BILL OF QUANTITIES (BEAM)

Item
Description Unit Qty Rate RM
no.
Concrete work
1 Cu.m 1.037 211.70 219.53
Concrete grade 25
Formwork
2
Sq.m
Formwork Sides 10.454
Soffit 1.742
Reinforcement
3
Y12, 43.598m kg 38.687 2.495 96.52
Y16, 7.148m 11.283 2.3615 26.64
R6, 116.144m 25.766 2.4991 64.39
(Assuming density of steel bar = 7850kg/m3
BILL OF QUANTITIES (COLUMN)

Item
Description Unit Qty Rate RM
no.
Concrete work
1 Cu.m 4.682 211.70 991.18
Concrete grade 25
Formwork
2
Sq.m 102.606
Formwork Sides

Reinforcement
3
Y12, 524.388m Kg 465.619 2.495 1161.72
Y16, 61.44m 96.986 2.3615 229.03
R6, 437.964m 97.220 2.4991 242.96
(Assuming density of steel bar = 7850kg/m3