Anda di halaman 1dari 7

5th International & 26th All India Manufacturing Technology, Design and Research Conference (AIMTDR 2014) December

12th–14th, 2014, IIT


Guwahati, Assam, India

SMED (Single-Minute Exchange of Die) methodology in Garment


manufacturing Industry: Case study in reducing Style Change over Time

Jonalee D. Bajpai

National Institute of Fashion Technology, Bangalore 560102

jonaleebajpai@rediffmail.com, jonalee.bajpai@nift.ac.in

Abstract
Globalization is a major trend in developing countries. Outsourcing of services from developing countries has
become the major trend to mainly reap the benefit of cheap labor cost and raw material to a certain extent. As a
result, Textile and Garment industry in developing countries like India, China, Philippines and Bangladesh, Sri
Lanka etc. have witnessed a major demand from textile giants in USA, UK and other European countries.
Shortening of fashion cycle, shortening of lead time, competitive pricing, high quality product, socially and
environmentally compliant work place are the emerging trends of Globalization.
On one hand new management philosophies demand that product lead times are kept as small as possible. On the
other hand, product customization has increased, thereby increasing the number of parts in a product family. As a
result batch sizes have reduced and continue to shrink [4]. Garment manufacturing units in India are embracing and
adopting the various new manufacturing concepts like 5S, Kaizen, Poka Yoke, SMED, DMAIC analysis etc.
This paper discusses the SMED concept and methodology as customized for reduction of style changeover time in
garment manufacturing industry and demonstrates a live case that reduced style change over time. The result
achieved showed considerable reduction in delay arising out of machine setting time, batch setting time and
demonstration delay.
Keywords: SMED, Style Change over, Garment industry, Manufacturing

1Introduction Exchange of die), DMAIC analysis etc. All these efforts


are to reduce the through put time of a garment which
India is one of the World’s second largest producers includes cutting, sewing and packing. With the lead
of textiles and garments. Today India is recognized as time getting shorter and order quantity getting smaller it
one of the leading sourcing destinations for readymade has become imperative for manufacturing units to
garments in both knitted and woven sectors. But Indian develop flexible production systems and quick change
Garment industry is facing the greatest challenge from over systems from one style to another. Quantities and
shorter fashion cycle, highly volatile market, higher complex design the production line setup has shrunk to
disposable income and new emerging manufacturing such level that sometimes a unit might need to produce
bases emerging all over the globe. Shorter lead time and multiple orders in a single day. This calls for higher
smaller order quantity is the bi product of shorter flexibility in terms of volume and style change over [1].
fashion cycle which in turn demands for a Over a period of time it has been realized that there is a
manufacturing layout that is flexible and with efficient huge loss in terms of time and man power in changing a
and quick response production system. It has become line from one style to another. This is also referred to as
increasingly important to economically manufacture the “start-up loss” in the garment industry. SMED is the
products in smaller and smaller batches. On one hand recent concept adopted by Indian garmentmanufacturing
new management philosophies demand that product units to reduce the style change over time which can
lead times (both development and manufacturing times) reduce the startup loss to a considerable extent and
are kept as small as possible. On the other hand, product manufacturing units can efficiently run smaller order
Customization has increased, thereby increasing the quantity in complicated styles which is the call for the
number of parts in a product family. As a result batch day. This paper discusses the application of SMED
sizes have reduced and continue to shrink [6]. Garment concept on reduction of style changeover time and
manufacturing units in India are embracing and demonstrates a live case that reduced style change over
adopting the various new manufacturing concepts like time.
5S, Kaizen, Poka Yoke, SMED (Single Minute

61-1
SMED (Single-Minute Exchange of Die) methodology in Garment manufacturing Industry: Case study in reducing Style Change over Time

2 SMED and Garment Manufacturing Units operators and persons movement are noted to segregate
necessary and un necessary movement in the setup time
The concept of SMED that was initially used in with the purpose to eliminate un necessary ones.
other manufacturing industry is gaining huge popularity
2.4 Analysis of the Elements and Micro elements:
in Garment manufacturing sectors in India. SMED
The machine setup Elements and Micro elements are
methodology was developed by Shiegeo Shino in Japan
analyzed so as to distinguish between External and
from 1950- 80s. This methodology can be adopted
Internal Elements. Internal elements are those where the
economically in any manufacturing process without
manufacturing has to come to a halt. External elements
much financial implication. In the garment
are those which can be carried out externally without
manufacturing industry SMED can be applied in the
interfering with the working of the machine. This can be
entire supply chain starting from fabric store to cutting
done in two phases-
room, to sewing room and as well as finishing and
Phase I: Separation of machine set up elements into
packaging. But most successful application of SMED is
External and Internal elements. This can be best done by
to reduce the set up time required to adapt the sewing
video recording the process and observing again and
line from one style to another. Setup time is the time
again. Then the elements are differentiated into sub
taken to tune and adapt one production line for a new
elements such as External and Internal process and the
style. It corresponds to the time required to go from the
wasted time as well as the idle time.
end of the last good part from one batch to the time
Phase II: From the checklist developed the next
when the first good part of the new style is produced [4]
important endeavor is to improve the as is style change
Set Up time over process. This can be achieved by the following
method.
End of last good part produced to First good part of
• The cycle time for each element is to be
new style
noted.
SMED methodology in Garment Manufacturing • Brainstorming and discussions should be
Sewing Floor in general and style change over time done to look for scope of improving each
in particular element by way of method or process or
machine or man improvement. The
The following steps describe the process reducing style
elements with longer duration should be
changeover time in Garment manufacturing units.
taken up first followed by next second
2.1 Analyze the as is process: The first step is to study longest time and so on
and analyze thoroughly the present process. This • Developing parallel elements when
process would help to identify and separate the non- applicable
value added activities in the process that would trigger • Reducing human error, reducing time delay
the areas of improvement. due to man power, tools and equipment in
2.2 Definition of Target Set up Time: It is important to availability etc.
set a target set up time one needs to achieve through the • Waste set up time and idle time should be
application of SMED. This would be the goal for the eliminated from the process.
team members to achieve. In Garment manufacturing it • Finally efforts should be to transform the
would depend on the part of the supply chain and the Internal elements into External Elements.
product. In a style set up time it would vary from Phase III: Further steps should be taken to
product to product depending on the degree of style improve the External and Internal elements by
variation and capacity of the plant. This would also means method or process or machine or man
depend on the phases of SMED application. In a sewing improvement.
floor the set up time would range anywhere between
half a day to one and half day. Target can be kept as 2.5Assignment of responsibilities: Finally all the
high as 60% to 70% if it is the first time SMED is External and Internal Elements are to be listed and
initiated and subsequently the target would go down as responsibilities are to be assigned and a timeline is to be
the scope of improvement would get reduced. established.
2.6Implementation of the Plan: The final step is
2.3 Documenting Elements and Micro elements of implementation of the planned process and look for
batch setting of the existing process: This involves in continuous improvement.
observing, mapping and documenting the as process of Real time study in Garment Manufacturing units reveals
batch setting process. The following things are to be that time consumed by various activities in batch setting
noted – the sequence of work with elements and micro for a style changeover can be classified into 5 major
elements well defined with time taken. Then the headings – Machine time, Batch Setting Time,

61-2
5th International & 26th All India Manufacturing Technology, Design and Research Conference (AIMTDR 2014) December 12th–14th, 2014, IIT
Guwahati, Assam, India

Demonstration time, Time delay due to operator and numbers and usually idle at this time they should be
Run Down Time and Run Up Time. involved in various activities in style changeover.
Machine time: Machine time is mainly the time Run Down Time and Run Up Time: Run Down Time
required to set the machine for the new style. Time is is the time when the current style under production
also involved in moving the machines from the main leaves the first machine in the line and the capacity
shop floor area to the maintenance area and back and drops. This Run Down Time continues till the current
rearranging them as per the garment process flow. Most style leaves the last machine in the line. Run Up Time
of the time is required in replacing machine with new starts from the time the first piece or first bundle is
machine of different specification, setting the machine loaded on to the first machine of the line and till the first
with folders and attachment as per the new style, setting good piece is produced and steady production at full
the stitch length, adjusting the presser foot and minute capacity occurs. Style Change over time starts with the
adjustment for fine tuning etc. Setting folders and start of Run Down time than Set Up Time to the end of
attachments consumes huge amount of machine setting Run up time. One should start style change over
time. Reducing machine time requires lots of spare or activities from the Run Down Time in order to reduce
extra machine so that setting the folders and attachment the style change over time. It has been observed that in
can be converted into External Element. But there is a India, in most cases style change over starts only from
need to strike a balance between the two. the Set Up time. Garment manufacturing have to make
Batch setting time: Batch setting time can also be the Run Down time productive in order to reduce the
assigned as waiting time as it results out of lack of pre- style change over time. SMED methodology successful
production planning in sewing floor. This is a non- in reducing the style change over time by making use of
value added activity that can be drastically reduced with the Run Down time and reducing the Run Up Time.
proper planning and time & action calendar, checklist,
3 CASE STUDY:
operator’s skill matrix etc. Much of the time is wasted
Reducing the style change over time in export
in trying to assemble the required tools, equipment,
garment manufacturing unit.
templates and man power to start the new style. This is
due to lack of pre planning for the task of style
3.1Objective:
changeover. It is observed that huge time is wasted in
search for right cut parts or cut bundles or the pre- • To reduce the style change over time using
production sample or sealed sample to start the SMED.
production on time. Flow of information as to which • To formulate a standardized action plan for
style is to be loaded in which line, lack of on time and batch setting / style change over.
appropriate technical specification about the style often
leads to huge confusion in the sewing floor that leads to 4 Research Methodology:
increase in style change over time.
Layout planning and machine planning is often seen to 1. Recording and Mapping the entire process of
be done during the Set up time which stands as style change over from the time when the
bottleneck point during style change over. previous style is reaching completion and new
Demonstration time: Demonstration time is the time style reaches a perfect flow.
required to demonstrate the critical operations in the 2. Analysis of the activity with time line and
new style to the operators with the right method and the noting down all the value added, non-value
right equipment. This is an important activity but a time added and necessary non value added elements.
consuming as the learning ability depends on the skill 3. Then categorizing the elements into Material
level of the operator and the style of the product. Repeat Time, Batch Setting time, Demonstration time,
orders or simpler styles may require very less or no time delay due to operator.
demonstration. At times re-demonstration takes a huge 4. Than the elements consuming more time are
time. noted and highlighted.
Time delay due to Operator: Due to lack of pool of 5. With the information of the As IS process, the
skilled operators, demonstration of critical operations elements are separated into Internal, External
cannot be converted to an External Element. Only after and Parallel elements.
the completion of the previous order can the 6. Finally finding the smarter ways to perform the
demonstration of the new order take place. Again a less work.
skilled operator takes more time in following a
demonstration and at many instances requires re- Study was conducted on the sewing floors to note down
demonstration. Absenteeism of operators also poses a the list of activities/elements that are involved in batch
huge obstacle in pre assigning operation for the new setting. The elements along with their time line were
style as per the skill matrix. As they are more in noted and classified under the following headings:

61-3
SMED (Single-Minute
Minute Exchange of Die) methodology iin
n Garment manufacturing Industry: Case study in reducing Style Change over Time

Machine time, Batch Setting time, Demonstration


400
time, Time delay due to operator.. Run Down time and 59 Machine time
350
Run Up time is not under the scope of study. The
300
following graphs represent the analysis of the 3 batch

Time in minutes
setting and the percentage of time consumed by each 250
Batch Setting
Time
head. 200

150 24%
Demonstratio
Style Change over time: Run Down Time + Set Up 100
11 n time
6%
Time +Run Up Time. 50

0
Time delay
Case 1 Machine time Batch Setting Demonstration Time delay due due to
Time time to operator operator
going style: Knitted Ladies polo shirt (Basic
Out-going Elemental breakdown of Set Up Time
style)
New style to be loaded: Knitted Ladies top with
metal zippers at the back (Critical Style)
Fig 2:: Elemental Breakdown of Set Up Time:
Time Case 2

250
Machine time
In the above case the out-going
going style and the new style
200
49% belong to the same category and same level of
Time in minutes

workmanship is involved. Hence time consumed for


Batch Setting time
150
demonstration is less than the machine setting time.
25%
100
22% Here the time consumption for demonstration is much
Demonstration time less than case 1 as this factory specializes in
50
4 manufacturing shirtt only and the style variations are
0 Time delay due to nominal. As the number of operations in the shirt is
operator
Machine time Batch Setting Demonstration Time delay due more hence the number of machines required is more.
time time
Elemental breakdown of Set Up Time
to operator
This lead to increase in the machine time required
which is 59%. As the more number of machines are
Fig 1:: Elemental Breakdown of Set Up
UpTime: Case 1 involved, the Batch
atch setting time is more which is 24%.
Time delay due to operator is 6% and the reasons
The new style has critical operations like zipper accounted to are same as in case 1.In this case too Style
attachment and requires special finishes (binding) that Change over time starts only when the current order is
requires special attachments and guides. The degree of out of the line completely.
workmanship involved is very high. As a result, the Thus it is observed that style
tyle change over time can be
demonstration level increased and time consumed for broadly classified into 5 headings: Machine time, Batch
demonstration was 49% followedd by batch setting time Setting time, Demonstration time, Time delay due to
and machine time which is 25%and 22% respectively. operator. The time content under each heading may vary
Time delay due to operators (4%) was mainly due to the case to case. The factors for time variation will mainly
negligence and reluctance. Waiting for line supervisor depend on the style variation and between the out-going
out
for demonstration, waiting for operators, waiting for style and the new style. The level of critical operation
sealed sample and waiting for templates were some of and difficulty in workmanship will account for variation
the reasons for delay due to lack of pre pre-production in style change over time. This will not only increase
planning that contributed to Batch setting time. Style the demonstration time but also involve involv re-
Change over time starts only when the current order is demonstration and longer machine set up time with
out of the line completely. more numbers of attachment and folders for efficient
production. The number of operation breakdown of the
Case 2 product is also another influencing factor in style
changeover time. More the number of operations
operati more
Out-going style: Mandarin
arin collar full sleeve woven machines are required and thus increases the machine
shirt with 3 button placket set up time. More machine set up time is also dependent
New style: Half sleeve woven classic shirt with two on the number of folders, guides and attachment
pockets with pocket flap required. Demonstration time is dependent on the
degree of style variation and the criticality
critica in operation.
Operator’s skill also depends on time consumed for
demonstration and re-demonstration.
demonstration.

61-4
5th International & 26th All India Manufacturing Technology, Design and Research Conference (AIMTDR 2014) December 12th–14th, 2014, IIT
Guwahati, Assam, India

Implementation of SMED: Supervisor(LS) (LI)/Line


Supervisor(LS)
After the analysis of the present process of style change
Repair and fine tuning Repair and fine tuning
over SMED methodology was applied for the next style
change over. Although a direct comparison between one of idle or spare of the idle machines are
change over with another cannot be compared in machines were done done during the run
during the set up time. down period. Action:
absolute figure as the product may not be identical but
Action: Mechanic Mechanic /Technician
comparison was done between similar styles. Style
Change over started as the Run Down time reaches its /Technician
peck which not only reduced the Set Up time but also Gauge Setting, Needle Gauge setting, Needle
reduced the Style Changeover time overall. Run Down plate setting, Machine plate setting and
time was made productive. oiling was done during Machine oiling starts
Set Up time only. from Run Down time
Table 1: The current status of the changeover Action: and spills over to Set Up
process of the factory as summarized Mechanic/Technician time. Action:
Mechanic /Technician
Activity Actual Before After
Attachment and folders Attachment and folders
SMED SMED
are attached only are attached first on to
during the machine set the idle machine during
Layout External Internal External up time. Action: the run down period.
Planning Sparingly Mechanic Action: Mechanic
External /Technician /Technician.
Machine cleaning was Machine cleaning starts
Layout Internal Internal Internal done during the setup from the run down
Change time. Action: period. Action :
Machine Internal Internal Internal/ Operator Operator
movement Sparingly External Un raveling of Bobbin Un raveling of bobbin
External Thread and filling of thread and filling of
bobbin done during bobbin thread starts
Machine Internal/ Internal Internal/ machine set up time. from Run Down period.
Maintenance External External Action Operator Spare Bobbins are also
Machine Internal/ Internal Internal/ used. Action: Operator
setting External External Fine tuning of Fine tuning of machines
Demonstrati Internal/ Internal Internal/ machines such as SPI, such as SPI, thread
on External External thread tension, presser tension, presser foot
Style External Internal External foot setting etc. were setting etc. were done
Analysis done during Run Up during Run Down and
WIP External Internal External time. Action: Set Up time. Action:
planning Operator Operator
Trims Status External Internal External Changing needle and Changing needle and
threading was done threading starts from
Operator External Internal External only during the Set Up Run Down time and
Allocation time. Action: spills over to Set Up
Buffer External Internal External Operator /Mechanic time. Action: Operator
Allocation
Table 2.2 Batch Setting Time
Table 2: Detailed discussion of the summary: Before Implementation After Implementation
Table 2.1 Machine Setting Style Analysis was Style Analysis is done
done during the Set Up much before the Set up
Before time. Action: time and critical
After Implementation
Implementation Production Manager operations and Bottle
Identification of Identification of (PM) / Line In charge neck operations are
machine was done machine is done during (LI) / Line Supervisor identified for special
during set up time. Run down period of the (LS). attention and
Action: Line In previous style. Action: : demonstration. Action:
charge (LI)/Line Line In charge

61-5
SMED (Single-Minute Exchange of Die) methodology in Garment manufacturing Industry: Case study in reducing Style Change over Time

PM/ LI / LS. It is observed that after implementation of SMED the


Layout planning and Layout plan and Style changeover time got considerably reduced. As
Machine planning was Machine plan is done discussed above internal elements were converted to
done during Set Up much before the Set Up external elements and the external elements started as
time. Action: PM / LI time. Action: PM / LS the Run Down Time reached its peak. Batch setting
/ LS planning was meticulously pre planned and waiting time
Operators were allotted Operators list is got drastically reduced. Machine setting time was 113
at random to the new prepared as per the skill minutes for 42 operations after SMED implementation
style on the spot during matrix for the new style against 90 minutes for 25 operations before SMED
the Set up time. during the Run Down implementation. Parallel activities of demonstration
Action: PM / LS time. Action: PM / LI / lowered the demonstration time although the number of
LS operations is more. Spare machines were efficiently
Preparation of Mock Preparation of Mock used for external elements.
Samples was done Samples to be
during Set up time. completed much before Fig3: Style Change over Time after SMED
Action LI / LS Set up time. Action: LI implementation
/LS
Ensuring sealed Ensuring sealed
sample, WIP (cut sample, WIP (cut Run Run Up
parts), trims, parts), trims, and Down Set Up
Time
Time Time
measurement charts measurement charts 8: 55:00
6:45:00 4:43:00
were done only during etc. to be done only
Set up time. Action: during Set up time.
PM / LI / LS Action: PM / LI / LS
Templates are made Templates are made Chart Title
during Set up time. much before Set up
250
Action: PM / LI / LS time. Action: PM / LI / 200
Axis Title

LS 150
100
50
0
Table 2.3 Demonstration time Batch Setting Demonstratio
Time delay
Machine time due to
Time n time
operator
Before Implementation After Implementation
Before 90 99 200 15
Demonstration for Demonstration for
After 113 22 121 10
critical operations was critical operations
solely a part of Set up commences as soon as
time. This used to take the Run down time
Fig4: Elemental Breakdown of Style Changeover –
place much after starts. This can be
Before and After SMED Implementation
machine setting time. parallel operation.
Action: PM/ LI / LS Action: PM/ LI / LS
Re-demonstration was Re demonstration was Conclusion: Style Change over time can be greatly
a major issue as the reduced as operators reduced and channelized by application of SMED
operators allocation allocation is pre methodology with minimum financial implication.
was not done prior to planned according to SMED and Value Stream Mapping can further increase
Set up time. skill matrix. the productivity of Set Up time and make Run down
Time productive.The case study reveals that there are 5
The following graph shows the time consumed main factors affecting style change over time in garment
during a style change over before (Case 1) and after manufacturing units in India, they areMachine time,
SMED implementation. Batch Setting time, Demonstration time, and Time
delay due to operator. The time required for each
Out-going style: Knitted Ladies top with metal zippers at the factor is affected by the variations in style of the product
back (Critical Style) between two subsequent batches which is evident from
No: of Operations: 25 the above cases. Application of SMED concept in the
New Style: Knitted pant with slant pocket and elasticated above case study showed considerable reduction in
waist band for top.
delay arising out of machine setting time, batch setting
No: of Operations: 42

61-6
5th International & 26th All India Manufacturing Technology, Design and Research Conference (AIMTDR 2014) December 12th–14th, 2014, IIT
Guwahati, Assam, India

time and demonstration delay. SMED is surely not a methodology”, Int J Prod Res, 2000, vol. 38, no.
destination but a continuous and gradual process. 11, pp. 2377-2395.

References
S. Shingo, “A revolution in manufacturing, the
SMED system”, 1985, Productivity Press. Antonio Carrizo Moreira, Gil Campos Silva Pais
M.C. Eti, S.O.T. Ogaji, S.D. Robert, (2011) “Single Minute Exchange of Die” –A case
“Implementing total productive maintenance in study Implementation Journal of Technology,
Nigerian manufacturing industries”, Appl Energy, Management and Innovation pp. 29.
2004, Vol. 79, pp. 385–40 Dr.Warkhedkar R M Desai M.S. (2011)
C. Moxham, R. Greatbanks, “Prerequisites for the “Productivity Enhancement by reducing adjustment
implementation of the SMED methodology: A time and setup change” International Journal of
study in a textile processing environment”, Mechanical Engineering & Industrial Engineering,
International Journal of Qual Reliab Man, 2001, pp. 37-42.
vol. 18, no. 4, pp. 404–414.
J. Santos, Richard A. Jose M. “Improving
Production with Lean Thinking”, ISBN: 978-0-471-
75486-2, pp. 89-115.
Ulutas Berna (2011) “An Application of SMED
Methodology” World Academy of Science,
Engineering and Technology, pp. 100-103
S. Shingo, A Revolution in Manufacturing: The
SMED System, Portland:Productivity Press
Inc,1985
R.R. Joshi, G.R. Nair, “An Application of SMED
Methodology: A Case Study in Small Scale
Industry”, (Aug 2012) International Journal of
Scientific Research Publication, Vol.2 Iss.8, ISSN
2250-3153
P. Hines, N. Rich (1997) “The seven value stream
mapping tools” International Journal of Operation
and Production Management, Vol.24, No.10,
pp.994-1011
H. Sun, R. Yam, N.G. Wai-Keung, “The
implementation and evaluation of Total Productive
Maintenance (TPM) - an action case study in a
Hong Kong manufacturing company”, Int J Adv
Manuf Technol, 2003, vol. 22, pp. 224–228.
L. Bamber, B.G. Dale, “Lean production: A study
of application in a traditional manufacturing
environment”, Prod Plan Control, 2000, vol. 11, no.
3, pp. 291–298.
C. Moxham, R. Greatbanks, “Prerequisites for the
implementation of the SMED methodology: A
study in a textile processing environment”, Int J
Qual Reliab Man, 2001, vol. 18, no. 4, pp. 404–
414.
] A.R. Mileham, S.J. Culley, G.W. Owen, R.I.
McIntosh, “Rapid Changeover– a pre-requisite for
responsive manufacture”, Int J Prod Man, 1999,
vol. 19, no. 8, pp. 785–796.
] R.I. McIntosh, S.J. Culley, A.R. Mileham, and
G.W. Owen, “A critical evaluation of Shingo's
'SMED' (Single Minute Exchange of Die)

61-7

Anda mungkin juga menyukai