GOBIERNO REGIONAL LA LIBERTAD

PROYECTO ESPECIAL CHAVIMOCHIC


CRONOGRAMA VALORIZADO DE OBRA

Obra MEJORAMIENTO DE LA CARRETERA CHAO - BUENAVISTA - EL PIE - SAN PEDRO - CHAGAGANDA - UNINGAMBAL- HUAYNAS - LOS TORITOS EN LOS DISTRITOS DE CHAO HUASO CALAMARCA QUIRUVILCA - REGION LA LIBERTAD

Cliente
Ubicación LA LIBERTAD - VIRU - VIRU
Plazo 270 DIAS CALENDARIO

PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES SEPTIMO MES OCTAVO MES NOVENO MES TOTAL
ITEM DESCRIPCION UND PRESUPUESTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO
% % % % % % % % % %
VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO

01.00 OBRAS PRELIMINARES 169,754.51 136,339.55 80.32% 33,414.96 19.68% 169,754.51 100.00%
01.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO glb 15,906.40 15,906.40 100.00% 0.00% 15,906.40 100.00%
01.02 CAMPAMENTO PROVISIONAL DE OBRA und 12,537.57 12,537.57 100.00% 0.00% 12,537.57 100.00%
01.03 CARTEL DE IDENTIFICACION DE OBRA 3.40x7.20 MT. und 2,161.36 2,161.36 100.00% 0.00% 2,161.36 100.00%
01.04 TOPOGRAFIA Y GEOREFERENCIACION km 98,279.28 64,864.32 66.00% 33,414.96 34.00% 98,279.28 100.00%
01.05 MANTENIENTO DE TRANSITO Y SEGURIDAD VIAL glb 20,850.38 20,850.38 100.00% 0.00% 20,850.38 100.00%
01.06 ACCESO A CANTERAS DME, PLANTAS Y FUENTES DE AGUA km 9,019.18 9,019.18 100.00% 0.00% 9,019.18 100.00%
01.07 DERECHO DE CANTERAS m3 11,000.34 11,000.34 100.00% 0.00% - 11,000.34 100.00%

02.00 MOVIMIENTO DE TIERRAS 8,440,486.01 1,111,770.22 13.17% 1,111,770.22 13.17% 1,111,770.22 13.17% 1,476,451.87 17.49% 1,476,451.87 17.49% 1,476,451.87 17.49% 675,819.73 8.01% 8,440,486.01 100.00%
02.01 CORTE EN MATERIAL SUELTO m3 1,904,846.27 272,393.02 14.30% 272,393.02 14.30% 272,393.02 14.30% 272,393.02 14.30% 272,393.02 14.30% 272,393.02 14.30% 270,488.17 14.20% 1,904,846.27 100.00%
02.02 CORTE EN ROCA SUELTA m3 2,672,929.96 408,958.28 15.30% 408,958.28 15.30% 408,958.28 15.30% 408,958.28 15.30% 408,958.28 15.30% 408,958.28 15.30% 219,180.26 8.20% 2,672,929.96 100.00%
02.03 CORTE EN ROCA FIJA m3 2,690,118.27 430,418.92 16.00% 430,418.92 16.00% 430,418.92 16.00% 430,418.92 16.00% 430,418.92 16.00% 430,418.92 16.00% 107,604.73 4.00% 2,690,118.27 100.00%
02.04 CONFORMACION DE TERRAPLEN C/MATERIAL PROPIO m3 127,197.53 39,176.84 30.80% 39,176.84 30.80% 39,176.84 30.80% 9,667.01 7.60% 127,197.53 100.00%
02.05 CONFORMACION DE TERRAPLEN C/MATERIAL DE PRESTAMO m3 403,194.44 129,022.22 32.00% 129,022.22 32.00% 129,022.22 32.00% 16,127.78 4.00% 403,194.44 100.00%
02.06 REMOCION DE DERRUMBES m3 73,048.54 21,184.08 29.00% 21,184.08 29.00% 21,184.08 29.00% 9,496.31 13.00% 73,048.54 100.00%
02.07 PERFILADO Y COMPACTADO DE LA SUB RASANTE m2 569,151.00 175,298.51 30.80% 175,298.51 30.80% 175,298.51 30.80% 43,255.48 7.60% 569,151.00 100.00%

03.00 BASE Y SUB BASES 2,398,451.86 557,853.87 23.26% 557,853.87 23.26% 617,986.97 25.77% 617,986.97 25.77% 46,770.19 1.95% 2,398,451.86 100.00%
03.01 BASE DE AFIRMADO m3 167,036.38 60,133.10 36.00% 60,133.10 36.00% 46,770.19 28.00% 167,036.38 100.00%
03.02 BASE DE AFIRMADO C/ESTABILIZADOR DE SUELOS m3 2,231,415.48 557,853.87 25.00% 557,853.87 25.00% 557,853.87 25.00% 557,853.87 25.00% 2,231,415.48 100.00%

04.00 PAVIMENTOS ASFALTICOS 684,869.50 431,783.55 63.05% 253,085.95 36.95% 684,869.50 100.00%
04.01 IMPRIMACION ASFALTICA. m2 111,606.00 111,606.00 100.00% 111,606.00 100.00%
04.02 TRATAMIENTO SUPERFICIAL BICAPA m2 457,396.50 320,177.55 70.00% 137,218.95 30.00% 457,396.50 100.00%
04.03 MORTERO ASFALTICO - SLURRY SEAL (e=10 mm) m2 115,867.00 115,867.00 100.00% 115,867.00 100.00%

05.00 OBRAS DE DRENAJE 3,612,908.62 52,169.40 1.44% 159,679.35 4.42% 118,496.42 3.28% 165,052.61 4.57% 736,285.70 20.38% 1,242,148.36 34.38% 627,085.60 17.36% 437,215.10 12.10% 74,776.08 2.07% 3,612,908.62 100.00%
05.01 ALCANTARILLA CIRCULAR TMC D=36¨ 559,052.31 23,411.40 4.19% 28,698.60 5.13% 107,285.41 19.19% 125,220.22 22.40% 202,097.97 36.15% 72,338.71 12.94% 559,052.31 100.00%
05.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS. m3 31,215.20 23,411.40 75.00% 7,803.80 25.00% 31,215.20 100.00%
05.01.02 BASE DE AFIRMADO H=0.20 m m2 3,404.43 3,404.43 100.00% 3,404.43 100.00%
05.01.03 CAMA DE ARENA h=0.10 m2 431.11 431.11 100.00% 431.11 100.00%
05.01.04 RELLENO PARA ESTRUCTURAS m3 42,648.15 17,059.26 40.00% 21,324.08 50.00% 4,264.82 10.00% 42,648.15 100.00%
05.01.05 ALCANTARILLA CIRCULAR TMC D=36" m 149,531.26 - - 29,906.25 20.00% 119,625.01 80.00% - - 149,531.26 100.00%
05.01.06 ALCANTARILLA CIRCULAR TMC D=24". m 23,286.75 23,286.75 100.00% 23,286.75 100.00%
05.01.07 CONCRETO F'c=175 KG/CM2 m3 151,748.59 60,699.44 40.00% 91,049.15 60.00% 151,748.59 100.00%
05.01.08 EMBOQUILLADO DE MAMPOSTERIA m3 25,261.90 25,261.90 100.00% - 25,261.90 100.00%
05.01.09 ENCOFRADO Y DESENCOFRADO m2 131,524.92 59,186.21 45.00% 72,338.71 55.00% 131,524.92 100.00%
05.02 BADENES 1,335,985.26 18,591.02 1.39% 35,675.42 2.67% 60,033.66 4.49% 41,449.04 3.10% 513,829.37 38.46% 568,273.93 42.54% 98,132.82 7.35% 1,335,985.26 100.00%
05.02.01 TRAZO Y NIVELACION m2 26,558.60 18,591.02 70.00% 7,967.58 30.00% 26,558.60 100.00%
05.02.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS. m3 92,359.48 27,707.84 30.00% 60,033.66 65.00% 4,617.97 5.00% 92,359.48 100.00%
05.02.03 RELLENO PARA ESTRUCTURA CON MATERIAL PROPIO. m3 45,523.28 20,485.48 45.00% 25,037.80 55.00% 45,523.28 100.00%
05.02.04 RELLENO PARA ESTRUCTURA CON MATERIAL GRANULAR m3 29,719.26 16,345.59 55.00% 13,373.67 45.00% 29,719.26 100.00%
05.02.05 ENCOFRADO Y DESENCOFRADO m2 92,618.29 55,570.97 60.00% 37,047.32 40.00% 92,618.29 100.00%
05.02.06 LOSA DE MANPOSTERIA DE PIEDRA m3 699,744.87 419,846.92 60.00% 279,897.95 40.00% 699,744.87 100.00%
05.02.07 EMBOQUILLADO DE MAMPOSTERIA m3 282,405.22 197,683.65 70.00% 84,721.57 42.86% 282,405.22 112.86%
05.02.08 JUNTA DE DILATACION m 67,056.26 53,645.01 80.00% 13,411.25 20.00% 67,056.26 100.00%
05.03 MUROS DE CONTENCIÓN 842,187.85 33,578.38 3.99% 100,592.52 11.94% 29,764.16 3.53% 16,318.16 1.94% 97,236.11 11.55% 471,776.47 56.02% 92,922.06 11.03% 842,187.85 100.00%
05.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS. m3 29,978.35 29,978.35 100.00% 29,978.35 100.00%
05.03.02 RELLENO PARA ESTRUCTURA CON MATERIAL GRANULAR m3 12,000.11 3,600.03 30.00% 8,400.08 70.00% 12,000.11 100.00%
05.03.03 FILTRO DRENANTE m3 91,194.30 91,194.30 100.00% 91,194.30 100.00%
05.03.04 MATERIAL IMPERMEABLE FC=100KG/CM2 m3 19,962.90 998.15 5.00% 18,964.76 95.00% 19,962.90 100.00%
05.03.05 GEOTEXTIL NO TEJIDO TIPO 2 m2 13,499.25 10,799.40 80.00% 2,699.85 20.00% 13,499.25 100.00%
05.03.06 TUBERIA DE DRENAJE PERFORADA PVC D=4" m 13,896.23 13,618.31 98.00% 277.92 2.00% 13,896.23 100.00%
05.03.07 TUBERIA DE DRENAJE D=2° m 1,607.85 1,607.85 100.00% 1,607.85 100.00%
05.03.08 CONCRETO F'c=175 KG/CM2 + 30% P.G. m3 476,751.67 95,350.33 20.00% 381,401.34 80.00% 476,751.67 100.00%
05.03.09 ENCOFRADO CARA NO VISTA EN SECO m2 180,750.26 90,375.13 50.00% 90,375.13 50.00% 180,750.26 100.00%
05.03.10 JUNTA DE DILATACION. m 2,546.93 2,546.93 100.00% 2,546.93 100.00%
05.04 GAVION 823,075.20 363,692.02 44.19% 437,215.10 53.12% 22,168.08 2.69% 823,075.20 100.00%
05.04.01 GAVION TIPO CAJA. (Zm-5AI-MM) m3 773,812.80 363,692.02 47.00% 410,120.78 53.00% 773,812.80 100.00%
05.04.02 GEOTEXTIL PARA ENROCADO m2 49,262.40 27,094.32 55.00% 22,168.08 45.00% 49,262.40 100.00%
05.05 CUNETAS 52,608.00 52,608.00 100.00% 52,608.00 100.00%
05.05.01 CONFORMACION DE CUNETAS m 52,608.00 52,608.00 100.00% 52,608.00 100.00%

06.00 PONTON DE CONCRETO ARMADO 308,570.04 32,162.66 10.42% 81,151.97 26.30% 107,950.57 34.98% 70,642.19 22.89% 16,662.65 5.40% 308,570.04 100.00%
06.01 MOVIMIENTO DE TIERRAS 31,759.65 31,759.65 100.00% 31,759.65 100.00%
06.01.01 DEMOLICION DE ESTRUCTURAS m3 5,391.96 5,391.96 100.00% 5,391.96 100.00%
06.01.02 TRAZO Y REPLANTEO m2 1,748.81 1,748.81 100.00% 1,748.81 100.00%
06.01.03 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO EQUIPO m3 4,022.55 4,022.55 100.00% 4,022.55 100.00%
06.01.04 EXCAVACION PARA ESTRUCTURA EN ROCA FIJA EQUIPO m3 6,698.22 6,698.22 100.00% - 6,698.22 100.00%
06.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 13,898.11 13,898.11 100.00% 13,898.11 100.00%
06.02 ESTRUCTURAS DE CONCRETO 211,499.45 403.01 0.19% 81,151.97 38.37% 107,950.57 51.04% 21,993.90 10.40% 211,499.45 100.00%
06.02.01 SOLADO DE CONCRETO f'c=100 kg/cm2 m2 4,152.00 4,152.00 100.00% 4,152.00 100.00%
06.02.02 CONCRETO F'c=140 KG/CM2 + 30% P.G m3 720.45 720.45 100.00% 720.45 100.00%
06.02.03 CONCRETO F'c=210 KG/CM2 m3 81,252.10 8,125.21 10.00% 73,126.89 90.00% 81,252.10 100.00%
06.02.04 CONCRETO F'c=280 KG/CM2 m3 13,583.02 13,583.02 100.00% 13,583.02 100.00%
06.02.05 ENCOFRADO Y DESENCOFRADO m2 20,150.62 403.01 2.00% 19,747.61 98.00% 20,150.62 100.00%
06.02.06 ACERO DE REFUERZO F'y=4200KG/CM2 kg 91,641.26 34,823.68 38.00% 34,823.68 38.00% 21,993.90 24.00% 91,641.26 100.00%
06.03 FALSO PUENTE 48,648.29 - 48,648.29 100.00% 48,648.29 100.00%
06.03.01 RELLENO PARA ESTRUTURAS m3 39,682.69 39,682.69 100.00% 39,682.69 100.00%
06.03.02 PREPARACION E INSTALACION DE FALSO PUENTE m2 8,965.60 8,965.60 100.00% 8,965.60 100.00%

XII CRONOGRAMA VALORIZADO DE OBRA - Página N° 1


GOBIERNO REGIONAL LA LIBERTAD
PROYECTO ESPECIAL CHAVIMOCHIC
CRONOGRAMA VALORIZADO DE OBRA

Obra MEJORAMIENTO DE LA CARRETERA CHAO - BUENAVISTA - EL PIE - SAN PEDRO - CHAGAGANDA - UNINGAMBAL- HUAYNAS - LOS TORITOS EN LOS DISTRITOS DE CHAO HUASO CALAMARCA QUIRUVILCA - REGION LA LIBERTAD

Cliente
Ubicación LA LIBERTAD - VIRU - VIRU
Plazo 270 DIAS CALENDARIO

PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES SEPTIMO MES OCTAVO MES NOVENO MES TOTAL
ITEM DESCRIPCION UND PRESUPUESTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO MONTO
% % % % % % % % % %
VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO VALORIZADO
06.04 TRABAJOS VARIOS 16,662.65 16,662.65 100.00% 16,662.65 100.00%
06.04.01 TUBERIA Ø 4" PVC SAP PARA DRENAJE und 128.25 128.25 100.00% 128.25 100.00%
06.04.02 DUCTO DE D=6° m 3,434.54 3,434.54 100.00% 3,434.54 100.00%
06.04.03 APOYO ELASTOMERICO DE NEOPRENO m 6,225.54 6,225.54 100.00% 6,225.54 100.00%
06.04.04 ACABADO DE VEREDAS ARENA - CEMENTO 1:3 m2 797.15 797.15 100.00% 797.15 100.00%
06.04.05 BARANDAS METALICAS PARA PUENTES m 6,077.17 6,077.17 100.00% 6,077.17 100.00%

07.00 SEÑALIZACIÓN Y SEGURIDAD VIAL 315,381.77 123,077.56 39.02% 113,364.64 35.95% 78,939.57 25.03% 315,381.77 100.00%
07.01 SEÑAL REGLAMENTARIA 0.80 x 1.20 M. und 44,565.00 44,565.00 100.00% 44,565.00 100.00%
07.02 SEÑAL PREVENTIVA (0.75M X 0.75M) und 14,115.64 14,115.64 100.00% 14,115.64 100.00%
07.03 SEÑAL IMFORMATIVA m2 22,678.39 22,678.39 100.00% 22,678.39 100.00%
07.04 POSTES DE SOPORTE DE SEÑALES und 52,148.16 41,718.53 80.00% 10,429.63 20.00% 52,148.16 100.00%
07.05 ESTRUCTURA DE SOPORTE DE SEÑALES TIPO E-1 und 36,978.24 36,978.24 100.00% 36,978.24 100.00%
07.06 ESTRUCTURA DE SOPORTE DE SEÑALES TIPO E-2 und 119,921.40 65,956.77 55.00% 53,964.63 45.00% 119,921.40 100.00%
07.07 HITOS KILOMETRICOS und 8,297.77 8,297.77 100.00% 8,297.77 100.00%
07.08 PINTURA SOBRE EL PAVIMENTO. m2 16,677.17 16,677.17 100.00% 16,677.17 100.00%

07.00 TRANSPORTE 7,247,933.93 1,036,449.63 14.30% 2,108,592.61 29.09% 3,847,954.26 53.09% 254,937.43 3.52% 7,247,933.93 100.00%
07.01 TRANSPORTE DE MATERIAL PARA AFIRMADO MENOR A 1 KM m3k 533,507.82 266,753.91 50.00% 266,753.91 50.00% 533,507.82 100.00%
07.02 TRANSPORTE DE MATERIAL PARA AFIRMADO MAYOR A 1 KM m3k 2,549,374.31 382,406.15 15.00% 1,912,030.73 75.00% 254,937.43 10.00% 2,549,374.31 100.00%
07.03 TRANSPORTE DE MATERIAL EXCEDENTE MENOR A 1 KM m3k 1,399,446.76 769,695.72 55.00% 629,751.04 45.00% 1,399,446.76 100.00%
07.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 KM m3k 2,765,605.04 829,681.51 30.00% 1,935,923.53 70.00% 2,765,605.04 100.00%

09.00 PROTECCIÓN AMBIENTAL 144,253.29 94,003.14 65.17% 11,735.12 8.14% 29,873.03 20.71% 5,478.00 3.80% 3,164.00 2.19% 144,253.29 100.00%
09.01 REVEGETACION ha 10,007.14 10,007.14 100.00% 10,007.14 100.00%
07.02 DEPOSITO DE DESECHOS m3 83,996.00 83,996.00 100.00% 83,996.00 100.00%
07.03 READECUACION AMBIENTAL DE AREAS EN CANTERAS m2 7,865.00 7,865.00 100.00% 7,865.00 100.00%
07.04 READECUACION DE AREAS DE CAMPAMENTO Y PATIO DE MAQUINAS m2 3,750.00 3,750.00 100.00% 3,750.00 100.00%
07.05 MONITOREO DE LA CALIDAD DEL AGUA pto 5,478.00 5,478.00 100.00% 5,478.00 100.00%
07.06 MONITOREO DE LA CALIDAD DEL AIRE pto 3,164.00 3,164.00 100.00% 3,164.00 100.00%
07.07 MONITOREO DE RUIDOS pto 171.60 120.12 70.00% 51.48 30.00% 171.60 100.00%
07.08 SEÑAL AMBIENTAL TEMPORAL und 5,729.00 5,729.00 100.00% 5,729.00 100.00%
07.09 SEÑAL AMBIENTAL PERMANENTE und 24,092.55 24,092.55 100.00% 24,092.55 100.00%

COSTO DIRECTO 23,322,609.53 1,332,441.84 1,480,019.63 1,907,806.20 2,299,873.57 4,006,914.37 5,564,022.45 5,711,516.90 945,238.49 74,776.08 23,322,609.53
GASTOS GENERALES 10% 2,332,260.95 133,244.18 148,001.96 190,780.62 229,987.36 400,691.44 556,402.25 571,151.69 94,523.85 7,477.61 2,332,260.95
UTILIDAD 5% 1,166,130.48 66,622.09 74,000.98 95,390.31 114,993.68 200,345.72 278,201.12 285,575.85 47,261.92 3,738.80 1,166,130.48
SUB TOTAL 26,821,000.96 1,532,308.11 1,702,022.57 2,193,977.13 2,644,854.61 4,607,951.53 6,398,625.82 6,568,244.44 1,087,024.26 85,992.49 26,821,000.96
I.G.V 18% 4,827,780.17 275,815.46 306,364.06 394,915.88 476,073.83 829,431.27 1,151,752.65 1,182,284.00 195,664.37 15,478.65 4,827,780.17

TOTAL 31,648,781.13 1,808,123.57 2,008,386.63 2,588,893.01 3,120,928.44 5,437,382.80 7,550,378.47 7,750,528.44 1,282,688.63 101,471.14 31,648,781.13

% MENSUAL DE AVANCE DE OBRA 5.71% 6.35% 8.18% 9.86% 17.18% 23.86% 24.49% 4.05% 0.32% 100.00%
% ACUMULADO DE AVANCE DE OBRA 5.71% 12.06% 20.24% 30.10% 47.28% 71.14% 95.63% 99.68% 100.00%