MontroyalBridgeReplacementProjectProgressReport04(September2017) ii
Table of Contents
1.0 ProjectSummary..................................................................................................................................3
2.0 ConstructionProgressandSchedule....................................................................................................4
2.1 PROGRESSINSEPTEMBER,2017.........................................................................................................4
2.1.1 EuroviaBCInc.(EBC)andSubcontractors..........................................................................4
2.1.2 ThirdPartyUtilities.............................................................................................................4
2.2 WORKANTICIPATEDFORJUNE2016...................................................................................................4
2.3 CONSTRUCTIONSCHEDULE.................................................................................................................5
2.3.1 MajorMilestones................................................................................................................5
2.3.2 Schedule/MilestoneImpactstoDate.................................................................................5
2.3.3 PotentialRisktoSchedule(Future)....................................................................................5
3.0 ProjectCostSummary..........................................................................................................................6
3.1 PROJECTBUDGET..............................................................................................................................6
3.2 MONTROYALBRIDGECONSTRUCTIONPROGRESSDRAW#6SEPTEMBER2017........................................6
4.0 SiteSafetySummary.............................................................................................................................6
5.0 TrafficSummary....................................................................................................................................7
5.1 IMPACTSTOONSTREETTRAFFIC.........................................................................................................7
5.2 IMPACTSTOOFFSTREETTRAFFICANDPARKTRAILUSERS.......................................................................7
6.0 EnvironmentalSummary......................................................................................................................7
7.0 CommunicationsSummary...................................................................................................................7
8.0 OtherAreasofBusiness........................................................................................................................8
9.0 KeyConstructionDocuments...............................................................................................................8
10.0ProgressPhotos....................................................................................................................................9
Document: 3350531
FOI 17-153 Page 2
MontroyalBridgeReplacementProjectProgressReport04(September2017) 3
1.0 PROJECTSUMMARY
PROJECTINFO:
ProjectName: MontroyalBridgeReplacementProject
ProjectFile: 11.5250.20/094.000
ProjectManager: TylerThompson
ProjectBudget: $8,400,000
PercentSpent: $3,012,278[~36%]
Location: MontroyalBoulevardbetweenGlencanyonDr.andSkylineDr.
Incl.MosquitoCreekTrailunderneathbridge.
CONSTRUCTIONINFO:
ContractNumber: ITT.083.16
Contractor: EuroviaBC(EBC)
ContractAdmin.: TylerThompson
PurchaseOrder: $5,006,318.46excl.GST
Completed[Percent]: $1,471,704.95[~31%]excl.GST
CompletionDate: August1st,2018
CURRENTSTATUS:
ProgressinSeptemberconsistedofinstallingtemporarywaterworksneededtoallow
demolitionoftheoldMontroyalBridge.Otherminorworksincludedinstallingrailingsonthe
NWretainingwallandpreparationsforbridgedemolition.
ProgressinOctoberwillincludethefollowingactivities:
Demolitionoftheoldbridge
Piledrivingforthenewbridge
Constructionofatemporaryshoringwall,whichisneededtosupportthedetourwhile
constructingpartsofthenewbridge
PlantingandrestorationoftheareaabovetheNWshotcretewall
FORECAST:
Althoughtherehavebeensomedelaysrelatedtotheinstallationoftemporarywaterworks,
crewsrecoveredtimetoo,openingthedetourbridgeaheadofschedule.Progresstodate
indicatestheprojectwillbecompletedontimeandwithinbudget.
Document: 3350531
FOI 17-153 Page 3
MontroyalBridgeReplacementProjectProgressReport04(September2017) 4
2.0 CONSTRUCTIONPROGRESSANDSCHEDULE
2.1 PROGRESSINSEPTEMBER,2017
2.1.1 EuroviaBCInc.(EBC)andSubcontractors
InstallationoftemporarywatermainsneededtobypasstheoldMontroyalBridge.
Chlorinationandpressuretestingofthetemporarywatermains..
2.1.2 ThirdPartyUtilities
FORTISGAS:[NoChangefromAprilProgressReport]
Fortiscompletedservicerelocationsfor557PalisadeandFirehall#3in2016.Two
temporaryserviceswereinstalledtoservice4590and4596SkylineDrthissummer,
whichwererequiredtodecommissionthegasmainwhichcrossestheoldMontroyal
Bridge.Thisworkwascompletedonlyafterafterlengthycostnegotiationswith
FortisBC.Fortisattemptedtoholdtheprojectschedulehostageforpayment.These
negotiationsregardingcostsharingareongoing.
BCHYDRO(BCH):
HydrocompleteditsTask004(lineandpoledemolition)thatwasrequiredbefore
bridgedemolition.
GoodlinesofcommunicationareopenbetweenDNV,BCH,andEBC.Coordinationis
ongoingandingoodstanding.
TELUS:
TelushadnoworkinSeptemberontheproject.Teluslinescrossingtheoldbridgewill
bepreservedwithonegirderstayingup.Goodlinesofcommunicationareopen
betweenDNV,TEL,andEBC.Coordinationisongoingandingoodstanding,although
uppermanagementcontinuescostsharingnegotiations.
SHAW:
ShawworkcompletedinlateMay.Goodlinesofcommunicationareopenbetween
DNV,Shaw,andEBC.Coordinationisongoingandingoodstanding.
2.2 WORKANTICIPATEDFOROCTOBER2017
Demolitionoftheoldbridge
Piledrivingforthenewbridge
Constructionofatemporaryshoringwall,whichisneededtosupportthedetour
whileconstructingpartsofthenewbridge
PlantingandrestorationoftheareaabovetheNWshotcretewall
Document: 3350531
FOI 17-153 Page 4
MontroyalBridgeReplacementProjectProgressReport04(September2017) 5
2.3 CONSTRUCTIONSCHEDULE
Seetablebelowforreferencestothelatestconstructionschedules.
2.3.1 MajorMilestones
DescriptionofWork Date
MobilizetoSite April11th,2017
CloseMosquitoCreekTrail May8th,2017
OpenDetourBridge September17,2017
DemolitionofExistingMontroyalBridge October,2017
BridgeDeckConcretePour February,2018
CompletedBridgeOpentoTraffic June,2018
SubstantialCompletion July23,2018
2.3.2 Schedule/MilestoneImpactstoDate
Significantdelaysrelatedtopoorwatermainconstructionbysubcontractors.
Thisisonthecriticalpathasthewaterworksneededtobedetouredpriorto
demolishingtheoldbridge
Offsettingthesedelays,thedetourbridgewasopenedearly.
Theresultisthattheprojectisbehindscheduleby4workingdays.Crewsplan
tomakeupforthisduringpiledriving.
2.3.3 PotentialRisktoSchedule(Future)
DNVimposedchangestoallowablehoursofSingleLaneAlternatingTraffic.
9am3pmSLATimposesrestrictionsonthelengthoftheworkingday,reducing
efficienciesandproduction.
Inclementweatherforbridgeconstruction(bridgedeckpourscheduledfor
February).
Poorsoilconditionsforpiledriving.
BCHydro,Telus,FortisBCcoordinationandscheduling.
Document: 3350531
FOI 17-153 Page 5
FOI 17-153 Page 6
MontroyalBridgeReplacementProjectProgressReport04(September2017) 7
5.0 TRAFFICSUMMARY
5.1 IMPACTSTOONSTREETTRAFFIC
SingleLaneAlternatingTraffic(SLAT)takeshastakenplaceoften,andisauthorizedto
continueoccurMondayFridaybetweenthehoursof9am3pm.Shortdelaysoccur
becauseofthis
SLATwasauthorizedbetweenthehoursof7am8pmonanumberofoccasionsforcritical
watermainwork.Thiscausesmoresignificantdelaysandwillonlybeauthorizedas
absolutelynecessary,althoughithelpswithcrewefficiencyandproduction.
Firetruckshaveemergencypriorityduringthistimeandaccessismaintainedinandoutof
theFirehallatalltimes.
5.2 IMPACTSTOOFFSTREETTRAFFICANDPARKTRAILUSERS
MosquitoCreekTrailisphysicallyclosedapproximated50mnorthandsouthofthesite.
Advancedsignagewaspostedatthenearesttrailheadsandthenearesttrailintersections
severalweekspriortothestartoftheclosure.Thetrailisexpectedtobeclosedforthe
durationoftheproject,untiltheendofsummerof2018.Pedestrianaccesswillbe
maintainedalongtheexistingsidewalkonMontroyalBoulevard.
6.0 ENVIRONMENTALSUMMARY
Therehavebeennoreportedenvironmentalincidentsonsite.Treeprotectionfencing,silt
fencing,andcatchbasinfiltershavebeeninstalledandmaintainedthroughoutthesite.
Alistofkeyenvironmentaldocumentsisbelow:
Last
Document eDocs
Updated
MontroyalBridgeEnvironmentalFolder 3096584
ConstructionEnvironmentalManagementPlan 3205021 May11,2017
ErosionandSedimentControlPlan 3200221 May5,2017
FLNROChangesAboutaStreamPermit 3126654 Feb15,2017
LatestEnvironmentalAuditReportSeptember 3351831 September26,
2017
7.0 COMMUNICATIONSSUMMARY
Aletterwillbesenttosurroundingresidentsshortlyadvisingthemofupcomingdemolitionand
piledriving(bothnoiseintensiveactivities).ResidentscanfindmoreinformationontheDistrict
websiteandtwitter
Document: 3350531
FOI 17-153 Page 7
MontroyalBridgeReplacementProjectProgressReport04(September2017) 8
Nearbyresidentscanexpecttoreceiveongoinginformationbyletterdrop(andinthecaseof
someimmediateneighbours,byphone,inpersonorbyemail)regardingupcomingconstruction
impactsandprojectupdates.Updateswillbekepttotimeswhenchangestotrafficisscheduled
orotherwisenesecary
Keymessagesforthenextphaseofworkare:
DemolitionoftheexistingbridgeisrequiredtomakewayforthenewMontroyalBridge.
Piledrivingwillbeginandwilltakeroughly6weekstocomplete,dependingonsoil
conditionencountered.Thisisnoisybutnecessarywork.
Singlelanealternatingtrafficmaybeineffect,asrequiredonweekdays,onlybetween9am
and3pm.Bridgeusersareaskedtoobeyallflaggersandspeedlimitsthroughthework
zone.
Residentsshouldseeareductionintrafficdelaysasthemajorityoftheworkwillnowtake
placeoffofthedetourfootprint.
Expectedprojectcompletionissummer2018.
TheMontroyalBridgeisoneofourtopinfrastructurereplacementpriorities.Theproject
wasfasttrackedduetoresultsfromthebridgesinspectionandcapacityassessment.
8.0 OTHERAREASOFBUSINESS
N/A
9.0 KEYCONSTRUCTIONDOCUMENTS
Document eDocs LastUpdated
EuroviaBCConstructionContract 3169554 May5,2017
IssuedforConstructionDrawingsSealed 3176364 April7,2017
ConstructionTrafficMitigationStrategy 3209892 May17,2017
ConstructionEnvironmentalManagementPlan 3205021 May11,2017
Document: 3350531
FOI 17-153 Page 8
MontroyalBridgeReplacementProjectProgressReport04(September2017) 9
10.0 PROGRESSPHOTOS
September11th2017ViewfromNWwalltowardsthebridges.Detourbridgeonleft,oldMontroyal
bridgeontheright.
September11th,2017NWviewshowingshotcretewall,557Palisadestairs,andpartiallyfinished
railings
Document: 3350531
FOI 17-153 Page 9
MontroyalBridgeReplacementProjectProgressReport04(September2017) 10
Document: 3350531
FOI 17-153 Page 10
FOI 17-153 Page 11
FOI 17-153 Page 12
total $ 875,000.00 $ 411,606.02