ANALISA HARGA SATUAN PEKERJAAN PENUTUP BESI & ALLUMINIUM

HARGA
No. URAIAN SAT VOLUME HARGA
SAT
(Rp) (Rp)
K-01 1 Kg Besi profil
– Besi profil WF Kg 1.1000 24,000.00 26,400.00
– Meni besi Kg 0.0800 30,400.00 2,432.00
– Pekerja Oh 0.0600 42,000.00 2,520.00
– Tukang besi Oh 0.0060 65,000.00 390.00
– Kepala tukang Oh 0.0060 75,000.00 450.00
– Mandor Oh 0.0003 80,000.00 24.00
Jumlah 32,216.00
Dibulatkan 32,216.00
K-02 1 Kg Perakitan baja
– Solar m’ 0.0100 7,150.0000 71.50
– Minyak pelumas m’ 0.0010 55,000.0000 55.00
– Sewa alat jam 0.0080 100,000.0000 800.00
– Pekerja Oh 0.0010 42,000.0000 42.00
– Tukang besi Oh 0.00001 65,000.0000 0.65
– Kepala tukang Oh 0.00001 75,000.0000 0.75
– Mandor Oh 0.00005 80,000.0000 4.00
Jumlah 973.90
Dibulatkan 974.00
K-03 1 Cm Pengelasan dengan las listrik
– kawat las kg 0.0400 23,600.00 944.00
– Solar ltr 0.0300 7,150.00 214.50
– Minyak pelumas ltr 0.0040 55,000.00 220.00
– Sewa alat jam 0.0170 100,000.00 1,700.00
– Pekerja org 0.0040 42,000.00 168.00
– Tukang org 0.0020 65,000.00 130.00
– Kepala Tukang org 0.0002 75,000.00 15.00
– Mandor org 0.0002 80,000.00 16.00
Jumlah 2,463.50
Dibulatkan 2,464.00
K-04 1 m2 Pintu Rolling Door
– Rolling door M2 1.0000 306,600.00 306,600.00
– Pekerja Oh 1.0500 42,000.00 44,100.00
– Tukang besi Oh 1.5000 65,000.00 97,500.00
– Kepala tukang Oh 0.1050 75,000.00 7,875.00
– Mandor Oh 0.0052 80,000.00 416.00
Jumlah 456,491.00
Dibulatkan 456,491.00
K-05 1 m2 Pintu Alluminium Natural
– Pintu alluminium natural m2 1.0000 211,800.00 211,800.00
– Pekerja Oh 1.0500 42,000.00 44,100.00
– Tukang besi Oh 1.0500 65,000.00 68,250.00
– Kepala tukang Oh 0.1050 75,000.00 7,875.00
– Mandor Oh 0.0052 80,000.00 416.00
Jumlah 332,441.00
Dibulatkan 332,441.00
K-06 1 m2 Terali Besi
– Besi strip 2 x 3 m’ 11.5000 5,500.00 63,250.00
– Pekerja Oh 1.2000 42,000.00 50,400.00
– Tukang las Oh 1.2000 65,000.00 78,000.00
– Kepala tukang Oh 0.0120 75,000.00 900.00
– Mandor Oh 0.0006 80,000.00 48.00
Jumlah 192,598.00
Dibulatkan 192,598.00
K-07 1 m2 Kawat Harmonika 4 cm
– Kawat harmonika M2 1.1000 35,900.00 39,490.00
– Paku biasa ½” – 1″ kg 0.0200 23,800.00 476.00
– Papan kayu kamper M2 0.0018 5,692,600.00 10,246.68
– Pekerja Oh 0.1000 42,000.00 4,200.00
– Tukang kayu Oh 0.1000 65,000.00 6,500.00
– Kepala tukang Oh 0.0100 75,000.00 750.00
– Mandor Oh 0.0050 80,000.00 400.00
Jumlah 62,062.68
Dibulatkan 62,063.00
K-08 1 m’ Talang Datar, Seng BJLS 28 lebar 90 cm
– Seng plat 3′ x 6′ BJLS 30 m’ 1.0500 20,801.00 21,841.05
– Paku biasa ½” – 1″ Kg 0.0150 23,800.00 357.00
– Kayu papan borneo super M3 0.0096 5,595,800.00 53,719.68
– Flincote / meni besi Kg 0.2500 30,400.00 7,600.00
– Pekerja Oh 0.1500 42,000.00 6,300.00
– Tukang kayu Oh 0.4000 65,000.00 26,000.00
– Kepala tukang Oh 0.0250 75,000.00 1,875.00
– Mandor Oh 0.0013 80,000.00 104.00
Jumlah 117,796.73
Dibulatkan 117,797.00
K-09 1 m’ Talang Miring, Seng BJLS 28 lebar 90 cm
– Seng plat 3′ x 6′ BJLS 30 m’ 1.0500 20,801.00 21,841.05
– Paku biasa ½” – 1″ Kg 0.0150 23,800.00 357.00
– Kayu papan borneo super M3 0.0190 5,595,800.00 106,320.20
– Flincote / meni besi Kg 0.3000 30,400.00 9,120.00
– Pekerja Oh 0.2000 42,000.00 8,400.00
– Tukang kayu Oh 0.4000 65,000.00 26,000.00
– Kepala tukang Oh 0.0250 75,000.00 1,875.00
– Mandor Oh 0.0013 80,000.00 100.00
Jumlah 174,013.25
Dibulatkan 174,013.00
K-10 1 m’ Talang 1/2 lingkaran D-15 cm, seng pelat BJLS 28 lebar 90 cm
– Seng plat 3′ x 6′ BJLS 30 m’ 1.0500 20,801.00 21,841.05
– Paku biasa ½” – 1″ Kg 0.1000 23,800.00 2,380.00
– Kayu papan borneo super kg 0.0190 5,595,800.00 106,320.20
– Besi strip Kg 0.5000 26,800.00 13,400.00
– Pekerja Oh 0.1500 42,000.00 6,300.00
– Tukang kayu Oh 0.3000 65,000.00 19,500.00
– Kepala tukang Oh 0.0300 75,000.00 2,250.00
– Mandor Oh 0.0080 80,000.00 640.00
Jumlah 172,631.25
Dibulatkan 172,631.00
K-11 1 m’ Pasang kusen pintu/jendela alluminium natural 4″
– Alumunium profil natural 4″ m’ 1.1000 151,100.00 166,210.00
– Skrup fixer bh 2.0000 250.00 500.00
– Sealant m’ 1.0000 7,500.00 7,500.00
– Pekerja Oh 0.0430 42,000.00 1,806.00
– Tukang kayu Oh 0.0430 65,000.00 2,795.00
– Kepala tukang Oh 0.0043 75,000.00 322.50
– Mandor Oh 0.0021 80,000.00 168.00
Jumlah 179,301.50
Dibulatkan 179,302.00
K-12 1 m’ Pasang kusen pintu/jendela alluminium warna 4″
– Alumunium profil warna 4″ m’ 1.1000 163,000.00 179,300.00
– Skrup fixer bh 2.0000 250.00 500.00
– Sealant m’ 1.0000 7,500.00 7,500.00
– Pekerja Oh 0.0430 42,000.00 1,806.00
– Tukang kayu Oh 0.0430 65,000.00 2,795.00
– Kepala tukang Oh 0.0043 75,000.00 322.50
– Mandor Oh 0.0021 80,000.00 168.00
Jumlah 192,391.50
Dibulatkan 192,392.00
K-13 1 m’ Pasang kusen pintu/jendela alluminium natural 3″
– Alumunium profil natural 3″ m’ 1.1000 81,000.00 89,100.00
– Skrup fixer bh 2.0000 250.00 500.00
– Sealant m’ 1.0000 7,500.00 7,500.00
– Pekerja Oh 0.0430 42,000.00 1,806.00
– Tukang kayu Oh 0.0430 65,000.00 2,795.00
– Kepala tukang Oh 0.0043 75,000.00 322.50
– Mandor Oh 0.0021 80,000.00 168.00
Jumlah 102,191.50
Dibulatkan 102,192.00
K-14 1 m’ Pasang kusen pintu/jendela alluminium warna 3″
– Alumunium profil warna 3″ m’ 1.1000 102,000.00 112,200.00
– Skrup fixer bh 2.0000 250.00 500.00
– Sealant m’ 1.0000 7,500.00 7,500.00
– Pekerja Oh 0.0430 42,000.00 1,806.00
– Tukang kayu Oh 0.0430 65,000.00 2,795.00
– Kepala tukang Oh 0.0043 75,000.00 322.50
– Mandor Oh 0.0021 80,000.00 168.00
Jumlah 125,291.50
Dibulatkan 125,292.00
K-15 1 m2 Pintu alluminium strip lebar 8 cm
– Alumunium profil 4″ natural m’ 4.4000 151,100.00 664,840.00
– Alumunium strip 6mm m2 1.0500 171,800.00 180,390.00
– Pekerja Oh 0.0850 42,000.00 3,570.00
– Tukang kayu Oh 0.0850 65,000.00 5,525.00
– Kepala tukang Oh 0.0085 75,000.00 637.50
– Mandor Oh 0.0042 80,000.00 336.00
Jumlah 855,298.50
Dibulatkan 855,299.00
K-16 1 m2 Pintu/jendela kaca rangka alluminium natural 4″
– Alumunium profil natural 4″ m’ 4.4000 151,100.00 664,840.00
– Profil alluminium T m’ 4.5000 12,200.00 54,900.00
– Sealant tube 0.2700 7,500.00 2,025.00
– Pekerja Oh 0.0850 42,000.00 3,570.00
– Tukang kayu Oh 0.0850 65,000.00 5,525.00
– Kepala tukang Oh 0.0085 75,000.00 637.50
– Mandor Oh 0.0050 80,000.00 400.00
Jumlah 731,897.50
Dibulatkan 731,898.00
K-17 1 m2 Pintu/jendela kaca rangka alluminium warna 4″
– Alumunium profil warna 4″ m’ 4.4000 163,000.00 717,200.00
– Profil alluminium T m’ 4.5000 12,200.00 54,900.00
– Sealant tube 0.2700 7,500.00 2,025.00
– Pekerja Oh 0.0850 42,000.00 3,570.00
– Tukang kayu Oh 0.0850 65,000.00 5,525.00
– Kepala tukang Oh 0.0085 75,000.00 637.50
– Mandor Oh 0.0050 80,000.00 400.00
Jumlah 784,257.50
Dibulatkan 784,258.00
K-18 1 m2 Jendela nako & teralis (10 klips)
– Jendela nako (rangka + kaca 5 mm) m2 1.1000 300,000.00 330,000.00
– Paku skrup 1cm – 2,5cm bh 10.0000 250.00 2,500.00
– Besi strip m’ 7.0000 5,500.00 38,500.00
– Pekerja Oh 0.2000 42,000.00 8,400.00
– Tukang kayu Oh 0.2000 65,000.00 13,000.00
– Kepala tukang Oh 0.0200 75,000.00 1,500.00
– Mandor Oh 0.0010 80,000.00 80.00
Jumlah 393,980.00
Dibulatkan 393,980.00
K-19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja siku
– Besi siku L 30.30.3 Kg 15.0000 24,000.00 360,000.00
– Baja pelat Kg 32.8000 24,000.00 787,200.00
– kawat las Kg 0.0500 23,600.00 1,180.00
– Pekerja Oh 0.2000 42,000.00 8,400.00
– Tukang kayu Oh 0.2000 65,000.00 13,000.00
– Kepala tukang Oh 0.0200 75,000.00 1,500.00
– Mandor Oh 0.0010 80,000.00 80.00
Jumlah 1,171,360.00
Dibulatkan 1,171,360.00
K-20 1 m2 Rangka jendela besi square tube (5 x 5) cm
– Besi square tube M 4.7600 7,300.00 34,748.00
– Besi lis kaca (1 x 1) cm Kg 4.5220 24,000.00 108,528.00
– Pengelasan Cm 20.0000 2,464.00 49,280.00
– Pekerja Oh 0.6500 42,000.00 27,300.00
– Tukang kayu Oh 0.6500 65,000.00 42,250.00
– Kepala tukang Oh 0.0650 75,000.00 4,875.00
– Mandor Oh 0.0320 80,000.00 2,560.00
Jumlah 269,541.00
Dibulatkan 269,541.00
K-21 1 m2 Pintu lipat (folding door) bahan besi
– Pintu lipat M2 1.0000 501,700.00 501,700.00
– Pekerja Oh 1.0500 42,000.00 44,100.00
– Tukang kayu Oh 1.0500 65,000.00 68,250.00
– Kepala tukang Oh 0.1050 75,000.00 7,875.00
– Mandor Oh 0.0052 80,000.00 416.00
Jumlah 622,341.00
Dibulatkan 622,341.00
K-22 1 m2 Tirai (venetions blinds and vertical blinds)
– Tirai M2 1.0000 537,300.00 537,300.00
– Pekerja Oh 0.3500 42,000.00 14,700.00
– Tukang kayu Oh 0.3500 65,000.00 22,750.00
– Kepala tukang Oh 0.0350 75,000.00 2,625.00
– Mandor Oh 0.0018 80,000.00 144.00
Jumlah 577,519.00
Dibulatkan 577,519.00

Oleh karena analisa AHS-SNI tahun 2011, maka harga satuan bahan dan upah perlu diubah
dengan harga satuan terbaru 2014, kalau koefisiennya (kolom 5) sama saja dari tahun 2007