DHDS: - ANNUAL RATE CONTRACT FOR CLEANING AND TESTING OF ( IBR ) WASTE HEAT BOILERS
75E101/201 & SULPHUR CONDENSERS 75E102/103/202/203 & OTHER MISCELLENIOUS JOB RELATED TO
THE FR DHDS SRU TRAIN 1 & 2 SHUT DOWN JOBS.
Provide necessary skilled Manpower, Tools & Tackles, Equipment, Consumables & non-
Consumables material(Unless Specified Otherwise), transportation, erection/dismantling of
Scaffolding as required and supervision to carry out Cleaning and Testing of Waste Heat
Boilers (WHBs) 75E101/201 & sulphur Condensers 75E102/103/202/203 at SRU, DHDS FR, & all
other miscellaneous job as per Job scope, SHE guidelines & other terms & conditions as
detailed below:-
SCOPE OF JOB:
Line Item no. 1
Cleaning & Testing of Waste Heat Boilers, 75E101/201, with IBR co-ordination
1. Install & remove the necessary blinds for the isolation of furnace before commencing
the jobs & after the completion of Waste heat boiler or entire SRU train-1 or 2
repair jobs respectively after obtaining permit from the HPCL supervisor. The
payment for spading & de-spading shall be done separately as per relevant PO line
item.
2. Isolate / remove all the existing Waste Heat Boiler mechanical / electrical /
instrument auxiliaries/ facilities / connections, clean, service, reinstall / hook-
up as instructed by HPCL supervisor and restore back the original working conditions
without making any damage to the existing equipment / facilities.
3. Make arrangement for entry into Shell & tube side by opening channel cover, Man-head
cover & and drop entire burner block after obtaining necessary entry permit. Erect
the scaffolding (as per the procedure attached in the attachment SC) at north side &
all other location wherever there is entry point of the vessel / exchanger or as
instructed by the HPCL engineer. Vendor to note that this scaffolding must be done
as per given in the attachment. Vendor must get the scaffolding approved from the
Fire & safety department. For scaffolding vendor to strictly follow instructions
from executing engineer for field requirement and erect the same. All the
scaffolding erected to be as per attachment and multiple vendors shall use the same
based on the nature of shutdown job and the scaffolding shall be available till
completion of all the jobs. Once the vessel/ exchanger is hand over to vendor,
vendor shall erect the scaffolding & shall remain their till all job as per HPCL
engineer is completed. Vendor shall also provide Fixed / Rope Ladders for Inspection
approach, as required. All types of Scaffolding materials is in the scope of the
vendor. Vendor shall be paid separately for building of scaffolding.
FRTD
Page 1 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 2 of 21
4. Clean the MR nos. punched on the shell & offer to HPCL Inspector & IBR Inspector.
5. Wire brush / grind / file / clean & make necessary arrangements for the thickness
measurements on the West heat boilers, shell, and tube & at the specified locations
shown by the concerned HPCL Inspection Authorities.
6. Remove the insulation on the mouth of the refractory plug & keep at a safe place to
re-use the same.
7. Pull out the Refractory plug. Take necessary precaution while removing & installing
back the refractory plug to the location. Hammering to the Refractory plug for
removal or installation is strictly prohibited. Hammering leads to break the
castable refractory of the plug. Vendor has to fabricate the fixture to remove or
install plug. Material required for fabrication of fixture shall issue by the HPCL
as the free issue. Fabrication of the fixture is in the scope of the vendor without
any extra cost to the HPCL. After use vendor shall surrender the fixture to HPCL for
future use.
8. Keep the plug at safe site as per instruction of the HPCL engineer.
9. In case of Waste Heat Boilers 75E101/201, remove Burner Housing assembly from the
Thermal Reactor 75F101/201, Removal of burner assembly is not included in the scope
of the vendor under this line item.
Note: Dropping, cleaning and re-fixing back of Burner Housing assembly shall be
paid separately as per the applicable PO Line Item no. 8.
10. Install Eductor Rings (to be issued by HPCL on Loan basis), with Air supply
connection, at Man heads for proper Air circulation inside the Equipment. Vendor has
to collect the educator ring from FR tool room or any other place as directed by the
HPCL engineer.
11. Remove Demister Pads. Clean it with steam / air & water. All the sulphur & other
impurities to be removed out. After completion of the cleaning job offer it to the
PAD & Inspection department. After getting clearance from the PAD/Inspection &
operation vendor shall re-fix it back.
12. Internal steam coil, clean thoroughly & hydro-test it as directed by the HPCL
engineer. If required disconnect the internal steam coil & re-weld as per
instruction by the HPCL engineer. Any repair work in coil to be carried out by the
vendor. Repair work shall be paid under relevant PO line item no.
13. Remove fallen Refractory, Hard Sulphur, etc. from ends Channels, as well as from the
75F101/201 internal areas.
14. All types of Exchanger cleaning shall be approved by HPCL Inspection/PAD/operation
department. After HPCL approval, IBR approval is required for cleaning of the
Exchanger. HPCL shall arrange IBR Inspector visit at site. However, Vendor to co-
ordinate with IBR Inspector for approval of Cleaning. Carry out Hydro test of the
Shell side for IBR certification & tube side if required & ask by HPCL for any
flange leak identification. Tube test shall be witness by the HPCL inspection or
Maintenance or operation department. Vendor to pressurize the Shell side or tube
side, with sweet Water. Vendor shall made a testing gauge fixture for installation
of the pressure gauge. All material except the Teflon tape shall be given as the
free issue material If during test tube leak is found then marked it & show to HPCL
Maintenance & Inspection department. After getting approval from HPCL engineer plug
the leaky Tubes. The PLUG shall be issued as a free issue item from HPCL. All types
of co-ordination with IBR inspector, is a part of the job without any extra cost to
the HPCL. However, HPCL shall arrange the visit of IBR Inspector to site. Vendor
shall remain careful while hydro testing, that pressure should not go beyond the
specific test pressure. Vendor shall first satisfy himself the testing , after this
vendor shall offer the test for HPCL inspection department , after getting the
clearance from HPCL, vendor shall release the pressure up to 5 kg/sq.cm & shall
raise the required test pressure one hour before the IBR inspector arrival to the
site or as instructed by the HPCL engineer. All above activities are under scope of
the job without any extra cost to the HPCL. During testing if tube gets leak &
vendors plugged it then it shall not be considered as repeat test as this shall be a
routine job & it is in the scope of the vendor. After completion of all job vendor
FRTD
Page 2 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 3 of 21
has to prepare the Shell side for Steam / Air / Nitrogen Test or leak test
Note: Replacement of Tubes and repair of Refractory lining, if any, is NOT included
in this Scope of Work. However, after Tube replacement/repair is carried out,
Vendor to carry out Shell Hydro test and obtain necessary IBR approval.
15. The internal steam coil Hydro test is a IBR test & vendor must get clearance from
the IBR. Any repair in the coil shall be carried out by the vendor. Repair payment (
welding ) shall be done separately as pre relevant line item.
16. Vendor shall unplug all Nozzles by Roding/Air blowing, up to the satisfaction of
HPCL Engineer.
17. Any minor structural repair work or the modification work to facilitate the entry in
the equipment or facilitate to expedite the job is in the scope of the vendor
without any extra cost to the HPCL. e.g. to facilitate the entry from the north side
, it is required to cut the railing & re-welding the same.
18. Vendor shall note that sometime this steam coil needs to be cut to facilitate the
other vendor to work for some other job. In this case vendor has to cut the coil,
re-weld & hydro testing to be carried out afterwards. Payment for re-welding job
shall be done as a butt-welding as per relevant line item of the PO.
19. After verification & approval of HPCL/IBR, Vendor to release the Water pressure and
gradually drain Water/ Condensate.
20. Safety Valve & all other types of valve to the first isolation irrespective of type,
rating & location with all valves on the exchangers, west heat boilers deck, of the
Equipment shall be removed & brought to Workshop by Vendor for servicing / repairing
or calibration. Repairing & calibration of the Valves are not in the scope of the
vendor & same shall be carried out by HPCL. Vendor shall collect back all the
valves from Workshop and re-install in position at Site. All valve removal,
shifting to work shop, bringing it back to site & installation is in the scope of
the vendor without any extra cost to the HPCL.
21. After completion of all related jobs, button-up the Equipment, remove Blinds and
hand over to HPCL for commissioning.
22. Any other associated activities to facilitate the above jobs, shall be a part of the
job.
23. Provide stand-by Crew for 10 Days after commissioning of the Equipment, for Hot
bolting, etc. on round the clock basis.
24. If Hydro test fails due to any reason other than leaks at Flange joints which
Vendor has attended during the job execution & as instructed in point no. 15,
Vendor shall be paid for Repeat Test corresponding Line Item. Such additional
payment shall be made by quantity adjustment of the applicable PO Line Item.
FRTD
Page 3 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 4 of 21
3. Pl. note that vendor must get prior written permission from HPCL engineer to carry
out this job.
FRTD
Page 4 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 5 of 21
1. Carry out Spading or De-spading or Gasket replacement jobs at Flanges of various
Sizes and Ratings, as per HPCL advise, using appropriate Gasket and with necessary
servicing of all Bolts for re-use to the maximum possible extent. In DHDS Plants, if
required and as per advice of the concerned HPCL Supervisor in-Charge, Vendor shall
have to use Torque Wrenches.
2. Payment shall be made as per the relevant PO Line Item.
3. All bolts must be de-greased before using. All final gaskets must be offered to HPCL
inspection department & must get signed on the gasket as well as on register for
payment purpose.
4. Without the valid signature on the register no payment shall be done for any de-
spading or gasket replacement job.
FRTD
Page 6 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 7 of 21
16. Payments shall made for entire job on each Hydraulic seal:- Blowing , spading ,
opening of the flanges , removal of the hydraulic seal from the pit , un-plugged,
clean, hydro tested and re-installed including re-installation of the roof sheet &
metallic cover plates.
FRTD
Page 7 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 8 of 21
23. All transportation required to complete the job in all respect is in the scope of
the vendor without any extra cost to the HPCL.
24. The weighment for measurement purposes shall be done at HPCLS weighbridge prior to
disposing the sulphur at the solidification basin. The vendor to arrange all types
of transportation required for the same. The weight has to be certified by HPCL site
in charge.
FRTD
Page 10 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 11 of 21
Line Item No. 22
Item C: Fabrication of Bends for up to 2 Dia Line Sizes
1. Provide necessary services to carry out Cold Bending of the above sized Pipes, where
required, using Cold Bending Machine.
2. Vendor shall take all due precaution while bending so that bending portion shall not
get damaged. For this portion vendor shall use fine sand as filling material & cold
bull plugged both the opening After bending both the bull plug & sand should be
removed & line must be blow off with steam or air.
3. Supply of Cold Bending Machine shall be in Vendors Scope as a part of the Job.
FRTD
Page 12 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 13 of 21
15. Any Spading / De-spading required for the jobs involved above shall be paid
separately, as per the relevant PO Line Item Rates.
16. As advised by HPCL Supervisor, For nipple/pipe of vent/drain bleeder connections,
vendor to offer Fit up of all socket welded Joints & offer these welds for
inspection / DPT examination for checking integrity after completion of welding.
Vendor to carry out DP check of socket welds for ensuring quality. Scope includes
all necessary equipments, materials, skilled personnel, etc required to carry out
DP Test as per advise of HPCL Supervisor. Only MAGNA FLUX or P-MET DP material is
acceptable. Cleaning of the area to be tested, by buffing etc. as required, is part
of the scope of work. No separate payment shall be made for carrying out such above
jobs including DP Testing. The HPCL MI inspection check shall be done for complete
new line fabrication only.
FRTD
Page 13 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 14 of 21
1. Vendor may have to carry out Branching of Pipelines, as required, in case Tees are
not available. Payment of the Joint shall be made on the basis of NB Diameter of the
Branch Pipeline.
2. Provide Reinforcement Pads as per Refinery Standard (2D, where D is the NB
Diameter of Branch Pipeline), wherever direct Tapping is taken from the Pipeline.
3. Payment for Reinforcement Pad Welding shall be made on the basis of NB Diameter of
Tapping.
FRTD
Page 14 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 15 of 21
Removal or Installation or replacement of the flanged valves of all rating, types &
at all elevation.
1. After necessary de-pressurization by HPCL and handing over to the
Vendor, carry out Spading/De-spading where required for isolation of
Vessel/Pipelines, to facilitate removal of the Flanged Valve.
2. Remove the existing Valve (if the job is at elevation, Vendor to bring
the Valve to Ground Level with the help of Chain-Pulley Block, etc.), tag the Valve
properly and transport the same to the designated Scrap Yard or Mechanical Workshop
or any other location, as advised by the concerned HPCL Supervisor for
servicing/reclamation purpose (Servicing/reclamation of any Valve is NOT INCLUDED in
Vendors Scope of work, which shall be separately arranged by HPCL).
3. HPCL shall provide Crane/Forklift assistance, at its sole discretion,
depending upon Valve Size and where assessed that it would not feasible to carry out
the jobs by manual rigging arrangements, like Chain-Pulley Blocks, etc.
4. After removal of the existing Valve, if new Valve cannot be installed
immediately in position, put Blind Flanges to cover the open ends of
Vessel/Pipeline, as a part of the job at no extra Cost to HPCL.
5. Transport new or serviced/reclaimed Valves and other Free-Issue
Materials from Warehouse/Mechanical Workshop/other location and install the same
with necessary servicing of all Bolts for re-use to the maximum possible extent.
Transportation of materials from Ware House/Mechanical Workshop or any other
location inside the Refinery premises is a part of Vendors Job scope.
6. Carry out necessary Spading/De-spading for commissioning of the
Vessel/Pipeline, using appropriate Gaskets, as per the instruction of HPCL
Supervisor. Payment for Spading/De-spading shall be made separately as per the PO
Line Item no. 9 & 10.
7. Payment for complete removal & installation of any Flanged Valve shall
be made as per the PO Line Item Rate. In case of only removal or only installation
of any Flanged Valve, 50% of the PO Line Item Rate shall be payable, by Quantity
adjustment. Calculation of Inch-Dia payment for Flanged Valves shall be based on one
side Flange NB Diameter only.
8. Pl. note that the valves which is on the first deck of the exchanger
or on the deck of the 75E101/102/103/201/202/203 or first isolation valve of these
exchangers/condenser are not covered under this items as these valves are in the
scope of the vendor under line Item No. 1. Without any additional cost to HPCL.
9. Due to un-sufficient manpower or any other reason , if vendor fails or
delays the work then HPCL shall carry out this job by some other vendor & cost shall
be deducted from the vendors bill. In this regards HPCL decision shall be final &
binding to the vendor.
10. Welded Valves shall not be paid under this Item as they shall be
included in the Weld Joint Rates under relevant PO line item.
FRTD
Page 15 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 16 of 21
7. Once the pressurizing is done, check the pressure gauge if pressure dropped out the
check all the flanges with soap solution.
8. During check if the leaky flange is noticed then tighten it properly if required
replace the gasket
8.1 If the leaky flange is from the vendor touched flange , then vendor shall not get
any payment for the repair work
8.2 If the leaky flange is not from the vendor touched flange, then vendor shall get
additional payment with respect to the spading rates of the line for repair work.
9. To attend the leak, vendor may be required to replace the gasket in this case vender
shall get only de-spading ( one time ) rates with respect to point no.6.
10. Vendor shall deploy enough & skilled manpower for this, else the job shall take more
time.
11. All material required for completing the job e.g. masking tape; Soap solution, soap
bottle etc. are in the scope of the vendor without any extra cost to HPCL.
12. For payment purpose HPCL operation people shall sign the check list. No payment
shall be given to vendor, if vendor fails to submit the duly signed check list by
HPCL operation people.
13. The leak test is carried out to confirm the all flanges are tighten properly & to
avoid the again shut down of the plant to replace the gasket. However even after
this test during actual start up or within a 10 days period any leak is noticed then
vendor has to attend it with respect to point no.6.
FRTD
Page 16 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 17 of 21
Vendor is required to break the concrete / RCC or Sulphur layer or refractory for
variety of purpose e.g.
A. For opening of the liquid sulphur pit vendor has to break the Concrete (RCC)
/ PCC sealing to lift the Concrete slab.
B. For Inspection purpose
C. As advise by the HPCL engineer
D. Inside the west heat boiler or condenser as advise by the HPCL engineer.
E. The Wall refractory of liquid sulphur pit etc.
F. Inside the exchanger 75E101/102/103/201/202/203 or 75B101/201 or 75F101/201
1. Break the existing RCC Paving, at the marked location, to enable Excavation.
2. Vendor shall be permitted to use Pneumatic Concrete breaking Tool only if DHDS
operation authority permitted. Supply of the required Diesel operated Air Compressor
shall be in Vendors scope as a part of the job.
3. Carry out segregation of broken Steel Rods. Segregated Steel Rods shall be shifted
to designated area inside the Refinery only, Sulphur should be transfer to the dry
sulphur pit immediately, transportation is in the scope of the vendor without any
extra cost to HPCL.. Concrete & refractory to be store at one place as shown by the
HPCL engineer. HPCL shall arrange for disposal separately for removed concrete only.
4. The location of the job shall be entire SRU / ARU connected unit.
5. In running unit some time rundown line un-plugging is done by HPCL at that time
Liquid sulphur is overflow in the ground. After sulphur becomes dry same should be
break transferred to the dry sulphur pit nearby.
6. Payment shall be made on per M3 basis of RCC broken / excavated. & for Sulphur on
weight MT basis
FRTD
Page 17 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 18 of 21
3. Vendor shall build the scaffolding strictly as per PO & hold it till the complete
Shutdown is not completed. In this regards HPCLs decision shall be final & binding
to the vendor.
Standby Services :-
1. To attend the flange leak.During start up few flanges which are not touched by the
vendor gets leak , same to be attended on priority basis.
Due to the aforesaid & other unexpected jobs, stand by services of semiskilled workers
are required to attend to these jobs.
Vendor shall note that during the stand by period if any flange leak or any job occur,
if same is attended by the vendor which was due to his own poor workman ship than he will
not get the stand by payment for that particular shift.
It is expected to start the Stand by services shift after 6 days, after all jobs having
been completed as per Job list & de-spading & as per PO line item is over.
Vendor shall not be eligible for payment,if repeat job occurs due to his own poor
workmanship during the stand by period.
Vendor shall arrange the standby services within 24 hours of notice from HPCL.
Minimum 1 shift of 8 hours per worker shall be paid evenif HPCL do not assign any job or
assigns jobs for less than 8 hours of actual work.
For jobs done beyond any 8 hours shift's actual work, payment for such Extra hour's work
shall be done against separate Line item.
Shift shall be counted basis "Reporting Time" and "Leaving Time" at Site, certified by
HPCL Maintenance.
Vendor shall follow all statutory rules regarding payment of Minimum wages, PF, ESIC,
duble wages for each extra hours work, etc. to the workers and submit documentary evidenc
to HR dept. as per rules.
NOTES TO VENDOR:
1. Before submission of his tender, the vendors/bidders shall thoroughly study the
entire tender document, visit the site, assess the full scope of work & seek
Technical clarification(s), if any, from Maint. Planning/Field Maint. And all non
technical clarification(s) shall be sought from Purchase department.
2. After PO placement, no compensation of any kind shall be claimed by the vendor for
lack of any information whatsoever connected with the works.
3. All the tender documents like, SOR, Job scope & notes to Vendors, drawings & other
documents asked or demanded by the Purchase department etc. shall form integral part
of the Tender & the Purchase Order
4. Vendor shall ensure use of skilled Manpower and specialist Riggers to carry out the
job of this nature, which usually has to be carried out in the running unit.
5. All Bolts & Nuts shall be serviced, segregated and stored properly for re-use.
Wherever necessary, Vendor shall cut WR Asbestos Gaskets of Exchangers as a part of
the job from the material issued by HPCL. Hot/Cold cutting of Nut-Bolts during
stripping of Exchanger Components and cutting of Stud Bars to the required Stud size
during re-assembly of Exchangers are included in scope of the job.
6. Repairs of any Roll leak, if required, will be separately arranged out by HPCL.
7. Vendor must take utmost care while handling the Tubes so as not to cause any damage
to the Tubes.
8. Any Refractory repair work will also be carried out by HPCL separately.
9. Vendor shall keep dismantled parts of Exchangers in such a manner not to obstruct
any Crane and Fork-lift movement.
10. Dropping and reinstallation of related Pipelines, if required, are included in the
Scope of jobs. Crane will be provided as per the requirement approved by the
concerned HPCL Maintenance in-Charge.
11. Rigging Tackles and fabrication of Fixtures, if required, would be in Vendor's
Scope. Material for fabrication of the same will however be provided by HPCL as FIM.
12. Vendor must return all Loan materials back to the issuing Tool Room, within Two Days
of job completion. Material Reconciliation Report shall be submitted along with the
Delivery Challan.
13. Vendors are advised to go through the Job Description and visit Site before
submission of their offer for the job. For any clarification, Vendor may contact the
concerned Maintenance Section in advance.
14. Vendor shall start the jobs immediately after handing over of the Equipment by HPCL
and complete the entire jobs within the shortest possible duration, as agreed with
the concerned Section of HPCL. Depending upon Plant exigency, jobs may have to be
carried out beyond normal Working Hours, including on Sunday/Hoilday and/or Round-
the-Clock basis for completion of the same within the Schedule. However, no separate
FRTD
Page 19 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 20 of 21
payment will be applicable for working beyond normal Working Hours/Round-the Clock
basis.
GENERAL NOTES:
1. Vendor to obtain proper Work Permit, issued by the competent Authority of HPCL,
before carrying out any job. Entire job will be subjected to stage-wise Inspection
and Approval by HPCL. All arrangements and materials for stage-wise Inspection, as
instructed by HPCL, are in Vendor's scope. Vendor will have to co-ordinate with HPCL
Inspection and Maintenance sections to expedite the job. Vendor to take up jobs as
per the priority set from time to time by HPCL Maintenance Engineer. Vendor shall
maintain proper documentation/record keeping, etc. of the jobs.
2. Transportation of materials from Warehouse/Planning Yard to the work site is in
Vendor's scope.
3. Fork-lift will be provided by HPCL for transportation of Exchanger Components and
shifting of scrap filled Drums.
4. Total job shall be carried out in a manner not to hinder any near-by activities.
5. Jobs shall be carried out in a manner not to cause any damage to the surroundings.
Damage, if caused while carrying out the job, shall be made good by the Vendor at no
extra cost to HPCL.
6. Vendor shall arrange adequate & skilled Manpower and Supervisor. Manpower deployed
by Vendor should be experienced in similar type of jobs. All Equipment, Tools &
Tackles used should be of appropriate Type and Size, approved by competent Authority
for its SWL. All Equipment shall be brought inside the Refinery with proper Gate
Entry only.
7. At any stage of work, if progress of the job is found unsatisfactory, HPCL reserves
right to carry out remaining portion of the job by hiring services of other Agencies
to meet the Job Completion Schedule and back charge the additional/incidental Cost
of such services to Vendor's Account.
8. Vendor must ensure that all good and re-usable materials are serviced and re-used.
9. Vendor to mobilise the manpower and other resources at short notice and carry out
pre-Shutdown activities, wherever possible and as advised by HPCL Site Engineer.
10. Vendor will be required to maintain Good Housekeeping during and after the
completion of the job until the job is satisfactorily accepted by HPCL. Vendor to
collect all Debris/Scrap generated from the work area and dump at designated places
inside the Refinery, as instructed by HPCL Site In-charge.
11. In case of doubt, the same can be inquired from the concerned HPCL Maintenance
Section.
12. In case of controversy, HPCL's decision will be final and binding on the Vendor.
13. Any minor changes in scope of work required for completion of work shall be carried
out by Vendor at no extra cost to HPCL.
14. Stand-by personnel shall be provided by Vendor during start-up/commissioning of the
Plant facilities.
15. In case of fabrication/machining requirement of any item outside the Refinery, Free-
issue materials, as per the Contract and based on requisition submitted by Vendor,
will be allowed through Shipping Memos (Returnable Gate Pass) on verification by
HPCL. On returning these materials in finished condition or while returning excess
material, Scrap generated by machining only, will be retained by the vendor and the
same to be considered while quoting for the job. Vendor must obtain necessary Gate
Entry stamping and submit the same to the executing Department for reconciliation &
records. Vendor should also give reconciliation statements of the all Free-issue
materials for each job executed.
16. For General Notes and Terms & Conditions related to Environment, Health & Safety
(EHS) for execution of jobs inside the Refinery premises, please refer to linked
documents provided along with the Tender.
17. HOW TO QUOTE: Please quote a single %age (+ or -), applicable to all the Line Item
Rates given in the Schedule of Rates provided in the Tender.
FRTD
Page 20 of 21
Attachment to PR
SRU TRAIN 1 & 2 TESTING & INSPECTION JOBS-IBR-SHUTDOWN-DHDS
Job scope & Notes to Vendors
Page 21 of 21
*********************** End of document *******************
FRTD
Page 21 of 21