Anda di halaman 1dari 1

SAW-CUT GROOVE 8MM WIDE

SAW-CUT GROOVE 8MM 65MM DEEP TO BE FILLED WITH


WIDE TO BE FILLED WITH POLYURETHANE SEALANT
RET. WALL/CHB WALL POLYURETHANE SEALANT
SLAB REINF.
SLAB REINF.
SPACED @ 400MM O.C.
POLYURETHANE SEALANT FLR. LVL. SLAB ON GRADE
20MM MIN.

SLAB
FLR. LVL.
20MM MIN.

"t"
SLAB
CONC. COVER

100
"t"
SLAB REINF. CONC. COVER

100
FLR. LVL.

VARIES
100
CONSTRUCTION JOINT GRAVEL BED

DOWEL LENGTH
250

VARIES
150MM THICK
EXTERIOR CHB WALL
COMPACTED GRAVEL SUBGRADE COMPACTED
COMPACTED GRAVEL SUBGRADE COMPACTED BEDDING (TYP.) TO 95% OF MAXIMUM
400 BEDDING (TYP.) TO 95% OF MAXIMUM

200
VAPOR BARRIER DRY DENSITY @ OPTIMUM
VAPOR BARRIER DRY DENSITY @ OPTIMUM MOISTURE CONTENT (MAX.
WHEN REQUIRED
WHEN REQUIRED MOISTURE CONTENT (MAX. DEPTH OF COMPRESSED
COMPACTED GRAVEL SUBGRADE COMPACTED DEPTH OF COMPRESSED
BEDDING (TYP.) TO 95% OF MAXIMUM FILL = (200mm PER LAYER).
FILL = (200mm PER LAYER). FOOTING TIE BEAM
VAPOR BARRIER DRY DENSITY @ OPTIMUM
WHEN REQUIRED MOISTURE CONTENT (MAX.
DEPTH OF COMPRESSED
FILL = (200mm PER LAYER).
SLAB-ON-GRADE CONSTRUCTION SLAB-ON-GRADE CONTRACTION
JOINT DETAIL JOINT DETAIL TYPICAL WALL TO TIE BEAM DETAILS
SLAB-ON-GRADE EXPANSION
JOINT DETAIL

2D (NO PIPE SLEEVE PROPOSED PIPE SLEEVE LOCATIONS


SHALL BE ALLOWED W/IN
THIS ZONE (TYP.)) SCH. 40 G.I. PIPE SLEEVE
CHB "t" 2 - EXTRA STIR. EA. SIDE
A PIPE SLEEVE
OF SLEEVE
2 EXTRA STIRRUPS
2D 0 2D
REQUIRED 50 .) EACH SIDE OF SLEEVE
MAIN REINFORCEMENTS TO BE YP B
CONTINUOUS (TOP & BOT. BARS) TOP BARS (T FACE OF TOP BARS
A
SUPPORT
CONCRETE FILLER

40
DEPRESSION
PIPE E.F. (DIAGONALS)
50
D=FOR BEAM
t=FOR SLAB

VERIFY

D
(MIN.) (MIN.) PIPE SLEEVE

D/5

D/5
CONCRETE

40
FILLER
WELDED TO SLEEVE
D/2

BOT. BARS A (TYPICAL)


FACE OF BOTTOM BARS
STIR. AS SCHED.
SLOPE 1:2 V:H SUPPORT 4d (MIN.) SECTION A - A

12mm GAP
MASTIC SEALANT
D/2

EACH SIDE

(MIN.)
PIPE SLEEVE L/4 L/2 L/4 NOTES:
REQUIRED PIPE SLEEVE
LIMIT LOCATION OF PIPE SLEEVE 1. SEEK STRUCT'L ENGINEER'S
D=FOR BEAM COMPRESSIBLE APPROVAL FOR PIPE SLEEVES
MATERIALS L PIPE SLEEVE MAXIMUM DIAMETER
SIDE IF BEAM CONSTRUCTION JOINT 2t=FOR SLAB W/ DIAMETERS BIGGER THAN
IS NOT WITHIN THE MIDDLE THIRD CHB WALL IS : (LEAST GOVERNS) THE MAXIMUM STIPULATED.
OF THE SPAN. LEGEND:
A) 1/5 OF BEAM DEPTH 2. PIPE SLEEVES SHALL BE
BEAM/SLAB CHANGE SOFFIT SECTION A-A 1. D = DEPTH OF BEAM/GIRDER
BEAM CONSTRUCTION 2. d = PIPE SLEEVE DIAMETER B) 100 MM LOCATED WITHIN TENSION
ZONES OF BEAM.

JOINT DETAIL DETAIL


PIPE SLEEVE THRU WALL 3. NO PIPE SLEEVE SHALL BE
ALLOWED AT TWICE THE

PIPE SLEEVE THRU BEAM DETAIL BEAM DEPTH (2D) FROM


THE SUPPORT.

SEE WALL
SCHEDULE
TABLE OF LAP SPLICE
W = 1.20m (max) PARAMETERS

550
200 W = 1.20m (max) 200 200 200

WALLS LESS THAN


MATERIAL psi MPa ACI 318-05

200 mm THK.
f'c 5000 34.5 DEV'T & SPLICE LENGTH

fy 60000 414 16mm & HIGHER


fyh 40000 276 12mm & LOWER
550 10 10
(TYP.) fyt 40000 fyt 40000
& BOTTOM BARS & BOTTOM BARS

WINDOW
AT INTERSECTION ANCHORAGE
Ldh(mm)
STANDARD HOOK (mm)
BEAM COMP.
TENSION LAP SPLICE (mm)
UNIT WT.
(mm) LENGTH (mm) SPLICE (mm) BEAM COLUMN
OPENING LAP CLASS (kg/m)
CHB WALL CHB WALL TOP BAR BOTTOM BAR TIED SPIRAL
WALLS LESS THAN A 300 300
200 mm THK. 10 600 150 160 110 120~120 300 300 300 0.616
B 390 390
DOOR A 530 410
H
H

OPENING SEE WALL 12 600 200 200 120 130~130 350 410 410 0.888
B 690 530
SCHEDULE
A 700 540
16 740 270 260 130 160~160 460 540 540 1.579
B 910 700
A 880 680
550

20 920 340 320 160 200~320 580 680 680 2.466


BARS B 1140 880

(TYP.)
BARS

550
A 1370 1060
25 1150 430 400 200 250~400 720 1060 1060 3.854
B 1780 1380
A 1540 1180
28 1300 480 480 260 810 1180 1180 4.833
B 2000 1530
550 A 1760 1350
32 1700 540 550 290 930 1350 1350 6.313
(TYP.) B 2290 1760
A 1980 1520
36 2150 610 650 360 1040 1520 1520 7.991
AT CORNER B 2570 1980

TYPICAL DOOR OPENING TYPICAL WINDOW OPENING NOTES:


1. DEVELOPMENT LENGTH OF INDIVIDUAL BARS WITHIN A BUNDLE, IN TENSION OR COMPRESSION, SHALL BE THAT FOR INDIVIDUAL BARS,

WITH LINTEL BEAM WITH LINTEL BEAM RC WALL CONNECTION AT INCREASED 20% FOR THREE-BUNDLED AND 33% FOR FOUR-BUNDLED BARS.
2. FOR COLUMNS AT ANY LEVEL, NO MORE THAN ALTERNATE BARS SHOULD BE SPLICED, NOTMORE THAN 33% OF THE BARS SHALL BE SPLICED WITHIN
THE REQUIRED LAP LENGTH, MINIMUM DISTANCE BETWEEN TWO ADJACENT SPLICED SHALL BE 600mm.

INTERSECTION 3. TOP BARS ARE HORIZONTAL BARS WITH MORE THAN 300mm DEPTH OF CONCRETE CAST BELOW REINFORCEMENT.
4. LAP SPLICE SHALL BE "CLASS B" TENSION LAP SPLICE IF MORE THAN ONE HALF OF THE BARS WERE SPLICED AT ANY SECTION, WHILE "CLASS A"
TENSION LAP SPLICE IF HALF OR FEWER THAN HALF OF BARS WERE SPLICED.

JEMAR ENGINEERING
SERVICES
ENGINEERING DESIGNS & CONSTRUCTION MANAGEMENT
JBM UNITS 201 & 202 GARNET PLACE, M.L. QUEZON ST., CABANCALAN, MANDAUE CITY
Telefax No. (032) 420-5176 Mobile No's: 0917-7204480 / 0922-7243999
E-mail Address: jemar.engineering@yahoo.com

Anda mungkin juga menyukai