Research Administrator Test Lane 4-1 Test Lane 4-2 Test Lane 4-3
(225)767-9124 Standard Construction Cement Treated Base Foamed Asphalt Base
Cement Treated Base Cement Treated Subbase Cement Treated Subbase
Lime Treated Working Table
LTRC 2.0” Asphalt pavement 2.0” Asphalt pavement 2.0” Asphalt pavement
8.5” Cement Treated Recycled 8.5” Cement Treated Recycled 8.5” Foamed Recycled Cement
Louisiana Cement Stabilized Base (6%) Cement Stabilized Base (6%) Stabilized Base
Transportation Research Center
12” Lime Treated (10%) 12” Cement Treated (5%) 12” Cement Treated (5%)