Anda di halaman 1dari 28

TESTING AND COMMISIONING

DET310

CHAPTER 6

PROTECTIVE RELAY
TESTING AND COMMISIONING
DET310

6.1 INTRODUCTION

-Power systems and their components need protection from natural hazards as
well as human error.
-Lightning, wind, ice, switching surges, resonance, trees, animals and humans
are some of the causes of faults.
-These faults produce overcurrents and/or overvoltages at various locations in
a power system and must be cleared before they cause before they damage
any machines, transformers, lines etc.
-This is generally accomplished by isolating the faulted portion (as small a
portion as possible) of the system so that the remainder of the system can
serve without interruption.
TESTING AND COMMISIONING
DET310

-continue:
-In low-voltage distribution systems, lightning (surge) arresters are used for
overvoltage protection and fuses and slow-acting circuit breakers are employed
for overcurrent protection.

-In high-voltage transmission systems reliable sensors, fast-acting relays and


circuit breakers are needed to clear the fault quickly so that the stability of the
remaining system is secured.

- In short, the protection, stability and security of a power system are affected by
the ability of the protection devices to detect and respond to system
abnormalities like overvoltages and overcurrents
TESTING AND COMMISIONING
DET310
6.1 Protection Components

Protection systems have three basic components:

-Sensors (transducers, detectors) to detect system abnormalities

-Relays (activators) to provide signals to activate the protection


devices.

-Circuit breakers (interrupters) to open (disconnect) the circuits


TESTING AND COMMISIONING
DET310

Figure 6.0
TESTING AND COMMISIONING
DET310

Continue:
In order to perform its functions properly, the protection system must
have the following characteristic:
a) Reliability: The reliability of the protection system is its ability to
operate upon the occurrence of any fault for which it was designed
to protect. In other words, the protection system should operate
when it is supposed to and not operate when it is not required.
b) Selectivity: Selectivity is the ability of the protection system to
detect a fault, identify the point at which the fault occurred and
isolate the faulted circuit element by tripping the minimum number
of circuit breakers. Selectivity of the protection system is obtained
by proper coordination of the operating currents and time delays of
the protective relays.
TESTING AND COMMISIONING
DET310

6.2 CLASSIFICATIONS OF RELAYS

Relays may be classified according to the technology


used:

a. electromechanical
b. static
c. digital
d. numerical
TESTING AND COMMISIONING
DET310

Continue:
c) Speed: The speed of the protection system refers to the operating
times of the protective relay. The potential damage to the faulted
element depends on the length of time the short-circuit currents are
allowed to flow. The speed of clearing or isolating the faulted system
component also affects the stability of the whole system.

d) Sensitivity: Sensitivity refers to the characteristic of a protective


relay that it operates reliably, when required, in response to a fault that
produces the minimum short-circuit current flowing through the relay.
TESTING AND COMMISIONING
DET310

6.2.1 ELECTROMECHANICAL RELAYS

Electromechanical relays can be classified into several


different types as follows:

a. attracted armature – comprises of iron cored electromagnet which attracts


an armature which is pivoted, hinged or supported.

b. moving coil- light coil which can be energised moves in a strong permanent
magnet field.

c. Induction – operated on the same principle as the induction motor

d. Thermal – operates based on the generated heats in a resistance winding


and temperature sensitive component

e. Timing relays- are used in conjunction with protection relays


TESTING AND COMMISIONING
DET310
6.2.2 Static Relays

-The term ‘static’ implies that the relay has no moving parts.

-In a protection relay, the term ‘static’ refers to the absence of


moving parts to create the relay characteristic.

-Their design is based on the use of analogue electronic devices


instead of coils and magnets to create the relay characteristic.

-Early versions used discrete devices such as transistors and


diodes in conjunction with resistors,capacitors, inductors,

- Advance versions enabled the use of linear and digital integrated


circuits in later versions for signal processing and implementation of
logic functions.
TESTING AND COMMISIONING
DET310
6.2.3 Digital Relays

-Digital protection relays introduced a step change in technology.


Microprocessors and microcontrollers replaced analogue circuits used
in static relays to implement relay functions.

-Compared to static relays, digital relays introduce A/D conversion of


all measured analogue quantities and use a microprocessor to
implement the protection algorithm.

-The microprocessor may use some kind of counting technique, or use


the Discrete Fourier Transform (DFT) to implement the algorithm.
TESTING AND COMMISIONING
DET310
6.2.4 Numerical Relays

-Typically, they use a specialised digital signal processor (DSP) as the


computational hardware, together with the associated software tools.

- The input analogue signals are converted into a digital representation


and processed according to the appropriate mathematical algorithm.

- Processing is carried out using a specialised microprocessor that is


optimised for signal processing applications, known as a digital signal
processor
TESTING AND COMMISIONING
DET310
TESTING AND COMMISIONING
DET310
TESTING AND COMMISIONING
DET310
6.3 Zone of Protection

-To limit the extent of the power system that is disconnected when a
fault occurs, protection is arranged in zones.(Figure 6.1).

- Ideally, the zones of protection should overlap, so that no part of the


power system is left unprotected. (Figure 6.2).
TESTING AND COMMISIONING
DET310

Figure 6.1
TESTING AND COMMISIONING
DET310

Figure 6.2
TESTING AND COMMISIONING
DET310
6.4 Protection principles
The best and common protection techniques can be classified into
2 categories
a) Overcurrent/earth fault-distance protection
b) Differential protection
TESTING AND COMMISIONING
DET310
6.4.1 Overcurrent and Earth-fault Protection

-Protection against excess current was naturally the earliest protection


system to evolve.

- The actuating quantity of an overcurrent relay is a current.

- The relay is designed to operate when the actuating quantity equals


or exceeds its pickup value.

- An overcurrent relay can either be an instantaneous type or a time-


delay type.
TESTING AND COMMISIONING
DET310
6.4.1.1 IDMTL relay
-Most commonly used type of relay.

-Characteristics of relay is the higher the current, the shorter the


operating time.

-The current/time tripping characteristics of IDMT relays may need to


be varied according to the tripping time required and the
characteristics of other protection devices used in the network.

-IEC 60255 defines a number of standard characteristics as follows:

a) Standard Inverse (SI)


b) Very Inverse (VI)
c) Extremely Inverse (EI)
d) Definite Time (DT)
TESTING AND COMMISIONING
DET310
TESTING AND COMMISIONING
DET310

The tripping
characteristics for
different TMS settings
using the SI curve
TESTING AND COMMISIONING
DET310
6.4.1.2 Setting of IDMTL relays

-In order to adjust the current setting, the relay coil is arranged to have
a tapped winding which is connected to a plug bridge.
(electromechanical relay)
-In modern relays, it is known as PLUG SETTING MULTIPLIER.
-Example: if Tap is set at 80% of 5A, then the current into the relay is
0.8 x 5A = 4A.
-TIME MULTIPLIER SETTING (TMS) the time the relay disc to move
through 180 degrees or relay operates to trip
- The setting is in term of percentage such as 10 %(0.1), 20%(0.2),
30% (0.3) etc.
TESTING AND COMMISIONING
DET310
Continue:
Tripping time of standard overcurrent relay:

Where: TMS = time multiplier setting


Ifault
I =( )
r Iprimary
TESTING AND COMMISIONING
DET310
Example:
Calculate tripping time of an overcurrent relay at 150% with the
The PSM setting is at 80%. CT ratio connected to the CT is 1000/5A
The TMS setting is 0.1
Solutions:
Time,

0.14
t = 0.1x
(1200 )0.02 − 1
800

t = 1.72 s
TESTING AND COMMISIONING
DET310
6.5 RELAY TESTING AND COMMISIONING
TESTING AND COMMISIONING
DET310
Continue:
Tripping time of standard overcurrent relay:

Where: TMS = time multiplier setting


Ifault
I =( )
r Iprimary
TESTING AND COMMISIONING
DET310
Continue:
Tripping time of standard overcurrent relay:

Where: TMS = time multiplier setting


Ifault
I =( )
r Iprimary

Anda mungkin juga menyukai