ID TaskTask Name Duration Start Finish Predecessors

Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 PEMBANGUNAN RUMAH TIPE 165 days Fri 26/05/17 Thu 11/01/18
GRANDWICH PARK 165 days
2 Struktur 145 days Fri 26/05/17 Thu 14/12/17
145 days
3 Persiapan 145 days Fri 26/05/17 Thu 14/12/17
145 days
4 bedeng Pekerja 5 days Mon 05/06/17 Fri 09/06/17 6

5 Gudang Material 5 days Thu 01/06/17 Wed 07/06/17 7

6 Kantor ( Direksi Keet ) 5 days Fri 02/06/17 Thu 08/06/17 5

7 Pembersihan Lahan 9 days Tue 30/05/17 Fri 09/06/17 9

8 Air kerja 1 day Tue 06/06/17 Tue 06/06/17 4

9 Pagar Keliling 6 days Fri 26/05/17 Fri 02/06/17


6 days
10 Keamanan 139 days Fri 26/05/17 Thu 14/12/17 189FF+1 day
139 days
11 Pekerjaan Pondasi 31 days Wed 07/06/17 Wed 19/07/17
31 days
12 Bowplang 6 days Wed 07/06/17 Wed 14/06/17 8
6 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
13 Galian Tanah 14 days Thu 08/06/17 Tue 27/06/17 12SS+1 day
14 days
14 Pasir urug 1 day Tue 13/06/17 Tue 13/06/17 13SS+3 days
1 day
15 Lantai Kerja 1 day Tue 13/06/17 Tue 13/06/17 14SS
1 day
16 Bekisting Pondasi 2 days Wed 14/06/17 Thu 15/06/17 15SS+1 day
2 days
17 Cor Beton K300 1 day Fri 16/06/17 Fri 16/06/17 20SS+1 day
1 day
18 Batu Kali 17 days Tue 27/06/17 Wed 19/07/17 17SS+7 days
17 days
19 Besi 8 mm 1 day Thu 15/06/17 Thu 15/06/17 16SS+1 day
1 day
20 Besi 10 mm 3 days Thu 15/06/17 Mon 19/06/17 19SS
3 days
21 Urugan Tanah Kembali 1 day Mon 17/07/17 Mon 17/07/17 17FS-1 day
1 day
22 Pekerjaan Tie Beam 7 days Fri 14/07/17 Mon 24/07/17
7 days
23 Galian tie beam 1 day Fri 14/07/17 Fri 14/07/17 17FS-2 days
1 day
24 Lantai kerja 1 day Mon 17/07/17 Mon 17/07/17 23FS-1 day
1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
25 Pasir Urug 1 day Mon 17/07/17 Mon 17/07/17 23FS-1 day
1 day
26 Bekisting 1 day Tue 18/07/17 Tue 18/07/17 25FS-1 day
1 day
27 Cor Beton K300 1 day Mon 24/07/17 Mon 24/07/17 29FS-1 day
1 day
28 Besi 8 mm 2 days Thu 20/07/17 Fri 21/07/17 26FS-1 day
2 days
29 Besi 13 mm 2 days Thu 20/07/17 Fri 21/07/17 28SS
2 days
30 Pekerjaan Sloof 7 days Wed 19/07/17 Thu 27/07/17
7 days
31 Bekisting Sloof 7 days Wed 19/07/17 Thu 27/07/17 18

32 Cor Beton K300 3 days Tue 25/07/17 Thu 27/07/17 35

33 Besi 8 mm 5 days Thu 20/07/17 Wed 26/07/17 31FS-1 day

34 Besi 10 mm 3 days Thu 20/07/17 Mon 24/07/17 33SS


3 days
35 Besi 13 mm 6 days Thu 20/07/17 Thu 27/07/17 34SS
6 days
36 Pekerjaan Plat Lantai dasar 15 days Thu 27/07/17 Wed 16/08/17
15 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
37 Urugan Tanah Level 6 days Thu 27/07/17 Thu 03/08/17 32

38 Pasir Urug 1 day Tue 01/08/17 Tue 01/08/17 37

39 Rabat beton ad 1:2:3 1 day Fri 04/08/17 Fri 04/08/17 40

40 Besi 8 mm 10 days Thu 03/08/17 Wed 16/08/17 38


10 days
41 Pekerjaan Kolom Lt Dasar 19 days Wed 09/08/17 Mon 04/09/17
19 days
42 Bekisting Kolom 10 days Thu 17/08/17 Wed 30/08/17 45FS-3 days

43 Cor Beton K300 3 days Thu 24/08/17 Mon 28/08/17 42FS-2 days

44 Besi 6 mm

45 Besi 8 mm 10 days Fri 11/08/17 Thu 24/08/17 47SS+2 days


10 days
46 Besi 10 mm

47 Besi 13 mm 19 days Wed 09/08/17 Mon 04/09/17 39


19 days
48 14 days Wed 27/09/17 Mon 16/10/17
14 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
49 Bekisting Kolom 8 days Thu 05/10/17 Mon 16/10/17 52FS-1 day
8 days
50 Cor Beton K300 2 days Wed 11/10/17 Thu 12/10/17 49FS-3 days

51 Besi 6 mm 2 days
2 days
52 Besi 8 mm 4 days Wed 27/09/17 Mon 02/10/17 54SS
4 days
53 Besi 10 mm

54 Besi 13 mm 6 days Wed 27/09/17 Wed 04/10/17 62

55 Pekerjaan Balok Lt 1 23 days Fri 01/09/17 Tue 03/10/17


23 days
56 Bekisting Balok 13 days Fri 01/09/17 Tue 19/09/17 43FS-1 day
13 days
57 Cor Beton K300 3 days Wed 13/09/17 Fri 15/09/17 58FS-3 days

58 Besi D8 12 days Thu 07/09/17 Fri 22/09/17 59SS


12 days
59 Besi D13 19 days Thu 07/09/17 Tue 03/10/17 56FS-3 days

60 Pekerjaan Plat Lt 1 17 days Wed 20/09/17 Thu 12/10/17


17 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
61 Bekisting Plat 6 days Wed 20/09/17 Wed 27/09/17 57FS-2 days
6 days
62 Cor Beton K300 3 days Mon 25/09/17 Wed 27/09/17 63FS-1 day

63 Besi D10 15 days Fri 22/09/17 Thu 12/10/17 61FS-1 day

64 Pekerjaan Balok Lt Atap 9 days Fri 20/10/17 Wed 01/11/17


9 days
65 Bekisting Balok 8 days Fri 20/10/17 Tue 31/10/17 50
8 days
66 Cor Beton K300 2 days Mon 30/10/17 Tue 31/10/17 67FS-2 days

67 Besi D8 6 days Wed 25/10/17 Wed 01/11/17 68SS


6 days
68 Besi D13 4 days Wed 25/10/17 Mon 30/10/17 65FS-2 days

69 Pekerjaan Tangga 22 days Fri 27/10/17 Mon 27/11/17


22 days
70 Bekisting Tangga 2 days Fri 27/10/17 Mon 30/10/17 65

71 Cor Beton K300 3 days Mon 06/11/17 Wed 08/11/17 66


3 days
72 Besi D8 19 days Wed 01/11/17 Mon 27/11/17 73SS
19 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
73 Besi D13 6 days Wed 01/11/17 Wed 08/11/17 70
6 days
74 MEP 116 days Mon 24/07/17 Mon 01/01/18
116 days
75 Sanitary Lantai Dasar 74 days Wed 26/07/17 Mon 06/11/17
74 days
76 Toilet Utama 2 days Tue 10/10/17 Wed 11/10/17
2 days
77 Closet duduk 1 day Wed 11/10/17 Wed 11/10/17 152

78 jet washer 1 day Tue 10/10/17 Tue 10/10/17 77SS

79 Wastafel 2 days Tue 10/10/17 Wed 11/10/17 78SS


2 days
80 Shower Set 1 day Tue 10/10/17 Tue 10/10/17 79SS
1 day
81 Floor Drain 1 day Tue 10/10/17 Tue 10/10/17 80SS
1 day
82 Clean Out 1 day Tue 10/10/17 Tue 10/10/17 81SS
1 day
83 Toilet Tamu 3 days Thu 12/10/17 Mon 16/10/17
3 days
84 Closet duduk 1 day Thu 12/10/17 Thu 12/10/17 77
1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
85 jet washer 1 day Fri 13/10/17 Fri 13/10/17 84SS+1 day
1 day
86 Wastafel 2 days Fri 13/10/17 Mon 16/10/17 85SS
2 days
87 Floor Drain 1 day Fri 13/10/17 Fri 13/10/17 86SS
1 day
88 Taman 2 days Mon 16/10/17 Tue 17/10/17
2 days
89 Kran 2 days Mon 16/10/17 Tue 17/10/17 87SS+1 day
2 days
90 Dapur 1 day Mon 16/10/17 Mon 16/10/17
1 day
91 Kitchen sink set 1 day Mon 16/10/17 Mon 16/10/17 87SS+1 day
1 day
92 Lain-lain 74 days Wed 26/07/17 Mon 06/11/17
74 days
93 Septictank & 3 days Wed 26/07/17 Fri 28/07/17 27
Rembesan 3 days
94 Bak Kontrol Grill 15 days Tue 17/10/17 Mon 06/11/17 91SS+1 day
66x66 cm 15 days
95 Bak Kontrol Tertutup 9 days Wed 18/10/17 Mon 30/10/17 94SS+1 day
66x66 cm 9 days
96 Sanitary Lantai Atas 30 days Tue 21/11/17 Mon 01/01/18
30 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
97 Toilet Anak 30 days Tue 21/11/17 Mon 01/01/18
30 days
98 Closet duduk 1 day Wed 27/12/17 Wed 27/12/17 155

99 jet washer 1 day Thu 28/12/17 Thu 28/12/17 98SS+1 day


1 day
100 Wastafel 2 days Fri 29/12/17 Mon 01/01/18 99SS+1 day
2 days
101 Shower Set 1 day Tue 21/11/17 Tue 21/11/17 100SS

102 Floor Drain 1 day Tue 21/11/17 Tue 21/11/17 101SS


1 day
103 Toilet Service 1 day Wed 22/11/17 Wed 22/11/17
1 day
104 Closet jongkok 1 day Wed 22/11/17 Wed 22/11/17 102SS+1 day
1 day
105 Floor Drain 1 day Wed 22/11/17 Wed 22/11/17 104SS
1 day
106 Kran 1 day Wed 22/11/17 Wed 22/11/17 105SS
1 day
107 Ruang Jemur 2 days Wed 22/11/17 Thu 23/11/17
2 days
108 Floor Drain 1 day Thu 23/11/17 Thu 23/11/17 106SS+1 day
1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
109 Kran 1 day Wed 22/11/17 Wed 22/11/17 108SS-1 day
1 day
110 Kanopi 1 day Thu 23/11/17 Thu 23/11/17
1 day
111 Roof Drain 1 day Thu 23/11/17 Thu 23/11/17 109SS+1 day
1 day
112 Sanitary Lantai Atap 1 day Thu 23/11/17 Thu 23/11/17
1 day
113 Roof Drain 1 day Thu 23/11/17 Thu 23/11/17 111SS 1 day
Yes 1 day
114 Mekanikal Lantai Dasar 9 days Mon 24/07/17 Thu 03/08/17
9 days
115 Pipa 1 1/4" air bersih 9 days Mon 24/07/17 Thu 03/08/17 29SS+2 days
9 days
116 Pipa 1" 2 days Tue 25/07/17 Wed 26/07/17 117SS
2 days
117 Pipa 1 1/4" 1 day Tue 25/07/17 Tue 25/07/17 118SS
1 day
118 Pipa 3" 1 day Tue 25/07/17 Tue 25/07/17 119SS
1 day
119 Pipa 4" 2 days Tue 25/07/17 Wed 26/07/17 120SS
2 days
120 Pipa 6" 2 days Tue 25/07/17 Wed 26/07/17 115SS+1 day
2 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
121 Mekanikal Lantai Atas 8 days Tue 26/09/17 Thu 05/10/17
8 days
122 Pipa 1 1/4" air bersih 4 days Tue 26/09/17 Fri 29/09/17 63

123 Pipa 1" 2 days Wed 27/09/17 Thu 28/09/17 122SS+1 day
2 days
124 Pipa 1 1/4" 1 day Thu 28/09/17 Thu 28/09/17 123SS+1 day
1 day
125 Pipa 3" 5 days Fri 29/09/17 Thu 05/10/17 124SS+1 day
5 days
126 Elektrikal Lantai Dasar 14 days Thu 12/10/17 Tue 31/10/17
14 days
127 Lampu Downlight 3" 2 days Thu 12/10/17 Fri 13/10/17 152FS+1 day

128 Lampu Downlight 5" 12 days Mon 16/10/17 Tue 31/10/17 151FS+1 day

129 Lampu Taman 1 day Tue 17/10/17 Tue 17/10/17 128SS+1 day
1 day
130 Lampu Dinding 1 day Thu 26/10/17 Thu 26/10/17 131SS+2 days
1 day
131 Stop Kontak standart 6 days Tue 24/10/17 Tue 31/10/17 174FS-1 day
6 days
132 Saklar Ganda 1 day Tue 24/10/17 Tue 24/10/17 131SS
1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
133 Saklar Triple 1 day Tue 24/10/17 Tue 24/10/17 132SS
1 day
134 Saklar hotel 1 day Wed 25/10/17 Wed 25/10/17 133SS+1 day
1 day
135 Panel Listrik (PP-LD) 1 day Wed 25/10/17 Wed 25/10/17 134SS
1 day
136 AC & instalasi 2 days Thu 26/10/17 Fri 27/10/17 135SS+1 day
2 days
137 Elektrikal Lantai Atas 9 days Thu 23/11/17 Tue 05/12/17
9 days
138 Lampu Downlight 3" 4 days Fri 24/11/17 Wed 29/11/17 139SS+1 day
4 days
139 Lampu Downlight 5" 5 days Thu 23/11/17 Wed 29/11/17 154FS+1 day

140 Lampu Taman & Dinding 1 day Fri 24/11/17 Fri 24/11/17 138SS
1 day
141 Stop Kontak standart 7 days Mon 27/11/17 Tue 05/12/17 178FS+1 day

142 Saklar Tunggal ex. Clipsal 1 day Mon 27/11/17 Mon 27/11/17 141SS
1 day
143 Saklar Ganda 1 day Mon 27/11/17 Mon 27/11/17 142SS
1 day
144 Saklar Triple 1 day Mon 27/11/17 Mon 27/11/17 143SS
1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
145 Saklar hotel 1 day Mon 27/11/17 Mon 27/11/17 144SS
1 day
146 Panel Listrik (PP-LA) 1 day Mon 27/11/17 Mon 27/11/17 145SS
1 day
147 AC & instalasi 1 day Mon 27/11/17 Mon 27/11/17 146SS
1 day
148 Arsitek 76 days Thu 28/09/17 Thu 11/01/18
76 days
149 Pekerjaan Plafond 52 days Thu 26/10/17 Fri 05/01/18
52 days
150 Lantai Dasar 11 days Thu 26/10/17 Thu 09/11/17
11 days
151 Pekerjaan 11 days Thu 26/10/17 Thu 09/11/17 174FS+1 day
Gypsumboard 9mm ex 11 days
Jayaboard
152 Pekerjaan Gypsumboard 5 days Thu 26/10/17 Wed 01/11/17 151SS
Watreproofing (KM/WC) 5 days
153 Lantai Atas 11 days Fri 22/12/17 Fri 05/01/18
11 days
154 Pekerjaan 11 days Fri 22/12/17 Fri 05/01/18 178
Gypsumboard 9mm ex 11 days
Jayaboard
155 Pekerjaan Gypsumboard 5 days Mon 25/12/17 Fri 29/12/17 154SS+1 day
Watreproofing (KM/WC) 5 days
156 Pekerjaan Plafond 7 days Mon 25/12/17 Tue 02/01/18 155SS
expose Beton + finish cat 7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
157 Pekerjaan Finishing Lantai 32 days Tue 31/10/17 Wed 13/12/17
32 days
158 Lantai Dasar 24 days Tue 31/10/17 Fri 01/12/17
24 days
165 Lantai Atas 11 days Wed 29/11/17 Wed 13/12/17
11 days
170 Pekerjaan Pasangan Dinding 61 days Thu 28/09/17 Thu 21/12/17
dan Plesteran 61 days
171 Lantai Dasar 19 days Thu 28/09/17 Tue 24/10/17
19 days
172 Pasangan Dinding satu 14 days Thu 28/09/17 Tue 17/10/17 62FS+1 day
bata 1pc : 5psr

173 Plesteran Dinding 1pc : 10 days Mon 02/10/17 Fri 13/10/17 172SS+2 days
3psr 10 days
174 Acian Dinding 1pc : 3psr 14 days Thu 05/10/17 Tue 24/10/17 173SS+3 days
14 days
175 Lantai Atas 20 days Fri 24/11/17 Thu 21/12/17
20 days
176 Pasangan Dinding satu 7 days Fri 24/11/17 Mon 04/12/17 182FS+1 day
bata 1pc : 5psr

177 Plesteran Dinding 1pc : 6 days Tue 05/12/17 Tue 12/12/17 176
3psr 6 days
178 Acian Dinding 1pc : 3psr 7 days Wed 13/12/17 Thu 21/12/17 177
7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
179 Pekerjaan Atap 16 days Wed 08/11/17 Wed 29/11/17
16 days
180 Baja Ringan 9 days Wed 08/11/17 Mon 20/11/17 66FS+2 days
9 days
181 Genteng 5 days Mon 20/11/17 Fri 24/11/17 180FS+1 day

182 Genteng Nok 4 days Wed 22/11/17 Mon 27/11/17 181

183 Alumunium Foil 4 days Fri 24/11/17 Wed 29/11/17 184SS


4 days
184 Waterproffing Dak 1 day Fri 24/11/17 Fri 24/11/17 185SS+1 day
1 day
185 Lisplank 2 days Thu 23/11/17 Fri 24/11/17 182

186 Pekerjaan Pengecatan 19 days Fri 08/12/17 Wed 03/01/18


19 days
187 Cat Dinding 18 days Mon 11/12/17 Wed 03/01/18 188SS+1 day
18 days
188 Cat Plafond 7 days Fri 08/12/17 Mon 18/12/17 167FS-1 day
7 days
189 Cat Daun Pintu 1 day Wed 13/12/17 Wed 13/12/17 187SS+2 days
1 day
190 Pekerjaan Kusen Pintu dan 15 days Fri 22/12/17 Thu 11/01/18
Jendela 15 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
191 Pengadaan dan 1 day Thu 11/01/18 Thu 11/01/18 194FS+1 day
pemasangan Kusen pintu 1 day
Sleding (Kusen
192 Pengadaan dan 1 day Fri 22/12/17 Fri 22/12/17 178
pemasangan Kusen pintu 1 day
(Kusen Alumunium ex
193 Pengadaan dan 4 days Wed 27/12/17 Mon 01/01/18 192
pemasangan Kusen 4 days
Jendela (Kusen
194 Pengadaan dan 1 day Fri 05/01/18 Fri 05/01/18 193
pemasangan Kusen 1 day
Jendela Bouvenlight
195 Pengadaan dan 2 days Thu 28/12/17 Fri 29/12/17 193SS+1 day
pemasangan Kusen pintu 2 days
(Kusen Engineering Wood
196 Pengadaan dan 3 days Tue 02/01/18 Thu 04/01/18 195
pemasangan daun pintu 3 days
kayu (Engineering wood
197 Pengadaan dan 6 days Tue 02/01/18 Tue 09/01/18 196SS
pemasangan daun pintu 6 days
kayu (Engineering wood
198 Pengadaan dan 6 days Wed 03/01/18 Wed 10/01/18 197SS+1 day
pemasangan daun pintu 6 days
kayu (Engineering wood
199 Pekerjaan Engsel dan Kunci 2 days Tue 02/01/18 Wed 03/01/18
2 days
200 Pull Handle (Kunci Pintu 1 day Tue 02/01/18 Tue 02/01/18 196SS
Utama) 1 day
201 Lockase (Kunci Pintu 1 day Tue 02/01/18 Tue 02/01/18 200SS
Utama) 1 day
202 Lever Handle (Pintu 1 day Tue 02/01/18 Tue 02/01/18 201SS
R.Tidur dan Dapur) 1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
ID TaskTask Name Duration Start Finish Predecessors
Mode
Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
203 Lockase (R. Tidur dan 1 day Tue 02/01/18 Tue 02/01/18 202SS
Dapur) 1 day
204 Lever Handle (Pintu R. 1 day Tue 02/01/18 Tue 02/01/18 203SS 1 day
Tidur Service) Yes 1 day
205 Lockase (Pintu R. Tidur 1 day Tue 02/01/18 Tue 02/01/18 204SS
Service) 1 day
206 Lever Handle (Pintu 1 day Tue 02/01/18 Tue 02/01/18 205SS
Km/Wc publik) 1 day
207 Lockase (Pintu Km/Wc 1 day Tue 02/01/18 Tue 02/01/18 206SS 1 day
publik) Yes 1 day
208 Silinder Knop (Pintu 1 day Tue 02/01/18 Tue 02/01/18 207SS 1 day
Km/Wc publik) Yes 1 day
209 Silinder Knop (Pintu 1 day Tue 02/01/18 Tue 02/01/18 208SS
Km/Wc Service) 1 day
210 Lockase (Pintu Km/Wc 1 day Wed 03/01/18 Wed 03/01/18 209SS+1 day
Service) 1 day
211 Pekerjaan Lain - lain 36 days Mon 13/11/17 Mon 01/01/18
36 days
212 Pekerjaan Cermin 1 day Mon 01/01/18 Mon 01/01/18 213SS+1 day
KM/WC Utama (uk. 500 x 1 day
700 mm = 3 unit)
213 Pekerjaan Kaca 1 day Fri 29/12/17 Fri 29/12/17 187
Tempered T= 12 mm
KM/WC R. Tidur utama +
214 Pekerjaan Railling Tangga 5 days Mon 13/11/17 Fri 17/11/17 71FS+3 days
Utama + R. Service

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Durasi Kelompok Bejo
Summary Manual Summary Rollup Progress
Date: Sat 10/06/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17