ABI - PHASE 1A
WOOD CHIP MILL E&I INSTALLATION
ID Task Name Duration Start Finish
March April May June July August September October November December
3/6 3/27 4/17 5/8 5/29 6/19 7/10 7/31 8/21 9/11 10/2 10/23 11/13 12/4
1 ABI Woodchip Mill E& I 130 days Thu 5/25/17 Wed
Installation 11/22/17
2 Contract signed 1 day Thu 5/25/17 Thu 5/25/17
3 Effectiveness of Contract 98 days Tue 5/30/17Thu 10/12/17
4 Engineering, Purchase & 90 days Tue 5/30/17 Mon
Manufacture
10/2/17
5 Grounding 75 days Tue 5/30/17 Mon 9/11/17

6 Cable Ladder & Support 85 days Tue 5/30/17 Mon 9/25/17

7 Cable Power & Control 89 days Tue 5/30/17 Fri 9/29/17

8 Lighting & Pole 80 days Tue 5/30/17 Mon 9/18/17

9 Lightning 80 days Tue 5/30/17 Mon 9/18/17

10 Instrument 90 days Tue 5/30/17 Mon 10/2/17

11 Panels Distibution,etc 85 days Tue 5/30/17 Mon 9/25/17

12 CCTV, File Alarm and 85 days Tue 5/30/17 Mon 9/25/17


Telephone

13 Junction Box, etc 85 days Tue 5/30/17 Mon 9/25/17

14 Delivery Materials 23 days Tue 9/12/17Thu 10/12/17


15 Grounding 8 days Tue 9/12/17 Thu 9/21/17

16 Cable Ladder & Support 8 days Tue 9/26/17 Thu 10/5/17

17 Cable Power & Control 8 days Mon 10/2/17 Wed 10/11/17

18 Lighting & Pole 8 days Tue 9/19/17 Thu 9/28/17

19 Lightning 8 days Tue 9/19/17 Thu 9/28/17

20 Instrument 8 days Tue 10/3/17 Thu 10/12/17

21 Panels Distibution,etc 8 days Tue 9/26/17 Thu 10/5/17

22 CCTV , Fire Alarm and 8 days Tue 9/26/17 Thu 10/5/17


Telephone

23 Junction Box, etc 8 days Tue 9/26/17 Thu 10/5/17

24 Mobililzation 77 days Tue 8/8/17Wed 11/22/17


25 Installations 77 days Tue 8/8/17Wed 11/22/17
26 Grounding 40 days Fri 9/22/17 Thu 11/16/17

27 Cable Ladder & Support 21 days Fri 10/6/17 Fri 11/3/17

28 Pulling Cable Power & 30 days Thu 10/12/17 Wed 11/22/17


Control

29 Cable Bus 14 days Fri 10/6/17 Wed 10/25/17

30 Lighting & Pole 30 days Fri 9/29/17 Thu 11/9/17

31 Instrument 22 days Fri 10/13/17 Mon 11/13/17

32 Panels Distibution,etc 21 days Fri 10/6/17 Fri 11/3/17

33 CCTV, File Alarm & 21 days Fri 10/6/17 Fri 11/3/17


Telephone

34 Lighting Panels 14 days Fri 9/29/17 Wed 10/18/17

35 Lighning 15 days Fri 9/29/17 Thu 10/19/17

36 LV Switchgear Panels 3 days Wed 11/15/17 Fri 11/17/17

37 LVMCC 400 & 690 Panels 6 days Mon 9/18/17 Mon 9/25/17

38 20kV Switchgear Panels 3 days Mon 9/18/17 Wed 9/20/17

39 UPS & Battery Charger 2 days Mon 9/18/17 Tue 9/19/17

40 Transformer 7 days Tue 8/8/17 Wed 8/16/17

41 Junction Box 7 days Mon 9/18/17 Tue 9/26/17

42 PMS Panels 5 days Tue 10/10/17 Mon 10/16/17

43 DCS Panels 5 days Tue 10/10/17 Mon 10/16/17

44 Telephone 4 days Fri 10/6/17 Wed 10/11/17

45 Commissioning 24 days Fri 10/20/17Wed 11/22/17


46 Lighting 3 days Fri 11/10/17 Tue 11/14/17
47 Lightening 2 days Fri 10/20/17Mon 10/23/17
48 Grounding 3 days Fri 11/17/17 Tue 11/21/17
49 Dsitribution Panels 4 days Mon 11/6/17 Thu 11/9/17
50 Instrumentation 7 days Tue 11/14/17Wed 11/22/17

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: ABI Wood Chip Mill E&I I
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Tue 5/16/17
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1