SLAB
FLR. LVL.
20MM MIN.
"t"
SLAB
CONC. COVER
100
"t"
SLAB REINF. CONC. COVER
100
FLR. LVL.
VARIES
100
CONSTRUCTION JOINT GRAVEL BED
DOWEL LENGTH
250
VARIES
150MM THICK
EXTERIOR CHB WALL
COMPACTED GRAVEL SUBGRADE COMPACTED
COMPACTED GRAVEL SUBGRADE COMPACTED BEDDING (TYP.) TO 95% OF MAXIMUM
400 BEDDING (TYP.) TO 95% OF MAXIMUM
200
VAPOR BARRIER DRY DENSITY @ OPTIMUM
VAPOR BARRIER DRY DENSITY @ OPTIMUM MOISTURE CONTENT (MAX.
WHEN REQUIRED
WHEN REQUIRED MOISTURE CONTENT (MAX. DEPTH OF COMPRESSED
COMPACTED GRAVEL SUBGRADE COMPACTED DEPTH OF COMPRESSED
BEDDING (TYP.) TO 95% OF MAXIMUM FILL = (200mm PER LAYER).
FILL = (200mm PER LAYER). FOOTING TIE BEAM
VAPOR BARRIER DRY DENSITY @ OPTIMUM
WHEN REQUIRED MOISTURE CONTENT (MAX.
DEPTH OF COMPRESSED
FILL = (200mm PER LAYER).
SLAB-ON-GRADE CONSTRUCTION SLAB-ON-GRADE CONTRACTION
JOINT DETAIL JOINT DETAIL TYPICAL WALL TO TIE BEAM DETAILS
SLAB-ON-GRADE EXPANSION
JOINT DETAIL
40
DEPRESSION
PIPE E.F. (DIAGONALS)
50
D=FOR BEAM
t=FOR SLAB
VERIFY
D
(MIN.) (MIN.) PIPE SLEEVE
D/5
D/5
CONCRETE
40
FILLER
WELDED TO SLEEVE
D/2
12mm GAP
MASTIC SEALANT
D/2
EACH SIDE
(MIN.)
PIPE SLEEVE L/4 L/2 L/4 NOTES:
REQUIRED PIPE SLEEVE
LIMIT LOCATION OF PIPE SLEEVE 1. SEEK STRUCT'L ENGINEER'S
D=FOR BEAM COMPRESSIBLE APPROVAL FOR PIPE SLEEVES
MATERIALS L PIPE SLEEVE MAXIMUM DIAMETER
SIDE IF BEAM CONSTRUCTION JOINT 2t=FOR SLAB W/ DIAMETERS BIGGER THAN
IS NOT WITHIN THE MIDDLE THIRD CHB WALL IS : (LEAST GOVERNS) THE MAXIMUM STIPULATED.
OF THE SPAN. LEGEND:
A) 1/5 OF BEAM DEPTH 2. PIPE SLEEVES SHALL BE
BEAM/SLAB CHANGE SOFFIT SECTION A-A 1. D = DEPTH OF BEAM/GIRDER
BEAM CONSTRUCTION 2. d = PIPE SLEEVE DIAMETER B) 100 MM LOCATED WITHIN TENSION
ZONES OF BEAM.
SEE WALL
SCHEDULE
TABLE OF LAP SPLICE
W = 1.20m (max) PARAMETERS
550
200 W = 1.20m (max) 200 200 200
200 mm THK.
f'c 5000 34.5 DEV'T & SPLICE LENGTH
WINDOW
AT INTERSECTION ANCHORAGE
Ldh(mm)
STANDARD HOOK (mm)
BEAM COMP.
TENSION LAP SPLICE (mm)
UNIT WT.
(mm) LENGTH (mm) SPLICE (mm) BEAM COLUMN
OPENING LAP CLASS (kg/m)
CHB WALL CHB WALL TOP BAR BOTTOM BAR TIED SPIRAL
WALLS LESS THAN A 300 300
200 mm THK. 10 600 150 160 110 120~120 300 300 300 0.616
B 390 390
DOOR A 530 410
H
H
OPENING SEE WALL 12 600 200 200 120 130~130 350 410 410 0.888
B 690 530
SCHEDULE
A 700 540
16 740 270 260 130 160~160 460 540 540 1.579
B 910 700
A 880 680
550
(TYP.)
BARS
550
A 1370 1060
25 1150 430 400 200 250~400 720 1060 1060 3.854
B 1780 1380
A 1540 1180
28 1300 480 480 260 810 1180 1180 4.833
B 2000 1530
550 A 1760 1350
32 1700 540 550 290 930 1350 1350 6.313
(TYP.) B 2290 1760
A 1980 1520
36 2150 610 650 360 1040 1520 1520 7.991
AT CORNER B 2570 1980
WITH LINTEL BEAM WITH LINTEL BEAM RC WALL CONNECTION AT INCREASED 20% FOR THREE-BUNDLED AND 33% FOR FOUR-BUNDLED BARS.
2. FOR COLUMNS AT ANY LEVEL, NO MORE THAN ALTERNATE BARS SHOULD BE SPLICED, NOTMORE THAN 33% OF THE BARS SHALL BE SPLICED WITHIN
THE REQUIRED LAP LENGTH, MINIMUM DISTANCE BETWEEN TWO ADJACENT SPLICED SHALL BE 600mm.
INTERSECTION 3. TOP BARS ARE HORIZONTAL BARS WITH MORE THAN 300mm DEPTH OF CONCRETE CAST BELOW REINFORCEMENT.
4. LAP SPLICE SHALL BE "CLASS B" TENSION LAP SPLICE IF MORE THAN ONE HALF OF THE BARS WERE SPLICED AT ANY SECTION, WHILE "CLASS A"
TENSION LAP SPLICE IF HALF OR FEWER THAN HALF OF BARS WERE SPLICED.
JEMAR ENGINEERING
SERVICES
ENGINEERING DESIGNS & CONSTRUCTION MANAGEMENT
JBM UNITS 201 & 202 GARNET PLACE, M.L. QUEZON ST., CABANCALAN, MANDAUE CITY
Telefax No. (032) 420-5176 Mobile No's: 0917-7204480 / 0922-7243999
E-mail Address: jemar.engineering@yahoo.com