ANNEXURE-C-23

CERTIFICATE OF EXPENSES INCURED TO PROCURE AND ERECT MACALLOY BARS AS


SUSPENDERS WHICH HAD TO BE CONDEMNED AS A SCRAP AFTER FAILURE OF
SUSPENDERS INSTALLED FOR FOB-2

Cost of procurement of Macalloy suspender for:-

a) FOB 1 which was condemned is scrap cost as per purchase


voucher ENCLOSURE No. C 1 (Weight = 1405 + 2200) = 3605 kgs Rs. 30,51,788.00

b) FOB 2 which was condemned to scrap


Cost as per ENCLOSURE No. C 1 Rs. 18,79,479.00

(Weight 865 + 1435) = 1500 Kg


Total wt. FOB 1 + FOB 2 = 3605 + 1500 = 5105 Kg
Say 5000 Kg

Total cost suspenders FOB 1 + FOB 2 Rs. 49,31,267.00


Credit for scrap @ Rs. 100 per kg = 5105 x 100 = Rs. 5,10,500 Rs. 5,10,500.00
Claimable amount Rs. 44,20,767.00

However the claim is limited as per the value of the relevant item of BOQ of the contract, as under:-

Value as per item no. Rs. 25,00,000.00

Less value of installation not done for FOB No. 1 Rs. 1,00,000.00

TOTAL Rs. 24,00,000.00


Less value of scrap retained by P&R @ Rs. 25 per Kg =
5000 kg x 25 Rs. 1,25,000.00

Net Amount of claim Rs. 22,75,000.00

Rupees Twenty Two Lacs and seventy five thousands only.

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE-C-24

CERTIFICATE OF USE OF M40 GRADE RMC WITH STEEL BAR REINFORCEMENT ON STEEL
DECK OF FOB-2 AS PER AGREEMENT ITEM 4.1 & 4.2 & LATER DEMOLISHING OF CONCRETE
& DISPOSAL OF MALBE AS PER AGREEMENT ITEM 9.1 & 1.1, BEFORE THE COLLAPSE OF
FOB-2 DECK ON 20.09.2010

(A) Cost towards supply and placing of M40 Grade RMC from M/s ACC Faridabad Plant:-
a) Quantity of RMC Procured from M/s ACC as per the Invoice no
1642023151 dt. 20.09.2010, not measured nor paid. 27.00 Cum
b) Value of concrete Supplied as per Agreement item no. 4.2 Rs. 18,90,000.00
@Rs. 7000/ Cum = 27 x 7000

(B) Cost of Procurement & placing of TMT Bars , Grade Fe500:-


a) Quantity of TMT bars conforming to grade Fe500 9720 Kg
Value of Reinforcement as per Agreement item no. 4.1
b) Rs. 4,56,840.00
@Rs. 47/Kg = 47 x 9720
c) Less for Scrap @ rs. 15/Kg = 15 x 9720 (-)Rs. 1,45,800.00
d) Total Amount Claimed 3,11,040.00

(C) Demolishing of Cement Concrete & Disposal of same after collapse


a) Quantity of Concrete Demolished & disposed off 27 Cum
Value of Concrete Demolished & disposed off as per Agreement
b) Rs. 27,000.00
item no. 9.1 @Rs. 1000/Cum = 27 x 1000

(D) Disposal of Earth/Malba/Building rubbish etc after collapse


a) Quantity of Earth/Malba/Building rubbish etc disposed off 27 Cum
Value of Earth/Malba/Building rubbish etc disposed off as per
b) Rs. 21,816.00
Agreement item no. 1.1 @Rs. 808/Cum = 27 x 808

(E) TOTAL VALUE OF CLAIM (A+B+C+D) Rs. 28,24,656.00

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/1

CERTIFICATE OF EXPENSES INCURRED TOWARDS TRANSPORTATION OF DAMAGED DECK


STEEL WORK OF FOB 2 FROM DELHI TO WORKSHOP

RATE PER MT
(i) Collection and loading in trailor at FOB 2 site Delhi (By
own crane and manpower market rate adopted) Rs. 200.00
(ii) Road Transportation from FOB site Delhi to Ropar base
workshop of the company by own vehicle (market rate
adopted) Rs. 1250.00
(iii) Unloading, handling and stacking of damaged structural
steel components of FOB 2 (By departmental crane and
manpower market rate adopted) Rs. 200.00
Total Prime Cost Rate per MT Rs. 1650.00 per
MT

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/2

CERTIFICATE OF COST OF SUBSTITUTION OF ORIGINAL RAW STEEL SECTIONS FOR THE


BEYOND REPAIR FOR SOME OF COMPONENT OF THE DAMAGED DECK OF FOB 2

RATE PER MT
(i) Cost total quantity of raw steel substituted in the deck
steel structure 17.196 MT @ Rs. 40000.00 pmt Rs. 6,87,840.00
(Average rate for steel plates, sections and quare tubes
adopted)
(ii) Less cost of scrap generated by damaged elements of Rs. 2,57,940.00
FOB 2
17.196 MT @ Rs. 15000 pmt
TOTAL @ Rs. 25000 per MT Rs. 4,29,900.00

NB: The detailed measurements are attached.

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/3

CERTIFICATE OF EXPENSES, INCURRED FOR RE-FABRICATED OF DAMAGED STEEL


STRUCTURE INCLUDING NEW STEEL MATERIALS FOR FOB 2

RATE PER MT
(i) Labour Charges paid to the Piece Rate Worker (PRW) Rs/ 2500.00
(ii) Consumables, supplied free by the Claimant to the
PRW excluding special painting works. Rs. 1500.00
(iii) Plant and machinery deployed by the Claimant
Crane, Hydra pick and carry crane, welding sets,
cutting sets, EOT Crane, Gensets and general T&P Rs. 4500.00
(iv) Special Painting of the fabricated structure as per Rs. 7000.00
specifications
TOTAL Prime Cost Rate Rs, 15,500.00 per MT

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/4

CERTIFICATE OF EXPENSES INCURRED TO TRANSPORT RE-FABRICATED ELEMENTS OF FOB


2 DECK FROM ROPAR BASE WORKSHOP TO DELHI FOB 2 SITE

RATE PER MT
(MARKET RATES)
(i) Loading in trailor by own cranes and manpower. Rs. 200.00
(ii) Road transport from Ropar workshop to Delhi FOB site by
own trailors. Rs. 1250.00
(iii) Unloading and stacking at FOB site by own crane and
manpower. Rs. 200.00
TOTAL Prime Cost Rate per MT Rs. 1650.00

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/5

CERTIFICATE OF EXPENSES INCURRED ON ASSEMBLING AND RE-ERECTION OF THE RE-


FABRICATED DECK STEEL STRUCTURE OF FOB 2

RATE PER MT
(i) Labour rate for assembling & Erection of FOB 2 at JLN
(As per work order of the PRW Attached) Rs. 1950.00
(ii) Free supply of consumable by the claimant (Electrodes,
wire, ropes, nuts & bolts etc.) Rs. 3000.00
(iii) Charges of Plant & Machinery like crane, Hydra Welding
machines, cutting sets, jacks, cribs, general T&P and
safety gadgets (Departmental, supply) Rs. 8000.00
(iv) Free supply of Electrical power and diesel and other Rs. 1000.00
facilities as per work order
TOTAL Prime Cost Rate Per MT Rs. 13950.00

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)


ANNEXURE NO. C 25/3

CERTIFICATE OF EXPENSES INCURRED ON RECTIFICATION OF THE DAMAGED


DECK WORKS OF FOB 2

RATE WEIGHT TOTAL AMOUNT


S. No. ITEM FOR RATE ANSLYSIS
(Rs./MT) (MT) (RS.)

A. Charges towards handling Rs. 500/- 71.5 Rs. 35,500/-

Fabrication Charges
B. Rs. 4,000/- 71.5 Rs. 2,86,000/-
( Dismantling, Cutting, Refitting & Welding)

C. Consumables charges Rs. 5,000/- 71.5 Rs. 3,57,500/-

D. Assembly Charges Rs. 2,000/- 71.5 Rs. 1,43,000/-

Non Destructive Testing Charges


E. L.S. Rs. 3,80,160/-
(Ultrasonic & Dye Penetration Test)

F. Sand Blasting & Painting Charges L.S. Rs. 1,18,320/-

G. Charges towards use of Machinery Rs. 2,000/- 71.5 Rs. 1,43,000/-

TOTAL AMOUNT (IN RUPEES) 14,63,480/-

Prepared By: Certified By:

(Harmandeep Singh) (I.M. Jain)