Anda di halaman 1dari 33

Municipality Exams

G+1 Test

1. Draw the reinforcement for the following concrete elements


a) Staircase flight (RFT details)

b) Combined footing& isolated footing (RFT details)

PREPARED BY:AHMED AMIN 1


c) Raft foundation (RFT details)

PREPARED BY:AHMED AMIN 2


d) Continuous beam at least 2 spans.

PREPARED BY:AHMED AMIN 3


e) Hollow block slab continuous from two sides.

2. What is the test before and after casting?


Before casting: Temperature test (temperature has to be less than 34) , Slump test
(the settlement not more than 11cm), cube samples for cube test which will be done
after 7 days and 28 days.
After casting: Shemidit hummer, ultra sonic, cube test (test will be done after 7 days
and 28 days), core test (will be done after cube test failed)

3. What are the cover and the de-shuttering for the following concrete elements? (footing, Tie
beam, Columns, Beams and slabs).
Footing (Cover= 5-7cm.. de-stuttering= 1 Day)
Tie Beam (Cover= 3cm.. de-stuttering= 2 Day)
Columns (Cover= 2.5-3cm.. de-stuttering= 2 Day)
Beams (Cover= 2.5cm.. de-stuttering= 14 Day (2L+2) where L the long span)
Slabs (Cover= 2.5cm.. de-stuttering= 14 Day (if L<3 after 7 day, if 3<L<6 after
10 day , if L<6 after 14 days)

4. What is the name of test which will make at site before placing footing and what is the
acceptable result?
Compaction test ( the relation between dry density and water content , result will be
95% of dry density ( also depend on specification of project)

PREPARED BY:AHMED AMIN 4


5. Explain briefly the steps of checking for the flowing items (excavation and preparation, axes,
?)footing, col and slabs
Excavation and Preparation :
)a .
)b .
)c shoring .
)d compaction
)e back filling road base pcc .
Axis:
)a
Footing :
)a
)b
)c
)d
)e cover
)f ( ).
)g
)h
)i .
Columns :
)a
)b
)c
)d
)e
)f
)g
)h
)i
Slabs:
)a
)b
)c
)d
)e
)f
)g cover

PREPARED BY:AHMED AMIN 5


6. What is the type of cracks may be appears in the structural elements (col and slabs) explain
?your answer with sketches
-1
:
.
: .
:
.
( : :
) ( .. :
)
-2 :
: .
.
.

?7. What is the bleeding in concrete

?8. What it mean by shotcrete concrete, self-compacted concrete


shotcrete

.
Self-compacted concrete
).Slump test = 60 cm (Dia

?9. What is the destructive test and non-destructive tests

Destructive test : . cube and core test


Non-destructive test : Ultrasonic test and loading test and
. schemidet hammer test

PREPARED BY:AHMED AMIN 6


10. What will you do if you have a G+1 building with corrosion? How you repair the corrosion in
steel building?

remove the concrete cover


clean the steel
paint steel and old concrete with Epoxies paint
Shotcrete and cover the steel again

11. What is the acceptable result for cube test after 7 days in grade 30 and 40?
Result after 7 days not less than 75% of grade after 28 days to be successful so the result =
.75*30= 22.5 N and .75*40= 30N.

12. What is the problems maybe face for the casted concrete?

13. Draw sketch for raft foundation (plan and vertical section passing with columns)and indicate
the arrangement and position main reinforcement and extra steel top& bottom also sketch the
moment diagram on the foundation. (see Q1).

14. Draw reinforcemet details for the shown corbel and the connection between corbel and steel
section .

PREPARED BY:AHMED AMIN 7


15. What it means by tower crane, where it locates in the building and for which kind of building
we use it?
.
. high rising construction . tower crane
Types :
1) Horizontal jib Jib moves only horizontal .
2) Luffing Jib Jib moves for both direction

PREPARED BY:AHMED AMIN 8


6-4.
tower crane 8-6.
tower crane :
)a .
)b cranes..
. )c
)d .

tower crane

16. Sketch the load diagram for tower crane and indicate the location of maximum load and
?minimum load

PREPARED BY:AHMED AMIN 9


17. Draw section reinforcement of single basement wall (full details)?

18. Show position of steel splices in continuous beams (top&bot)

PREPARED BY:AHMED AMIN 10


19. Draw the steel development for the shown systems

PREPARED BY:AHMED AMIN 11


20. Draw the moment for the following

PREPARED BY:AHMED AMIN 12


PREPARED BY:AHMED AMIN 13
?21. Explain some types of concrete joints

Construction Joint :
.minimum shear
Expansion Joint :
. 2 44 64 12.
Settlement Joint : .
2 .
Isolation Joint : .
Control Joint :
.

?22. What is the difference between damp (moisture) proofing and water proofing
Damp proofing is intended to keep out soil moisture, while waterproofing keeps out both
moisture and liquid water.

PREPARED BY:AHMED AMIN 14


23. What is the precautions during concrete casting in hot weather?
Covering water tank and aggregate
Spray water above shutter before casting
Covering the concrete and curing
Casting in night if possible
Using ice with water of mix
Maximum concrete degree should not more than 34

24. What is the types of cement used in footing and slabs

SRC (Sulphate Resistance Portland ) for footing . and OPC( Ordinary Portland cement) for slabs.

25. What are the types of shoring used in high rise buildings? Draw sketch for each type?

1- Contiguous Piles
2- Secant Piles
3- Diaphragm Walls
4- Soldger
5- H-Beams with concrete Panels

1- Contiguous Piles

5 ~ 7.5 cm gap

) 2 basements(
piles piles

2- Secant Piles
3-

piles
pile ) 3 basements (
pile

3- Diaphragm Walls

PREPARED BY:AHMED AMIN 15


4- Soldger

5- H-Beams with concrete Panels


6 ~ 5 ) one basement (

26. Discuss the dewatering for high rising building

If the GWL is higher than the foundation level dewatering is used to pull the water 1 m below the
foundation. Removing dewatering until weight of structure is greater than the uplift pressure so that the
water doesnt affect the stability of the building.

27. What types of slabs used in high rising buildings?


Flat slab, Paneled beam, solid slab, Post tension slabs.

28. If the concrete compressive strength test after 28 days failed, what should be safety if the
structure?

. core

.
.

29. What are the minimum overlapping length under different straining action?
Columns 45D Beam& Slabs ( 60D at tension , 40D at comp.)
30. What is the difference between theodolite and total station?
Theodolite for calculation of angels only, but total station for all (angels, level and coordination)
31. Describe slump test

workability

h
.

Foundation = 2-3 (5-7 cm)


Columns =3-5 (7-13 cm)
Slabs & Beams = 2-4 (5-10 cm)
Piles = 6-8 (15-20 cm)

PREPARED BY:AHMED AMIN 16


32. Sketch the main steel for pile cap (group of 3 piles)

33. In isolated footing, in which direction will be the main steel, why?
.

PREPARED BY:AHMED AMIN 17


34. Draw a section in a roof water proofing system and how to test it?

35. What it means by punch and how we control it?


Punching shear will happen in flat slab, means that columns will penetrate the slabs.
It happens when the thickness of slab around columns is small and more load.
We can control it by making drop panel or column head or increase dim. of column.

36. What it mean by deflection, where it happened and how we avoid it?
:Deflection


long term ( ) short term (
) shrinking

37. What is the required depth of boreholes in different stages (isolated , combined footing, raft,
piles foundation ) as per BS?
- Isolated and combined , depth of borehole= 2 width of footing.
- Raft, depth of borehole=1.5 width of building.
- Piles, depth of borehole= length of pile+5D (where D is the damiterer of piles

Note: Depth of borehole not less than 10 m.

38. How many boreholes required for a site area 900 m2?
Minimum boreholes are 2.
- As per BS 1 borehole for each 300m2 So for area 900 m2 , required 3 boreholes.

PREPARED BY:AHMED AMIN 18


?39. What is the different types of piles
)Classification based on load transfer: (End Bearing Piles (2~2.5 ) 0.75m

,(Friction Piles (3~5 ) 1 m),( Tension Piles).


(Classification based on method of installation ( Driven or displacement piles),
)replacement piles
)Classification based on Material (Steel piles),(concrete piles

Note: Piles Spacing = (2~5 )depends on soil type, piles type and piles diameter.

Piles should penetrate (2~4) inside the bearing stratum

?40. What is the different between strap beam and tie beam

?41. What the different between quality control and quality assurance

Quality control
Quality Assurance
.
?42. When we have to go for pile foundations
If the top layers of the soil are soft and good bearing stratum at a reasonable depth.

.44 .


. .
.44 7 .
28 7
28


.

PREPARED BY:AHMED AMIN 19


45. Draw an organization chart for site project.

46. What is mean by safety third party certificate and when it finished and renewed and for which
machineries you make?
(
) 6 man lift
47. What is the additional for concrete?
waterproofing admixtures which used in tunnels, basements, swimming
pool....Example pudlow, Ash
Densifier ( ) ....Example: Micro silica
Corrosion inhibitors () .Example: calcium nitrates ()
Plasticizer () .Example: silica, FEB flow
Decrease hydration temperature & increase strength.Example GGBS
Retarders ( & ) Accelerators ()

48. What is the ratio in concrete mix design?

49. Bored Piles


The statement is to fix casing and punching it vertically by hammering and/or
drilling to specific depth and to proceed with removing the soil from inside
After finishing, steel reinforcement to be fixed in the crane and pushed down and
steel should be fixed also by dewells in the casing to prevent floating of the steel
during the concrete casting
If the ground water table is high, precaution should be taken to keep the casing full
of water up to the level of water table or even higher to prevent boiling at the scat
of the pile which is turns will cause excessive settlement (Dewatering).

PREPARED BY:AHMED AMIN 20


:
( Auger machine( CFA


case Casing System
### Max Accepted deviation for any pile is 7cm and if we have more than that value, we have
to redesign the pile cap for this pile

50. What is the Pilling Tests?


1- Static Load Test (for 1% of the piles)
2- Dynamic Load Test (for 5% of the piles)
3- Integrity Test ( for all piles)
4- Sonic Test ( for piles more than 30 m length)
### Settlement of piles not more than 6 ~ 8 mm
### Code range of piles settlement of pile not more than 25 mm
### Piles should penetrate (2~4) inside the bearing stratum.

PREPARED BY:AHMED AMIN 21


Static Load Test for Piles
Working piles test load = 1.5 x Design load

Total Time for the test 23 Hours

1st Cycle ( 80 minutes) - Loading


25% P 50% P 75% P 100% P

20 Minutes 20 Minutes 20 Minutes 20 Minutes

2ND Cycle (90 Minutes) Un loading

75% P 50% P 25% P 0% P

10 Minutes 10 Minutes 10 Minutes 60 Minutes

3rd Cycle (1100 Minutes) Loading Again

100% P 125% P 150% P

360 Minutes 20 Minutes 720 Minutes

4th Cycle (110 Minutes) Unloading

125% P 100% P 75% P 50% P 25% P 0% P

10 Minutes 10 Minutes 10 Minutes 10 Minutes 10 Minutes 60 Minutes

Result : Settlement of piles should not exceed 6`8 mm or 1.5mm/hr or 10% pile

### If the piles type is friction piles, then the static test must be done only after 28 days.

Sonic Test
Used for to check the pile section through the pile and no cracks or soil failure
inside the pile body

51. What is the bentonite benefits?


Used to prevent soil failure for the piles sides
Pile Caps
Caps considered as footing for columns and transfers the load through the piles
And not through the soil underneath, so compaction under pile caps is not required.
At least 60 cm from piles steel should penetrate the pile cap.
Approximately the pile cap depth is equal to double of piles diameter.

PREPARED BY:AHMED AMIN 22


Piles reinforcement steel ratio = 0.8% piles concrete cross section .
52. Shoring Pile Side Load Calculations
F = 1m x L x 1 ton
F* = x x L x Kp x L
Kp = 0.33
Ka = 1/Kp 3

53. What is the Foundation Types


Shallow foundations (Isolated footings, strap footings , raft footings)
Deep foundations (Piles, Caison, piers)

-: 3 30 N -
22.5 N , 27 N and 30 N

N 2665 = -
N 2565 = 44 X 4685 = %85
N 2265 = 44 X 4675 = %75
%85 <=
%75 <=

PREPARED BY:AHMED AMIN 23


- 30 N 4 ( )cm51x51x51-:
51 52 31 04

- 25( 1 2665 = )28/2
45( 2 4465 = )44/2
= 42/2
2
4

.54 :

))(1 L.L + D.L) OR (1.25(L.L + D.L.
( )Deflection

-:
-1 < %75
> %75

?55. What is the relation between cubes and cylinder results


Cylinder strength = 0.8 cube strength

56. Dismantling of form shutters


Side forms (columns, beams sides ) after 2 days
Soffits (propped) after 7 days
Soffits (un propped) after 14 days
Cantilever (2m) after 21 days

57. What is the rings purpose


Keep vertical steel bars in position
Resist against buckling
Resist against shear force
Keep concrete cover fixed for structural element

58. Design of mix Design (example 30N) for piling


Cement = 400 kg/m3
W = 180 L
W/C = 180/400 = 0.45
Slump = 150 25 mm

PREPARED BY:AHMED AMIN 24


59. Concrete Cover for structure elements
Beams and Slabs = 2~3 cm
Columns = 3 ~ 3.5 cm
Footings and Piles = 7.5 cm

60. Concrete Delivery Note should show the following:


Date
Truck No.
Company Name (supplier)
Main contractor Name
Site Details and Location
Type of concrete and temperature
Concrete grade
Slump value
Concrete quantities
Truck leave time
Admixtures information
Cement quantities

.61

Cubes or cylinder crush test


Core test
Loading test
Rebound hummer test
Sonic-ultra test

Types of Slabs and Usual % Reinforcement


Solid Slab (100-120) kg/m
Flat Slab (160-185) ) kg/m
Wafle Slab(160-185) ) kg/m
Hurdy Slab (160-185) )kg/m
Post Tension Slab (60-65) kg/m
Hollow core slab (Cables)
Paneled Beam Slab (150-180) kg/m

PREPARED BY:AHMED AMIN 25


.26






.26

.

.26 slump
test
.

?65. What is the difference between target mean strength and characteristic strength for concrete
) ( Fc: Characteristic strength
) ( Fm: Target mean strength
S: Standard deviation 6.1 N/mm
K: Constant = 1.64

Fm = Fc + K x S

Example: for Fc = 30 N/mm


Fm = 30 +(1.64 x 6.1) = 40 N/mm

66. Post Tension



Dooms

post tension
Control hire cracks
To resist ve moment above columns
To resist punching or shear forces
Classes of post tension
Class (1) no cracks allowed like water tanks

PREPARED BY:AHMED AMIN 26


Class (2) cracks limited
Class (|3) cracks allowed

Poor strip

44
.

Grouting Usage
.

Duct
duct B.M.

24~16 ( N 12~9
)
\.

Anchors

Flowers

duct

67. Steel reinforcement Tests


1- Tension test
2- Bend and re-bend test
3- Chemical test
4- Yield
Used for design
5- Stain

PREPARED BY:AHMED AMIN 27


)Modulus of Elasticity (E

Ec (Concrete) = 140 ton/cm2
Es (steel) = 2100 ton/cm2

Thermal Modulus
1 = 10 ^-5
= ( mm / m / c ) 1.2 x 10^-5

)Poissons Ratio (

For concrete = 0.15
For Steel = 0.25

Percentage of Salts in Water


1- Soluble sulphate (SO3) 0.1% or 1000 P.P.M

2- CL 0.05 % or 500 P.P.M

3- C2 CO3 0.1% or 1000 P.P.M


4- PH Value at 25 = 0.0
5- Organic Materials = 0.0

PREPARED BY:AHMED AMIN 28


68. Draw the section for Raft or combined foundation with 16 top and bottom +

additional 25 @ 100 bottom + 20 @ 200 top

Note (Additional top between columns and additional bottom at columns)

16 both way 2 layers

20 @ 200 extra top

25 @ 200 extra bottom

16 both way 2 layers

Sec.x

69. What is the lab length splice for Bar D 40


Only using couplers (no splice)

PREPARED BY:AHMED AMIN 29


)shear force( .04

Min. Shear Area

S/3
S/3 S/3

PREPARED BY:AHMED AMIN 30


71. What is the connection between beam and columns for high rise building
Continuity for columns stirrups and increase columns stirrups (1m) below and above
connection
Increase beam stirrups near support (seismic zone)(L/4 or safer L/3)

1m

1m

72. From soil report we can determine and estimate


1- Bearing Capacity
2- Type of foundation
3- Type of cement
4- Expected settlement
5- Getting water table level

PREPARED BY:AHMED AMIN 31


73. Soil Tests

1- Plate Bearing Test


75 x 75 45 x 45 30 x 30
2~1.5

12

) (
( ) =

74. For Soil Investigations


Buildings: Boreholes should be every 20m in each direction
Roads: Boreholes should be every 30m in each direction
Depth of boreholes should be (1.5~2) short raft length

: .75
Slump cone
Cubs moulds
Tedolite
Thermometer
Measuring tape
Staff level
Micrometer
Scale


Solid Block = 7N -1
Hollow BLOCK = 4.5 N -2
Hurdy Block = 5 N -4

PREPARED BY:AHMED AMIN 32


High Rise Building Considerations:

76. What is the structure system in high rise building


For concrete (in high rise building
1- Core system
2- Core and shear walls
3- Tubular system
4- Vertical trusses for steel buildings

77. What is the scaffolding type for slab and core wall for high rise building

For slabs panel forms (DOKA :ex, the doka flex floor system for slabs)
For core climbing system with platforms.
Wind effect and seismic effect considered during design
Elevations finishing by cradles and not by traditional scaffolding
If height > 55 m hocks should be used for cradles robes
Dismantling cranes from the top of the building by special type of cranes
named (Derek) which can be fixed in the roof slab and dismantling the
main tower crane then another smaller Derek crane used to dismantle
the big Derek then the last small Derek can be transfer in the lift
Drainage cant be directly free fall (vertical u shape pipe will be each 4
floors)

( KHK )

Standard ultimate yield load = 4 tons, but we consider 600~700 kg


during design for the slab shutter
We have to consider heavy members alone as big beams which leads to
failure due to buckling of standards
We have to consider L.L values for the previous slab which will carry the
new slab during casting
Maximum opening for any base jack should not exceed 20 cm , in order
to avoid buckling for this member
Bracing to be considered and tilting with columns and walls is a must.

PREPARED BY:AHMED AMIN 33

Anda mungkin juga menyukai