DAILY ACTIVITY REPORT (MECHANICAL- CPP) DATE-19.08.

1
SL NO. PACKAGE EQUIPMENT CENTRE ACTIVITY AT SITE

Monorail beam erection work


1 CHP PRIMARY CRUSHER/COAL SHED in progress &rafter bracing
erection &welding in progress

Sheeting work &final welding


TRANSFER HOUSE 1 in progress

TRANSFER TOWER 2 No activity

Idler frame & idler erection


CONVEYOR 1A & 1B work in progress

Erection & final welding of


CONVEYOR 2A &2B Floor beams at Trussel TR-3 in
progress.
CONVEYOR 3A &3B No activity

CONVEYOR 4A & 4B No activity

CONVEYOR 5A & 5B No activity

Primary screen received from


SECONDARY CRUSHER HOUSE Hari Machines & unloaded at
site.

2 BOILER & ESP BOILER -I


STRUCTURAL Completed

PRESSURE PART Completed

ROTATING EQUIPMENTS Completed

HOT AIR PATH Completed


COLD AIR PATH Completed

Sand filling for RDO


completed.shifting of fire
FLUE GAS PATH wood to combustion bed in
progress.

FUEL PATH Completed

Insulation work of MDC


INSULATION hopper in progress

ESP Placing of insert plates


&checking completed ready
for casting.
BOILER -II

Erection & welding of 13 M


floor platform in progress.
STRUCTURAL Erection of bed material
&lime stone outlet chute in
progress.
DM water filling for internal
hydro test completed.
Erection of piping support for
PRESSURE PART drain line & feed water line in
progress. Fitup &erection of
non integral piping support in
progress.

id fan foundation
modification in progress &
ROTATING EQUIPMENTS foundation work for PA & SA
FAN in progress.

Erection of seal air ducting in


HOT AIR DUCTING progress.

Erection &welding of
COLD AIR DUCTING secondary air ducting work in
progress .
Erection of ID FAN ducting
completed &welding work in
progress. Erection of
FLUE GAS DUCTING economiser casing in
progress.Connecting duct
from boiler to economiser
work in progress.

burner ducting completed &


FUEL PATH MDC welding in progress.

INSULATION No activity

Emitting electrode erection in


ESP progress & hopper erection in
progress.

Pipe assembly for raw water


LP PIPING RAW WATER PUMP HOUSE pump outlet.
3
CLARIFIER WATER PUMP HOUSE No activity
allignment of columns to be
CW AND ACW PUMP HOUSE completed

No activity as monitoring
UTILITY WATER PUMP HOUSE basin work yet to start.

Erection of instrument air


pipe line in progress. Corner
COMPRESSOR HOUSE flashing (Sheeting work) in
progress.

FIRE FIGHTING SYSTEM No activity

LDO SYSTEM No activity

Fabrication of racks between


clarified water pump house
PIPE RACK &main rack, in progress.
Doubling with welding on
pipe rack in progress.
400mm ACW pipe painting
FABRICATION &ERECTION OF PIPING wrapping in progress .

COOLING FANS ,GEAR BOXES PROPELLER SHAFT


4 No activity
TOWER & STRUCTURALS

DISTRIBUTION PIPE LINES No activity

DRIFT ELIMINATORS & SPLASH No activity


GUARDS

fixing of stand posts for


DECK RAILING WORK. Railing work in progress.

Erection &welding of
5 TG BUILDING STRUCTURAL supporting beams for
staircase in progress.

TURBINE No activity

TURBOGENERATOR No activity
Expansion of tubing in
CONDENSER progress & dome welding in
progress.

Erection of Condensate float


AUXILLARIES tank to be taken up.

Fabrication of boiler feed


FABRICATION &ERECTION OF PIPING pump delivery line in
progress.

Overhead oil tank erection


LUBE OIL SYSTEM completed.

Insulation work of 10.5 M


AC DUCTING WORK control room roof in progress.
Duct fabrication completed.

Staircase erection completed


ASH SILO STRUCTURAL & weldind is in progress.
6
ERECTION OF EMBEDED PLATES & No activity
OPENING
ASH HANDLING EQUIPMENT No activity

Insert plates for pipe line


ASH TRANFER PIPE LINE fixing progress .

WATER
7 TREATMENT STRUCTURAL Completed
PLANT

Electrical panels received and


EQUIPMENT ERECTION unloaded at site and awaiting
for fluidtech erection team.

FABRICATION &ERECTION OF PIPING No activity

Truss erection work


CHEMICAL HOUSE completed

MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER

1 GIRI CONSTRUCTIONS 34
(HAZEMAG)
2 THERMAX 284
3 GPR 18
4 APT 14
5 SUVENDU SAHU 12
JOSEPH
6 8
CONSTRUCTIONS
DATE-19.08.13
PLANNED FOR TOMORROW REMARK

Hoppers, railings &


chutes for feeder
Same to continue breaker awaited at
site

All matreials received


Same to continue at site

16 TON materials have


not been despatched
by party despite of
repeated
reminders.They are
emphasising on
payment.

Same to continue

Same to continue
Civil foundation work
yet to be completed

Trussel fabrication
completed & gallery
to be received.party
not despatching
further materials
despite of repeated
reminders.

Material not received


at site

Civil work yet to be


completed
Same to continue

Same to continue

Same to continue

Same to continue
Same to continue

Same to continue

Erection work
awaiting completion
of fan foundation.

Same as above
Same to continue

Same to continue

Insulation work to
start after hydro test.

Same to continue

clearing of raw water pump


house area for starting of
vertical pump erection.

Purlins still awaited.


Same to continue Purlins still awaited.

Same to continue

No activity

Civil foundation work


No activity to start.fabricated
tank awaited at site

Same to continue
Fabrication of pipe supports for
CW Pump inlet

Civil work yet to be


completed &
No activity mobilisation to be
started by Paltech

No activity same as above

No activity same as above

Same to continue
Same to continue

All other available


equipments have
Same to continue been placed in
position.

Same to continue

Same to continue

Same to continue
Same to continue

Erection of remaining
small pumps to be
No activity taken up during
erection of panels

No activity

Purlin erection to
No activity start after gable wall
completion.