PETROCHEMICAL COMPANY
Jubail Export Refinery Project
M. R. Al-Khathlan Contract No. 3000235436, Auxiliary Utilities (Package 5C)
CONSTRUCTION QUALITY PLAN
1 Purpose
2 Scope
QA - Quality Assurance
QC - Quality Control
QAM - Quality Assurance Manager
QCM - Quality Control Manager
PC - Planning Control
4 References
5 Responsibilities
5.2 The project’s site safety officers assigned for the project shall be
responsible for the development, implementation and maintenance of
MRK's safety policy and plan throughout the project execution activities.
He shall coordinate with the Project Engineer and Site Foremen and
multicasts crew deployed under the project for its successful
implementation.
5.5 The QA/QC Manager shall directly coordinate with the Project Manager
for the execution of all quality activities with the same level of authority.
5.6 The QA/QC Manager shall review all quality related documents, material
certificates and non conformances prior to taking any action.
5.7 The QA/ QC Manager and QC Supervisors shall review all Request for
Inspection (RFI) forms from various QC Discipline Inspectors and make a
summary report daily basis.
5.9 The Instrumentation QC Inspector shall carry out inspections and shall
release hold points by signing various quality records as a documentary
evidence of inspection conforming to specifications.
5.10 The site Foremen (Instrumentation) and safety officer shall jointly and
severely be responsible for the observance of all safety precautions
required by MRK's safety plan and wherever applicable to the
manufacturer’s safety indications.
5.11 The Instrumentation and Electrical QC Inspectors shall ensure that the
cable splicing and termination work is carried out as per manufacturer's
instructions. He shall be responsible for all documentations, test
reports, material certificates and non-conformance reports.
6 Safety
6.1 The assigned safety officer shall ensure that the work permit is obtained
prior to starting any work, if it is applicable.
6.2 Safety officer shall ensure that all personnel protective equipments (PPE)
are made available with all crafts as per the required standard and
specifications.
6.3 For higher voltage cable testing a person shall be stationed at any point
where the test item is accessible to unauthorized persons. Barriers shall
be erected and signs must be posted to be read as:
6.4 All Instrumentation and electrical cables and equipments ends shall be
guarded against accidental contact and shall be separated from all ends
or elements not subjected to testing.
7 Work Procedure
7.1 General
The quality plan for Instrumentation shall address all the prescriptions
related to the construction practice, particularly the installation,
interconnections and system integration issues.
7.2.2 Symbols
• Each field and control room instruments shall have a name plate
showing the identification tag number, other instruments such as
switches, fuses, terminal strips and assorted accessories. The control
panels and cabinets shall be appropriately identified by means of
nameplates and/or tag numbers.
The pressure gauges for steam services shall be equipped with siphon
tube. The takeoff point shall not be located near the pressure regulators,
valves etc., which tend to cause turbulence.
The orifice type flow meters shall not be installed on vertical piping, but
vertical orifice runs may be allowed, where necessary, on non-flushing
liquids, gas and steam
7.4.5 Analyzers
2) Flow signals originating from direct reading flow meters such as vortex
shedding meters shall be simulated by transmitter junction box and
injecting a 4-20 milliamp signal in the output leads.
The power output signal from the control room shall be verified and to be
present and correct at the transmitters.
7.4.12 For the loop check a 4-20 milliamp signal shall be injected at the
transmitter attached junction box to verify the signal integrity.
Upon recognition, indication of ambient temperature shall be
verified.
7.4.14 Alarm states for the process variables shall be verified if specified
for the loop under check, including pre-alarm, alarm and return
from alarm values.
b) Miscellaneous Inputs
These are loops that will be verified with the assistance of a vendor
representative and include items such as analyzers and machinery protection
equipment.
c) Process Output
1) Motors
1. AOV’s and ZV’s shall be operated from the push buttons at control
room console where applicable and the local push buttons. ESD
interlocks of these valves shall be verified.
3. All local and control room alarm indication shall be verified for
both operation and closed states, including ESD alarms and
bypass switches where applicable.
f) Local Loops
This section includes the supply and installation of the fire alarm panel
and devices. The fire alarm initiating devices are associated with the
cabling and conduit installation, etc. The instillation processes shall be
in accordance with NEC, NFPA and local codes as shown in the
drawings.
• All works performed and all material supplied under this section shall be
free from defects and will remain so for a period of at least one year from
the date of acceptance.
7.6.1 Wiring
• Wire tagging and terminations shall be checked and "tug" tested (A tug
test involves physically stressing a wire termination to determine
whether it has been crimped and terminated properly. The intent is not
to break wiring or stress insulation but to test the integrity of the
termination).
The fiber optic cables (FOC) route for all new cables shall be approved by
SATORP prior to start the trenching and cabling works. Cable routing
shall be done in accordance with the requirements of JERES-T-624.
All buried and above ground cables route shall be marked in accordance
with SATORP standard drawing AA-036897. The maximum attenuation
of each fiber within cable when normalize to a length of 1 Km at wave
length=1.300NMshall be 0.5 db/KM or less at wave length = 1550NM
shall be 0.3db/KM or less as per table-4 of JERES-T-634.
a) Shall be 10 times the cable diameter, when the cable is not under
tension as per the requirements of JERES-T-624 Para 5.1.10.
b) Shall be 20 times the cable diameter, when the cable is under tension as
per the requirement of JERES-T-624 Para 5.1.10.
c) Pulling tension on fiber optic cables shall not exceed 600 pounds as per
the requirement of JERES-T-624 Para 5.1.11.
d) Cable should be pulled in a straight line and never bend and wrapped.
a) End to end testing shall be carried out on all outside planned fiber optic
cables facilities.
c) On reel acceptance tests by the approved testing agency, reel test report
shall be submitted to SATORP PMT/PID for their review and record.
9.1 All checks will be accepted only if the verification of correct responses or
resultant signal has been in existence during simulation or actuation
period.
9.2 The client witness and/or authorized representative shall issue final
acceptance of instrument loops being checked by signing-off on space
provided on the instrument loop check report form/checklist.
9.3 All devices not proper signal setting shall be-calibrated or adjusted
accordingly to the normal settings conditions. The defective and/or
damaged instruments and devices shall be replaced by calibrated and
tested units.
10 Records