configuration throughout construction. This will minimize the impact to motorists and improve safety.
Construction efficiency will be facilitated by always maintaining positive drainage and minimizing the need for temporary
construction and major traffic shifts.
The major construction phases identified in the preliminary project baseline schedule can be summarized as follows:
Phases 1 & 2: Construct noise walls, utility relocations, drainage trunk lines and new/reconstructed frontage roads
along the new right-of-way lines. Construct cross road overpass bridges and permanent/temporary widening to the
outside of the existing General Purpose Lanes (GPL) of IH 635.
Phase 3: Shift GPL traffic to the outside of the existing pavement, construct the Managed Lanes and overhang
structures in the center.
Phase 4: Shift GPL into final configuration and complete all ramps between the GPL and Frontage Roads
1.2.1 IH 635 Section
LBJ Development Partners understands that the IH 635 Section is the most complex portion of the IH 635 Managed Lanes
Project and has committed extensive resources during the proposal stage analyzing the sequencing and phasing. Our
preliminary schedule anticipates beginning construction in April 2011 and reaching Service Commencement within the
deadlines required in the ITP.
Milestone Dates
NTP1: April 28, 2009
Financial Close: October 20, 2010
NTP2: April 18, 2011
Substantial Completion /
Service Commencement: April 18, 2016
Final Acceptance: July 17, 2016
1.2.5 Phasing
LBJ Development Partners has carefully analyzed the construction elements and developed four major phases of construction,
which are detailed in the following sections. Each major construction phase contains multiple sub-phases/stages that relate to
construction at particular locations and features.
Phase 1
In Phase 1, there are no major main lane traffic shifts. The critical work of this phase includes removal of major
culverts and/or portions thereof that cross IH 635 and replacement of the Joe Ratliff Walkway Bridge directly over IH
635 main lanes. These removals will accommodate installation of median barriers during Phase 1 and 2 traffic
operations.
In Phase 1A, traffic is maintained on existing general purpose lanes and frontage roads while constructing
permanent frontage roads in non-conflicting traffic areas. Temporary pavement at several locations will be
constructed to shift traffic for Phase 1B and Phase 2 work. Traffic will be shifted at select cross-streets to allow for
bridge column construction. The first half of Marsh Lane, Rosser Road, Welch Road, Montfort Road and Preston
Road cross street bridges will also be constructed during this phase. The new Joe Ratliff Walkway Bridge will be
constructed in its entirety during this phase.
In Phase 1B, transitions between permanent and temporary pavement is constructed on frontage roads as traffic is
maintained and shifted. Marsh Lane, Welch Road, Montfort Road and Preston Road cross street bridges will be
completed during this phase.
The final portion of Phase 1 (Phase 1C) will include construction of the remaining middle portion of Rosser Road.
Phase 2
In Phase 2, the major traffic shifts from Phase 1 traffic operations are IH 635 between the western project limit to
just east of Marsh Lane (Sta 155+00); east of Midway Road (Sta. 200+00 to Sta. 237+00); and near Preston Road
(Sta. 295+00 to Sta. 340+00). These shifts allow eastbound and westbound temporary pavement construction
between Marsh Lane and Preston Road to enable construction of the complete bridge structures between these two
facilities during Phase 3. Critical work in this phase includes construction of temporary ramps and alternate ramp
connections which will be provided on the newly constructed temporary pavement in preparation of future major
traffic shifts.
In Phase 2A, the outside portions of the general purpose lanes will be constructed for Phase 3 while leaving out
some transitions near existing on/off ramps to maintain traffic. Critical work in this phase includes construction of the
outside portions of Webb Chapel Road in order to maintain traffic during the Phase 3 construction of the roadway.
Alternate ramp connections on the newly constructed temporary pavement to and from the DNT will be provided.
Phase 2B includes construction of the remaining outside portions of the general purpose lanes near the on/off ramp
locations that were started in Phase 2A. Other construction activities include construction of portions of the two
steel aqueducts near the Dallas North Tollway. Temporary connections will be provided between the completed
steel segments and the existing box structures to maintain proper drainage during construction.
Permanent pavement and CD bridges for the eastbound and westbound IH 635 CD roads over the Dallas North
Tollway will be constructed in Phase 2C. These will include temporary widenings to all for the diversion of general
purpose traffic onto the bridges.
Phase 3
Most of the major construction activities take place in Phase 3. Traffic is shifted to the outside portions of the
general purpose lanes completed in Phases 1 and 2. Temporary pavement widening will take place at Josey Lane,
Hillcrest Road and Park Central Drive. These roads will be constructed in halves while maintaining traffic on the
other half. The demolition and removal of the major culverts and/or portions thereof remaining will be completed in
this phase. All the managed lanes (depressed and at grade) will be constructed in this phase. The Dallas North
Tollway bridge over the managed lanes will be constructed in phases while maintaining all existing lanes of traffic.
The bridges and accesses for the managed lanes and the direct connectors at all locations will be constructed, with
the exception of between Rosser Road and Marsh Lane. The remaining accesses will be completed during Phase
4 when traffic at the conflicting locations is shifted.
In Phase 3A, construction of the inside portions of the general purpose lanes and slip ramps is completed. These
locations, directly over the managed lanes, will provide access to and from the depressed managed lanes and the
general purpose lanes. Elevated direct connector ramps along IH-35E, between IH-635 to the north and the Loop
12/IH-35E interchange to the south, are constructed in this phase. Phase 3A includes construction of one half of
Josey Lane, Midway Road, Hillcrest Road and Park Central Drive (cross streets running underneath IH 635).
Construction of the U-turn lanes at Webb Chapel Road is completed while maintaining traffic on existing lanes.
In Phase 3B, the remaining half of Josey Lane, Midway Road, Hillcrest Road and Park Central Drive is completed
as well as the middle portion of Webb Chapel Road. Webb Chapel Road traffic will be maintained on the newly
constructed outside lanes constructed in Phase 2.
Phase 4
All remaining construction activities will be completed in Phase 4. The main elements of work include the remaining
portions of the frontage roads and tie-ins to the IH 635 general purpose lanes. All traffic will be shifted to the
completed portions of the general purpose lanes in its final configuration. For certain locations, new temporary
pavement and temporary ramps will be required to construct the permanent ramps and frontage roads.
In Phase 4A, the remaining ramp and frontage road portions are to be constructed.
In Phase 4B, the remaining underpass portions of the managed lane access ramp between Marsh Lane and Rosser
Road will be constructed. Temporary pavement and shoring will be required for the construction of the westbound
off ramp to Marsh Lane. All remaining frontage road and ramp portions will be completed. IH 635 will be opened to
all traffic at the end of this phase.