SKEMA DAERAH IRIG

a = 1.6 lt/dt/ha
SALURAN PRIMER MERJAN KIRI
BMKi.3 BMKi.4 BMKi.5
A = 576 Ha A = 561 Ha A = 545 Ha
Q = 1.138 m3/dt Q = 1.108 m3/dt Q = 1.077 m3/dt
BMKi.2 L = 0.75 km L = 1.50 km L = 1.70 km
Ruas 3 Ruas 4 Ruas 5
A = 587 Ha
Q = 1.160 m3/dt MKi.2.ka MKi.3.ka MKi.4.ka
L = 1.00 km 11 Ha 18 l/dt 15 Ha 24 l/dt 16 Ha 26 l/dt
Ruas 2

BMKi.1 MKi.1.ka
A = 600 Ha 13 Ha 21 l/dt
Q = 1.185 m3/dt
L = 0.05 km
Ruas 1
BENDUNG MERJAN
B.M.0

A = 222 Ha
Q = 0.439 m3/dt
L = 0.30 km
Ruas 1
BMKa.1 MKa.1.ki
65 Ha 104 l/dt
A = 157 Ha
Q = 0.310 m3/dt
L = 0.35 km MKa.2.ki MKa.2.ki
Ruas 2 59 Ha 94 l/dt 98 Ha 157 l/dt

BMKa.2 Sal Muka BMMKa.2.ki


A = 98 Ha
Q = 0.174 m3/dt
L = 1.10 km
EMA DAERAH IRIGASI MERJAN
a = 1.6 lt/dt/ha

BMKi.5 BMKi.6 BMKi.7 BMKi.8 BMKi.9


A = 529 Ha A = 513 Ha A = 396 Ha A = 387 Ha
Q = 1.045 m3/dt Q = 1.013 m3/dt Q = 0.782 m3/dt Q = 0.764 m3/dt
L = 0.85 km L = 0.60 km L = 0.60 km L = 1.15 km
Ruas 6 Ruas 7 Ruas 8 Ruas 9

MKi.5.ka MKi.6.ka MKi.7.ka.3 MKi.8.ka


16 Ha 26 l/dt 16 Ha 26 l/dt 420Ha l/dt 9 Ha 14 l/dt

A = 64 Ha
Q = 0.114 m3/dt
L = 0.75 km
Sal Muka MKi.7.ka.2
MKi.7.ka.1 64 Ha 102 l/dt
11 Ha 18 l/dt

MKi.15.ki MKi.15.ka MKi.14.ka


58 Ha 93 l/dt 132 Ha 211 l/dt 24 Ha 38 l/dt

Saluran Muka Ruas 15


A = 58 Ha A = 190 Ha
Q = 0.103 m3/dt Q = 0.375 m3/dt
L = 1.10 km L = 0.65 km
BMKi.15

KEMENTE
DIREKTORAT J
DIR

SKEMA IR
DAERAH IRIGA
BMKi.9 BMKi.10
A = 373 Ha
Q = 0.737 m3/dt
L = 0.90 km
Ruas 10
A = 319 Ha
MKi.9.ka Q = 0.630 m3/dt
14 Ha 22 l/dt L = 2.05 km
Ruas 11

MKi.10.ka BMKi.11
54 Ha 86 l/dt

A = 306 Ha
Q = 0.604 m3/dt
L = 1.80 km
MKi.11.ka Ruas 12
13 Ha 21 l/dt

MKi.12.ka BMKi.12
50 Ha 80 l/dt
A = 256 Ha
Q = 0.506 m3/dt
MKi.13.ka L = 0.85 km
42 Ha 67 l/dt Ruas 13

Ruas 14 BMKi.13
A = 214 Ha
0.375 m3/dt Q = 0.423 m3/dt
L = 0.85 km
BMKi.14

KEMENTERIAN PEKERJAAN UMUM


DIREKTORAT JENDERAL SUMBER DAYA AIR
DIREKTOTAR IRIGASI

SKEMA IRIGASI
DAERAH IRIGASI MERJAN

Mei 2010
Daftar Ukuran Saluran

Luas Debit Perb b/h Lereng Kekasaran Lebar Tinggi


No. Nama Saluran A Q n m k b h
ha m3/dt m m
1 2 3 4 5 6 7 8 9

Primer Merjan Kanan


1 Tersier MKa.2.ka 98 0.157 1 1 35 0.50 0.50
2 Muka MKa.2.ka 98 0.174 1 1 35 0.50 0.50
3 Tersier MKa.2.ki 59 0.094 1 1 35 0.40 0.40
4 Primer MKa ruas 2 157 0.310 1 1 35 0.60 0.60
5 Tersier MKa.1.ki 65 0.104 1 1 35 0.40 0.40
6 Primer MKa ruas 2 222 0.439 1.2 1 35 0.80 0.67
Primer Merjan Kiri
1 Tersier MKi.15.ki 58 0.093 1 1 35 0.40 0.40
2 Muka MKi.15.ki 58 0.103 1 1 35 0.40 0.40
3 Tersier MKi.15.ka 132 0.211 1 1 35 0.55 0.55
4 Primer Mki Ruas.15 190 0.375 1 1 35 0.65 0.65
5 Tersier MKi.14.ka 24 0.038 1 1 35 0.30 0.24
6 Primer Mki Ruas.14 214 0.423 1.2 1 35 0.80 0.67
7 Tersier MKi.13.ka 42 0.067 1 1 35 0.35 0.30
8 Primer Mki Ruas.13 256 0.506 1.2 1 35 0.85 0.71
9 Tersier MKi.12.ka 50 0.080 1 1 35 0.35 0.35
10 Primer Mki Ruas.12 306 0.604 1.2 1 35 0.90 0.75
11 Tersier MKi.11.ka 13 0.021 1 1 35 0.30 0.15
12 Primer Mki Ruas.11 319 0.630 1.3 1 35 0.95 0.73
13 Tersier MKi.10.ka 54 0.086 1 1 35 0.35 0.35
14 Primer Mki Ruas.10 373 0.737 1.3 1 35 1.05 0.81
15 Tersier MKi.9.ka 14 0.022 1 1 35 0.30 0.15
16 Primer Mki Ruas.9 387 0.764 1.3 1 35 1.05 0.81
17 Tersier MKi.8.ka 9 0.014 1 1 35 0.30 0.11
18 Primer Mki Ruas.8 396 0.782 1.3 1 35 1.10 0.85
19 Tersier MKi.7.ka.1 11 0.018 1 1 35 0.30 0.13
20 Tersier MKi.7.ka.2 64 0.102 1 1 35 0.40 0.40
21 Muka MKi.7.ka.2 64 0.114 1 1 35 0.40 0.40
22 Tersier MKi.7.ka.3 42 0.067 1 1 35 0.35 0.30
23 Primer Mki Ruas.7 513 1.013 1.5 1 40 1.35 0.90
24 Tersier MKi.6.ka 16 0.026 1 1 35 0.30 0.18
25 Primer Mki Ruas.6 529 1.045 1.5 1 40 1.40 0.93
26 Tersier MKi.5.ka 16 0.026 1 1 35 0.30 0.18
27 Primer Mki Ruas.5 545 1.077 1.5 1 40 1.40 0.93
28 Tersier MKi.4.ka 16 0.026 1 1 35 0.30 0.18
29 Primer Mki Ruas.4 561 1.108 1.5 1 40 1.40 0.93
30 Tersier MKi.3.ka 15 0.024 1 1 35 0.30 0.17
31 Primer Mki Ruas.3 576 1.138 1.5 1 40 1.40 0.93
32 Tersier MKi.2.ka 11 0.018 1 1 35 0.30 0.13
33 Primer Mki Ruas.2 587 1.160 1.5 1 40 1.40 0.93
34 Tersier MKi.1.ka 13 0.021 1 1 35 0.30 0.15
35 Primer Mki Ruas.1 600 1.185 1.5 1 40 1.40 0.93

Catatan
NFR = a = 1,6 l/dt et = 0,80 es = 0,90 ep = 0,90 C = 0,80
Q tersier = (C.a.A)/(et)
Q sekunder = (C.a.A)/(et.es)
Q Primer = (C.a.A)/(et.es.ep)
Saluran

Luas Tamp Jari 2 Hid Kecepatan Kemiringan


F R V I Keterangan
m2 m m/dt
10 11 12 13 14

0.50 0.26 0.31 0.0004808


0.50 0.26 0.35 0.0005936
0.32 0.21 0.30 0.0005729
0.72 0.31 0.43 0.0007113
0.32 0.21 0.33 0.0006954
0.98 0.36 0.45 0.0006316

0.32 0.21 0.29 0.0005536


0.32 0.21 0.32 0.0006835
0.61 0.29 0.35 0.0005247
0.85 0.34 0.44 0.0006798
0.13 0.13 0.30 0.0010620
0.98 0.36 0.43 0.0005869
0.20 0.16 0.34 0.0010915
1.10 0.39 0.46 0.0006078
0.25 0.18 0.33 0.0008387
1.24 0.41 0.49 0.0006403
0.07 0.09 0.31 0.0018345
1.23 0.41 0.51 0.0007120
0.25 0.18 0.35 0.0009783
1.50 0.45 0.49 0.0005709
0.07 0.09 0.33 0.0021275
1.50 0.45 0.51 0.0006145
0.05 0.07 0.32 0.0026885
1.65 0.47 0.48 0.0005021
0.06 0.08 0.31 0.0022095
0.32 0.21 0.32 0.0006741
0.32 0.21 0.36 0.0008322
0.20 0.16 0.34 0.0010915
2.03 0.52 0.50 0.0003745
0.09 0.11 0.30 0.0014146
2.18 0.54 0.48 0.0003280
0.09 0.11 0.30 0.0014146
2.18 0.54 0.49 0.0003481
0.09 0.11 0.30 0.0014146
2.18 0.54 0.51 0.0003689
0.08 0.10 0.30 0.0015389
2.18 0.54 0.52 0.0003888
0.06 0.08 0.31 0.0022095
2.18 0.54 0.53 0.0004038
0.07 0.09 0.31 0.0018345
2.18 0.54 0.54 0.0004219
PERENCANAAN MUKA AIR

Nama Saluran Elevasi


Nama Luas Areal Q Elevasi
No tertinggi
Bangunan Primer Sekuder Tersier (A) (ha) (m3/det) (m)
(m)
1 BI4Kn 41.79 0.122 14.00
2 BI4Kr 30.76 0.119 14.10
3 BI4 SSI5 72.55 0.268 14.00 14.10
4 BI3Kn 14.50
5 BI3Kr 15.00
6 BI3 SSI4 15.00
7
8
9
10
11
12
13
14
15
16
17
18
Panjang Sal Dimensi Saluran
DH (m) Io Ia
(m) k m n h b

0.0003423 35 1 1 0.485 0.485


0.0003490 35 1 1 0.479 0.479
804 0.0003529 35 1 1 0.647 0.647

1200 0.000363 35 1 1 0.665 0.665


El. Hilir El. Hulu
0.15 h Ia x L
(DWL) (UWL)

0.11646 14.21646 0.283732 14.50019

0.1197 15.1197 0.4356 15.5553


Urutan Perhitungan Tabel Ukuran Saluran

1 Isi kolom 2 nama saluran mulai dengan petak Tersier paling bawah dilanjutkan Sekunder dan Primer

2 Isi kolom 3 luas masing masing petak tersier hasil pengukuran luas

3 Masih kolom 3 dilanjutkan dengan sekunder dan primer (hasil perjumlahan / kumulatif)

4 Isi kolom 4 Debit saluran dengan rumus untuk tersier Q = (C.a.A)/(et) , sekunder Q = (C.a.A)/(et.es)
dan primer Q = (C.a.A)/(et.es.ep)

5 Isi kolom 5, 6, dan 7 sesuai kriteria irigasi

6 Isi kolom 8 dengan coba coba hingga menghasilkan kecepatan sesuai kriteria irigasi

7 Untuk saluran tersier yang debitnya kecil dan menghasilkan kecepatan kecil (tidak sesuai kriteria)
ganti nilai kolom 9 dengan mengecilkan tinggi air saluran secara coba coba hingga menghasilkan
kecepatan sesuai kriteria Irigasi.

8 Kolom 10, 11, 12 dan 13 sudah rumus dan akan otomatis keluar hasilnya
r dan Primer