Time Schedule & Laporan Ha

No. Jenis Pekerjaan Harga Bobot (%)


1
S SE
1 Membobok Tembok Rp280,000.00 8.79 2.93 2.93
2 Pemipaan Rp465,000.00 14.60
3 Penarikan Kabel Rp415,600.00 13.05

4 Rp555,000.00 17.42
Pemasangan Komponen Listrik
5 Instalasi Rp1,335,000.00 41.91
6 Uji Coba Rangkaian Rp135,000.00 4.24

Total Harga Rp3,185,600.00


Total Bobot (%) 100.00 2.93 2.93
Bobot Rencana Komulatif (%) 2.93 5.86
Bobot Realisasi Komulatif (%) 2.93 3.00
Selisih (%) 0.00 2.86
Time Schedule & Laporan Harian Pelaksanaan Proyek Sangsangg Villa and HomeStay

Waktu Pelaksanaan
Minggu Ke
1 2 3
R K J S SE R K J S SE R
2.93
2.43 2.43 2.43 2.43 2.43 2.43
2.61 2.61 2.61 2.61 2.61

3.48 3.48 3.48 3.48

6.98

5.36 2.43 2.43 2.43 5.04 5.04 2.61 6.09 6.09 3.48 10.47
11.22 13.66 16.09 18.52 23.56 28.60 31.21 37.31 43.40 46.89 57.35
10.00 12.00 15.00 18.52 23.56 28.60 32.21 38.20 44.40
1.22 1.66 1.09 0.00 0.00 0.00 -1.00 -0.89 -1.00
angg Villa and HomeStay

Waktu Pelaksanaan
Minggu Ke
%
3 4
K J S SE R K J
100%

3.48 50%

6.98 6.98 6.98 6.98 6.98


1.41 1.41 1.41
0%

10.47 6.98 6.98 6.98 8.40 1.41 1.41


67.82 74.81 81.79 88.78 97.17 98.59 100.00