Vinyl kg 44,000.00
63 Besi Strip Kaca Nako kg 11,000.00
64 Profil alumunium "T" m1 12,200.00
65 Besi Hallow ( 2 x 4 x 4) cm (400cm) btg 22,600.00
66 Besi Hallow ( 4 x 4) cm (400 cm) btg 29,200.00
67 Besi Rail Pengamanan kg 459,300.00
68 Jendela Besi m2 390,200.00
69 Jendela Besi tahan api m2 501,700.00
70 Pintu gulung besi m2 501,700.00
71 Pintu Roliing Door m2 306,600.00
72 Jendela nako kaca ryben + tralis 6 klips set 170,000.00
73 Jendela nako kaca ryben + tralis 7 klips set 200,000.00
74 Jendela nako kaca ryben + tralis 8 klips set 230,000.00
75 Jendela nako kaca ryben + tralis 10 klips set 290,000.00
76 Jendela nako kaca bening + tralis 4 klips set 120,000.00
77 Jendela nako kaca bening + tralis 5 klips set 140,000.00
78 Jendela nako kaca bening + tralis 6 klips set 170,000.00
79 Jendela nako kaca bening + tralis 7 klips set 210,000.00
80 Jendela nako kaca bening + tralis 8 klips set 230,000.00
81 Jendela nako kaca bening + tralis 10 klips set 300,000.00

I BAHAN KACA
1 Kaca Polos 2 mm ( ASAHI ) m2 69,000.00
2 Kaca Polos 3 mm ( ASAHI ) m2 87,400.00
3 Kaca Polos 5 mm ( ASAHI ) m2 111,000.00
4 Kaca Polos 8 mm ( ASAHI ) m2 183,100.00
5 Kaca Rayband 5 mm ( ASAHI ) m2 148,700.00
6 Kaca Rayband 8 mm ( ASAHI ) m2 323,400.00
7 Kaca Rayband 12 mm ( ASAHI ) m2 627,000.00
8 Kaca cermin 5 mm m2 150,500.00
9 Kaca cermin 6 mm m2 186,400.00
10 Kaca cermin 8 mm m2 234,300.00
11 Kaca Patri Lokal Terpasang ( ASAHI ) m2 1,621,100.00
12 Kaca Patri Ex Luar Negeri Terpasang m2 3,425,700.00
13 Kaca 6 mm Gravver m2 1,263,900.00
14 Glass Block DN 20 x 20 ( Kedawung ) bh 22,000.00
15 Glass Block DN 20 x 20 Ex LN bh 125,700.00
16 Sealant kg 211,800.00
17 Jendela Nako bh 109,200.00
J BAHAN PAKU DAN MUR BAUT
1 Paku 1/2" s/d 2" kg 23,800.00
2 Paku 2" s/d 5" kg 23,400.00
3 Paku 8 cm s/d 15 cm kg 20,000.00
4 Paku Beton 2 cm s/d 5 cm bh 1,600.00
5 Paku Kait Lengkap bh 900.00
6 Paku Cacing kg 57,100.00
7 Besi Beugel Kuda - Kuda kg 21,700.00
8 Duk Angker bh 7,500.00
9 Angker Mur Baut dia. 19 / Panjang 60 cm bh 71,800.00
10 Mur Baut HTB dia. 19 s/d 16 ( 5 cm ) bh 15,900.00
11 Mur Baut Biasa dia. 19 s/d 16 ( 5 cm ) bh 9,300.00
12 Piser dia.12 s/d 20 cm bh 5,300.00
13 Paku skrup 3" bh 800.00
14 Ramset / Dinabolt bh 7,200.00
15 Baut Besar bh 600.00
16 Baut Kecil bh 300.00
17 Paku GRC kg 35,000.00
18 Paku gypsum kg 17,500.00
19 Sekrup fixer bh 250.00

K BAHAN PERPIPAAN
1 Besi Pipa Untuk Hydrant BSP 1" bt 166,700.00
2 Besi Pipa Untuk Hydrant BSP 1.25" bt 210,200.00
3 Besi Pipa Untuk Hydrant BSP 1.5" bt 298,000.00
4 Besi Pipa Untuk Hydrant BSP 2" bt 351,800.00
5 Besi Pipa Untuk Hydrant BSP 2.5" bt 439,300.00
6 Besi Pipa Untuk Hydrant BSP 3" bt 595,000.00
7 Besi Pipa Untuk Hydrant BSP 4" bt 869,600.00
8 Besi Pipa Untuk Hydrant BSP 6" bt 1,423,400.00
9 Besi Pipa Hitam 1" t = 2 mm bt 172,300.00
10 Besi Pipa Hitam 2" t = 2 mm bt 227,900.00
11 Besi Pipa Hitam 3" t = 2mm bt 365,800.00
12 Besi Pipa Hitam 4" t = 2 mm bt 573,100.00
13 Besi Pipa Hitam 6" t = 2 mm bt 772,400.00
14 Pipa GIP Medium A 1/2" ( 6 m1 ) bt 109,100.00
15 Pipa GIP Medium A 3/4" ( 6 m1 ) bt 159,400.00
16 Pipa GIP Medium A 1" ( 6 m1 ) bt 181,500.00
17 Pipa GIP Medium A 1 1/4" ( 6 m1 ) bt 259,300.00
18 Pipa GIP Medium A 1 1/2" ( 6 m1 ) bt 280,500.00
19 Pipa GIP Medium A 1 3/4" ( 6 m1 ) bt 326,400.00
20 Pipa GIP Medium A 2" ( 6 m1 ) bt 467,400.00
21 Pipa GIP Medium A 2 1/2" ( 6 m1 ) bt 672,100.00
22 Pipa GIP Medium A 3" ( 6 m1 ) bt 849,900.00
23 Pipa GIP Medium A 4" ( 6 m1 ) bt 920,300.00
24 Macam2 Sambungan GIP 1/2" bh 6,300.00
25 Macam2 Sambungan GIP 3/4" bh 8,600.00
26 Macam2 Sambungan GIP 1" bh 16,700.00
27 Macam2 Sambungan GIP 1 1/4" bh 19,800.00
28 Macam2 Sambungan GIP 1 1/2" bh 20,700.00
29 Macam2 Sambungan GIP 1 3/4" bh 22,700.00
30 Macam2 Sambungan GIP 2" bh 51,200.00
31 Macam2 Sambungan GIP 2 1/2" bh 60,400.00
32 Macam2 Sambungan GIP 3" bh 75,900.00
33 Macam2 Sambungan GIP 4" bh 118,600.00
34 Pipa PVC RUCIKA type AW 1/2" bt 40,100.00
35 Pipa PVC RUCIKA type AW 3/4" bt 52,200.00
36 Pipa PVC RUCIKA type AW 1" bt 63,200.00
37 Pipa PVC RUCIKA type AW 1 1/4" bt 79,900.00
38 Pipa PVC RUCIKA type AW 1 1/2" bt 105,900.00
39 Pipa PVC RUCIKA type AW 2" bt 110,700.00
40 Pipa PVC RUCIKA type AW 2 1/2" bt 167,100.00
41 Pipa PVC RUCIKA type AW 3" bt 205,100.00
42 Pipa PVC RUCIKA type AW 4" bt 347,900.00
43 Pipa PVC RUCIKA type AW 6" bt 640,000.00
44 Pipa PVC RUCIKA type AW 8" bt 818,300.00
45 Pipa PVC MASPION ABU ( AW ) 1/2" bt 22,500.00
46 Pipa PVC MASPION ABU ( AW ) 3/4" bt 27,800.00
47 Pipa PVC MASPION ABU ( AW ) 1" bt 40,500.00
48 Pipa PVC MASPION ABU ( AW ) 1 1/4" bt 58,500.00
49 Pipa PVC MASPION ABU ( AW ) 1 1/2" bt 60,200.00
50 Pipa PVC MASPION ABU ( AW ) 2" bt 75,800.00
51 Pipa PVC MASPION ABU ( AW ) 2 1/2" bt 126,300.00
52 Pipa PVC MASPION ABU ( AW ) 3" bt 145,700.00
53 Pipa PVC MASPION ABU ( AW ) 4" bt 256,800.00
54 Macam2 Sambungan Paralon 1/2" bh 4,400.00
55 Macam2 Sambungan Paralon 3/4" bh 4,700.00
56 Macam2 Sambungan Paralon 1" bh 4,900.00
57 Macam2 Sambungan Paralon 1 1/4" bh 7,200.00
58 Macam2 Sambungan Paralon 1 1/2" bh 9,500.00
59 Macam2 Sambungan Paralon 1 3/4" bh 13,500.00
60 Macam2 Sambungan Paralon 2" bh 15,800.00
61 Macam2 Sambungan Paralon 2 1/2" bh 26,400.00
62 Macam2 Sambungan Paralon 3" bh 29,700.00
63 Macam2 Sambungan Paralon 4" bh 34,000.00
64 Sambungan Pipa PVC Jenis AW 4" TY bh 89,900.00
65 Lem Paralon tb 10,100.00
66 Solatip Ledeng gl 4,200.00
67 Pipa PVC 4" Berlobang Jenis AW m1 36,700.00
68 PVC Waterstop lebar 150 m1 53,500.00
69 PVC Waterstop lebar 200 m1 57,900.00
70 PVC Waterstop lebar 230 m1 65,700.00
71 PVC Waterstop lebar 250 m1 74,700.00
72 PVC Waterstop lebar 300 m1 83,600.00
73 PVC Waterstop lebar 320 m1 92,500.00

L BAHAN SANITAIR
1 Stop Kran 3/4" KIT bh 103,900.00
2 Stop Kran 1" KIT bh 124,200.00
3 Stop Kran 1 1/2" KIT bh 208,000.00
4 Stop Kran 2" KIT bh 267,900.00
5 Stop Kran 2 1/2" KIT bh 713,200.00
6 Stop Kran 3" KIT bh 830,300.00
7 Check Valve 1/2" bh 86,400.00
8 Double Neple 1/2" bh 32,400.00
9 Water Mur 1/2" bh 40,200.00
10 Gate walve 1/2" bh 55,500.00
11 Saringan Air Lt. KM Stainless Steel bh 66,600.00
12 Apooer Bath Tube bh 267,800.00
13 Kran Stainless Lokal Kait bh 46,100.00
14 Shower Dengan Tiang bh 221,000.00
15 Shower Tanpa Tiang bh 134,800.00
16 Kran Tembok Sun Eui dia. 1/2" bh 86,900.00
17 Kran Tembok ITAP dia. 1/2" bh 40,900.00
18 Kran Bebek Sun Eui 1/2" bh 144,600.00
19 Kran Bebek ITAP 1/2" bh 51,500.00
20 Kran Panas Dingin San Eui Standard bh 228,400.00
21 Bath Cape Washteren unit 2,098,700.00
22 Tempat Sabun Poslin bh 46,300.00
23 Wastafel Lengkap TOTO LW 230 unit 1,012,700.00
24 Wastafel Lengkap INA unit 699,900.00
25 Closet Jongkok Poslin Warna TOTO unit 205,600.00
26 Closet Jongkok Standard Putih Poslin TOTO unit 188,200.00
27 Closet Jongkok Lengkap Sistem Jet TOTO unit 2,032,900.00
28 Closet Duduk Warna Standard TOTO C 240 Lengkap unit 1,724,700.00
29 Wastafel Bulat Warna Standard Lengkap unit 910,800.00
30 Closet Duduk Warna Standard INA Lengkap bh 1,272,100.00
31 Urinoir Lengkap TOTO Warna Standard Lengkap unit 1,773,400.00
32 Penyekat Poslin Urinoar TOTO lbr 495,900.00
33 Kitchen Zink Stainless Standard Lokal ( 1 Lubang ) bh 397,800.00
34 Kitchen Zink Stainless Non Standard Franke ( 1 Lubang ) bh 1,272,300.00
35 Kitchen Zink Stainless Non Standard Franke ( 2 Lubang ) bh 1,650,200.00
36 Talang PVC U - 15 cm btng 60,000.00

M BAHAN PENUTUP ATAP


1 Atap Plastik Gelombang 80 x 180 lbr 33,100.00
2 Atap Fiber Glass Tipis 80 x 180 ( Gelombang ) lbr 47,100.00
3 Atap Fiber Glass Tebal 80 x 180 ( Gelombang ) lbr 100,000.00
4 Atap Alumunium Natural USR 26 ( JAINDO ) m2 140,600.00
5 Atap Alumunium Warna USR 26 ( JAINDO ) m2 164,700.00
6 Atap Asbes Gel. Kecil 80 x 180 x 4 mm lbr 77,200.00
7 Atap Asbes Gel. Besar 80 x 180 x 5 mm lbr 111,100.00
8 Atap Seng Gelombang 80 cm x 180 cm x 3 mm lbr 62,900.00
9 Atap Seng Gelombang 80 cm x 180 cm x 5 mm lbr 83,100.00
10 Atap Seng Gelombang 270 cm x 105 cm x 4mm lbr 73,300.00
11 Atap Seng Gelombang 240 cm x 105 cm x 4mm lbr 65,900.00
12 Atap Seng Gelombang 210 cm x 105 cm x 4mm lbr 58,500.00
13 Atap Seng Gelombang 150 cm x 105 cm x 4mm lbr 42,300.00
14 Atap Seng Gelombang 150 cm x 102 cm x 5mm lbr 78,500.00
15 Atap Seng Gelombang 180 cm x 102 cm x 5mm lbr 97,200.00
16 Atap Asbes Gelombang 300 cm x 105 cm x 4 mm lbr 80,000.00
17 Atap Tegola Kubota, lengkap m2 487,100.00
18 Atap Tegola Kwalitas Sedang m2 283,600.00
19 Alumunium Foile m2 19,600.00
20 Atap Genteng Plentong pres Bakar KW I bh 1,900.00
21 Atap Genteng Plentong pres Molen Oven KW I bh 2,700.00
22 Atap Genteng Flam pres Molen Oven Jatiwangi bh 2,300.00
23 Bubung Genteng pres Bulat Ex Jatiwangi bh 7,500.00
24 Genteng Bubungan Ex Jatiwangi Segi Tiga bh 4,800.00
25 Genteng Bubungan Beton bh 10,500.00
26 Genteng Metal ( Rainbow Roof ) m2 203,100.00
27 Genteng Metal Hana m2 172,700.00
28 Nok Atas Metal ( Rainbow Roof ) lbr 138,500.00
29 Nok Atas Metal Hana lbr 80,900.00
30 Nok Pingir Metal ( Rainbow Roof ) lbr 105,300.00
31 Nok Pingir Metal Hana lbr 100,800.00
32 Wall Flasing ( Rainbow Roof ) lbr 83,900.00
33 Wall Flasing Hana lbr 88,700.00
34 Atap Genteng Beton Warna 14.5/m2 m2 96,700.00
35 Genteng Beton Natural bh 8,500.00
36 Sirap Kelas I ( 80 / m2 ) m2 26,400.00
37 Genteng Keramik Natural Intan 14.5 / m2 m2 112,400.00
38 Genteng Keramik Glasur Standard 14.5 /m2 m2 142,200.00
39 Genteng Keramik Glasur Special 14.5 /m2 m2 139,300.00
40 Genteng Keramik Glasur Premium 14.5 /m2 m2 145,100.00
41 Genteng Murando Natural 1m2 = 18 bh bh 2,700.00
42 Genteng Murando Glasur 1m2 = 18 bh bh 4,000.00
43 Bubung Murando Natural bh 7,500.00
44 Bubung Murando Glasur bh 10,700.00
45 Bubungan Genteng Keramik bh 10,000.00
46 Atap Genteng Kodok bh 3,000.00
47 Bubungan Genteng Kodok bh 4,500.00
48 Bubungan Genteng Plentong bh 6,000.00
49 Bubungan Stel Gelombang bh 7,500.00
50 Nok Stel Gelombang lbr 38,100.00
51 Nok Atap Seng lbr 37,500.00
52 Nok standar 40 cm 18, SWG 22 m2 75,000.00
53 Pelat Asbes tebal 4 mm lbr 21,000.00
54 Pelat Asbes tebal 3.5 mm lbr 16,400.00
55 Trusses ZAM-75 t=0.8 Rangka Utama m1 34,500.00
56 Trusses ZAM-75 t=0.5 Rangka Utama m1 22,000.00
57 Reng 16-DB Roof Battens t=0.48 mm m1 11,000.00
58 Foot Plate t= 1.22 mm m1 7,200.00
59 PLD - Diafragma Plate bh 2,200.00
60 WIND Bracing m1 1,700.00
61 Tensioner ( Pengaku Tali angin ) bh 7,200.00

N BAHAN MEKANIKAL
1 Jockey Pump kap. 80 gln/menit 100 m1 ( 18.6 kW ) unit 71,396,400.00
2 Electrical Pump kap. 750 gln/menit 120 m1 ( 90 kW ) unit 216,358,900.00
3 Diesel Pump kap. 750 gln/menit 120 m1 ( 105 kW ) unit 591,647,100.00
4 Presure Tank kap. 500 liter lengkap unit 36,997,300.00
5 Hydran Box dlm Gedung ( Lengkap ) unit 6,854,400.00
6 Fire House 1.5 x 30 m + nose unit 4,866,100.00
7 Exhose Fan H 360 W 60 x 60 cm unit 6,862,900.00
8 Exhose Fan H 380 W CFM 55 x 55 cm unit 5,491,100.00
9 Exhose Fan H 100 W 40 x 40 cm unit 1,092,600.00
10 AC Split 3 PK Setara TOSHIBA unit 30,791,800.00
11 AC Split 2 PK Setara TOSHIBA unit 21,926,500.00
12 AC Split 1 PK Setara TOSHIBA unit 5,174,100.00
13 Mesin AC Split DAIKIN ( Indoor / Outdoor Unit ) 1 BTU 4,200,000.00

O BAHAN ELEKTRIKAL
1 Kabel NYA 1 x 1.5 Prima ( 1 rol = 50 m' ) ROLL 102,700.00
2 Kabel NYA 1 x 2.5 Prima ( 1 rol = 50 m' ) ROLL 151,700.00
3 Kabel NYM 2 x 1.5 Prima ( 1 rol = 50 m' ) m' 6,600.00
4 Kabel NYM 3 x 1.5 Prima ( 1 rol = 50 m' ) m' 7,600.00
5 Kabel NYM 2 x 2.5 Prima ( 1 rol = 50 m' ) m' 4,900.00
6 Kabel NYM 3 x 2.5 Prima ( 1 rol = 50 m' ) m' 10,900.00
7 Kabel NYM 4 x 2.5 Prima ( 1 rol = 50 m' ) m' 7,600.00
8 Kabel NYM 2 x 4 Prima ( 1 rol = 50 m' ) m' 6,300.00
9 Kabel NYM 3 x 4 Prima ( 1 rol = 50 m' ) m' 15,400.00
10 Kabel NYM 4 x 4 Prima ( 1 rol = 50 m' ) m' 20,700.00
11 Kabel NYM 2 x 6 Supreme ( 1 rol = 50 m' ) m' 11,800.00
12 Kabel NYM 3 x 6 Supreme ( 1 rol = 50 m' ) m' 13,700.00
13 Kabel NYM 4 x 6 Supreme ( 1 rol = 50 m' ) m' 18,600.00
14 Kabel NYM 2 x 10 Supreme ( 1 rol = 50 m' ) m' 17,600.00
15 Kabel NYM 3 x 10 Supreme ( 1 rol = 50 m' ) m' 119,700.00
16 Kabel NYM 4 x 10 Supreme ( 1 rol = 50 m' ) m' 26,500.00
17 Kabel NYM 4 x 16 Supreme ( 1 rol = 50 m' ) m' 29,700.00
18 Kabel NYY 2 x 4 Supreme ( 1 rol = 50 m' ) m' 12,000.00
19 Kabel NYY 3 x 4 Supreme ( 1 rol = 50 m' ) m' 19,300.00
20 Kabel NYY 4 x 4 Supreme ( 1 rol = 50 m' ) m' 23,800.00
21 Kabel NYY 2 x 6 Supreme ( 1 rol = 50 m' ) m' 14,500.00
22 Kabel NYY 3 x 6 Supreme ( 1 rol = 50 m' ) m' 19,200.00
23 Kabel NYY 4 x 6 Supreme ( 1 rol = 50 m' ) m' 18,500.00
24 Kabel NYY 2 x 10 Supreme ( 1 rol = 50 m' ) m' 20,400.00
25 Kabel NYY 3 x 10 Supreme ( 1 rol = 50 m' ) m' 25,800.00
26 Kabel NYY 4 x 10 Supreme ( 1 rol = 50 m' ) m' 35,500.00
27 Kabel NYY 4 x 16 Supreme ( 1 rol = 50 m' ) m' 41,900.00
28 NSFB FUJI EA - 100 A bh 841,900.00
29 NSFB FUJI EA - 150 A bh 2,182,600.00
30 Rumah Panel 30 x 60 cm ( Kosong ) unt 153,500.00
31 Skring Kas 2 grop Biasa unt 204,800.00
32 Skring Kas 3 grop Biasa unt 222,600.00
33 Skring Kas 5 grop Biasa unt 468,800.00
34 MCB 1 PAS bh 55,100.00
35 MCB 3 PAS bh 106,000.00
36 Tahanan 50 A Merk Fuji bh 521,100.00
37 Saklar Broko Tunggal Standard ( 1 Phase ) bh 23,800.00
38 Saklar Broko Seri Standard ( 1 Phase ) bh 26,300.00
39 Stop Kontak Broko Standard ( 1 Phase ) bh 23,800.00
40 Stop Kontak Broko 3 Phase (Out Bow) bh 87,700.00
41 Stop Kontak Broko 3 Phase ( In Bow) bh 144,900.00
42 Stop Kontak Handle 3 Phase bh 87,800.00
43 Instalas Titik Lampu / Stop Kontak (Upah dan Alat) ttk 179,600.00
44 Lampu pijar 25 Watt s/d 100 Watt bh 61,200.00
45 Lampu Neon Phillips 20 Watt bh 29,700.00
46 Lampu Neon Phillips 40 Watt bh 35,200.00
47 Trapo TL 20 W (Phillips) bh 41,800.00
48 Trapo TL 40 W (Phillips) bh 37,900.00
49 Trapo TL 20 W (Sinar) bh 40,600.00
50 Trapo TL 40 W (sinar) bh 41,300.00
51 Stater Neon Phillips bh 8,300.00
52 Stater Neon Biasa bh 6,500.00
53 Rumah TL In Bow / Out Bow 2 x 20 W (kosongan) bh 144,000.00
54 Down Light + SL 25 W bh 306,900.00
55 Lampu SL Philip 25 W bh 306,900.00
56 Lampu Sirkel TL 20 W Lengkap bh 67,900.00
57 Lampu Mercuri 80 W bh 147,400.00
58 Lampu Taman + Tiang + Lampu 1 Buah bh 307,600.00
59 Lampu Baret 30 cm + Neon bh 221,700.00
60 Lampu Neon Arcrilik 2 x 40 W Lengkap bh 738,000.00
61 Jarum Penangkal Petir 16 bh 101,500.00
62 Kawat BC ( Tembaga ) kg 65,100.00
63 Pentanahan Penangkal Petir ttk 423,700.00
64 Pentanahan Panel ttk 296,100.00

P BAHAN ALAT PENGANTUNG DAN KUNCI


1 Kunci Silinder ALFA untuk Pintu Alumunium bh 410,900.00
2 Tarikan Pintu Alumunium bh 408,600.00
3 Kunci 2 Slaag ROYAL bh 126,500.00
4 Rel Henderson Lengkap bh 864,300.00
5 Rel maraton I Pintu unt 193,100.00
6 Kunci 2 Slaag Silinder SEIS Asli type 210 s/d type 226 bh 335,900.00
7 Kunci 2 Slaag Ancor Asli bh 165,300.00
8 Kunci 2 Slaag ISO bh 207,300.00
9 Kunci KM Bulat Kualitas Biasa bh 54,400.00
10 Kunci kM Bulat ALFA bh 102,700.00
11 Kunci 2 Slaag Silinder Utama Standard bh 586,600.00
12 Kunci Gembok Besar bh 85,200.00
13 Kunci 2 Slaag Kuda Terbang bh 94,500.00
14 Kunci Lemari bh 46,800.00
15 Espangolet ps 51,600.00
16 Grendel 15 cm bh 49,800.00
17 Grendel 5 cm bh 5,500.00
18 Hak Angin Kait Jendela Biasa ps 7,100.00
19 Hak Angin Jendela Antik ps 29,000.00
20 Hak Angin Sendok Stainless / Kuningan bh 32,200.00
21 Sloot Pintu Berikut Rantai bh 31,500.00
22 Sloot Jendela Tunggal bh 33,000.00
23 Engsel Pintu Unilon Standard ps 21,000.00
24 Engsel Jendela Unilon ps 15,000.00
25 Engsel Patrun ps 13,700.00
26 Engsel Harmonika m1 9,100.00
27 Door Closer Kelas Standard ( Kelas Sedang ) unt 420,000.00
28 Door Closer Kelas Standard ( Kelas Baik ) unt 597,500.00
29 Door Closer Kelas Rendah unt 200,000.00
30 Door Holder unt 205,400.00
31 Door Stoper unt 255,500.00
32 Tarikan Almari Rata-rata bh 19,500.00
33 Seng BJLS 30 Lebar 60 cm ( 1 rol 50 m' ) m1 43,500.00
34 Seng BJLS 30 Lebar 90 cm ( 1 rol 50 m' ) m1 53,500.00
35 Seng BJLS 30 / 3 x 0.3 mm lbr 86,900.00
36 Seng Plat lbr 50,100.00
37 Waterstop Lebar 200 mm m1 57,900.00

Q BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN


1 Aspal Bitumen kg 12,459.00
2 Aspal Emulsi kg 12,459.00
3 Aspal Curah kg 10,890.00
4 Aspal Concrete / Laston( AC -WC) ton 1,348,300.00
5 Aspal Threated Base ( ATB ) ton 1,200,200.00
6 Lataston /Hot Rolls Sheet ( HRS ) ton 1,666,900.00

R BAHAN PENGISAP AIR SUMUR DALAM


1 Pompa Kodok unit 172,600.00
2 Pompa Dragon Tegal unit 243,800.00
3 Pompa Dragon Asli unit 718,500.00
4 Mesin Pompa Air 100 W - Sanyo unit 1,100,200.00
5 Mesin Pompa Air 150 W - Sanyo unit 1,890,700.00
6 Pompa Zet Pump 250 W - Sanyo unit 4,961,500.00
7 Pompa Zet Pump 450 W - Sanyo unit 7,878,000.00
8 Pompa Submersible kap. 150 liter / menit 3 KW unit 27,151,200.00
9 Gear Pump Kap. 60 liter / menit unit 15,702,700.00
10 Deep Well dengan kelengkapannya kap. 150 liter / menit unit 172,052,500.00
11 Hand Oil Pump unit 5,195,300.00

S BAHAN PENAMPUNG AIR


1 Tangki Air Fiber Glass 0.5 m3 ( Excel ) bh 1,172,500.00
2 Tangki Air Fiber Glass 1 m3 ( Excel ) bh 1,316,400.00
3 Tangki Air Fiber Glass 2 m3 ( Excel ) bh 1,954,200.00
4 Bak KM Fiber 60 x 60 bh 255,300.00
5 Bak Taraso WC 40 x 40 bh 118,500.00
6 Bak KM Taraso 60 x 60 bh 161,100.00

T ALAT TUKANG
1 Palu 0.5 kg bh 39,300.00
2 Cangkul bh 24,500.00
3 Singkup bh 41,400.00
4 Sekrop bh 50,100.00
5 Pengki bh 12,300.00
6 Linggis bh 41,700.00
7 Rool Meter 30 meter ( Bahan Plastik ) bh 101,000.00
8 Rool Meter 5 meter ( Bahan Besi ) bh 37,800.00
9 Selang Plastik untuk Water Pas dia. 0.5 cm m 1,600.00
10 Water Pas Alumunium 60 cm bh 88,200.00

U BAHAN BAKAR DAN PELUMAS


1 Minyak Tanah lt 18,000.00
2 Kayu Bakar dari Kayu Karet m3 151,100.00
3 Bahan Bakar Residu lt 28,435.00
4 Minyak Solar lt 7,150.00
5 Bensin Premium lt 7,800.00
6 Plus Oil lt 3,300.00
7 Oil Mesran 40 SAE lt 55,000.00
8 Elpiji / botol 15 kg 104,600.00
9 Asitilin / Botol 15.1 kg btl 88,900.00
10 Angin ( O2 ) / botol btl 66,400.00
11 Karbit kg 19,400.00
12 Minyak Bekisting ltr 40,500.00
13 Rapidrant Gln 15,700.00
14 Soda Api kg 35,600.00
15 Sabun kg 2,400.00
16 Arang Kayu kg 11,100.00
17 Kawat Las bh 1,400.00

V BAHAN PAGAR
1 Panel Beton Pracetak lbr 199,200.00
2 Kolom Beton Pracetak btg 264,000.00

B. BIDANG PERTAMANAN
1 Aglonema batang 50,000.00
2 Bambu krisik/jepang batang 50,000.00
3 Furadan kg 24,000.00
4 Kompos/pupuk kandang karung 25,000.00
5 M atoa (2 m) batang 40,000.00
6 Palm (botol, ekor tupai, putri, dll) tinggi 2 m batang 100,000.00
7 Philo batang 75,000.00
8 Pohon pelindung (angsana, mahoni, kamboja dll) tinggi 2m batang 25,000.00
9 Pohon perdu (kaca piring, puring, mawar, melati, dll) batang 10,000.00
10 Rumput gajah mini m2 15,000.00

harga sudah termasuk PPN dan keuntungan

Analisa Harga Satuan Pekerjaan Penanaman Pohon

Diposkan : o6 Juni2014
Oleh : Endang Kusman

NO. URAIAN KOEF SAT. HARGA SAT. (Rp) HARGA (Rp)


O-01 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon pelindung 1.0000 btng 25,000.00 25,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 28,274.00
Dibulatkan 28,274.00
O-02 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Bambu krisik/jepang 1.0000 btng 50,000.00 50,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 53,274.00
Dibulatkan 53,274.00
O-03 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon perdu 1.0000 btng 10,000.00 10,000.00
Pekerja 0.0200 org 42,000.00 840.00
Mandor 0.0020 org 80,000.00 160.00
Jumlah 12,024.00
Dibulatkan 12,024.00
O-04 1 M2 Tanam rumput gajah (silang papan catur)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Rumput gajah mini 0.5000 m2 15,000.00 7,500.00
Pekerja 0.0400 org 42,000.00 1,680.00
Mandor 0.0040 org 80,000.00 320.00
Jumlah 10,500.00
Dibulatkan 10,500.00

Kembali ke AHA-SNI

Analisa Harga Satuan Pekerjaan Penanaman Pohon

Diposkan : o6 Juni2014
Oleh : Endang Kusman

NO. URAIAN KOEF SAT. HARGA SAT. (Rp) HARGA (Rp)


O-01 1 Lubang (70x70x70) cm, tanam pohon pelindung tinggi 2m
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon pelindung 1.0000 btng 25,000.00 25,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 28,274.00
Dibulatkan 28,274.00
O-02 1 Lubang (70x70x70) cm, tanam bambu krisik/jepang
Pupuk kandang 0.0800 krg 25,000.00 2,000.00
Furadan 0.0010 kg 24,000.00 24.00
Bambu krisik/jepang 1.0000 btng 50,000.00 50,000.00
Pekerja 0.0250 org 42,000.00 1,050.00
Mandor 0.0025 org 80,000.00 200.00
Jumlah 53,274.00
Dibulatkan 53,274.00
O-03 1 Lubang (40x40x40) cm, tanam pohon perdu (polibag)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Furadan 0.0010 kg 24,000.00 24.00
Pohon perdu 1.0000 btng 10,000.00 10,000.00
Pekerja 0.0200 org 42,000.00 840.00
Mandor 0.0020 org 80,000.00 160.00
Jumlah 12,024.00
Dibulatkan 12,024.00
O-04 1 M2 Tanam rumput gajah (silang papan catur)
Pupuk kandang 0.0400 krg 25,000.00 1,000.00
Rumput gajah mini 0.5000 m2 15,000.00 7,500.00
Pekerja 0.0400 org 42,000.00 1,680.00
Mandor 0.0040 org 80,000.00 320.00
Jumlah 10,500.00