DAILY ACTIVITY REPORT (M

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B

1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B
SECONDARY CRUSHER HOUSE

BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL
PRESSURE PART

ROTATING EQUIPMENTS

2 BOILER & ESP

HOT AIR DUCTING

COLD AIR DUCTING


FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP
TG TO BOILER INTERCONNECTION

RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE


COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM

PIPE RACK
FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS

DECK RAILING WORK.

STRUCTURAL
TURBINE

TURBOGENERATOR

5 TG BUILDING CONDENSER

AUXILLARIES

FABRICATION & ERECTION OF PIPING


LUBE OIL SYSTEM

AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL
EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 8
(HAZEMAG)
2 THERMAX 125
3 GPR 30
4 APT 16
5 SUVENDU SAHU 0
JOSEPH
6 12
CONSTRUCTIONS

7 ION EXCHANGE 5
VITY REPORT (MECHANICAL- CPP) DATE-11.10.13
ACTIVITY AT SITE

Erection of feeder breaker platform assembly to complete.

Sheeting work & Final welding completed .

Erection of diagonal beams connecting main columns


started & is in progress. Rework on the main columns of
Transfer Tower-2 completed. Fabrication & welding of
staircase column completed. Alignment work completed
and welding in progress. Tie members of Main Column
structures being erected. Rework on the foundation
completed.Precaution for predicted cyclone has been
taken by tieing guy ropes to the columns.

Column grouting work completed.


Erection & Welding of handrailing is in progress. Grouting
of all the columns completed.

Foundation work 3B is in progress. Erection of gallery of


3A completed.

Precaution for predicted cyclone has been taken by tieing


guy ropes to the trussels.Erection of bottom section of 4
nos of Columns of TR-6 was completed.Columns Erection
of TR-5 completed. Erection of tie beam of TR-6 & TR-5 is
in progress.

Assembly work of Structures & final welding completed.


Casting of half portion of 17.0 M slab completed.

Final painting work in progress.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation work at SA FAN duct is in progress.Insulation of


outlet duct of ESP connecting to ID FAN is in progress.
Insulation of remaining pipes in furnace is in
progress.Insulation of PA duct started. Insulation of by
pass ducts from BAC started. Insulation work at PA & SA
FAN was taken up.

No activity

Fixing of net in pent house for insulation. Final painting


work in progress. Erection of monorail support structure &
monorail for ID FAN completed & welding is in progress.
Erection of monorail support structure & monorail for PA
FAN & SA FAN is in progress.
Welding of supporting structures in progress. Erection of
steam vent support completed. Erection & welding of IBD
Vent completed. Refractory work in furnace zone is in
progress.

Erection of expanion bellow in ID Fan -4 was taken


up.Erection of ID FAN-3 completed & alignment is in
progress. ID FAN-4 foundation modification completed &
erection of its fan casing is in progress. Erection &
alignment of rotor of PA FAN-3 & 4 completed. Erection of
rotor of SA FAN-3 & SA FAN-4 completed & alingnment is
in progress.

Erection & welding of PA Duct connecting to windbox


completed . Ducting from PA line to MDC is in
progress.Ducting from PA AIR line to Wind box is in
progress .Erection of PA FAN to APH connecting duct
completed & final welding is in progress. Erection of duct
connecting APH to ESP completed & welding in progress.

Erection & welding of secondary air duct fitting work in


progress .Ducting work from SA FAN to APH is in
progress.Erection of damper & silenser for SA Fan
completed.
Refractory work inside furnace zone started.Welding work
at ID FAN ducting in progress. Erection of economiser
casing completed & Welding of economiser casing
completed.

Welding of chute connection to drag chain feeder of coal


bunker is in progress.MDC welding in progress. Erection &
welding of MDC Bypass to ash seperator completed. Fixing
of ceramic cyclones pipes in MDC completed.Erection of
MDC bypass lineis in progress. Erection of air slide in MDC
is in progress.

Insulation work to be taken up.

Assembly of pent house structure is in progress. Emitting


electrode erection completed. Erection of 2nd & 4th field
hopper completed final welding of hopper is in progress.
Erection of chequered plates on the roof completed.Pent
house roof sheeting work is in progress. Fabrication of 5th
field hopper completed & to be erected.
Fabrication of Connecting walkway is in progress. fixing of
anchor plates on TG building for walkway is in progress.

Erection of one pump was completed under the


supervision of mather & platt Engineers. Clearing of
basement for the erection of second pump is in progress.

Fabrication of Monorail Gantry in progress.

Erection of cooling water pump(CW) base frame


completed. Fabrication of reducer for cooling water inlet is
in progress. Erection of Crane Gantry beams for EOT crane
to complete. Erection of side runner for side sheeting
work to complete.Fixing of deck sheet in MCC ROOM
completed.

No activity as monitoring basin Civil work yet to start.


Erection of globe valves inside compressor house
completed & erection of pipe connecting valve to
compressor to start. Erection of pipe rack support
connecting to main pipe rack completed. Fabrication of
Pipelines in progress. Erection of compresed air pipe near
boiler is in progress & doubling of pipes on pipe rack is
under process.

One truck containing GI &MS pipes recived &


unloaded.Fire fighting pumps have reached transporters
Godown.GPR informed and freight clearance by GPR is
awaited.

Civil foundation work has started.

Fabrication of remaining cable rack completed & erection


is in progress. Final welding of pipe rack connecting beams
completed. Erection of columns & connecting beam for
pipe rack connecting from main pipe rack to DM Plant is in
progress.
CT MAKEUP Piping from clarified water pump house to
main pipe rackis in progress. Final welding of 1400NB pipe
near cooling tower completed till pump house. Erection &
welding of 80 NB DM make up line is in progress.
Fabrication of Man hole on CW line is in progress.

All materials shifted close to Cooling Tower.

No activity

No activity

Railing work at staircase completed .

Fixing of supporting angle for closing of temporary


opening at 23.5 M Level.Fixing of handrailing in staircase
completed final finishing work to be completed. Roof
sheeting of staircase head room completed & side
sheeting to start.
Shifting of turbine assembly materials to the TG Deck is in
progress. Upper casing of turbine was erected with
exhaust hood upper part for the assembly.

Insertion of generator rotor &fixing it in position was


completed with proper supervision of BHEL
Representatives.

No activity

No activity

Fabrication of boiler feed pump delivery line in progress.


Fabrication & assembly of pipe valves connecting
condensate float tank is in progress.Segrigation of piping
material for assembly is in progress.
Fabrication & Erection of lube oil pipe line & pipe supports
is in progress.

No activity

No activity

No activity

No activity

No activity

Completed
Erection of agitator pump with its assembly in acid
preparation tanks completed final positioning to be done.
Assembly of pipes in MGF near cooling tower is in
progress. Erection of level gauge on DM tank-2 completed.
Erection of pump in nutralisation pit completed.Filling of
material inside SSF is in progress.

Erection &welding of pipe connecting clarifier to clarified


water tank was taken up &is in progress,.Pipe connecting
sludge transfer pump completed. Fabrication & erection of
connecting pipe from raw water to clarifier is in progress.
Assembly of pipes from clarifier to chemical house is in
progress.PVC Piping from DM plant to DM tank was
completed.

Erection of purlins completed & levelling completed.


Fixing of flanges to puddle pipes in acid preparation tank
completed.Main water pipe through Chemical house has
been erected .Final welding of main water pipe was
completed.

No activity
DATE-11.10.13
PLANNED FOR REMARK
TOMORROW

Hoppers, railings & chutes for feeder breaker


Same to continue awaited at site. Party has been followed up.

No activity Transfer Chutes awaited at Site

Grouting of foundation bolt to


be completed

Follow up on for Short Post and stringers for


inclined ramp.
Welding of handrailing will be Idler frames & Idler not received at site.
continued.

Civil foundation work yet to be completed

One lot gallery material received at site


&loaded.Trussel fabrication completed & gallery
to be received.party not despatching further
Erection of connecting beams materials despite of repeated reminders. Rigorous
of TR-5 & TR-6 to continue. followup required as party is not able to provide
any evidence of work in progress.WITHOUT
GALLERY IT IS NOW UNSAFE TO HOLD THE
ERECTED TRUSSELS FOR LONG.

Erection work to start after


transfer house -2 erection
completion.
Civil work to continue. Civil work yet to be completed

All fabrication scraps being cut


for use & house keeping work
to continue. Painting work to
continue.
Same to continue

Same to continue
welding of supporting
structures for pipes to Refractory work started.
continue. Refractory work to
continue.

Same to continue

Balance Erection work awaiting completion of fan


Same to continue foundation.

Same to continue
Same to continue

Same to continue

Same to continue
Same to continue

Erection second pump work to


start.

Same to continue

Alignment of Crane Gantry 8-TON crane for CW & ACW pump house received
at site. Alignment of base frame to be taken after
beams to continue. erection of suction line to pump.
Final Alignment pipe rack
support connecting to main
pipe rack & erection of
connecting beam Pipe fittings awaited at site.
completed.Erection of
compressed air line in pipe
rack to continue. Piping work
for instrument air line to start.

Cables & conduits of fire sensors at TG Building


Fixing of Fire Sensor Cables 10.5M control room roof have reached Site. GI &
and Conduits to continue. MS PIPES received at site.

Civil foundation work started.fabricated tank


Same to continue received at site.

Erection of columns for DM


plant to continue.
Same to continue

Civil work yet to be completed & mobilisation to


be started by Paltech.Paltech to mobilise site by
Same to continue 15/9/13. Civil work not yet completed. Expected
completion by 30/10/13.

Shifting completed same as above

Shifting completed. same as above

West side railing work of cooling tower staircase


to be taken up after completion of deck railing.

Fixing of handrailing to
continue.
Erection Work In progress with supervision of
Same to Continue. BHEL Representatives.

Generator rotor insertion to


start.

No activity

All other available equipments have been placed


No activity in position.

Approval given by IBR for all pressure line


No activity erection & welding.
Same to continue

Materials indented for supply of cooling water to


No activity A.C.Units

No activity

No activity
Pipe assembly work to be
continued. Erection of pipe
support inside DM plant to
start.

Same to Continue

Sheeting work to start.