W E S T VA L L E Y F C P L I N E 1 - P R O C E S S I N G
SUBMIT TED BY 2 4 J U LY 2 0 1 7
pg | 1
The decision to hire JP Cullen was the
right choice because JP Cullens ability to
combine the different trades under one hat
and work together as a team, pull in the
necessary subcontractors who accepted
the challenge, access materials and
equipment needed immediately, and their
ability to get the job done quickly and safely.
Manager Plant Engineering,
Hormel Foods Corporation
pg | 2
pg | 3
pg | 4
July 24, 2017
Frito-Lay
Adam Roth, Dresden Huston, and Tim Jackson
7701 Legacy Drive, 4A243
Plano, TX 75024
JP Cullen is uniquely qualified to bring Frito-Lay solutions that no other contractor can - we are confident the content of
this proposal will prove it. We respect your process and are proud to be invited to submit a proposal for the West Valley
FCP Warehouse project.
We have assembled a team of construction and engineering experts to ensure that this project is managed successfully
for Frito-Lay, your shareholders, your employees, and JP Cullen.
Some of JP Cullens recent similar projects include:
Frito-Lay Automations:
JP Cullen has completed processing and packaging jobs as well as equipment and conveyor installations projects very
similar to Frito-Lays for many Fortune 500 Clients and smaller clients throughout the United States and Wisconsin
including clients in the Food and Beverage, Aerospace, Automotive, Chemical, General Manufacturing and Power
industries.
Our clients have tough jobs with high expectations and no room for error with safety, budgets, or quality. From
conception to budgeting to project completion, we provide a full spectrum of construction services. Our extensive
experience in managing projects with budgets from $1,000 to over $80 million allows you to focus on your business and
daily activities, while JP Cullen executes the details of construction. You will receive a trustworthy and proven partner to
manage your project. Theres a reason weve stayed in business for 125 years - Let us show you.
We look forward to the opportunity to serve as your construction professional to meet and exceed your expectations for
this project.
Sincerely,
1
Tom, Ericks, and Brandons only responsibility is to plan the project using a checklist
we have developed that contains all of our lessons learned and best practices. At
the end, they will have finalized a comprehensive schedule that includes input
from all of the major subcontractors and Frito-Lay, and an execution plan that
incorporates the teams goals for the project.
JP Cullen studies Frito-Lays project and works closely with Frito-Lay to better
understand what will make this a successful project. For example, at Frito-Lays
Rosenberg, TX plant, JP Cullens BIM team went down ahead of the job team and
did some imaging to model the work area six weeks ahead of the crew going to the
site. Having these images and models was another reason for success. Frito-Lay
asked that we complete the job in 8 days and we met the challenge. We helped
them get to production faster so they can make chips and ultimately sell their
products and have a better ROI.
2
costs, minimizes mistakes, and results in panoramic photographs. JP Cullen takes
the data we receive from the Laser Scan and creates 3D BIM Models. Our team
utilizes BIM to ensure that the detailed design and system components are both
integrated and coordinated to create a successful project. JP Cullen uses BIM for
greater MEPF coordination, team collaboration, and schedule savings as well as
reduction in change orders and project costs.
COLLABORATING TO DEVELOP COST SAVING ALTERNATIVES.
We listen and communicate with Frito-Lay and the entire team to develop innovative
solutions that meet your needs and wants while staying on budget and on schedule.
4
the work on your project as possible. This benefits Frito-Lays project directly because
cost, project completion, and quality determine project success. Our trades include:
demolition, masonry, concrete, steel, carpentry and millwork.
We have developed a project execution schedule, reviewed deviations, cost
alternatives, and opportunities for Value Engineering, as well as developed a project
execution plan, assembled a strong project team with hundreds of years of experience
in delivering very similar projects and experience in working for Frito-Lay. We have the
design and construction ability to make this a successful project.
pg | 7
TA B L E
N T E N T S
O F C O
PROJECT PROJECT PROJECT
PRICING DEVIATIONS EXECUTION PLAN