FLOW CHART SLO

DISCRIPTION PJI-PJIS-SAS SUCOFINDO PLN BARISTAND DISNAKER ESDM


Check Design Document :
-Main Equipment drawing
-Single Line 2.Result :
-Main Equipment spec. submission the
1.Submission
-Grounding system drawing technical report to
-Layout drawing Disnaker-ESDM
-Fire fighting drawing
-Equipment layout drawing
-Manual book
Main Technical
-Report of UKL-UPL Equipment report
-Permit certificate
-Main equipment certificate

Design review :
-Grounding Design 1.Submission
-Short circuit level 2.Reult submission
-Electrical protection the technical report
-Mechanical Protection to Disnaker-ESDM
-Metering system 3. result :
(mechanical&electrical) Setting relay Technical
-Setting relay protection submit approval report
(must be approve by P2B)
-Clearance distance
-Crepage distance
1.Result :submission
Review of Data record testing- the report to ESDM
commissioning :
- Main Equipment
-Boiler Aux.
-Steam Turbine Aux
-Generator aux
-Transformer
Technical
-Hidrant testing report
-Grounding resistance
-Fucntion test mechanical &
electrical protection
-UPS system
-Oil transformer analisys
-Test sub system & system

1
FLOW CHART SLO

-Squential interlock
-Protection system data record
-Pneumatic and electrical test data
record
-Running test data record

Test system :
- No load test
- Dummy synchrone test
- Synchonization
- Load test 25%-75%-100% 1.Submissio
- Rejection load test (100%)
- NDC test 72 hours
n the final
- Realibility Run technical SLO
-Performance test
report to
Environmental test : ESDM
-Vibration
-Emision
CERTIFICATE
-WWTP system
-Catodic Protection

Technical Report