DAILY ACTIVITY REPORT (MECHAN

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B
1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE


BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART
2 BOILER & ESP
ROTATING EQUIPMENTS

HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING


FUEL PATH

INSULATION

ESP

TG TO BOILER INTERCONNECTION

RAW WATER PUMP HOUSE


CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM
PIPE RACK

FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS

DECK RAILING WORK.


STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER

5 TG BUILDING AUXILLARIES

FABRICATION &ERECTION OF PIPING

LUBE OIL SYSTEM

AC DUCTING WORK
STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL

EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 28
(HAZEMAG)
2 THERMAX 242
3 GPR 22
4 APT 13
5 SUVENDU SAHU 4
JOSEPH
6 10
CONSTRUCTIONS
7 ION EXCHANGE 4
ORT (MECHANICAL- CPP) DATE-14.09.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW

Final welding of Vertical bracing in progress.


Erection of feeder breaker platform assembly is Same to continue
in progress.

Sheeting work & Final welding completed .

Dismantling work is in progress with proper Rework on the main columns


precautions. All the three columns of staircase of transfer tower-2 to be
removed and tie bracings connecting to started.
staircase columns has been removed.

Column grouting work completed.


Alignment & Welding of walkway completed. Erection & Welding of
Erection & Welding of handrailing is in handrailing to continue.
progress.

Foundation bolts to be placed.

Levelling of ramp for trussel erection Erection process to be taken


completed. Final welding of trussel TR-6 is up.
under progress.

Assembly work of Structures completed & final same to continue


welding is in progress.

Pipe inserts at 17.5m level fabricated and


inserted. Fabrication of Impactor discharge same to continue
opening frames completed .
All fabrication scraps being
cut for use & house keeping
Final painting work in progress. work to continue. Painting
work to continue.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation of PA duct,pipes & bottom portion of


economiser casing connecting to MDC is in
progress.Insulation of SA Duct header
connecting to furnace taken up &is in progress. Same to continue
Insulation of duct connecting ID FAN to
chimney in progress.

No activity

Final painting work in progress. Erection of


monorail support structure & monorail for ID Same to continue
FAN is in progress.

External hydrotest completed sucessfully in


presence of Deputy Director of Factories and welding of supporting
Boilers. Welding of supporting structures in structures for pipes to
progress.Erection of steam vent support is in continue.
progress.
Erection of ID FAN-3 completed & alignment is
in progress. ID FAN-4 foundation modification
in progress & foundation work for SA FAN
completed. Erection of base frame of PA FAN-3 Same to continue
&4 completed & alignment is in progress.
Erection of base frame of SA FAN-3 & SA FAN-4
in progress .

Fabrication work of SA fan delivery line in


progress. wind box erection completed.
Erection of PA Duct connecting to windbox Same to continue
started & welding is in progress.

Erection & welding of secondary air duct fitting Same to continue


work in progress .

Welding work at ID FAN ducting in progress.


Welding & Erection of economiser casing in Same to continue
progress. Connecting duct from furnace to
economiser work is in progress.
MDC welding in progress. Erection & welding
of MDC Bypass to ash seperator is in progress. Same to continue
Fixing of ceramic cyclones pipes in MDC is in
progress.

Insulation work to be taken up.

Assembly of pent house structure is in progress.


Emitting electrode erection in progress.
Assembly & welding of 1st,3rd fields Hopper Same to continue
completed. Erection of 1st & 3rd field hopper
completed.Assembly of 2nd field hopper is in
progress.

Erection & Welding of connecting beams from


TG to Boiler completed. Erection & welding of
tie beams is in progress.

Both Raw water pump sole plates Assembly work to be taken


positioned,levelled,grouted & curing is under
up.
progress.
Erection &welding of longitudinal tie Grouting work will be
completed. Grouting of columns is in progress. continued.

Erection of cooling water pump(CW) base


No activity
frame completed.

No activity as monitoring basin work yet to


start.

No activity

Fire fighting pumps have reached transporters


Godown.GPR informed and freight clearance by Fixing of Fire Sensor Cables
and Conduits to start.
GPR is awaited

Clearing of the Cooling Tower materials for Foundation layout to start.


foundation layout is completed.
Fabrication of remaining pipe racks completed
& painting work is in progress. Erection of pipe
rack supporting column near boiler is in
progress.alignment of pipe rack near clarified Same to continue
water pump house completed. Fabrication of
remaining cable rack is in progress.Painting of
cable rack started.

Wrapping coating of 1400NB Pipes for CW line


is under progress. Welding of bend at cooling
tower puddle pipe completed. Assembly of
suction line of CW inlet completed &welding is Same to continue
in progress. Fabrication of reducers for CW line
completed & painting is in progress. Welding of
flanges to puddle pipes in cooling tower to be
taken up.

All materials shited close to Cooling Tower Same to continue

No activity Shifting to continue

No activity Shifting to continue

Railing work at deck nearing completion.


Final welding of staircase & Fixing of chequered
plates for steps completed.Fixing of handrailing
to be taken up.

Temporary platform for fixing bolts of turbine


started.TG Floor being Cleaned to start Erection Same to Continue
Activities of Turbine.

No activity

Expansion work of tube end is in progress &


welding of vaccum pipes to condenser is in Same to continue
progress.

Positioning & Alignment of condensate float


tank completed.

Fabrication of boiler feed pump delivery line in No activity


progress.

Fabrication & Erection of lube oil pipe line &


pipe supports is in progress. Same to continue

Insulation work of 10.5 M control room roof


completed.Erection of AC duct & rapping of Same to continue
insulation is in progress.
Final welding is in progress & fixing of gratings Same to continue
completed.

No activity No activity

No activity

No activity

Completed

Shifting of MGF connecting pipes completed &


Shifting of sand bags to cooling tower in Same to continue
progress. Assembly & sand fill to start.

No activity

Erection of purlins completed & levelling No activity


completed.
No activity
.13
REMARK

Hoppers, railings & chutes for feeder


breaker awaited at site. Party has been
followed up.

All materials received at site

Follow up on for Short Post and


stringers for inclined ramp.
Idler frames & Idler not received at
site.

Civil foundation work yet to be


completed

Trussel fabrication completed & gallery


to be received.party not despatching
further materials despite of repeated
reminders. Rigorous followup required
as party is not able to provide any
evidence of work in progress.

Civil work yet to be completed


Refractory work to be taken up during
the next week.
Balance Erection work awaiting
completion of fan foundation.
Plastering work of Raw water pump
house is in progress which will be
completed and pump erection work
shall start.
Alignment of base frame to be taken
after erection of suction line to pump.

Pipe fittings awaited at site.

Cables & conduits of fire sensors at TG


Building 10.5M control room roof have
reached Site

Civil foundation work to


start.fabricated tank awaited at site
One vehicle containing 1400 dia Pipes
received at site & unloading
completed.

Civil work yet to be completed &


mobilisation to be started by
Paltech.Paltech to mobilise site by
15/9/13.

same as above

same as above

West side railing work of cooling tower


staircase to be taken up after
completion of deck railing.
Work stopped to give way for
completion of civil work.

Erection Work to start by 16/9/13

All other available equipments have


been placed in position.

IBR Approval awaited

Materials indented for supply of


cooling water to A.C.Units
Sheeting work to be done after
completion of grouting of anchor bolts
of purlins.