III. PERALATAN
Sub Jumlah I -
Sub Jumlah II -
III. PERALATAN
1. Excavator / jam 0.4000 #REF! #REF!
2. Dump Truck / jam 0.0200 #REF! #REF!
III. PERALATAN
III. PERALATAN
III. PERALATAN
LEMBAR PERSETUJUAN
GAMBAR / SKETSA
KOMENTAR / SARAN :
Diajukan Oleh :
Diketahui/Disetujui Oleh : Konsultan Supervisi, Kontraktor Pelaksana
Direksi PT. RAYA SINERGIS,
................................................................... ................................................ .
JADWAL WAKTU PELAKSANAAN
I. PEKERJAAN PERSIAPAN
II. PEKERJAAN TANAH
A. PONDASI
B. LANTAI 1
C. LANTAI 2
D. LANTAI 3
E. LANTAI 4
F. ATAP
III. PEKERJAAN ARSITEKTUR
1. PEKERJAAN PASANGAN & PLESTERAN BATA
A. LANTAI 1
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
2. PEKERJAAN PLAFOND & GRC
A. LANTAI 1
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
E. LANTAI ATAP
3. PEKERJAAN LANTAI
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
E. ATAP
4. PEKERJAAN KOSEN PINTU & JENDELA + AKSESORIS
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
5. PEKERJAAN PENGECETAN
A. LANTAI 1
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
IV. PEKERJAAN MEP
1. PEKERJAAN INSTALASI AIR BERSIH
A. LANTAI 1
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
2. PEKERJAAN INSTALASI AIR KOTOR
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
E. ATAP
3. FIXTURE FURNISHING DAN EQUIPMENT
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
4. PEK. SUMBER DAYA LISTRIK
PANEL LISTRIK
5. PEK. RAK KABEL & FIXTURE ARMATURE PENERANGAN
A. LANTAI 1
B. LANTAI 2
C. LANTAI 3
D. LANTAI 4
6. INSTALASI PENANGKAL PETIR
PENANGKAL PETIR
7. PEKERJAAN SIGNAGE
PEKERJAAN LOGO & HURUF
8. PEK. BIO SEPTICK + INSTALASI & KELENGKAPAN LAINNYA
MUH.YAMIN AHMAD, ST
Direktur Utama
BACK UP DATA
1
I. Pekerjaan Persiapan
1. Pekerjaan Pengukuran dan pemasangan Lump sum 1.00 Ls
Bouwplank pj lebar
2. Pekerjaan Pembongkaran 21.00 x 12.00 = 252.00 m2
12 m
21 m
1m
1,00
lebar atas lebar bawah tinggi panjang
tambahan galian p= 1,0 x 3 = 3,0 m 1.20 + 1.00 x 1.00 x 3.00 = 3.30 m3
2
JUMLAH 49.06 m3
2. Galian Tanah Pondasi PG2 - m3
pj lebar tinggi jumlah
3. Galian Tanah Pondasi Poer 3.50 x 3.50 x 2.00 x 12.00 = 294.00 m3
3,50 m 2m
3b. Relokasi pipa PDAM (Pipa PVC dia. 3") Panjang = 16.00 m'
4. Pek. Pondasi Poer Plat (K1) (300 x 300) cm pj lebar tinggi jumlah
- Pekerjaan Beton 3.00 x 3.00 x 0.65 x 12.00 = 70.20 m3
3m
0,65 m
3m
BACK UP DATA
2
- Pekerjaan Besi
Besi (ulir U32)
Besi ulir d. 19 mm pj banyak jumlah berat/m
290 cm 3.10 x 28.00 x 12.00 x 2.25 = 2,343.60 Kg
10 cm 19 mm 10 cm
- Pekerjaan Besi
Besi ulir U32
pj banyak jumlah berat/m
Besi 19 mm (ulir) 3.35 x 16.00 x 12.00 x 2.25 = 1,447.20 Kg
D. 19
255 cm
10 cm
70 cm
BACK UP DATA
3
5 50 cm
5
pj lebar sisi jumlah
Pekerjaan Bekisting 2x Pakai 3.00 x 0.65 x 4.00 x 6.00 = 46.80 m2
- Pekerjaan Besi
Besi (ulir U32) pj banyak jumlah berat/m
Besi 16 mm (ulir) p= 12 m 12.62 x 8.00 x 4.00 x 1.56 = 629.99 Kg
p= 16 m 16.62 x 8.00 x 3.00 x 1.56 = 622.25 Kg
Jumlah = 1,252.24 Kg
10 cm
banyak (kg) jumlah
7a. Grouting (permukaan angkur) 5.00 x 12.00 = 60.00 Kg
pj lebar tinggi jumlah
8. Pekerjaan lantai kerja bawah pondasi poer (p1) 3.20 x 3.20 x 0.10 x 12.00 = 12.29 m3
3,20 m
t= 10 cm
0,10 m
0,85 m
pj lebar tebal
tambahan lap. Pasir bawah pondasi p = 9 m 9.00 x 0.85 x 0.05 = 0.38 m3
4.03 m3
pj lebar tebal
10. Lapisan pasir bawah pondasi batu kali PG2 - x - x 9.00 = - m3
pj lebar tebal
11. Pasangan batu kosong PG1 85.80 x 0.85 x 0.15 = 10.94 m3
0,15 m
0,85 m
pj lebar tebal
tambahan pas. batu kosong p = 9 m 9.00 x 0.85 x 0.15 = 1.15 m3
jumlah 12.09 m3
pj lebar tebal
12. Pasangan batu kosong PG2 - x - x 9.00 = - m3
BACK UP DATA
5
80 cm
3. Plat lantai beton, termasuk : beton, lantai kerja panjang lebar tebal jumlah
- Plat lantai t= 15 cm (lantai) 5.75 x 5.75 x 0.12 x 2.00 = 7.94 m3
4.75 x 5.75 x 0.12 x 4.00 = 13.11 m3
Jumlah = 21.05 m3
4. Pek. Kolom, Balok Baja (LT 1) tinggi/pj tinggi/pj tot berat/12 m jumlah
Pek. Kolom H beam 350.350 mm ( 3.541 / 12.00 ) x 1,644.0 x 12 = 5,821.40 Kg
( termasuk baut, las, plat baja & aksesoris
lainnya lengkap ) pj lebar luas tot berat/luas tot
BACK UP DATA
6
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.966 x 1.160 x 1.00 x 3.00 = 20.76 m2
596,6 cm
IWF 300.150 mm
BACK UP DATA
7
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.628 x 1.160 x 1.00 x 8.00 = 52.23 m2
562,8 cm
IWF 300.150 mm
JUMLAH = 58.39 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
BACK UP DATA
8
JUMLAH = 39.22 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
( termasuk baut, las, plat baja & aksesoris x Berat banyak jumlah = Kg
lainnya lengkap ) Plat sambungan 3.25 x 2.00 x 6.00 = 39.00 Kg
baut+mur 3/4"-5 cm 0.20 x 7.00 x 6.00 = 8.40 Kg
baut+mur 3/4"-7 cm 0.22 x 2.00 x 6.00 = 2.64 Kg
Sub Jumlah 1,364.63 Kg
cut cut
pjg lebar sisi jumlah
30 cm
5.970 x 1.160 x 1.00 x 6.00 = 41.55 m2
15 cm cut (a) pjg lebar sisi jumlah
597 cm 0.062 x 0.15 x 4.00 x 6.00 = 0.22 m2
IWF 300.150 mm Sub Jumlah 41.77 m2
BACK UP DATA
9
BACK UP DATA
10
cut cut
pjg lebar sisi jumlah
30 cm
1.970 x 1.160 x 1.00 x 3.00 = 6.86 m2
15 cm cut (a) pjg lebar sisi jumlah
197 cm 0.062 x 0.15 x 4.00 x 3.00 = 0.11 m2
IWF 300.150 mm Sub Jumlah 6.97 m2
JUMLAH 12.74 m2
18 cm
30 cm
4,5 cm
30 cm
BACK UP DATA
11
JUMLAH 2.10 m2
panjang P tot. Berat tot. jumlah
Pek. Balok IWF 200.100 mm (p=1,04 m ( 1.020 / 12.00 ) x 256.00 x 3 = 65.28 Kg
Kanopi
( termasuk baut, las, plat baja & aksesoris Berat banyaknya jumlah
lainnya lengkap ) Plat sambungan 2.25 x 2.00 x 3.00 = 13.50 Kg
baut+mur 3/4"-5 cm 0.20 x 4.00 x 3.00 = 2.40 Kg
baut+mur 3/4"-7 cm 0.22 x 4.00 x 3.00 = 2.64 Kg
Jumlah 83.82 Kg
BACK UP DATA
12
8 cm
8 cm 8 mm- 15 cm
panjang lebar jumlah jumlah / 2
Pekerjaan Bekisting 2x Pakai 3.50 x 0.44 x 3.00 / 2.00 = 2.31 m2
- Plat Bordes
panjang P tot. Berat tot. jumlah
balok bordes pj blk ( 2.40 / 12.00 ) x 168.00 x 2 = 67.20 Kg
lbr. Blk ( 1.20 / 12.00 ) x 168.00 x 3 = 50.40 Kg
atc. ( 0.80 / 12.00 ) x 168.00 x 1 = 11.20 Kg
skor ( 1.72 / 12.00 ) x 168.00 x 1 = 24.08 Kg
sub jumlah = 152.88 Kg
skor panjang luas tot Berat tot. jumlah
plat bordes/kembang t = 5 mm ( 2.82 / 2.88 ) x 110.00 x 2 = 215.42 Kg
BACK UP DATA
13
C LANTAI DUA
1. Pek. Kolom, Balok Baja panjang P tot. Berat tot. jumlah
Pek. Kolom H beam 350.350 mm (termasuk baut, las,- ( 4.00 / 12.00 ) x 1,644.0 x 12 = 6,576.00 Kg
plat, baja & aksesoris lainnya lengkap )
8 cm
8 cm 8 mm- 15 cm
tinggi lebar jumlah jumlah / 2
Pekerjaan Bekisting 2x Pakai 3.50 x 0.44 x 28.00 / 2.00 = 21.56 m2
( termasuk baut, las, plat baja & aksesoris Berat banyaknya jumlah
lainnya lengkap ) Plat sambungan (b) 6.50 x 2.00 x 3.00 = 39.00 Kg
skor (c) 8.20 x 2.00 x 3.00 = 49.20 Kg
Plat pengaku (d) 0.75 x 4.00 x 3.00 = 9.00 Kg
baut+mur 3/4"-5 cm 0.20 x 8.00 x 3.00 = 4.80 Kg
baut+mur 3/4"-7 cm 0.22 x 8.00 x 3.00 = 5.28 Kg
Sub Jumlah 764.14 Kg
BACK UP DATA
14
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.966 x 1.160 x 1.00 x 3.00 = 20.76 m2
596,6 cm
IWF 300.150 mm
JUMLAH = 23.09 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.628 x 1.160 x 1.00 x 8.00 = 52.23 m2
562,8 cm
IWF 300.150 mm
BACK UP DATA
15
JUMLAH = 58.39 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
30 cm
panjang lebar sisi jumlah
15 cm (a) 4.966 x 1.160 x 1.00 x 6.00 = 34.56 m2
496,6 cm
IWF 300.150 mm
15 cm tebal 10 mm
BACK UP DATA
16
JUMLAH = 39.22 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
cut cut
pjg lebar sisi jumlah
30 cm
5.970 x 1.160 x 1.00 x 6.00 = 41.55 m2
15 cm cut (a) pjg lebar sisi jumlah
597 cm 0.062 x 0.15 x 4.00 x 6.00 = 0.22 m2
IWF 300.150 mm Sub Jumlah 41.77 m2
JUMLAH 42.69 m2
panjang P tot. Berat tot. jumlah
Pek. Balok IWF 300.150 mm (B2) p= 4 m ( 3.97 / 12.00 ) x 440.40 x 1 = 145.70 Kg
(WC/KM)
( termasuk baut, las, plat baja & aksesoris Berat banyaknya jumlah
lainnya lengkap ) Plat sambungan 3.25 x 2.00 x 1.00 = 6.50 Kg
baut+mur 3/4"-5 cm 0.20 x 12.00 x 1.00 = 2.40 Kg
baut+mur 3/4"-7 cm 0.22 x - x - = - Kg
Sub Jumlah 154.60 Kg
BACK UP DATA
17
cut cut
pjg lebar sisi jumlah
30 cm
3.970 x 1.160 x 1.00 x 1.00 = 4.61 m2
15 cm cut (a) pjg lebar sisi jumlah
397 cm 0.062 x 0.15 x 4.00 x 1.00 = 0.04 m2
IWF 300.150 mm Sub Jumlah 4.64 m2
BACK UP DATA
18
15 4 10 mm
6 mm - 15 cm
BACK UP DATA
19
- Plat Bordes
panjang P tot. Berat tot. jumlah
balok bordes pj blk ( 2.40 / 12.00 ) x 168.00 x 2 = 67.20 Kg
lbr. Blk ( 1.50 / 12.00 ) x 168.00 x 3 = 63.00 Kg
atc. ( 0.70 / 12.00 ) x 168.00 x 1 = 9.80 Kg
skor ( 1.72 / 12.00 ) x 168.00 x 1 = 24.08 Kg
sub jumlah = 164.08 Kg
skor panjang luas tot Berat tot. jumlah
plat bordes/kembang t = 5 mm ( 3.52 / 2.88 ) x 110.00 x 2 = 268.89 Kg
BACK UP DATA
20
D LANTAI TIGA
1. Pek. Kolom, Balok Baja panjang P tot. Berat tot. jumlah
Pek. Kolom H beam 350.350 mm (termasuk baut, las,- ( 4.00 / 12.00 ) x 1,644.0 x 12 = 6,576.00 Kg
plat, baja & aksesoris lainnya lengkap )
8 cm
8 cm 8 mm- 15 cm
tinggi lebar jumlah jumlah / 2
bekisting 2 x pakai 3.50 x 0.44 x 28.00 / 2.00 = 21.56 m2
panjang P tot. Berat tot. jumlah
Pek. Balok IWF 300.150 mm (B1) p= 6 m ( 5.966 / 12.00 ) x 440.40 x 3 = 656.86 Kg
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan (b) 6.50 x 2.00 x 3.00 = 39.00 Kg
skor (c) 8.20 x 2.00 x 3.00 = 49.20 Kg
Plat pengaku (d) 0.75 x 4.00 x 3.00 = 9.00 Kg
baut+mur 3/4"-5 cm 0.20 x 8.00 x 3.00 = 4.80 Kg
baut+mur 3/4"-7 cm 0.22 x 8.00 x 3.00 = 5.28 Kg
Sub Jumlah 764.14 Kg
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.966 x 1.160 x 1.00 x 3.00 = 20.76 m2
596,6 cm
IWF 300.150 mm
BACK UP DATA
21
JUMLAH = 23.09 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan (b) 6.50 x 2.00 x 8.00 = 104.00 Kg
skor (c) 8.20 x 2.00 x 8.00 = 131.20 Kg
Plat pengaku (d) 0.75 x 4.00 x 8.00 = 24.00 Kg
baut+mur 3/4"-5 cm 0.20 x 16.00 x 8.00 = 25.60 Kg
baut+mur 3/4"-7 cm 0.22 x - x - = - Kg
Sub Jumlah 1,937.18 Kg
30 cm
panjang lebar sisi jumlah
15 cm (a) Cat dasar 5.628 x 1.160 x 1.00 x 8.00 = 52.23 m2
562,8 cm
IWF 300.150 mm
BACK UP DATA
22
JUMLAH = 136.66 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan (b) 6.50 x 2.00 x 6.00 = 78.00 Kg
skor (c) 8.20 x 2.00 x 6.00 = 98.40 Kg
Plat pengaku (d) 0.75 x 4.00 x 6.00 = 18.00 Kg
baut+mur 3/4"-5 cm 0.20 x 8.00 x 3.00 = 4.80 Kg
baut+mur 3/4"-7 cm 0.22 x 8.00 x 3.00 = 5.28 Kg
Sub Jumlah 1,297.99 Kg
30 cm
panjang lebar sisi jumlah
15 cm (a) 4.966 x 1.160 x 1.00 x 6.00 = 34.56 m2
496,6 cm
IWF 300.150 mm
15 cm tebal 10 mm
BACK UP DATA
23
JUMLAH = 3.53 m2
7 cm plat strip tebal 5 mm Lebar 7 cm
(plat pengaku)
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan 3.25 x 2.00 x 6.00 = 39.00 Kg
baut+mur 3/4"-5 cm 0.20 x 7.00 x 6.00 = 8.40 Kg
baut+mur 3/4"-7 cm 0.22 x 6.00 x 2.00 = 2.64 Kg
Sub Jumlah 1,364.63 Kg
cut cut
pjg lebar sisi jumlah
30 cm
5.970 x 1.160 x 1.00 x 3.00 = 20.78 m2
15 cm cut (a) pjg lebar sisi jumlah
597 cm 0.062 x 0.15 x 4.00 x 3.00 = 0.11 m2
IWF 300.150 mm Sub Jumlah 20.89 m2
JUMLAH 21.34 m2
panjang P tot. Berat tot. jumlah
Pek. Balok IWF 300.150 mm (B2) p= 4 m ( 3.97 / 12.00 ) x 440.40 x 1 = 145.70 Kg
(WC/KM)
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan 3.25 x 2.00 x 1.00 = 6.50 Kg
baut+mur 3/4"-5 cm 0.20 x 12.00 x 1.00 = 2.40 Kg
baut+mur 3/4"-7 cm 0.22 x - x - = - Kg
Sub Jumlah 154.60 Kg
BACK UP DATA
24
cut cut
pjg lebar sisi jumlah
30 cm
3.970 x 1.160 x 1.00 x 1.00 = 4.61 m2
15 cm cut (a) pjg lebar sisi jumlah
397 cm 0.062 x 0.15 x 4.00 x 1.00 = 0.04 m2
IWF 300.150 mm Sub Jumlah 4.64 m2
BACK UP DATA
25
15 4 10 mm
6 mm - 15 cm
BACK UP DATA
26
Plat Bordes
panjang P tot. Berat tot. jumlah
balok bordes pj blk ( 1.30 / 12.00 ) x 168.00 x 2 = 36.40 Kg
lbr. Blk ( 1.30 / 12.00 ) x 168.00 x 3 = 54.60 Kg
skor ( 1.50 / 12.00 ) x 168.00 x 1 = 21.00 Kg
sub jumlah = 112.00 Kg
BACK UP DATA
27
E LANTAI EMPAT
1. Pek. Kolom, Balok Baja panjang P tot. Berat tot. jumlah
Pek. Kolom H beam 350.350 mm (termasuk baut, las,- ( 4.000 / 12.00 ) x 1,644.0 x 12 = 6,576.00 Kg
plat, baja & aksesoris lainnya lengkap )
berat banyak jumlah
Plat sambungan (a) 12.60 x 4.00 x 12.00 = 604.80 Kg
Plat sambungan (b) 6.30 x 4.00 x 12.00 = 302.40 Kg
baut+mur 3/4"-5 cm 0.20 x - x - = - Kg
baut+mur 3/4"-7 cm 0.22 x 72.00 x 12.00 = 190.08 Kg
Jumlah 7,673.28 Kg
15 cm tebal 10 mm
BACK UP DATA
28
8 cm
( termasuk baut, las, plat baja & aksesoris 0.15 x berat banyak jumlah = Kg
lainnya lengkap ) Plat sambungan (b) 4.50 x 2.00 x 3.00 = 27.00 Kg
skor (c) 5.80 x 2.00 x 3.00 = 34.80 Kg
Plat pengaku (d) 0.40 x 8.00 x 3.00 = 9.60 Kg
baut+mur 3/4"-5 cm 0.20 x 8.00 x 3.00 = 4.80 Kg
baut+mur 3/4"-7 cm 0.22 x 8.00 x 3.00 = 5.28 Kg
Sub Jumlah 613.21 Kg
25 cm
panjang lebar sisi jumlah
12,5 cm (a) Cat dasar 5.988 x 0.988 x 1.00 x 3.00 = 17.75 m2
598,8 cm
IWF 250.125 mm
JUMLAH = 19.51 m2
5 cm plat strip tebal 5 mm Lebar 5 cm
(plat pengaku)
BACK UP DATA
29
( termasuk baut, las, plat baja & aksesoris 0.15 x berat banyak jumlah = Kg
lainnya lengkap ) Plat sambungan (b) 4.50 x 2.00 x 8.00 = 72.00 Kg
skor (c) 5.80 x 2.00 x 8.00 = 92.80 Kg
Plat pengaku (d) 0.40 x 8.00 x 8.00 = 25.60 Kg
baut+mur 3/4"-5 cm 0.20 x 16.00 x 8.00 = 25.60 Kg
baut+mur 3/4"-7 cm 0.22 x - x - = - Kg
Sub Jumlah 1,548.71 Kg
25 cm
panjang lebar sisi jumlah
12,5 cm (a) Cat dasar 5.628 x 0.988 x 1.00 x 8.00 = 44.48 m2
5628 cm
IWF 250.125 mm
JUMLAH = 49.17 m2
5 cm plat strip tebal 5 mm Lebar 5 cm
(plat pengaku)
BACK UP DATA
30
25 cm
panjang lebar sisi jumlah
12,5 cm (a) Cat dasar 4.988 x 0.988 x 1.00 x 6.00 = 29.57 m2
498,8 cm
IWF 250.125 mm
JUMLAH = 33.64 m2
5 cm plat strip tebal 5 mm Lebar 5 cm
(plat pengaku)
cut cut
pjg lebar sisi jumlah
25 cm
5.988 x 0.0988 x 1.00 x 1.00 = 0.59 m2
125 cm cut (a) pjg lebar sisi jumlah
598,8 cm 0.060 x 0.125 x 4.00 x 1.00 = 0.03 m2
IWF 250.125 mm Sub Jumlah 0.56 m2
BACK UP DATA
31
JUMLAH = 0.88 m2
5 cm plat strip tebal 5 mm Lebar 5 cm
(plat pengaku)
cut cut
pjg lebar sisi jumlah
25 cm
2.988 x 0.0988 x 1.00 x 2.00 = 0.59 m2
125 cm cut (a) pjg lebar sisi jumlah
298,8 cm 0.060 x 0.125 x 4.00 x 2.00 = 0.06 m2
IWF 250.125 mm Sub Jumlah 0.53 m2
JUMLAH = 1.16 m2
5 cm plat strip tebal 5 mm Lebar 5 cm
(plat pengaku)
BACK UP DATA
32
( termasuk baut, las, plat baja & aksesoris berat banyak jumlah
lainnya lengkap ) Plat sambungan 3.25 x 2.00 x - = - Kg
baut+mur 3/4"-5 cm 0.20 x 12.00 x - = - Kg
baut+mur 3/4"-7 cm 0.22 x - x - = - Kg
Jumlah - Kg
15 cm
panjang lebar sisi jumlah
7,5 cm (a) Cat dasar 4.988 x 0.988 x 1.00 x 6.00 = 29.57 m2
498,8 cm
IWF 150.75 mm
BACK UP DATA
33
15 4 10 mm
6 mm - 15 cm
pj lebar jumlah 2xpakai
Pekerjaan Bekisting 2x Pakai 4.50 x 0.41 x 4.00 2.00 = 3.69 m2
Jumlah 3.69 m2
1a. Pek. Kuda-kuda Baja H beam 350.350 (termasuk panjang P tot. Berat tot. jumlah
baut, las, plat baja & aksesoris lainnya lengkap ) ( 0.974 / 12.00 ) x 1,644.0 x 7 = 934.07 Kg
BACK UP DATA
34
25 cm
IWF 250.125 mm
panjang lebar sisi jumlah
25 cm Cat dasar 0.25 x 0.125 x 2.00 x 1.00 = 0.06 m2
0.75 x 0.010 x 1.00 x 1.00 = 0.01 m2
12,5 cm (b) Luas banyaknya sisi jumlah
Plat sambungan tebal 10 mm 0.00038 x 4.00 x 2.00 x 1.00 = 0.0030 m2
Sub Jumlah 0.07 m2
JUMLAH = 1.42 m2
BACK UP DATA
35
BACK UP DATA
36
BACK UP DATA
37
54
25 cm
BACK UP DATA
38
15 cm
panjang lebar sisi jumlah
7,5 cm Cat dasar 1.080 x 0.740 x 1.00 x 8.00 = 6.39 m2
108 - 125 cm 1.250 x 0.740 x 1.00 x 6.00 = 5.55 m2
IWF 150.75 mm 1.150 x 0.740 x 1.00 x 4.00 = 3.40 m2
Sub Jumlah 15.35 m2
panjang lebar sisi jumlah
Cat dasar 0.30 x 0.075 x 2.00 x 8.00 = 0.36 m2
30 cm 0.75 x 0.010 x 1.00 x 8.00 = 0.06 m2
(a) Luas banyaknya sisi jumlah
0.00038 x 8.00 x 2.00 x 8.00 = 0.05 m2
Sub Jumlah 0.37 m2
BACK UP DATA
39
4a. Pek. Gording Canal C 125.50.20 mm p=6m ( 18.00 / 6.00 ) x 27.10 x 8 = 650.40 Kg
( termasuk baut, las, plat baja & aksesoris ( 14.00 / 6.00 ) x 27.10 x 8 = 505.87 Kg
lainnya lengkap ) JUMLAH 1,156.27 Kg
BACK UP DATA
40
BACK UP DATA
41
200 cm
300 cm
BACK UP DATA
42
BACK UP DATA
43
BACK UP DATA
44
50 cm JUMLAH = 6.93 m2
kolom tengah Lt.2 Plesteran 0.70 x 3.30 x 3 = 6.93 m2
acian 0.70 x 3.30 x 3 = 6.93 m2
50 cm JUMLAH = 13.20 m2
BACK UP DATA
45
BACK UP DATA
46
BACK UP DATA
47
BACK UP DATA
48
50 cm JUMLAH = 6.93 m2
Plesteran 0.70 x 3.30 x 3 = 6.93 m2
kolom tengah Lt. 3 acian 0.70 x 3.30 x 3 = 6.93 m2
50 cm JUMLAH = 13.20 m2
kolom tengah Lt. 3
pj tinggi reali banyak
Plesteran 2.00 x 3.30 x 2 = 13.20 m2
acian 2.00 x 3.30 x 2 = 13.20 m2
BACK UP DATA
49
BACK UP DATA
50
BACK UP DATA
51
BACK UP DATA
52
50 cm JUMLAH = 6.93 m2
Plesteran 0.70 x 3.30 x 3 = 6.93 m2
kolom tengah Lt. 4 acian 0.70 x 3.30 x 3 = 6.93 m2
50 cm JUMLAH = 13.20 m2
kolom tengah Lt. 4
pj tinggi reali banyak
Plesteran 2.00 x 3.30 x 2 = 13.20 m2
acian 2.00 x 3.30 x 2 = 13.20 m2
BACK UP DATA
53
BACK UP DATA
54
BACK UP DATA
55
B LANTAI DUA
1 Pemasangan Rangka plafond hollow Rangka 2x4 & pas. rangka plafond / plafond
4x4x0,30 mm pj lebar banyak
2 Pekerjaan Plafond Gypsum 9 mm rangka/plafond 15.88 x 11.88 x 1 = 188.65 m2
klm tepi (-) 0.19 x 0.19 x 3 = 0.11 m2
klm tepi tgh (-) 0.50 x 0.19 x 6 = 0.57 m2
klm tengah (-) 0.50 x 0.50 x 2 = 0.50 m2
wc wc (-) 3.88 x 2.88 x 1 = 11.17 m2
+3,20 m 12 m JUMLAH = 176.30 m2
16 m
t = 0,60 m
BACK UP DATA
56
No. Gambar Sketsa Perhitungan Jumlah
JUMLAH = 26.00 m2
C LANTAI TIGA
1 Pemasangan Rangka plafond hollow Rangka 2x4 & pas. rangka plafond / plafond
4x4x0,30 mm pj lebar banyak
2 Pekerjaan Plafond Gypsum 9 mm rangka/plafond 15.88 x 11.88 x 1 = 188.65 m2
klm tepi (-) 0.19 x 0.19 x 3 = 0.11 m2
klm tepi tgh (-) 0.50 x 0.19 x 6 = 0.57 m2
klm tengah (-) 0.50 x 0.50 x 2 = 0.50 m2
wc wc (-) 3.88 x 2.88 x 1 = 11.17 m2
12 m JUMLAH = 176.30 m2
16 m
BACK UP DATA
57
t = 0,60 m
JUMLAH = 26.00 m2
D LANTAI EMPAT
1 Pemasangan Rangka plafond hollow Rangka 2x4 & pas. rangka plafond
4x4x0,30 mm pj lebar banyak
2 Pekerjaan Plafond Gypsum 9 mm rangka/plafond 15.88 x 11.88 x 1 = 188.65 m2
klm tepi (-) 0.19 x 0.19 x 3 = 0.11 m2
klm tepi tgh (-) 0.50 x 0.19 x 6 = 0.57 m2
klm tengah (-) 0.50 x 0.50 x 2 = 0.50 m2
wc wc (-) 3.88 x 2.88 x 1 = 11.17 m2
12 m JUMLAH = 176.30 m2
t = 0,60 m
JUMLAH = 26.00 m2
JUMLAH = 79.60 m2
18 m
3 PEKERJAAN LANTAI
A LANTAI SATU
1 Pasang Granit 60 x 60 cm
Pek. Tegel granit 60 x 60 cm
pj lebar banyak
tegel RU - x - x - = - m2
12 m tegel KM (-) - x - x - = - m2
JUMLAH = Err:522 m2
16 m
2 Pasang Keramik 60 x 60 KM/WC
Pek. Tegel granit 60 x 60 cm KM
pj lebar banyak
tegel granit - x - x - = - m2
- x - x - = - m2
JUMLAH = - m2
B LANTAI DUA
1 Pasang Granit 60 x 60 cm
C LANTAI TIGA
1 Pasang Granit 60 x 60 cm
D LANTAI EMPAT
1 Pasang Granit 60 x 60 cm
E LANTAI ATAP
1 Waterproofing membran Plat Atap & KM/WC
Lantai 2,3,4
lebar tinggi banyak
KM/WC 1.85 x 1.80 x 8 = 26.64 m2
1.35 x 1.80 x 8 = 19.44 m2
2m pintu (-) 0.70 x 1.80 x 6 = 7.56 m2
Sub jumlah = 38.52 m2
3 LANTAI 3.00
WC/KM Sub jumlah = 115.56 m2
3m
18
Lantai 2
pj lebar banyak
lantai atap lantai 2 0,97 Lantai 2 16.15 x 0.97 x - = - m2
Sub jumlah = - m2
16,15
TOTAL = 169.56 m2
BACK UP DATA
64
5 PEKERJAAN PENGECETAN
A LANTAI SATU
1 Cat Plafond beton pj tinggi reali banyak/sisi
1a Cat Listplank beton cat 18.15 x 0.92 x 2 = 33.40 m2
1m 16,15 m 1 m
2 cat tembok shaft 3,5 m cat dinding bata dalam
0 pj tinggi reali banyak
skor tembok 0.61 x 3.50 x 2 = 4.27 m2
JUMLAH = 4.27 m2
cat dinding bata luar
SHAFT pj tinggi reali banyak
61 cm 61 cm tembok 0.61 x 3.50 x 2 = 4.27 m2
JUMLAH = 4.27 m2
BACK UP DATA
65
BACK UP DATA
66
SHAFT
61 cm 61 cm
6m
BACK UP DATA
67
3,05 m
3,38 m
2,39 m
0,70 m 1,20 m
km Lt. 2,3,4
TOTAL CAT DINDING DALAM 200.13 m2
TOTAL CAT DINDING LUAR 153.71 m2
BACK UP DATA
68
BACK UP DATA
69
BACK UP DATA
70
8 cm
MARKUS DONDAN, ST
(Pengawas PU)
5.4
59.4
4.4
26.4
85.8
3.4
363.100
354.1 PER TANGGAL 16 -8-2017
6,474.20
OK 5.966
8 baut
8 baut
764.14
0.061275
27.2
26.5 0.0612
16 baut
1,937.18
8 baut
8 baut
1,297.99
3999.3106 jumlah iwf 300.150 (1)
8 baut
1,364.63
154.72
117.90
241.32
1878.569 B2
5.25
4.25
370.83
68.22
83.82
1,157.19
212.37
18.00
Err:522 JUMLAH
0.13
27.23
10.39
2.31
6.30
368.30
23.07
50.03
6,576.00
1.19
254.15
96.97
21.56
764.14
16 baut
1,937.18
1,297.99
116.70
1635.932 jumlah iwf 300.150 B2
0.30
48.11
12.67
3.69
23.52
1,067.83
195.97
6.30
432.97
25.67
52.62
6,576.00
764.14
1,937.18
8 baut
1,297.99
3999.3106 jumlah iwf 300.150 B1
8 baut
1,364.63
154.60
118.02
242.40
0.30
48.11
12.67
3.69
23.52
1,069.19
196.22
6.20
25.67
51.63
7,673.28
1.19
254.15
96.97
21.56
613.21
1,548.71
1,062.75
3,224.67
186.14
194.69
380.8344 (B2)
3,605.51 total b2
-
-
0.30
48.11
12.67
3.69
5.83
521.02
48.53
-
934.07 0.974
44.20
128.40
586
1,446.65
0.037994
195.89
1,815.14 jumlah iwf 250
0.000531
0.013
1,180.46
650.40
505.87
1,156.27
0.000133
0.0065
63.00
39.93
1.37
6.44
125.41
4.14
12.00
224.00
18.00
1.59
71.96
13.28
66.79
72.60
72.60
66.79
72.60
72.60
7.26
8.54
8.54
7.26
8.54
8.54
20.46
41.93
41.81
29.56
60.13
60.07
13.52
13.52
31.72
39.55
2.86
1.98
44.15
44.15
14.29
sudut
0,0024 m3
v bata = 0,20 x 0,10 x 0,05
35.75 = 0,001 m3
= 0,02 m2 ( x 20)
35.75 = 0,2 m (x 10)
4.64
9.90
9.90
6.93
6.93
6.93
13.20
13.20
13.20
175.13
225.32
225.32
7.26
8.54
8.54
7.26
8.54
8.54
19.81
11.10
11.10
-
11.10
21.00
8.40
2.10
10.50
8.40
2.10
10.50
56.78
61.16
61.16
20.46
41.81
41.81
29.56
60.13
60.07
13.52
13.52
33.86
79.10
5.72
3.96
12.48
-
76.06
76.06
14.29
35.75
35.75
###
4.75
9.90
9.90
6.93
6.93
6.93
13.20
13.20
13.20
177.38
257.23
257.23
7.26
8.54
8.54
7.26
8.54
8.54
19.81
11.10
11.10
11.10
21.00
8.40
2.10
10.50
8.40
2.10
10.50
56.78
61.16
61.16
20.46
41.81
41.81
29.56
60.13
60.07
13.52
13.52
79.10
5.72
3.96
12.48
-
76.06
76.06
14.29
35.75
35.75
182.30
257.23
257.23
7.26
8.54
8.54
7.26
8.54
8.54
21.00
8.40
2.10
10.50
8.40
2.10
10.50
56.78
61.16
61.16
70.84
3.96
74.80
74.80
176.30
10.11
79.97
26.00
176.30
10.11
79.97
26.00
176.30
176.30
10.11
79.97
26.00
79.60
Err:522
80.37
1.41
179.11
9.99
34.35
1.47
179.11
9.99
34.35
1.47
179.11
9.99
34.35
1.47
38.52
54.00
-
33.40
4.27
4.27
20.84
20.97
29.94
30.07
6.73
6.79
39.55
1.43
0.99
36.69
17.17
9.90
6.93
13.20
20.46
19.33
19.78
10.50
200.13
153.71
176.30
10.11
12.18
9.99
24.36
19.98
19.46
38.93
2.94
6.25
3.45
6.75
0.05
11.28
4.33
0.99
MUTUAL CHEK 0% (MC-0%)
UNIT KERJA : BALAI BESAR WILAYAH SUNGAI POMPENGAN JENEBERANG :CV.EXINDO CONSULTAN
PAKET PEKERJAAN : RENOVASI GEDUNG KANTOR BBWSPJ : HK.02.03/SATKER-BBWSPJ/PPK-KTL/002/IV/2017
TAHUN ANGGARAN : 2017 : 10 APRIL 2017
PROVINSI : SULAWESI SELATAN : Rp. 3.720.203.000,- (PPn)
No. Kontrak Awal CONTRAC CHANGE ORDER (CCO) BOBOT RENCANA (%)
Item Uraian Pekerjaan Satuan Harga Satuan Jumlah Harga SELISIH (+/-) Harga Satuan Harga Satuan Jumlah Harga KONTRAK MC-0
Volume Volume
(Rp) (Rp) (Rp) (Rp) Negosiasi (Rp) (Rp) (%) (%)
1 2 3 4 5 6=4x5 13 14 15=13x14
I. Pekerjaan Persiapan
1. Pengukuran dan Pemasangan Bouwplank Ls 1.00 3,907,120.00 3,907,120.00 - 1.00 3,907,120.00 3,907,120.00 0.12%
2. Pekerjaan Pembongkaran m2 192.00 57,272.00 10,996,224.00 3,436,320.00 252.00 57,272.00 14,432,544.00
II. Pekerjaan Struktur
A. Pondasi
1. Galian tanah pondasi PG1 m3 57.38 36,891.00 2,116,805.58 721,956.87 76.95 36,891.00 2,838,762.45
2. Galian tanah pondasi PG2 m3 7.85 36,891.00 289,594.35 -289,594.35 - - -
3. Galian tanah pondasi Poer (P1) m3 307.20 36,891.00 11,332,915.20 -1,029,258.90 279.30 36,891.00 10,303,656.30
3.a Pembuangan hasil bongkaran dan galian tanah keluar m3 - - - 24,530,986.12 197.46 - 124,230.00 24,530,986.12
lokasi pekerjaan
4 Pondasi Poer plat P1 ( 300 x 300 ) cm
Pekerjaan Beton m3 54.00 936,138.00 50,551,452.00 15,165,435.60 70.20 936,138.00 65,716,887.60
Pekerjaan Pembesian
Besi Kg 6,998.22 14,468.00 101,250,246.96 40,511,557.44 9,798.30 14,468.00 141,761,804.40
Pekerjaan Bekisting 1x Pakai m2 72.00 155,391.00 11,188,152.00 3,356,445.60 93.60 155,391.00 14,544,597.60
5 Pedestal Kolom K1 ( 60 x 60 ) cm
Pekerjaan Beton m3 12.53 936,138.00 11,729,809.14 -4,045,988.44 8.21 936,138.00 7,683,820.70
Pekerjaan Pembesian
Besi D 19 mm Kg 878.76 14,468.00 12,713,899.68 8,224,189.92 1,447.20 14,468.00 20,938,089.60
Besi 10 mm Kg 497.74 13,334.00 6,636,865.16 -2,470,256.84 312.48 13,334.00 4,166,608.32
Pekerjaan Bekisting 2x Pakai m2 43.85 310,522.00 13,616,389.70 -5,120,507.78 27.36 310,522.00 8,495,881.92
6 Balok Sloof Tipe S1 25/40 cm
Pekerjaan Beton m3 8.50 936,138.00 7,957,173.00 196,588.98 8.71 936,138.00 8,153,761.98
Pekerjaan Pembesian
Besi D 16 mm (ulir) Kg 1,073.20 14,468.00 15,527,057.60 2,590,397.02 1,252.24 14,468.00 18,117,454.62
Besi 12 mm (polos) Kg 150.92 13,334.00 2,012,367.28 -627,865.93 103.83 13,334.00 1,384,501.35
Besi 8 mm (polos) Kg 327.33 13,334.00 4,364,618.22 148,847.76 338.49 13,334.00 4,513,465.98
Pekerjaan Bekisting 2x Pakai m2 68.00 164,054.00 11,155,672.00 269,048.56 69.64 164,054.00 11,424,720.56
7 Pekerjaan Angkur Besi 14 mm pada Sloef Kg 77.03 13,334.00 1,027,118.02 -1,027,118.02 - 13,334.00 -
8 Pekerjaan Angkur Besi 19 mm pada Sloef Kg - - - 2,279,092.51 170.92 - 13,334.00 2,279,092.51
9 Pekerjaan Grouting plat dudukan kolom Kg - - - 3,482,640.00 60.00 - 58,044.00 3,482,640.00
10 Pekerjaan lantai kerja bawah pondasi poer (p1) m3 12.29 887,571.00 10,908,247.59 -1,775.14 12.29 887,571.00 10,906,472.45
11 Lapisan pasir bawah pondasi batu kali PG1 m3 3.61 183,783.00 663,456.63 -663,456.63 - 183,783.00 -
12 Lapisan pasir bawah pondasi batu kali PG2 m3 0.65 183,783.00 119,458.95 -119,458.95 - 183,783.00 -
3. Balok Latai
Pekerjaan Beton m3 1.67 887,571.00 1,482,243.57 -1,218,634.98 0.30 887,571.00 263,608.59
Pekerjaan Pembesian
Besi 10 mm Kg 340.51 13,334.00 4,540,360.34 -3,898,834.93 48.11 13,334.00 641,525.41
Besi 6 mm Kg 55.16 13,334.00 735,503.44 -566,534.99 12.67 13,334.00 168,968.45
Pekerjaan Bekisting 2x Pakai m2 30.38 310,522.00 9,433,658.36 -8,287,832.18 3.69 310,522.00 1,145,826.18
4. Plat beton, termasuk: beton, besi, & bekisting
- Plat Lantai t= 12 cm + (8,00)
Pekerjaan Beton m3 21.58 936,138.00 20,201,858.04 1,813,018.46 23.52 936,138.00 22,014,876.50
Pekerjaan wiremesh DM 8 Kg 1,069.41 14,823.00 15,851,864.43 -23,487.56 1,067.83 14,823.00 15,828,376.87
Pekerjaan Bekisting floodeck KR 0,70 m2 196.22 95,241.00 18,688,189.02 -23,572.15 195.97 95,241.00 18,664,616.87
4.a List plank Beton
Pekerjaan Beton m3 - - - 1,428,471.70 1.53 936,138.00 1,428,471.70
Pekerjaan wiremesh DM 8 kg - - - 1,027,050.43 69.29 14,823.00 1,027,050.43
Pekerjan Bekisting 2x pakai m2 - - - 3,573,442.32 37.52 95,241.00 3,573,442.32
- Plat meja beton
Pekerjaan Beton m3 0.12 887,571.00 106,508.52 11,644.93 0.13 887,571.00 118,153.45
Pekerjaan Pembesian
Besi 10 mm Kg 9.32 13,334.00 124,272.88 127,819.72 18.91 13,334.00 252,092.60
Pekerjaan Bekisting 2x Pakai m2 1.66 373,522.00 620,046.52 -309,276.22 0.83 373,522.00 310,770.30
Tangga baja (lengkap pengelasan baut dan aksesoris
lainnya)
5. - Tangga baja m' 5.23 1,419,589.00 7,424,450.47 11,938,743.49 13.64 1,419,589.00 19,363,193.96
D LANTAI TIGA
1. Pek. Kolom, Balok Baja
- Pek. Kolom H beam 350.350 mm (termasuk baut, las,- Kg 6,576.00 29,343.00 192,959,568.00 - 6,576.00 29,343.00 192,959,568.00
plat, baja & aksesoris lainnya lengkap )
- Pek. Pengecetan dasar baja m2 - - - 2,036,952.00 68.40 29,780.00 2,036,952.00
- Kolom Beton Kp ( 11 x 11 )
Pekerjaan Beton m3 0.45 887,571.00 399,406.95 653,074.74 1.19 887,571.00 1,052,481.69
Pekerjaan Pembesian
Besi 10 mm Kg 92.48 13,334.00 1,233,128.32 -1,233,128.32 254.15 -
Besi 8 mm Kg 14.98 13,334.00 199,743.32 1,093,249.33 96.97 13,334.00 1,292,992.65
Pekerjaan Bekisting 2x Pakai m2 16.50 310,522.00 5,123,613.00 1,571,241.32 21.56 310,522.00 6,694,854.32
2. Pek. Balok Baja + 12,00
- Pek. Balok IWF 300.150 mm (B1) (termasuk baut, las, plat Kg 4,475.58 29,343.00 131,326,943.94 -29,262,678.43 3,478.32 29,343.00 102,064,265.51
baja & aksesoris lainnya lengkap )
- Pek. Balok IWF 300.150 mm (B2) (termasuk baut, las, plat Kg 686.29 29,343.00 20,137,807.47 30,741,976.43 1,733.97 29,343.00 50,879,783.90
baja & aksesoris lainnya lengkap )
- Pek. Pengecetan dasar baja m2 - - - 4,243,947.80 142.51 29,780.00 4,243,947.80
3. Balok Latai
Pekerjaan Beton m3 1.67 887,571.00 1,482,243.57 -1,218,634.98 0.30 887,571.00 263,608.59
Pekerjaan Pembesian
Besi 10 mm Kg 340.51 13,334.00 4,540,360.34 -3,898,834.93 48.11 13,334.00 641,525.41
Besi 6 mm Kg 55.16 13,334.00 735,503.44 -566,534.99 12.67 13,334.00 168,968.45
Pekerjaan Bekisting 2x Pakai m2 30.38 310,522.00 9,433,658.36 -8,287,832.18 3.69 310,522.00 1,145,826.18
4. Plat beton, termasuk: beton, besi, & bekisting
- Plat Lantai t= 12 cm + (12,00)
Pekerjaan Beton m3 21.58 936,138.00 20,206,047.26 1,808,829.25 23.52 936,138.00 22,014,876.50
Pekerjaan wiremesh DM 8 Kg 1,069.41 14,823.00 15,851,864.43 -23,487.56 1,067.83 14,823.00 15,828,376.87
Pekerjaan Bekisting floordeck KR 0,70 m2 196.22 95,241.00 18,688,189.02 -23,572.15 195.97 95,241.00 18,664,616.87
- Plat meja beton
Pekerjaan Beton m3 0.12 887,571.00 106,508.52 11,644.93 0.13 887,571.00 118,153.45
Pekerjaan Pembesian
Besi 10 mm Kg 9.32 13,334.00 124,272.88 127,819.72 18.91 13,334.00 252,092.60
Pekerjaan Bekisting 2x Pakai m2 1.66 373,522.00 620,046.52 -309,276.22 0.83 373,522.00 310,770.30
Tangga baja (lengkap pengelasan baut dan aksesoris
lainnya)
5. - Tangga baja m' 5.23 1,419,589.00 7,424,450.47 11,938,743.49 13.64 1,419,589.00 19,363,193.96
E LANTAI EMPAT
1. Pek. Kolom, Balok Baja
Pek. Kolom H beam 350.350 mm (termasuk baut, las,- Kg 6,576.00 29,343.00 192,959,568.00 - 6,576.00 29,343.00 192,959,568.00
plat, baja & aksesoris lainnya lengkap )
- Pek. Pengecetan dasar baja m2 - - - 2,036,952.00 68.40 29,780.00 2,036,952.00
- Kolom Beton Kp ( 11 x 11 ) + reservoir
` Pekerjaan Beton m3 0.45 887,571.00 399,406.95 653,074.74 1.19 887,571.00 1,052,481.69
Pekerjaan Pembesian
Besi 10 mm Kg 92.48 13,334.00 1,233,128.32 2,155,713.11 254.15 13,334.00 3,388,841.43
Besi 8 mm Kg 14.98 13,334.00 199,743.32 1,093,249.33 96.97 13,334.00 1,292,992.65
Pekerjaan Bekisting 2x Pakai m2 16.50 310,522.00 5,123,613.00 1,571,241.32 21.56 310,522.00 6,694,854.32
2. Ring Balok Baja, baja talang + 12,00
- Pek. Balok IWF 250.125 mm (B1a) (termasuk baut, las,- Kg 2,841.60 29,343.00 83,381,068.80 13,568,222.76 3,304.00 29,343.00 96,949,291.56
plat baja & aksesoris lainnya lengkap )
- Pek. Balok IWF 100.50 mm (B1a) (termasuk baut, las,- Kg 117.56 29,343.00 3,449,563.08 -3,449,563.08 - 29,343.00 -
plat baja & aksesoris lainnya lengkap )
- Pek. Balok IWF 125.50 mm (B1a) (termasuk baut, las,- Kg 740.32 29,343.00 21,723,209.76 -21,723,209.76 - 29,343.00 -
plat baja & aksesoris lainnya lengkap )
Pek. Balok Canopi IWF 150.75 mm (B1a) (termasuk baut, las,- Kg 23,358,201.72 796.04 29,343.00 23,358,201.72
plat baja & aksesoris lainnya lengkap )
- Pek. Pengecetan dasar baja m2 - - - 4,243,947.80 142.51 29,780.00 4,243,947.80
3. Balok Latai
Pekerjaan Beton m3 1.88 887,571.00 1,668,633.48 -1,405,024.89 0.30 887,571.00 263,608.59
Pekerjaan Pembesian
Besi 10 mm Kg 383.41 13,334.00 5,112,388.94 -4,470,863.53 48.11 13,334.00 641,525.41
Besi 6 mm Kg 62.11 13,334.00 828,174.74 -659,206.29 12.67 13,334.00 168,968.45
Pekerjaan Bekisting 2x Pakai m2 34.21 310,522.00 10,622,957.62 -9,477,131.44 3.69 310,522.00 1,145,826.18
SUB JUMLAH IV 405,914,600.82 7,054,468.17 412,969,068.99
1 2 3 4 5 6=4x5 13 14 15=13x14
4. Plat beton, termasuk: beton, besi, & bekisting
- Plat Lantai t= 12 cm (talang beton +16,00)
Pekerjaan Beton m3 7.14 936,138.00 6,684,025.32 -3,956,403.77 2.91 936,138.00 2,727,621.55
Pekerjaan wiremesh DM 8 Kg 353.92 14,823.00 5,246,156.16 -1,165,334.92 275.30 14,823.00 4,080,821.24
Pekerjaan Bekisting floordeck KR 0,70 m2 64.94 95,241.00 6,184,950.54 -1,372,899.02 50.53 95,241.00 4,812,051.53
- Plat meja beton
Pekerjaan Beton m3 0.12 887,571.00 106,508.52 11,644.93 0.13 887,571.00 118,153.45
Pekerjaan Pembesian
Besi 10 mm Kg 9.32 13,334.00 124,272.88 127,819.72 18.91 13,334.00 252,092.60
Pekerjaan Bekisting 2x Pakai m2 1.66 373,522.00 620,046.52 -309,276.22 0.83 373,522.00 310,770.30
F ATAP + 16,00
1. Pek. Kuda-kuda Baja IWF 350.350 (termasuk baut, las,- Kg 767.20 29,343.00 22,511,949.60 -22,511,949.60 - 29,343.00 -
plat baja & aksesoris lainnya lengkap )
1a. Pek. Kuda-kuda Baja H beam 350.350 (termasuk baut, las,- Kg 28,139,937.00 959.00 29,343.00 28,139,937.00
plat baja & aksesoris lainnya lengkap )
1b. - Pek. Pengecetan dasar baja m2 - - - 521,150.00 17.50 29,780.00 521,150.00
2. Pek. Kuda-kuda Baja IWF 250.125 (termasuk baut, las,- Kg 1,593.66 29,343.00 46,762,765.38 -3,003,671.74 1,491.30 29,343.00 43,759,093.64
plat baja & aksesoris lainnya lengkap )
2a. - Pek. Pengecetan dasar baja m2 - - - 1,501,209.80 50.41 29,780.00 1,501,209.80
3. Pek. Kuda-kuda Baja IWF 150.100 (termasuk baut, las,- Kg 134.40 29,343.00 3,943,699.20 -3,943,699.20 - 29,343.00 -
plat baja & aksesoris lainnya lengkap )
3a. - Pek. Pengecetan dasar baja m2 651,586.40 21.88 29,780.00 651,586.40
4. - Pek. Gording Canal C 100.50.20 (termasuk baut, las,- Kg 1,041.07 29,343.00 30,548,117.01 -30,548,117.01 - - -
plat baja & aksesoris lainnya lengkap )
5a. - Pek. Gording Canal C 125.50.20 (termasuk baut, las,- Kg - - - 48,208,592.80 1,642.93 29,343.00 48,208,592.80
plat baja & aksesoris lainnya lengkap )
5b. - Pek. Pengecetan dasar Gording Canal C 125.50.20 m2 - - - 3,295,335.68 110.66 29,780.00 3,295,335.68
6. Plat gording dan Pengaku rafter 6 mm Kg 140.00 29,343.00 4,108,020.00 -2,259,411.00 63.00 29,343.00 1,848,609.00
6a. - Pek. Pengecetan dasar baja m2 85,468.60 2.87 29,780.00 85,468.60
7. Trekstank 12 mm Kg 63.96 29,343.00 1,876,778.28 -930,528.68 32.25 29,343.00 946,249.60
7a. Pengecetan Cat dasar m2 - - - 40,798.60 1.37 29,780.00 40,798.60
8. Braching 16 mm Kg 152.00 29,343.00 4,460,136.00 -780,300.79 125.41 29,343.00 3,679,835.21
8a. Pengecetan Cat dasar m2 - - - 123,289.20 4.14 29,780.00 123,289.20
9. Jarum Keras 5/8" Bh 16.00 100,000.00 1,600,000.00 -400,000.00 12.00 100,000.00 1,200,000.00
10. Shear Connector 1/2" Kg 174.00 29,343.00 5,105,682.00 -5,105,682.00 - 29,343.00 -
11. Plat Simpul 10 mm Kg 373.00 29,343.00 10,944,939.00 -10,944,939.00 - 29,343.00 -
12. Plat Simpul 16 mm Kg 233.00 29,343.00 6,836,919.00 -6,836,919.00 - 29,343.00 -
13. Pekerjaan Atap Spandeck 0,35 fin Coating m2 217.38 97,293.00 21,149,552.34 644,079.66 224.00 97,293.00 21,793,632.00
14. Pekerjaan Nok Atap Spandeck m' 16.15 97,989.00 1,582,522.35 181,279.65 18.00 97,989.00 1,763,802.00
15. Plat beton, termasuk: beton, besi, & bekisting
- Plat Lantai t= 12 cm (reservoir beton +16,00)
Pekerjaan Beton m3 - - - - - 936,138.00 -
Pekerjaan wiremesh DM 8 Kg - - - - - 14,823.00 -
Pekerjaan Bekisting floordeck KR 0,70 m2 - - - - - 95,241.00 -
SUB JUMLAH V 180,397,040.10 -10,536,939.90 169,860,100.20
1 2 3 4 5 6=4x5 13 14 15=13x14
III PEKERJAAN ARSITEKTUR
1 PEKERJAAN PASANGAN & PLESTERAN BATA
A LANTAI SATU
1. Pasangan dinding bata merah 1 : 5 pada kolom m2 96.00 98,938.00 9,498,048.00 -2,968,140.00 66.00 98,938.00 6,529,908.00
2. Plesteran dinding bata 1 : 5 pada kolom m2 96.00 58,044.00 5,572,224.00 -1,741,320.00 66.00 58,044.00 3,830,904.00
3. Acian dinding bata pada kolom m2 96.00 34,076.00 3,271,296.00 -1,022,280.00 66.00 34,076.00 2,249,016.00
4. Pasangan dinding bata merah 1 : 3 SHAFT m2 54.60 103,912.00 5,673,595.20 -5,153,515.64 5.01 103,912.00 520,079.56
5. Plesteran dinding bata 1 : 5 SHAFT m2 54.60 58,044.00 3,169,202.40 -2,675,538.18 8.51 58,044.00 493,664.22
6. Acian dinding bata SHAFT m2 54.60 34,076.00 1,860,549.60 -1,570,733.22 8.51 34,076.00 289,816.38
B LANTAI DUA
1. Pemasangan Rangka plafond hollow Rangka 2x4 & m2 170.76 94,469.00 16,131,526.44 62,396.77 171.42 94,469.00 16,193,923.21
4x4x0,30 mm
2. Pekerjaan Plafond Gypsum 9 mm m2 170.76 55,675.00 9,507,063.00 36,773.34 171.42 55,675.00 9,543,836.34
3. Pemasangan Rangka + plafond PVC m2 16.74 94,469.00 1,581,411.06 -527,042.55 11.16 94,469.00 1,054,368.51
4. Pek. ACP PVDF t= 4 mm : PVDF 4 mm : 0,4 mm + m2 96.08 495,310.00 47,589,384.80 10,259,900.87 116.79 495,310.00 57,849,285.67
Aksesoris lengkap + Rangka Siku
5. Pek. ACP PVDF cutting t= 4 mm : PVDF 4 mm : 0,4 mm + m2 13.12 504,865.00 6,623,828.80 989,535.40 15.08 504,865.00 7,613,364.20
Aksesoris lengkap + Rangka Siku cutting fasad
3 PEKERJAAN LANTAI
A LANTAI SATU
1. Pasang Granit 60 x 60 cm m2 - 294,948.00 - - 294,948.00 -
2. Pasang Keramik 60 x 60 KM/WC m2 - 278,363.00 - - 278,363.00 -
3. Pasang Dinding Keramik 30 x 60 cm m2 - 350,289.00 - - 350,289.00 -
4. Pasang Granit Meja Beton 60 x 60 cm m2 - 294,948.00 - - 294,948.00 -
B LANTAI DUA
1. Pasang Granit Tile 60 x 60 cm m2 170.76 361,288.00 61,693,538.88 238,630.72 171.42 361,288.00 61,932,169.60
2. Pasang Granit Tile 60 x 60 KM/WC m2 16.74 361,288.00 6,047,961.12 -1,937,045.61 11.38 361,288.00 4,110,915.51
3. Pasang Dinding Granit Tile 30 x 60 cm m2 33.75 372,884.00 12,584,835.00 12,813,338.32 68.11 372,884.00 25,398,173.32
4. Pasang Granit Meja Beton 60 x 60 cm m2 1.66 294,948.00 489,613.68 -250,115.90 0.81 294,948.00 239,497.78
C LANTAI TIGA
1. Pasang Granit Tile 60 x 60 cm m2 170.76 361,288.00 61,693,538.88 238,630.72 171.42 361,288.00 61,932,169.60
2. Pasang Granit Tile 60 x 60 KM/WC m2 16.74 361,288.00 6,047,961.12 -1,937,045.61 11.38 361,288.00 4,110,915.51
3. Pasang Dinding Granit Tile 30 x 60 cm m2 33.75 372,884.00 12,584,835.00 12,813,338.32 68.11 372,884.00 25,398,173.32
4. Pasang Granit Meja Beton 60 x 60 cm m2 1.66 294,948.00 489,613.68 -250,115.90 0.81 294,948.00 239,497.78
D LANTAI EMPAT
1. Pasang Granit 60 x 60 cm m2 170.76 361,288.00 61,693,538.88 238,630.72 171.42 361,288.00 61,932,169.60
2. Pasang Granit Tile 60 x 60 KM/WC m2 16.74 361,288.00 6,047,961.12 -1,937,045.61 11.38 361,288.00 4,110,915.51
3. Pasang Dinding Granit Tile 30 x 60 cm m2 33.75 372,884.00 12,584,835.00 12,813,338.32 68.11 372,884.00 25,398,173.32
4. Pasang Granit Meja Beton 60 x 60 cm m2 1.66 294,948.00 489,613.68 -250,115.90 0.81 294,948.00 239,497.78
E LANTAI ATAP
1. Waterproofing membran Plat Atap & KM/WC m2 130.09 262,092.00 34,095,548.28 25,588,828.24 227.72 262,092.00 59,684,376.52
B LANTAI TIGA
1. Tipe P1 Buah 5.00 1,656,034.00 8,280,170.00 - 5.00 1,656,034.00 8,280,170.00
2. Tipe P2 Buah 1.00 3,246,994.00 3,246,994.00 -3,246,994.00 - 3,246,994.00 -
3. Tipe J1 Buah 4.00 1,311,036.00 5,244,144.00 - 4.00 1,311,036.00 5,244,144.00
4. Tipe J2 Buah 4.00 1,343,533.00 5,374,132.00 -5,374,132.00 - 1,343,533.00 -
5. Tipe V1 Buah 2.00 334,436.00 668,872.00 - 2.00 334,436.00 668,872.00
C LANTAI EMPAT
1. Tipe P1 Buah 5.00 1,656,034.00 8,280,170.00 - 5.00 1,656,034.00 8,280,170.00
2. Tipe P2 Buah - 3,246,994.00 - - - 3,246,994.00 -
3. Tipe J1 Buah 5.00 1,311,036.00 6,555,180.00 -1,311,036.00 4.00 1,311,036.00 5,244,144.00
4. Tipe J2 Buah 4.00 1,343,533.00 5,374,132.00 -5,374,132.00 - 1,343,533.00 -
5. Tipe V1 Buah 2.00 334,436.00 668,872.00 - 2.00 334,436.00 668,872.00
5 PEKERJAAN PENGECETAN
A LANTAI SATU
1. Cat Plafond beton m2 192.00 28,479.00 5,467,968.00 -5,467,968.00 - 28,479.00 -
1a. Cat Dasar Bundeck m2 - - - 5,701,008.75 191.44 - 29,780.00 5,701,008.75
2 Cat dinding bata dalam (shaft) m2 - - - - - 34,361.00 -
3 Cat dinding bata luar (shaft) m2 - - - 292,240.31 8.51 34,361.00 292,240.31
B LANTAI DUA
1. Cat dinding bata dalam m2 301.70 28,583.00 8,623,491.10 -4,617,726.57 140.15 28,583.00 4,005,764.54
2. Cat dinding bata luar m2 201.13 34,361.00 6,911,027.93 -2,946,558.83 115.38 34,361.00 3,964,469.10
3. Cat Plafond Gypsum m2 170.76 28,479.00 4,863,074.04 18,810.38 171.42 28,479.00 4,881,884.42
4. Cat Listplank beton m2 - - - 410,998.79 11.96 34,361.00 410,998.79
C LANTAI TIGA
1. Cat dinding bata dalam m2 1.20 28,583.00 34,299.60 3,971,464.94 140.15 28,583.00 4,005,764.54
2. Cat dinding bata luar m2 0.80 34,361.00 27,488.80 3,936,980.30 115.38 34,361.00 3,964,469.10
3. Cat Plafond Gypsum m2 170.76 28,479.00 4,863,074.04 18,810.38 171.42 28,479.00 4,881,884.42
D LANTAI EMPAT
1. Cat dinding bata dalam m2 1.20 28,583.00 34,299.60 3,971,464.94 140.15 28,583.00 4,005,764.54
2. Cat dinding bata luar m2 0.80 34,361.00 27,488.80 3,936,980.30 115.38 34,361.00 3,964,469.10
3. Cat Plafond Gypsum m2 154.02 28,479.00 4,386,335.58 1,661,479.10 212.36 28,479.00 6,047,814.68
4. Pengecetan baja m2 897.34 29,974.00 26,896,869.16 -26,896,869.16 - 29,974.00 -
E LANTAI ATAP
1. Cat dinding bata luar m2 - - - 1,632,937.80 47.52 34,361.00 1,632,937.80
IV PEKERJAAN MEP
1. PEKERJAAN INSTALASI AIR BERSIH
1. Top Reservoir (office) 2 M3 + Pemasangan + Aksesoris Unit 1.00 3,787,276.00 3,787,276.00 - 1.00 3,787,276.00 3,787,276.00
2. Pompa air (tot head 100 m) + rumah Pompa Unit 1.00 4,531,775.00 4,531,775.00 - 1.00 4,531,775.00 4,531,775.00
3. Sumur Dalam (Bor) kedalaman 40 m + Instalasi Unit 1.00 12,044,885.00 12,044,885.00 - 1.00 12,044,885.00 12,044,885.00
Pemipaan dari tandon atas ke shaft lantai
1. Pipa diameter 3" Mtr. 20.00 65,516.00 1,310,320.00 - 20.00 65,516.00 1,310,320.00
2. Gate Valve diameter 3" Bh 4.00 816,404.00 3,265,616.00 - 4.00 816,404.00 3,265,616.00
A LANTAI DUA
1. Diameter 1/2" Mtr. 12.00 24,533.00 294,396.00 -30,666.25 10.75 24,533.00 263,729.75
2. Diameter 3/4" Mtr. 8.00 29,415.00 235,320.00 - 8.00 29,415.00 235,320.00
B LANTAI TIGA
1. Diameter 1/2" Mtr. 12.00 24,533.00 294,396.00 -30,666.25 10.75 24,533.00 263,729.75
2. Diameter 3/4" Mtr. 8.00 29,415.00 235,320.00 -117,660.00 4.00 29,415.00 117,660.00
C LANTAI EMPAT
1. Diameter 1/2" Mtr. 12.00 24,533.00 294,396.00 -30,666.25 10.75 24,533.00 263,729.75
2. Diameter 3/4" Mtr. 8.00 29,415.00 235,320.00 -117,660.00 4.00 29,415.00 117,660.00
C LANTAI TIGA
1. Diameter 4" Mtr. 24.00 97,252.00 2,334,048.00 -1,701,910.00 6.50 97,252.00 632,138.00
2. Diameter 3" Mtr. 28.00 65,516.00 1,834,448.00 -1,162,909.00 10.25 65,516.00 671,539.00
3. Peralatan bantu, sambungan, Tee, Elbow, bracket / Ls 1.00 750,000.00 750,000.00 - 1.00 750,000.00 750,000.00
support, dll.
D LANTAI EMPAT
1. Diameter 4" Mtr. 24.00 97,252.00 2,334,048.00 -1,701,910.00 6.50 97,252.00 632,138.00
2. Diameter 3" Mtr. 28.00 65,516.00 1,834,448.00 -1,162,909.00 10.25 65,516.00 671,539.00
3. Peralatan bantu, sambungan, Tee, Elbow, bracket / Ls 1.00 1,250,000.00 1,250,000.00 - 1.00 1,250,000.00 1,250,000.00
support, dll.
B LANTAI TIGA
1. Wastafel Bh 2.00 817,829.00 1,635,658.00 - 2.00 817,829.00 1,635,658.00
2. Kloset Duduk Bh 1.00 1,572,974.00 1,572,974.00 - 1.00 1,572,974.00 1,572,974.00
3. Kloset Jongkok Bh 1.00 875,316.00 875,316.00 -875,316.00 - 875,316.00 -
4. Floor Drain Bh 2.00 147,654.00 295,308.00 - 2.00 147,654.00 295,308.00
5. Cermin 6 mm + lengkap fin bingkai Bh 2.00 625,047.00 1,250,094.00 - 2.00 625,047.00 1,250,094.00
6. Kran air Bh 2.00 223,644.00 447,288.00 - 2.00 223,644.00 447,288.00
C LANTAI EMPAT
1. Wastafel Bh 2.00 817,829.00 1,635,658.00 - 2.00 817,829.00 1,635,658.00
2. Kloset Duduk Bh 1.00 1,572,974.00 1,572,974.00 - 1.00 1,572,974.00 1,572,974.00
3. Kloset Jongkok Bh 1.00 875,316.00 875,316.00 - 1.00 875,316.00 875,316.00
4. Floor Drain Bh 2.00 147,654.00 295,308.00 - 2.00 147,654.00 295,308.00
5. Cermin 6 mm + lengkap fin bingkai Bh 2.00 625,047.00 1,250,094.00 - 2.00 625,047.00 1,250,094.00
6. Kran air Bh 2.00 223,644.00 447,288.00 - 2.00 223,644.00 447,288.00
B LANTAI DUA
1. Instalasi titik lampu Ttk. 26.00 445,226.00 11,575,876.00 - 26.00 445,226.00 11,575,876.00
2. Instalasi titik stop kontak Ttk. 5.00 278,906.00 1,394,530.00 278,906.00 6.00 278,906.00 1,673,436.00
3. Down light 1 x 18 watt Bh 26.00 153,540.00 3,992,040.00 - 26.00 153,540.00 3,992,040.00
4. Saklar seri Bh 5.00 49,525.00 247,625.00 - 5.00 49,525.00 247,625.00
5. Saklar tunggal Bh 2.00 45,325.00 90,650.00 - 2.00 45,325.00 90,650.00
6. Stop kontak 200 VA Ex. Panasonic Bh 5.00 46,900.00 234,500.00 - 5.00 46,900.00 234,500.00
7. Stop kontak AC 200 VA Ex. Panasonic Bh - - - 470,835.00 5.00 94,167.00 470,835.00
8. Panel Penerangan Listrik Box MCB Lengkap Bh - - - - - 232,577.00 -
9. Lampu Strip LED untuk ACP cutting M' - - - 3,206,112.00 48.00 66,794.00 3,206,112.00
C LANTAI TIGA
1. Instalasi titik lampu Ttk. 26.00 445,226.00 11,575,876.00 - 26.00 445,226.00 11,575,876.00
2. Instalasi titik stop kontak Ttk. 8.00 278,906.00 2,231,248.00 -557,812.00 6.00 278,906.00 1,673,436.00
3. Down light 1 x 18 watt Bh 26.00 153,540.00 3,992,040.00 - 26.00 153,540.00 3,992,040.00
4. Saklar seri Bh 5.00 49,525.00 247,625.00 49,525.00 6.00 49,525.00 297,150.00
5. Saklar tunggal Bh 2.00 45,325.00 90,650.00 -45,325.00 1.00 45,325.00 45,325.00
6. Stop kontak 200 VA Ex. Panasonic Bh 8.00 46,900.00 375,200.00 -140,700.00 5.00 46,900.00 234,500.00
7. Stop kontak AC 200 VA Ex. Panasonic Bh - - - 470,835.00 5.00 94,167.00 470,835.00
8. Panel Penerangan Listrik Box MCB Lengkap Bh - - - - - 232,577.00 -
D LANTAI EMPAT
1. Instalasi titik lampu Ttk. 26.00 445,226.00 11,575,876.00 - 26.00 445,226.00 11,575,876.00
2. Instalasi titik stop kontak Ttk. 8.00 278,906.00 2,231,248.00 -557,812.00 6.00 278,906.00 1,673,436.00
3. Down light 1 x 18 watt Bh 26.00 153,540.00 3,992,040.00 - 26.00 153,540.00 3,992,040.00
4. Saklar seri Bh 5.00 49,525.00 247,625.00 49,525.00 6.00 49,525.00 297,150.00
5. Saklar tunggal Bh 2.00 45,325.00 90,650.00 -45,325.00 1.00 45,325.00 45,325.00
6. Stop kontak 200 VA Ex. Panasonic Bh 8.00 46,900.00 375,200.00 -140,700.00 5.00 46,900.00 234,500.00
7. Stop kontak AC 200 VA Ex. Panasonic Bh - - - 470,835.00 5.00 94,167.00 470,835.00
8. Panel Penerangan Listrik Box MCB Lengkap Bh - - - - - 232,577.00 -
6. PEKERJAAN PENANGKAL PETIR Unit 1.00 4,827,305.00 4,827,305.00 - 1.00 4,827,305.00 4,827,305.00
7. PEKERJAAN SIGNAGE
1. Pekerjaan Logo + Lampu Ls 1.00 7,500,000.00 7,500,000.00 - 1.00 7,500,000.00 7,500,000.00
2. Pekerjaan Huruf + Lampu Ls 1.00 12,500,000.00 12,500,000.00 - 1.00 12,500,000.00 12,500,000.00
8. PEKERJAAN SEPTIC TANK Unit 1.00 7,555,522.00 7,555,522.00 - 1.00 7,555,522.00 7,555,522.00
TRIMO,TRIMO,SE.MM
SE. MM SULHAERI BAE,ST SULHAIRI,THURSINA
BAE, ST MUH.YAMIN AMIN.ST
ARDI NUR,ST ANDI HAIKAL,ST
Nip:196801
NIP. 19680120 20200701
200701 1 005 1 005 Nip:1977110320091 2 2001
Koord. Pengawas PU
DIREKTUR UTAMA
Site Engineer
DAFTAR SISA BOBOT PEKERJAAN SAMPAI 5 NOVEMBER 2017
NO.
URAIAN PEKERJAAN SISA BOBOT
ITEM
1 2 3
B LANTAI SATU ###
3. Plat lantai beton, termasuk : beton, lantai kerja ###
- Plat lantai t= 15 cm (lantai) 0.39%
SUB JUMLAH II 0.39%
F ATAP + 16,00 ###
13. Pekerjaan Atap Spandeck 0,35 fin Coating 0.64%
14. Pekerjaan Nok Atap Spandeck 0.05%
SUB JUMLAH V 0.70%
3 PEKERJAAN LANTAI
B LANTAI DUA
2. Pasang Granit Tile 60 x 60 KM/WC 0.12%
3. Pasang Dinding Granit Tile 30 x 60 cm 0.38%
4. Pasang Granit Meja Beton 60 x 60 cm 0.01%
C LANTAI TIGA
2. Pasang Granit Tile 60 x 60 KM/WC 0.12%
3. Pasang Dinding Granit Tile 30 x 60 cm 0.75%
4. Pasang Granit Meja Beton 60 x 60 cm 0.01%
D LANTAI EMPAT
2. Pasang Granit Tile 60 x 60 KM/WC 0.12%
3. Pasang Dinding Granit Tile 30 x 60 cm 0.75%
4. Pasang Granit Meja Beton 60 x 60 cm 0.01%
B LANTAI TIGA
1. Tipe P1 0.24%
3. Tipe J1 0.12%
SUB JUMLAH VIII 2.95%
C LANTAI EMPAT
1. Tipe P1 0.24%
3. Tipe J1 0.16%
5. Tipe V1 0.02%
5 PEKERJAAN PENGECETAN
A LANTAI SATU
1a. Cat Dasar Bundeck 0.17%
3. Cat dinding bata luar (shaft) 0.01%
B LANTAI DUA
1. Cat dinding bata dalam
2. Cat dinding bata luar 0.04%
4. Cat Listplank beton 0.01%
2. Cat dinding bata luar 0.08%
D LANTAI EMPAT
1. Cat dinding bata dalam 0.12%
2. Cat dinding bata luar 0.07%
3. Cat Plafond Gypsum 0.18%
E LANTAI ATAP
1. Cat dinding bata luar 0.05%
IV PEKERJAAN MEP
1. PEKERJAAN INSTALASI AIR BERSIH
1. Top Reservoir (office) 2 M3 + Pemasangan + Aksesoris 0.11%
2. Pompa air (tot head 100 m) + rumah Pompa 0.13%
Pemipaan dari tandon atas ke shaft lantai
1. Pipa diameter 3"
SUB JUMLAH IX 1.48%
B LANTAI TIGA
1. Wastafel 0.05%
2. Kloset Duduk 0.05%
4. Floor Drain 0.01%
5. Cermin 6 mm + lengkap fin bingkai 0.04%
6. Kran air 0.01%
C LANTAI EMPAT
1. Wastafel 0.05%
2. Kloset Duduk 0.05%
3. Kloset Jongkok 0.03%
4. Floor Drain 0.01%
5. Cermin 6 mm + lengkap fin bingkai 0.04%
6. Kran air 0.01%
B LANTAI DUA
3. Down light 1 x 18 watt 0.12%
9. Lampu Strip LED untuk ACP cutting 0.09%
SUB JUMLAH XI 0.59%
C LANTAI TIGA
3. Down light 1 x 18 watt 0.12%
D LANTAI EMPAT
1. Instalasi titik lampu 0.34%
2. Instalasi titik stop kontak 0.05%
3. Down light 1 x 18 watt 0.12%
4. Saklar seri 0.01%
6. Stop kontak 200 VA Ex. Panasonic 0.01%
7. Stop kontak AC 200 VA Ex. Panasonic 0.01%
6. PEKERJAAN PENANGKAL PETIR 0.14%
No. BOBOT RENCANA (%) APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
Item Uraian Pekerjaan 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
KONTRAK MC-0
1 2
I. Pekerjaan Persiapan 0.44% 0.54% 0.27% 0.27%
0.27% 0.27% 0.00% 0.00%
II. Pekerjaan Struktur 63.00% 66.60% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 3.92% 1.08%
0.84% 1.82% 2.80% 0.96% 1.82% 2.96% 0.22% 0.15% 0.02% 1.17% 1.14% 0.24% 10.39% 5.34% 4.85% 7.92% 6.62% 7.69% 6.10% 2.47%
III PEKERJAAN ARSITEKTUR 31.22% 28.20% 4.03% 4.03% 4.03% 4.03% 4.03% 4.03% 4.03% 5.14% 5.14% 5.14% 5.14%
AMANDEMEN WAKTU
1.01% 1.53% 0.94% 4.15% 5.06% 2.26% 2.18% 1.06%
IV PEKERJAAN MEP
1. PEKERJAAN INSTALASI AIR BERSIH 0.78% 0.77% 0.39% 0.39% 0.17% 0.17%
0.08% 0.00% 0.36%
2. PEKERJAAN INSTALASI AIR KOTOR 1.08% 0.48% 0.24% 0.24% 0.07%
BOBOT RENCANA 0.27% 0.27% 3.92% 3.92% 3.92% 3.92% 3.92% 4.03% 4.03% 3.92% 3.92% 3.92% 3.92% 4.55% 4.55% 7.95% 7.95% 7.95% 8.61% 4.75% 4.99% 4.27% 0.30% 0.30%
MC-0 & ADDENDUM 1
KUMULATIF BOBOT RENCANA 100.00% 100.00% 0.27% 0.54% 4.46% 8.38% 12.30% 16.21% 20.13% 24.16% 28.19% 32.11% 36.03% 39.94% 43.86% 48.41% 52.96% 60.90% 68.85% 76.79% 85.40% 90.15% 95.14% 99.41% 99.70% 100.00%
BOBOT REALISASI 0.27% 0.27% 0.84% 1.82% 2.80% 0.96% 1.82% 2.96% 0.22% 0.15% 0.02% 1.39% 1.14% 0.24% 10.39% 5.34% 4.85% 7.92% 6.62% 7.69% 8.24% 4.00% 1.55% 4.29% 0.00% 5.06% 2.26% 2.18% 1.66%
REALISASI KUMULATIF REALISASI 0.27% 0.54% 1.38% 3.20% 6.00% 6.96% 8.78% 11.75% 11.97% 12.12% 12.14% 13.54% 14.68% 14.92% 25.30% 30.64% 35.49% 43.41% 50.03% 57.72% 65.96% 69.96% 71.51% 75.80% 0.00% 80.86% 83.12% 85.30% 86.95%
DEVIASI (+/-) 0.00% 0.00% -3.08% -5.18% -6.30% -9.25% -11.35% -12.42% -16.22% -19.99% -23.88% -26.41% -29.18% -33.49% -27.65% -30.26% -33.36% -33.38% -35.37% -32.43% -29.17% -29.45% -28.20% -24.20%
TRIMO,SE.MM RADEN ACHMAD ARIFIN,ST SULHAERI BAE,ST THURSINA ARDI NUR,ST NERI PANGGALOANGAN,ST ANDI HAIKAL,ST
Nip:196801 20200701 1 005 Nip:19750615 200604 1 007 Nip:1977110320091 2 2001 Pelaksana Lapangan Site Engineer
KETERANGAN
DG.KUMIS FIX TULANGAN
DG.AMIR
LAPORAN HARIAN
bulan april
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
BULAN MEI
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 1 Mei 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 48
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 26 Mei 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 49
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 27 Mei 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 79
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 26 Juni 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 80
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 27 Juni 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 100
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 17 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 101
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 18 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 102
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 19 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 103
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 20 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 104
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 21 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 105
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 22 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tenaga Kerja Bahan Bangunan
Jenis bahan yang Jumlah yang Jumlah yang Alat-Alat Kerja
Jumlah Keahlian
Didatangkan Diterima Ditolak
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 106
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 23 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tenaga Kerja Bahan Bangunan
Jenis bahan yang Jumlah yang Jumlah yang Alat-Alat Kerja
Jumlah Keahlian
Didatangkan Diterima Ditolak
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 107
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 24 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 108
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 25 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 109
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 26 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 110
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 27 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 111
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 28 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 112
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 29 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 113
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 30 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 114
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 31 Juli 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Sikat baja
Kuas Rol kecil
Kuas 3
Masker las
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 115
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 01 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Sikat baja
Kuas Rol kecil
Kuas 3
Masker las
Tali tambang
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 116
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 02 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
- Orang Tukang Besi Baut 3/4" 2" (5 cm) 211 bh Mesin Pemotong besi 2
- Orang Tukang Kayu Baut 3/4" 2,5" (7 cm) 196 bh Mesin Bor Magnit 2 bh
Masker las
Tali tambang
Tangga bambu
Kunci-kunci baut
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 117
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 03 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tangga bambu
Kunci-kunci baut
1. Pekerjaan Pemasangan Kolom H 350.350 (Lt.1, Lt2, Lt.3) sebanyak 5 tiang 2,500.25 Kg
2. Pekerjaan Pemasangan Balok Lantai IWF 300.150 mm (Lt.1) 3 segmen 582.72 Kg
3. Pekerjaan Pengecetan Balok IWF 300.150 mm 5 m2
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 118
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 04 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Masker las
Tali tambang
Tangga bambu
Kunci-kunci baut
1. Pekerjaan Pemasangan Kolom H 350.350 (Lt.1, Lt2, Lt.3) sebanyak 1 tiang 1,644.00 Kg
2. Pekerjaan Pemasangan Balok Lantai IWF 300.150 mm (Lt.1, Lt2, Lt 3, Lt4) 1,397.60 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 119
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 05 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
2. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt4) 1 balok 182.25 Kg
3. Pekerjaan Pemasangan Balok (B1) Lantai IWF 300.150 mm (Lt 3, Lt4) 4 balok 875.81 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 120
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 06 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tali tambang
Tangga bambu
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 121
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 07 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Kuas 3
Masker las
Tali tambang
Tangga bambu
Safety belt 2 buah
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 122
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 08 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tangga bambu
Safety belt 2 buah
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 123
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 09 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Masker las
Tali tambang
Tangga bambu
Safety belt 2 buah
2. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt1,Lt2,Lt3, Lt.4) 182.25 Kg
3. Pekerjaan Pengecetan Kolom H (A3, A4) dan Balok IWF 300.150 mm 5.00 m2
Pekerjaan dimulai pada Waktu
Jam 08.00 (pagi) sampai dengan jam 17.00 (sore) lanjut mulai jam sampai jam (malam)
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 124
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 10 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
3. Pek. Pemas. Balok Lantai (B1, B2) IWF 300.150 mm (Lt1,Lt2,Lt3, Lt4))5, 6 2,553.57 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 125
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 11 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tali tambang
Tangga bambu
Safety belt 2 buah
3. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt1) 2 balok 917.12 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 126
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 12 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Kuas 3
Masker las
Tali tambang
Tangga bambu
Safety belt 2 buah
3. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt1) 2 balok 917.12 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 127
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 13 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 128
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 14 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
3. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt1) 2 balok 917.12 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 129
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 15 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tangga bambu
Safety belt 2 buah
3. Pekerjaan Pemasangan Balok Lantai (B1) IWF 300.150 mm (Lt1) 2 balok 917.12 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 130
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 16 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Masker las
Tali tambang
Tangga bambu
Safety belt 2 buah
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 131
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 17 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 132
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 18 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tali tambang
Tangga bambu
4. Pekerjaan Pemasangan Balok IWF 300.150 mm (Lt1, Lt3) sbyk 8 potong 1,130.00 Kg
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 133
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 19 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Kuas 3"
Masker las
Tali tambang
Tangga bambu
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 134
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 20 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 135
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 21 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 136
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 22 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tenaga Kerja Bahan Bangunan
Jenis bahan yang Jumlah yang Jumlah yang Alat-Alat Kerja
Jumlah Keahlian
Didatangkan Diterima Ditolak
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 137
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 23 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Tenaga Kerja Bahan Bangunan
Jenis bahan yang Jumlah yang Jumlah yang Alat-Alat Kerja
Jumlah Keahlian
Didatangkan Diterima Ditolak
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 138
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 24 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 139
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Jumat Pengawas dari Kontraktor :
Tanggal : 25 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 140
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Sabtu Pengawas dari Kontraktor :
Tanggal : 26 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 141
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Minggu Pengawas dari Kontraktor :
Tanggal : 27 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 142
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Senin Pengawas dari Kontraktor :
Tanggal : 28 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 143
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Selasa Pengawas dari Kontraktor :
Tanggal : 29 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 144
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Rabu Pengawas dari Kontraktor :
Tanggal : 30 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
LAPORAN HARIAN
Unit Kerja : BALAI BESAR WILAYAH SUNGAI POMPENGAN Halaman No. : 145
JENEBERANG Kontraktor : PT. RAYA SINERGIS
Hari : Kamis Pengawas dari Kontraktor :
Tanggal : 31 Agustus 2017 Pengawas dari Direksi :
Pekerjaan : Renovasi Gedung Kantor BBWSPJ Pengawas dari Konsultan :
Pada hari Senin tanggal tujuh bulan Agustus Tahun dua ribu tujuh belas (07-08-2017), kami yang bertanda tangan dibawah ini :
Pihak Pertama dan Pihak Kedua bersama-sama telah melakukan Pemeriksaan Fisik :
Dengan ini menyatakan bahwa tingkat Kemajuan Fisik pekerjaan telah mencapai = 30.9097 %
Demikian Berita Acara ini dibuat dengan sebenarnya untuk dapat dipergunakan sebagaimana mestinya.
Mengetahui / Menyetujui :
Pejabat Pembuat Komitmen (PPK)
Ketatalaksanaan,
TRIMO, SE. MM
NIP. 19680120 200701 1 005
BERITA ACARA TINGKAT KEMAJUAN FISIK
BALAI PENDIDIKAN DAN PELATIHAN NOMOR :
PEKERJAAN UMUM WILAYAH V MAKASSAR TANGGAL :
PEKERJAAN : REHABILITASI GEDUNG DAN BANGUNAN KANTOR
Pada hari ............... tanggal .............................................. bulan .................... Tahun dua ribu tiga belas, kami yang bertanda tangan dibawah ini :
Pihak Pertama dan Pihak Kedua bersama-sama telah melakukan Pemeriksaan Fisik :
Dengan ini menyatakan bahwa tingkat Kemajuan Fisik pekerjaan telan mencapai = 80.07 %
Demikian Berita Acara ini dibuat dengan sebenarnya untuk dapat dipergunakan sebagaimana mestinya.
Mengetahui / Menyetujui :
Satker Diklat PU. Wil. V Makassar
Pejabat Pembuat Komitmen (PPK),
Pada hari ............... tanggal .............................................. bulan .................... Tahun dua ribu tiga belas, kami yang bertanda tangan
dibawah ini :
Pihak Pertama dan Pihak Kedua bersama-sama telah melakukan Pemeriksaan Fisik :
Dengan ini menyatakan bahwa tingkat Kemajuan Fisik pekerjaan telan mencapai = 100.00 %
Demikian Berita Acara ini dibuat dengan sebenarnya untuk dapat dipergunakan sebagaimana mestinya.
Mengetahui / Menyetujui :
Satker Diklat PU. Wil. V Makassar
Pejabat Pembuat Komitmen (PPK),
Ir. SISKA MARABINTANG, M.Si
NIP. 19650515 199603 2 003