TRANSFER HOUSE 1
TRANSFER TOWER 2
CONVEYOR 1A & 1B
1 CHP
CONVEYOR 2A &2B
1 CHP
CONVEYOR 3A &3B
CONVEYOR 4A & 4B
CONVEYOR 5A & 5B
SECONDARY CRUSHER HOUSE
BOILER -I
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
BOILER -II
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
TG TO BOILER INTERCONNECTION
3 LP PIPING
FIRE FIGHTING SYSTEM
LDO SYSTEM
PIPE RACK
FABRICATION &ERECTION OF PIPING
STRUCTURAL
TURBINE
TURBOGENERATOR
5 TG BUILDING CONDENSER
AUXILLARIES
AC DUCTING WORK
STRUCTURAL
STRUCTURAL
EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING
CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 8
(HAZEMAG)
2 THERMAX 125
3 GPR 30
4 APT 16
5 SUVENDU SAHU 0
JOSEPH
6 12
CONSTRUCTIONS
7 ION EXCHANGE 5
VITY REPORT (MECHANICAL- CPP) DATE-11.10.13
ACTIVITY AT SITE
No activity
Completed
Completed
Completed
No activity
Completed
No activity
No activity
No activity
No activity
No activity
No activity
No activity
No activity
No activity
No activity
Completed
Erection of agitator pump with its assembly in acid
preparation tanks completed final positioning to be done.
Assembly of pipes in MGF near cooling tower is in
progress. Erection of level gauge on DM tank-2 completed.
Erection of pump in nutralisation pit completed.Filling of
material inside SSF is in progress.
No activity
DATE-11.10.13
PLANNED FOR REMARK
TOMORROW
Same to continue
welding of supporting
structures for pipes to Refractory work started.
continue. Refractory work to
continue.
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Alignment of Crane Gantry 8-TON crane for CW & ACW pump house received
at site. Alignment of base frame to be taken after
beams to continue. erection of suction line to pump.
Final Alignment pipe rack
support connecting to main
pipe rack & erection of
connecting beam Pipe fittings awaited at site.
completed.Erection of
compressed air line in pipe
rack to continue. Piping work
for instrument air line to start.
Fixing of handrailing to
continue.
Erection Work In progress with supervision of
Same to Continue. BHEL Representatives.
No activity
No activity
No activity
Pipe assembly work to be
continued. Erection of pipe
support inside DM plant to
start.
Same to Continue