1. Filling with ordinary soil in 15cm thick layers & hand compaction without sprinkling water including
excavation of material 10m lead & 1.5m lift.(Ref.2.1,2.25b & 2.27 of Norms Book.) Unit per m
As per Ref. 2.1 Unskilled labour - 0.70 md.@ Rs.1
As per Ref. 2.25b Unskilled labour - 0.25 md.@ Rs.
As per Ref. 2.27 Additional lead of av. 40m
Each 10m lead 0.12 md.* 4 = 0.48 md. @rs.150.00/md. = Rs.72.00
Sub-Total = Rs.214.50
Tools @ 3 % = Rs.6.43
Total = Rs.220.93/m3
2.Supply & filling empty bags with local sand, sewing them closed and placing them inc
haulage upto 100m distance.(Ref.16.23 of Norms Book) Unit Per 100 Sacks.
Unskilled labour - 10.00 md. @ Rs.150.00/ md. = Rs.1500.00
Material Empty bag = 100 sacks @ Rs.5.16/sack = Rs.516.00
Sewing thread 0.75 kg.@ Rs.60.00/kg. = Rs.45.00
Total = Rs.2061.00/100 sacks
Rate / sack = Rs.20.61
3.Excavation of soft clay & silty soils including disposal upto 10m lead and 1.5m lift.
(Ref. 2.1 of Norms Book) Unit Per m3
Unskilled labour - 0.70 md.@ Rs.150.00/md. = Rs.105.00
Tools @ 3% = Rs.3.15
Total = Rs.108.15/m