JADWAL WAKTU PELAKSANAAN MINGGU 1

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20
DEVIASI 1.00

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 2

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05
DEVIASI 1.00 1.85

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 3

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05 10.73
DEVIASI 1.00 1.85 2.53

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 4

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05 10.73 20.25
DEVIASI 1.00 1.85 2.53 7.05

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 5

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05 10.73 20.25 30.71
DEVIASI 1.00 1.85 2.53 7.05 11.51

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 6

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05 10.73 20.25 30.71 35.41
DEVIASI 1.00 1.85 2.53 7.05 11.51 10.21

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 7

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.20 3.20 8.20 13.20 19.20 25.20 32.20 41.20 54.20 69.20 84.20 94.20 100.00
REALISASI MINGGUAN 1.20 5.05 10.73 20.25 30.71 35.41 38.91
DEVIASI 1.00 1.85 2.53 7.05 11.51 10.21 6.71

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 8

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 9

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235 56.717
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035 2.517

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 10

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235 56.717 71.855
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035 2.517 2.655

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 11

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235 56.717 71.855 85.341
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035 2.517 2.655 1.141

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 12

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235 56.717 71.855 85.341 99.708
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035 2.517 2.655 1.141 99.708

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA
JADWAL WAKTU PELAKSANAAN MINGGU 13

NO URAIAN PEKERJAAN BOBOT (%) OKTOBER NOVEMBER DESEMBER JANUARI


1 2 3 4 5 6 7 8 9 10 11 12 13

I DIVISI 1.0. UMUM 100%

Section 1.1.1.1 Pekerjaan Persiapan Dan Lain-Lain 1.53 1.00 0.27 0.27

II DIVISI 2.0 PEKERJAAN STRUKTUR

Section 2.1.1 Pekerjaan Tanah 0.22 0.05 0.05 0.05 0.05 0.05 50%

Section 2.1.2 Pekerjaan Beton 92.26 2.68 4.95 4.95 5.28 5.28 6.33 8.33 12.33 14.33 14.33 9.33 4.87

III DIVISI 3.0 PEKERJAAN STRUKTUR

Pekerjaan Dinding, Plesteran, Dan acian 6.00 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0%

JUMLAH 100.00 1.00 3.00 5.00 5.00 6.00 6.00 7.00 9.00 13.00 15.00 15.00 10.00 5.80
KOMULATIF MINGGUAN 0.200 3.200 8.200 13.200 19.200 25.200 32.200 41.200 54.200 69.200 84.200 94.200 100.000
REALISASI MINGGUAN 1.200 5.052 10.726 20.246 30.710 35.411 38.907 41.235 56.717 71.855 85.341 99.708 100.000
DEVIASI 1.000 1.852 2.526 7.046 11.510 10.211 6.707 0.035 2.517 2.655 1.141 5.508 -

Mengetahui :
Kepala Sekolah SMK Mandala Sila

J.SINAGA