METHOD STATEMENT
TABLE OF CONTENTS
1.0 Purpose 3
4.0 Responsibilities 4
5.0 Procedure 5
8.0. Attachments 7
1.0 PURPOSE
The purpose of this Method of Statement is to provide a proper guidelines for
Pressure and leak test of Air line and impulse tubing to insure mechanical integrity of
of system at shaybah NGL Recovery and Utilities project, Pkg#2.
4.0 RESPONSIBILITIES
4.1 Construction Manager
4.1.1 Construction Manager shall be responsible for the over-all direction, monitoring and
control of all the activities related to Pressure and Leak Test for Air Line and Impulse tubing.
4.1.2 Construction Manager shall ensure that Field Supervisor effectively implement
within this Method Statement and related applicable project documents.
4.1.3 Constructions Manager shall be responsible for providing enough manpower as
per construction and Testing schedule.
4.3 QC Manager
4.3.1 QC Manager has the overall responsibility for all QC activities of the project.
He shall be interacting with Construction Manager related to all QC activities.
4.3.2 QC Manager shall be responsible for the control and compliance with design
drawings and specifications for Pressure and leak test of Air Line and impulse tubing
before and during the operation.
4.4 QC Inspectors
4.4.1 QC Inspector shall be responsible for the QC activities, material control and
traceability, non - conformance management and compilation of Pressure and Leak
Test of Air Line and impulse tubing.
Doc No : SJ-NGL2-MS-0027
METHOD STATEMENT Rev : 1
LEAK TEST FOR AIR LINE AND Date : 05. June. 2014
IMPULSE TUBING
Page : 05 of 07
5.0 PROCEDURE
5.1.2 Necessary and required test equipment, instruments, Pressure gauges and accessories shall
be made available to facilitate performance of test.
5.1.3 All instrument sub-headers and branch system piping, instrument transmission lines shall
be blown free of dirt or scales using clean, oil free, dry plant instrument air or dry bottled
nitrogen prior to testing.
5.1.5 Leaking fittings, pipe or tubing shall be repaired or replaced as required to provide system
integrity.
5.1.6 After repair the piping system involved shall be re tested until integrity is demonstrated.
5.2 Air Line Leak Test
5.2.1 Instrument Airline to be tested as per SAES-L-150 using the Dry Instrument air or Nitrogen.
Instrument air may be tested at its operating pressure as required by SAES-L-150.
Doc No : SJ-NGL2-MS-0027
METHOD STATEMENT Rev : 0
LEAK TEST FOR AIR LINE AND Date : 13. May. 2014
IMPULSE TUBING
Page : 06 of 07
5.2.2 Disconnect all air consuming pilots, if any, from the section of tubing to be tested.
5.2.3 Connect the Airline to Instrument Air supply system. Dry air to be used for testing the
Lines. 1
5.2.4 Open air supply valve slowly and pressurize air line to operating pressure of instrument
air supply system.
5.2.5 When the system has been fully pressurized it shall be held for Thirty (30) minutes and
checked for leakage at each joint using bubble solution or soap solution. 1
5.2.6 No alteration to Air Line should be attempted until air supply has been isolated and air line
De-Pressurized.
5.2.7 Any observed leakage shall be corrected and a re-test of the system shall be carried out
until a satisfactory result is obtained.
5.2.8 For connection to existing Instrument air lines manufacturers installation procedures for
fitting shall be followed and a GAP inspection gauge used to verify proper make up of
tube connectors.
5.2.9 All new tube connection shall be visually inspected after change over for any leakage.
5.3.4 A preliminary check at not more than 25% of operating pressure shall be made with the
supplying manifold valve closed to permit examination for leaks by observing pressure
gauge used in the test.
5.3.5 The test pressure shall then be increased to full test pressure and shall be held for at least
thirty (30) minutes with supplying manifold valve closed to permit examination for leaks by
observing pressure gauge used in the test.
5.3.5 Leaks, which cause the test pressure to decrease more than one graduation on test gauge
during the holding period, shall not be acceptable.
5.3.6 For connection to existing process tubing during cut over manufacturer installation
procedure for the correct make up of tube connectors shall be followed, a GAP inspection
gauge shall be used to verify proper makeup of fitting. All new tube connection shall also
be visually inspected after change over for leakage.
Doc No : SJ-NGL2-MS-0027
METHOD STATEMENT Rev : 1
LEAK TEST FOR AIR LINE AND Date : 05. June. 2014
IMPULSE TUBING
Page : 07 of 07
6.3 Every test conducted shall be recorded on applicable checklist and shall be signed off by
Subcon, Contractor and Company Quality Representative.
8 Attachments
8.1 Test Manifold Diagram Fig.1
8.2 Job Safety Analysis
SN Material Description Quantity Remarks
1 Pressure/Leak Test Manifold 1
2 Pressure Guage 5 Check Pressure Range
3 PRV 5 Check pressure Range
4 High Pressure Tubing 100 Mtr Check Max pressure
5 Tube Fitting 10 Each Check Type n Size
6 Tafelone Tape 50
7 GAP inspection Gauge 2 Verify size from Hook up.
8 Open Spanner 4 Set Check Size
9 Snoop for Leak Detector 20 bottle