Anda di halaman 1dari 12

CONCRETE PAVEMENT CHARACTERISTICS AND d.

) With continuous reinforcement,


BEHAVIOR transverse joints omitted. Hair cracks are
checked by the steel and developed at
The behavior of concrete pavement that is
close intervals.
expose to loading and environmental effect
e.) Faulting is countered by aggregate
entirely depends upon the:
interlock and steel bars.
Quality of concrete 3. The longitudinal cracks on the pavement
Underlying sub-grade slab more than one lane wide are
Base course inevitable.
Concrete 4. Pavement slab is supported by foundation
that deflects when loaded but recover
- strong in resisting compression load acting when the load is removed, assuming that
on it, but considerably weak in resisting the foundation materials are elastic or like
tensile stress. a dense liquid.
- also expand and contract due to
DEFINITION OF TERMS
temperature changes. It expands when wet
and contracts when dried. Deterioration of concrete pavement is due to
- After pouring, concrete shrinks as the stress brought about by 1 rad, moisture and
mortar hardens and the cement hydrates temperature.
- Concrete pavement changes in length with
Distress of concrete is generally grouped into the
time of day for being exposed to different
following categories:
elements of weather changes
- A curl tendency is very likely due to the a. Distortion
effect of daily and seasonal temperature b. Cracking
and moisture differences between the top c. Disintegration
and bottom of slab.
Distortion is a vertical displacement of concrete
CONCRETE PAVEMENT DESIGN ASSUMES THE slab at the joint of the cracks. Distortion is due to
FOLLOWING CONSIDERATIONS failure or weakness of concrete joints.
1. That the pavement slab was designed as Faulting is the result of pumping tremendous
plain concrete beams. force or load that developed under the pavement.
2. That, transverse cracks on the concrete For faulting to occur, there must be free water on
pavement cannot be avoided. The designer the top of the base course and pavement
however, presumes that the pavement deflection across the joint due to heavy axle loads.
cracks could be controlled, by providing
reinforcement to the slab joints with the Causes of faulting:
following assumptions. a. Loss of slab support
a.) With reinforcement, cracks on the slab b. Erosion of sub base
will be confined to a weekend plain joints
spaced at 4.50 to 6.00 meters distance. Cracking can take many forms in concrete
b.) Vertical offsetting across the narrow pavement that could be the result from; applied
cracks will be prevented by aggregate load, temperature or moisture changes
interlock, or by dowel bars. The most common type of cracks:
c.) With simply reinforced slab, cracks will
only appear at weakened plane joints a. Corner cracks associated with excessive
spaced at 12-20 meters interval. Hair corner deflection.
cracks that can be held tightly by the steel
between joints.
b. Transverse cracks associated with mixture 22.5 32 .45 .30
or temperature stress, or poor construction
25.0 32 .45 .30
methods.
27.5 32 .45 .30
Disintegration appears in the form of durability
cracking, scaling or spalling, as the result of mix 30.0 32 .45 .30
design or construction related problems like:
Source : AASHTO Interior Guide & Proposed
a. Durability cracking. Result from freeze- Revision 1980
thaw action
b. Scaling. A network of shallow fine hairline
cracks which extend through the upper
surface of the concrete. This is the result
from deicing salts, improper construction,
freeze-thaw cycle, or steel reinforcement
too closed to the surface
c. Spalling is the breaking or chipping of the
joint edges. It is the result from excessive
stresses at joint, weak concrete, poorly
designed or constructed joints FIGURE 8-1 BASIC TYPE OF CONCRETE
Changes in temperature and moisture content PAVEMENT JOINTS
create slab curling, flexure stresses and overall LONGITUDINAL JOINTS
lengthening and shortening of the slabs. The
Longitudinal joints are provided between
tendency of the slab to shorten is due to
adjacent traffic lanes. It is considered as hinges to
temperature drop or dying that create tensile
provide edge support, but allows rotation between
stresses. On the other hand, the tendency to
the slabs. By this joint, flexural stresses that might
lengthen is due to temperature rise or increased in
cause irregular cracks along the length of the road
moisture that creates compression stresses.
are relieved or neutralized. Longitudinal joints
TRANSVERSE EXPANSION JOINTS cannot be considered as a major problem under
Expansion Joints provide space allowance the following assumptions:
for the lengthening of slab due to expansion. 1. That there is no big load transfer across it.
Because of the many buckling upward of concrete 2. That, the expansion and contraction
pavement, Engineers have come up with a movement developed across the pavement
conclusion that these blowups serves as width is very small.
conclusive evidence that expansion joint is
necessary.

TABLE 8-2 RECOMMENDED DMENSIONS OF


DOWELS FOR CONCRETE PAVEMENT JOINTS

Pavement Dowel Dowel Dowel


Thickness Diameter Length Spacing
cm. mm meter meter

15.0 20 .45 .30


FIGURE 8-2 LONGITUDINAL JOINT LOAD
17.5 25 .45 .30
TRANSFER
20.0 25 .45 .30 3. When lanes are constructed at different time
using side forms, the joints are provided with
key way in the first slab to accept load The reinforcement holds the fractured faces on
transfer. rigid contacts preserving the aggregate interlock
4. For longitudinal joint, deformed tie bars are and the intrusion of dirt or water. These reinforcing
used because the purpose is to hold the bars, however, is not intended to resist flexural
slabs tightly together, rather to allow the stress being produced by loads or curling.
joints to open and close.
The reinforcing steel bars are mounted in one layer
5. The diameter and spacing of tie bars are along the mid-depth of the slab. The formula used
based on the forced needed to pull the in designing this reinforcement for concrete slab
narrow pavement slab over the sub-grade to joint is
the joint.
=
6. The length of tie bar is determined from the
embedment inside the concrete necessary to Where:
develop the strength of the bar.
As = Area of steel cross section per foot of slab.
L = Length of slab between joints in feet.
f = Coefficient of friction between the slab and
the sub-grade called the coefficient of sub-grade
resistance ranging from1 to 2 with 1.5
recommended by AASHTO Interim Guide.
S = Working stress in the reinforcing steel in
CONSTRUCTION JOINT pounds per sq. in. AASHTO Interim Guide
suggested working stress from 30,000 to 45,000
If concrete pouring will be interrupted for
psi depending upon the type and grade of steel.
quite some time that cold joint will be inevitable,
the practice is to provide a transverse construction Wielded fabrics are also used as reinforcements
joints. Deformed tie bars are used to hold the joint for concrete pavement made from cold drawn
tightly closed together. However, if the steel wired having the following properties:
construction joint replaces a contraction joint, the
Minimum allowed 80,000 psi
use of dowels is the alternative.
tensile strength
Construction joints and cracks should be
Yield Strength 70,000 psi
cleaned and sealed to prevent infiltration of water
to the sub-grade and to keep dirt out of the joints. Reinforcing bars of 40,000 to 75,000 psi.
Materials for such purpose includes harder paving billet, rail or axle steel
and air blown asphalt sometimes mixed with yield strength among
mineral filler, rubber asphalt, and various rubber the from
compounds. They are poured hot and stiff, then
cooled, and others are placed cold. There are some
pre-formed sealant made of strips of extruded The SUB-GRADE and SUB-BASE for Concrete
neoprene compressed for insertion into the groove Pavement
joints, the sealant will expand and fill the space
The construction standard for sub-grade and
completely.
embankment are precise and almost typical for all
REINFORCEMENT OF JOINTS pavement types. Under the concrete pavement
Steel reinforcement for concrete pavement literature, the under course of selected material is
joints is specified in the design to prevent the always imposed upon between the sub-grade or
widening of cracks produced by shrinkage or embankment and the concrete slab.
thermal contraction. SUB-GRADE
- the natural ground grade and compacted 6. Specifying a permeable sub-base for pavements
on which the pavement is built. carrying high volumes of heavy trucks for which
past experience indicates the potential for
Preparation of the subgrade includes: pavement faulting and pumping.

1. Compacting soils at moisture contents and PUMPING


densities that will ensure uniform and stable
- the ejection of water and sub-grade soil
pavement support.
through the joints and cracks along the
2. Whenever possible, setting gradelines high edges of the concrete pavement.
enough and making side ditches deep enough
CONCRETE PROPORTIONS
to increase the distance between water table
and the pavement. The fundamental rule to obtain good concrete is
3. Crosshauling and mixing of soils to achieve the proper selection of cement aggregate and
uniform conditions in areas where there are water thus:
abrupt horizontal changes in soil type.
1. Type 1 or II cement is specified for concrete
4. Using selective grading in cut and fill areas to
pavement
place the better soils nearer to he top of the
final grade elevation. 2. Water for concrete must be clean, free from
5. Improving extremely poor soils by treatment acids, alkali and oil. Water that is suited for
with cement or lime, or importing better soils, drinking purposes is acceptable for mixing
whichever is more economical. cement except water containing large amount
of sulfate.
SUB-BASE
3. If concrete is to be strong, sound and durable,
- defined as the layer of material that lies the aggregate must have similar properties.
immediately below the concrete 4. The mineral aggregate of concrete is about 75%
pavement. of the volume or about 80% of the weight of
normal pavement
When the use of a sub-base is considered
5. The maximum size of coarse aggregate is 2
appropriate, the best results are obtained by:
inches. The use of larger aggregates, according
1. Selecting sub-base materials that meet to some experienced highway engineers,
minimum requirements for preventing mud- increases its length and durability. With larger
pumping of sub-grade soils. aggregate, less water is needed thereby,
2. Specifying gradation controls that will ensure a increasing the ratio of cement to water. Under
reasonably constant sub-base gradation for
the cement-ratio principle, concrete is stronger
individual projects.
when water content is less.
3. Specifying a minimum sub-base depth of 4 in.
4. Specifying a minimum density for untreated ADMIXTURE
sub-bases of 105 percent of AASHTO T99 for
A substance added in mixing to change the
heavily travelled projects.
characteristic of concrete mixture. There are
5. Specifying a cement-treated or lean concrete
varieties of admixtures available the air-
sub-base that provides a strong and uniform
entraining admixture, which is very common.
support for the pavements and joints; provides
Others, like water reducer, retarder, accelerator,
an all-weather working platform; and
Pozzolan ad plasticizer are also used.
contributes a smoother pavements by giving
firm support to the forms or paver during AIR ENTRAINMENT
construction.
The entrapment of air in the concrete
mixture in the form of evenly distributed small
bubbles. It is used to increase the concrete aggregate and a less fluid cement-water paste can
resistance to surface scaling caused by increase the be used.
concrete resistance to surface scaling caused by
On how to reduce the amount of cement-
deicing with calcium or sodium chloride. Another
water paste and the cost of the mixture we have to:
working advantage of air entrainment is improving
its workability and reduces bleeding in fresh 1. Allow the larger size of aggregate that can be
concrete. accommodated in the pavement slab.

The effectiveness of air entrainment is to 2. Ascertain the aggregate is uniformly graded


increase the concrete durability that is influenced from coarse to fine.
by: 3. Avail of the biggest quantity of coarse
aggregate consistent with proper workability.
1. Percentage of air present in the mixture.
4. Adopt the lowest slump consistent with the
2. Grading of aggregates.
proper pouring and finishing.
3. Size and distribution of air bubbles.
Slump Test
CEMENT and WATER RATIO
- is the old traditional and most widely used
The strength and other desirable properties
method in determining the consistency of
if concrete mixture varies depending upon the
concrete.
ratio of concrete to mixing water. A non-air-
- A Truncated Cone of metal sheet 12 inches high
entrained concrete with a water cement ratio by
with base and top diameters 8 inches and 4
weight of 5 gallons of water per bag of cement may
inches is filled 3 layers with fresh concrete.
have a compressive strength of about 5,300 psi in
- Each layer is rodded 25 times. Then the cone is
28 days. On the other hand, a mixture of concrete
lifted off vertically, allowing the concrete to
with 7 gallons of water per bag of cement has
subside. The slump is the height in inches that the
developed strength of 3.700 psi only for 28 days.
top of the specimen falls.
Durability is dependent on the water-cement ratio
that should be properly controlled to obtain the
richness of the paste. AASHTO Guide specification
for highway construction established the max.
water cement ratio at 6 gallons per bag of cement
on normal conditions and 5 gallons per bag of
cement fir severe atmospheric conditions.

CONCRETE MIXTURE

The objective in mixing concrete is to use


more aggregates and as a little cement as possible,
while maintaining the workability necessary for a Kelly Ball Method
successful pouring and consolidation. - a metal cylinder 15 cm diameter and 12 cm high
For structural concrete poured in with hemisphere bottom shaped weighing 14 kg.
inaccessible small areas around reinforcing bars, it - a graduated handle rising from the top of the
is necessary to over-fill the voids or spaces around ball passes through a metal frame that is 30 cm
the aggregate and reinforcement using free apart. The ball is placed on the surface of the
flowing cement in water paste form. On the fresh concrete. Its penetration is measure by
contrary, pavement where the slab is open and thin comparing its position with that of the frame.
with an access to manipulate from the surface, a - The advantage is that reading could be taken
drier mixture can be poured inside the form with immediately on the concrete being poured on the
ease and success. Thus, a higher percentage of roadway. On the contrary, the slump test requires
more time but could be conducted only on constructed on the prepared base in accordance
selected samples. with the plans and specifications.
MATERIAL REQUIREMENTS

PORTLAND CEMENT
- shall conform to the applicable requirements of
Item 0-700, hydraulic cement. Only type 1 or the
normal or common Portland cement should be
used. Different brands or the same brands from
different mills shall not be mixed nor shall they
be used alternately unless approved by the
supervising engineer.

FINE AGGREGATE
1. Fine aggregate shall consist of natural sand,
stone screening or other inert materials with
similar characteristics or combination thereof,
CURING of CONCRETE PAVEMENT having hard, strong and durable particles. It
Newly placed concrete pavement needs curing. shall be free from injurious amounts of
Curing may be accomplished by several methods organic impurities.
but basically; all the methods could be categorized 2. Fine aggregates from different sources of
into two: supply should not be mixed or stored in the
same pile nor used alternately.
1. Those that keep the surface constantly wet or 3. Fine aggregates should not contain more than
cover it with water absorbent material that is re- 3 mass percent of materials passing the
wetted from time to time. 0.075mm (No. 200) sieve by washing nor more
2. Those that pavement evaporated from the than one mass percent each of clay lumps or
water already in the concrete which is retained shale.
is sufficient enough for hydration. 4. The use of beach sand will not be allowed
without the approval of the supervising
The chemical action between cement and engineer.
water produces strength of concrete. If the 5. If the fine aggregate is subjected to 5 cycles of
concrete dries out quickly, hydration and strength the sodium sulfate soundness test, the
processes will stop, but when moisture becomes weighed loss should not exceed 10 mass
available during hydration, strength gain will percent.
continue. The shortest period of curing for normal 6. If fine aggregate is subjected to test for
concrete is 5 days according to AASHTO organic impurities and a color darker than the
recommendation. standard is produced, it should be rejected.
However, when tested for the effect of organic
impurities on the strength of mortar by
DPWH SPECIFICATIONS ON CONCRETE
AASHTO T-71, the fine aggregate may be
PAVEMENT
used if the relative strength at 7 and 28 days
Concrete pavement is categorized under is not less than 95 mass percent.
item 311 of DPWH standard specifications, which
Table 8-4 grading requirements for fine
provides that:
aggregates
This item shall consist of Portland cement
Sieve Designation Mass Percent
Concrete pavement with or without reinforcement,
10.0 mm 3/8 100 50.0 2 - 90 - 90 -
100 100
4.75 mm No. 4 95-100
37.5 1 25 - 60 35 - 70 -
1.18 mm No. 16 45-80
25.0 1 - 0 - 15 35 - 70
0.30 mm No. 50 5-30
20.0 0 - - -
0.15 mm No. 0-10
1
100
0
12.0 0-5 0-5 10 - 30

4.75 No. 4 - - 0-5

COARSE AGGREGATE
1. Coarse aggregate shall consist of WATER
crushed stone, gravel, blast furnace slag, or Water to be used in concrete mixing or
other approved inert materials of similar curing or other designated applications
character or combination thereof, having should be clean and free from oil, salt, acid,
hard, strong durable pieces, free from any alkali, grass or other substances injurious to
adherent coatings the finished product. Drinking water if used
2. Coarse aggregate should contain not needs to be tested.
more than one mass percent of material REINFORCING STEEL
passing the 0.075mm (No. 200) sieve nor The specifications state that: dowels and tie
more than 0.25 mass percent of clay lumps, bars to be used in concrete pavement shall
not more than 3.5 mass percent of soft conform to the requirements of AASHTO M-31 or
fragments. M-42 except that rail steel shall not be used for tie
3. If the coarse aggregate was subjected bars to be bended and re-straightened during
to 5 cycles of the sodium sulfate soundness construction. Specifications further provide that:
test, the lost weight should not exceed 12 1. Tie bars shall be deformed bars.
mass percent. It should have a mass 2. Dowels shall be plain round bars delivered
percent of wear not exceeding 40 when to the site with one half of each dowel
tested by AASHTO T-96. length painted with one coat of approved
4. If slag is used, its density should not lead or tar paint.
be less than 1120 kilogram per cubic meter. 3. The sleeves of dowels shall be metal of
The gradation of the coarse aggregate approved design to cover 50mm plus or
should conform to Table 8-5. Only one minus 5mm of the dowels, with a closed
grading specification should be used from end, with a suitable stop to hold the end of
any one source. the sleeve at least 25mm from the end of
the dowel.
Table 8-5 grading requirements for coarse
4. Sleeve shall be of such design that they do
aggregate
not collapse during construction.
Mass Percent Passing
JOINT FILLERS
Grading Gradin Gradin
Siev Designatio - Joint fillers should be mixed
A g g
e n asphalt and mineral or rubber filler.
B C
mm Inch The pre-formed joint fillers are
75.0 3 100 - - punched to admit the dowels. Filler for
each joint should be furnished in a
63.0 2 90 - 100 100 100
single place for the full depth and
width of the joint the cement content and the proportions
of aggregate and water that will produce a
STORAGE OF CEMENT AND AGGREGATE workable concrete having a slump of
- The storage house for cement
between 40 and 70 mm (11/2 to 3) if not
should be waterproof with raised floor
vibrated, or between 10 to 40 mm if
from the ground to protect the cement
vibrated and flexural strength of not less
from rain or dampness.
than 3.8 Mpa (550 psi) when tested by the
1. The provisions for storage should be ample third-point method or 4.5 Mpa (650 psi)
enough and the shipment of cement as when tested by the mid-point method or a
received is separately stored in such a compressive strength of 24.1 Mpa (3,500
manner as to allow the earliest deliveries to psi) when tested at fourteen days.
be used first and to provide easy access for
identification and inspection of each
shipment. 3. The designer should consider the use of
2. Storage house must have the capacity to lean concrete (econo-concrete) mixture
accommodate sufficient quantity of using local materials or specifically
cement to allow sampling at least 12 days modified conventional concrete mixture in
before the cement is used. base course and in the lower course of
3. To secure uniformity of concrete mixture,
composite, monolithic concrete
the coarse aggregate are separated into
pavements using a minimum of 75 mm of
two or more sizes. Different sizes of
conventional concrete as the surface
aggregates are stored in separate bins or in
course.
separate stockpiles sufficiently remote
from each other to prevent the materials at
the edge on the piles from becoming QUALITY CONTROL OF CONCRETE
intermixed
For quality control of concrete in general,
the DPWH specifications provides that:
PROPORTIONING, CONSISTENCY AND The contractor shall be responsible for the
STRENGTH OF CONCRETE quality control of all materials during the handling,
Prepare a design mixture based on the blending, mixing and placement operations. The
absolute volume method as specified in the contractor shall furnish the engineer a Quality
American Concrete Institution (ACI) standard Control Plan detailing the production control
Recommended Practice for selecting Proportion procedures and the type and frequency of
for normal and heavyweight concrete. sampling and testing to insure that the concrete
produced complies with the specifications. The
1. The intent of this specification is to require supervising Engineer shall be provided free access
approximately 9.0 bags of cement per to recent plant production records, and if
cubic meter of concrete based on a 40 kg requested informational copies of design,
weight per bag of cement. However, materials certifications and sampling and resting
leaner or richer mixture may be used in reports.
order to meet the minimum strength REQUIRED QUALIFICATION OF WORKMEN
requirements.
Concrete Butcher The person performing the
batching of mixing operation, capable of
2. The engineer will determine from the
accurately conducting aggregate surface moisture
laboratory tests. The materials to be used,
determinations and establishing correct scale and thoroughly re-rolled or tamped.
weight for concrete materials. Imperfections or variations above the
grade should be corrected by tamping or
Concrete Technician The person responsible for
concrete production control and sampling and by cutting as necessary.
testing for quality control proficient in concrete 2. Grading and Alignment form shall be
technology having a sound knowledge of the set sufficiently advance from the point
specifications as they relate to concrete where the concrete is being placed. After
production. He shall be: setting to correct grade, the base is
thoroughly tamped, mechanically or by
Capable of conducting test on concrete and
hand, at both edge of the form base inside
concrete materials in accordance with the
and outside. The forms should not deviate
specifications.
from the true line by more than one
Capable of adjusting concrete mix designs for
centimeter at any point.
improving workability and specification
3. Grading and Alignment the alignment
compliance and preparing trial mix design.
and grade elevation of the forms should be
He shall be qualified to act as the concrete
checked and corrections be made
batcher in the absence of the batcher.
immediately before the placing of concrete.
Prior to the placing of concrete, the crown
PREPARATION OF GRADE and elevation are verified by holding an
After the base or sub-grade have been approved template in a vertical position
placed and compacted to the required density, the moving backward and forward on the
areas that will support the paving machine and the forms.
grade on which the pavement is to be constructed
HANDLING, MEASURING AND BATCHING OF
should be trimmed to the proper elevation by
MATERIALS
means of a properly designed machine extending
the work at least 60 cm beyond each edge of the The batching plant and equivalent layout
proposed concrete pavement. must provide a smooth and flow of continuous
supply and transport of materials to the work.
If loss of density results from the trimming
Stockpiles are built up in layers of not more than
operations, it should be restored by additional
one meter in thickness with each layer completely
compaction before concrete is placed. If any traffic
in place before beginning the next that should not
is allowed to use the prepared sub-grade or the
be allowed to cone down over the next lower
surface, it should be checked and corrected
layer.
immediately ahead of the placing of concrete. The
sub-grade or base should be uniformly moistened All washed aggregates and aggregate
when the concrete is placed. produced or handled by hydraulic methods are
stockpiled or binned for draining at least twelve
Setting of Forms
hours before being batched.
1. Base Support The foundation under the
The mixer should be charged without loss
forms should be hard and true to grade, so
of cement and batched material should be charged
that the form when set will be firmly in
without loss of cement and should be weighed for
contact with its whole length at the
each material required within a tolerance of 1% for
specified grade. Any roadbed, which is cement and 2% for aggregates. Water may be
below the established grade, should be measured by volume or by weight and the
filled with approved granular materials to accuracy of measuring water shall be within a
grade in lifts of three centimeters or less, range of x > 1% error.
Mixing Concrete agitators, or non-agitating trucks. The time
elapsed from the time water is added to the
The concrete may be mixed at the site, in a central
mix until the concrete is deposited in place at
plant or by truck mixers of approved type and
the site shall not exceed 45 minutes when the
capacity. Mixing time will be measured from the concrete is hauled in non-agitating trucks, nor
time when all materials except water are already 90 minutes when hauled in truck mixers or
inside the drum. truck agitators, except that in hot weather or
under conditions contributing to quick
1. Ready mix concrete shall be mixed and
hardening of concrete by the supervising
delivered in accordance with ASSHTO M-157
Engineer.
requirements, except that the minimum
7. Re-tempering concrete by adding water or by
required revolutions at the mixing speed for
any other means shall not be permitted, except
transit mixed concrete may be reduced to not
that when concrete is delivered in truck mixers,
less than that recommended by the mixers
additional water may be added to the batch
manufacturer. The number of revolutions
materials and additional mixing is perform
recommended by the mixer manufacturer
increasing the slump to meet the requirements
should be indicated on a serial plate attached to
if permitted by the Engineer, provided that all
the mixer.
these operations are performed within 45
2. When mixing is done at the site or in a central
minutes after the initial mixing operations and
mixing plant, the mixing time should not be less
the water cement ration is not exceeded.
than 50 seconds nor more than 90 seconds,
unless mixing performance tests provide Limitation of Mixing
adequate mixing of the concrete in a shorter
No concrete should be mixed, placed or
time period. Mixing time ends when the
finished, when natural light is insufficient, unless
discharge chute of the mixer opens. The
an adequate and approved artificial lighting
contents of the individual mixer drum shall be
system is operated.
removed completely before a succeeding batch
is loaded therein. PLACING OR DEPOSITING OF CONCRETE
3. The volume of concrete mix per batch should Concrete is deposited in such a manner
not exceed the mixers nominal capacity in cubic requiring minimal re-handling. Unless truck mixers
meter, as indicated on the manufacturers or non-agitating hauling equipment are equipped
standard rating plate attached on the mixer with a means to discharge concrete without
except that an overload up to 10 % above the segregation of the materials, the concrete should
mixers normal capacity may be permitted be unloaded inside the form in a manner to
provided that concrete test data for strength, prevent segregation of the particles.
segregation and uniform consistency are
satisfied and no spoilage of concrete should 1. Placing of concrete between transverse joints
take place. without the use of intermediate bulkheads.
4. The batches shall be charged into the drum with Necessary hand spreading shall be done with
a portion of the mixing water enter in advance shovels, not rakes. Workers are not allowed to
of the cement and aggregates. The flow of water walk on.
should be uniform that all water shall be inside 2. Where concrete is to be placed adjoining a
the drum at the end of the first 15 seconds of previously constructed lane, and mechanical
equipment will be operated upon the existing
the mixing period.
lane, that previously constructed lane must have
5. The throat of the drum shall be kept free of
attained the strength for 14 day concrete. If
concrete accumulation that may restrict the free
finishing equipment is carried on the existing
flow of materials into the drum. lane paving in adjoining lanes may be permitted
6. Mixed concrete from the central mixing plant only after 3 days.
shall be transported in truck mixers, truck
3. Vibrators should not be allowed to come in 1. The expansion joint filler should be continuous
contact with a joint assembly, grade or side from form to form shaped to the sub-grade
form. In no case it be operated longer than 15 and to the key-way along the form.
seconds in any one location. 2. Pre-formed joint filler should be furnished in
4. Concrete should be deposited as near as lengths equal to the pavement width or to the
possible to the expansion and contraction joints
width of the lane.
without disturbing them, but should not be
3. Finished joint should not deviate more than
dumped from the discharge bucket of hopper
6mm from a straight line. If joint fillers are
into a joint assembly unless the hopper is well
centered on the joint assembly. assembled in sections, there should be no
offsets between adjacent units.
Concrete Joint 4. No plugs of concrete should be permitted
Concrete joints are constructed according anywhere within the expansion space.
to the type, dimensions and at the locations as
Transverse Contraction Joint
indicated on plans or special provisions.

All joints should be protected from the 1. Transverse contraction joint is provided when
intrusion of injurious foreign materials until after there is an interruption of more than 30 minutes
sealed. in the concreting operations.
2. No transverse should be located within 1.50
Concrete Pavement Joints are classified into:
meters of an expansion joint, contraction joint,
1. Longitudinal Joint plane or weakness.
2. Transverse Joint 3. If sufficient concrete has been mixed at the right
3. Transverse Contraction Joint time of interruption to form a slab of at least
4. Longitudinal Contraction Joint
1.50 meters long the excess concrete from the
5. Load Transfer Device
last preceding joint should be removed and
Longitudinal Joint disposed of as directed.

1. Deformed steel bars or special length, size,


Classification of Transverse Contraction Joint
spacing and materials are placed perpendicular
a. Transverse Strip Contraction Joint is installing as
to the longitudinal joints. Tie bar should not be
parting strip to be left in place as specified.
painted or coated with asphalt or other
materials or enclosed in tubes or sleeves. b. Formed Groove is installed by depressing an
2. Except those made of rail steel, tie bars maybe approved tool or device into the plastic
bent at right angles against the form of the first concrete.
lane constructed and straightened into final
The tool or device remain in place at least until
position before the concrete of the adjacent
the concrete has attained its initial set, and to be
lane is placed.
removed without disturbing the adjacent
3. The longitudinal joints are sawed before the end
concrete.
of the curing period or shortly thereafter and
before any equipment or vehicles are allowed c. Sawed Contraction Joint is made by sawing
on the pavement. The sawed area should be groove in the surface of the pavement. Sawing
thoroughly cleaned and if required, the joint is done as soon as the concrete hardened
should be filled immediately with sealer. sufficiently to permit sawing without excessive
4. Longitudinal pavement insert type joints should raveling, and the time is usually within 24 hours
be formed by placing a continuous strip a i. Joints are sewed before uncontrolled
plastic material which will react adversely with shrinkage cracking takes place.
the chemical constituent of the concrete. ii. If necessary, the sawing operations should
Transverse Expansion Joint be carried during the day or night
regardless of weather conditions.
iii. The sawing of any joint is omitted if crack 25.0 32 45 30
occurs at or near the joint prior to the time
27.5 32 45 30
of sawing.
iv. Sawing should be discontinued when crack 30.0 32 45 30
develops ahead of the saw. In General, all
Source: AASHTO Interim Guide and proposed
joints should be sawed in sequence.
revision 1980
v. If extreme condition exists making it
impractical to prevent erratic cracking by
early sawing, the contraction joint groove is
REMOVAL OF FORMS
formed prior to the initial setting of
concrete. Forms for concrete pavement should
remain in place undisturbed within 24 hours after
Load Transfer Device
pouring. The removal could be done as follows:
Load transfer device is provided along the
1. Crowbars are used in removing forms,
longitudinal centerline of the pavement either by
pulling out nails and pins but care should
tongue and groove concrete or by steel dowels
be exercised not to break the pavement
under the following considerations:
edges.
1. When dowel is used, it should be held in 2. In case a portion of the concrete slab is
position parallel to the surface and centerline of spelled off, it should be repaired
the slab by a metal device that is left embedded immediately with fresh mortar mixture of
in the pavement. 1:2.
2. The portion of each dowel painted with one 3. Major honeycombed area will be
coat of lead or tar should be thoroughly coated considered as defective work, to be
with an approved bituminous material or an removed and replaced.
approved lubricant, to prevent the concrete
from binding to the portion of dowel.
3. The sleeves for dowel should be metal, design Protection of Pavement
to cover 50 mm plus or minus 5mm of the
Concrete pavement and its appurtenances
dowels with a water tight closed end with a
should be protected against public traffic, and
suitable stop to hold the end of the sleeves at
traffic caused by the workers. Protection of the
least 25 mm from the end of the dowel.
pavement includes the posting of watchmen to
4. In lieu of using dowel assemblies at contraction
direct traffic and the posting and maintenance of
joints, dowels may be place in the full thickness
warning signs, lights, pavement bridges or
of the pavement by a mechanical device
crossovers, etc. Any damage to the pavement prior
approved by the Engineer.
to the final acceptance of the work shall be
RECOMMENDED DIMENSION OF DOWEL FOR repaired or replaced depending upon the extent of
CONCRETE PAVEMENT the damaged.

Pavement Dowel Dowel Dowel


Thickness Diameter Length Spacing
(cm) (mm) (cm) (cm)
15.0 20 45 30

17.5 25 45 30

20.0 25 45 30

22.5 32 45 30

Anda mungkin juga menyukai