Anda di halaman 1dari 58

Chapter 8 Operations Scheduling

Professor JIANG Zhibin

Based on: POA Steven Nahmias


Chapter 8 Operations Scheduling

Contents
Introduction
Job Shop Scheduling Terminology
Sequencing Rules
Sequencing Theory for a Single Machine
Sequencing Theory for Multiple Machines
Assembly Line Balancing
Advanced Topics for Operations scheduling
Introduction-What is Operations Scheduling ?
Forecast of future demand
 Implement the production
orders generated in MRP under
given objectives ; Aggregate plan
 Allocate production resources
(machine, workers et al.) to
production orders (jobs or tasks Master production schedule (MPS)
and their due dates) in an Schedule of production quantities by
optimized manners; products and time period
 The results are time allocations
of production resources to Material Requirement Planning (MRP)
different jobs (job sequences on Generate Production orders and
each production resources); purchase order
 All the orders can be completed
while all production resources Operations Scheduling
are utilized with their loads To meet quantities and time
being balanced. requirements for MRP
Introduction-Objectives of Job Shop Scheduling

 Objectives of operations scheduling


1) Meet due date;
2) Minimize WIP inventory;
3) Minimize the average flow time through the systems;
4) Provide for high machine/worker (time) utilization (minimize idle
time);
5) Reduce setup cost;
6) Minimize production and worker costs

Discussion
1) and 3) aim at providing a high level of costumer service;
 2), 4), 5) and 6) are to provide a high level of plant efficiency;
Impossible to optimize all above objectives simultaneously;
 Proper trade off between cost and quality is one of the most
challenging strategic issues facing a firm today;
Introduction-Objectives of operations Scheduling

Discussion (Cont.)
Some of these objectives conflicts, e.g.
Reduce WIP inventory  Worker idle time may increase or
machine utilization may decrease;
Reasons: differences in the throughput rate from one part of
the system to the another may force the faster operations to
wait, if there is no buffer for WIP between 1 and 2 .

Fig 8-3 A Process Composed of Two Operations in Series


Introduction-Functions of Scheduling and Control is SF

 The following functions must be performed in scheduling


and control a shop floor
Allocating orders, equipments, and personnel to work
centers or other specified location-Short term capacity
planning;
Determining the sequence of orders (i. e. job priorities);
Initializing performance of the scheduled work,
commonly termed the dispatching of jobs;
Shop-floor control, involving
Reviewing the status and controlling the progress of
orders as they are being worked on;
Expediting the late and critical orders;
Revising the schedules in light of changes in order
status.
Introduction-Elements of the Shop Floor Scheduling Problems

 The classic approaches to shop floor scheduling focuses on the


following six elements
 1. Job arrival patterns: static or dynamic
Static: jobs arrive in batch;
Dynamic: jobs arrive over time interval according to
some statistical distribution.
 2. Numbers and variety of machines in the shop floor
If there is only one machine or if a group of machines can
be treated as one machine, the scheduling problem is much
more simplified;
As number of variety of machines increase, the more
complex the scheduling problems is likely to become.
Introduction-Elements of the Shop Floor Scheduling Problems

 The classic approaches to job shop scheduling focuses on


the following six elements (cont.)
 3. Ratio of workers to machines
Machine limited system: more workers than
machine or equal number workers and machines;
Labor-limited system: more machines than worker.
 4. Flow pattern of jobs: flow shop or job shop
Flow shop: all jobs follow the same paths from one
machine to the next;
Job shop: no similar pattern of movement of jobs
from one machine to the next.
Introduction-Elements of the Job Shop Scheduling Problems

Flow shop:
 Each of the n jobs
must be processed
through the m
machines in the
same order.
 Each job is
processed exactly
once on each
machine.

An assembly line is a classic example of flow shop


 Every cars go through all the stations one by one in the same sequences;
 Same tasks are performed on each car in each station;
 Its operations scheduling is simplified as assembly line balancing;
 An assembly balancing problem is to determine the number of stations and to
allocate tasks to each station.
Introduction-Job Shop

Drilling Center
Turnning Center

Grinding Center Milling Center

A job shop is organized by machines which are grouped


according to their functions.
Introduction-Job Shop

Work Center 2
Work Center 1

Job A

Work Center 4 Work Center 3


Job B

 Not all jobs are assumed to require exactly the same number of operations,
and some jobs may require multiple operations on a single machine
(Reentrant system, Job B twice in work center 3 ).
 Each job may have a different required sequencing of operations.
 No all-purpose solution algorithms for solving general job shop problems ;
 Operations scheduling of shop floor usually means job shop scheduling;
Introduction-Elements of the Shop Floor Scheduling Problems

 The classic approaches to shop floor scheduling focuses on


the following six elements (cont.)
 5. Job sequencing
Sequencing or priority sequencing: the process of determining
which job is started first on some machines or work center by
priority rule;
Priority rule: the rule used in obtaining a job sequencing;

 6. Priority rule evaluation criteria


To meet corresponding objectives of scheduling;
Common standard measures
Meeting due date of customers or downstream operations;
Minimizing flow time (the time a job spends in the shop
flow);
Minimizing WIP;
Minimizing idle time of machines and workers (Maximizing
utilization).
Job Shop Scheduling Terminology

1. Parallel processing versus sequential processing


 Sequencing Processing: the m machines are distinguishable, and
different operations are performed by different machines.
 Parallel processing: The machines are identical, and any job can be
processed on any machine.
Job A
M1 M2 Job A
M1 M2

Job B
M3 M4 Job B
M3 M4
 M1, M2, M3, and M4 are different;
 Job A has 2 operations which should
be processed on different Machines:  M1, M2, M3, and M4 are
M1and M2; identical;
 Job B has 3 operations which should  Jobs A and B can be processed
be processed on different Machines: on any one of the 4 machines
M3, M2 and M4;
Job Shop Scheduling Terminology
2. Flow time
 The flow time of job i is the time that elapses from the initiation of
the first job on the first machine to the completion of job i.
 The mean flow time, which is a common measure of system
performance, is the arithmetic average of the flow times for all n
jobs
Machines Mean Flow Time=(F1+F2+F3)/3

M1 Job 1 Job 2 Job 3

M2 Job 1 Job 2 Job 3

F1: FT of Job Time


1
F2: FT of Job 2

F3: FT of Job 3
Job Shop Scheduling Terminology
3. Make-span
 The make-span is the time required to complete a group of jobs (all n
jobs).
 Minimizing the make-span is a common objective in multiple-
machine sequencing problems.

Machines

M1 Job 1 Job 2 Job 3

M2 Job 1 Job 2 Job 3

F1: FT of Job 1 Time


F2: FT of Job 2

F3: FT of Job 3
Make-span of the 3 jobs
Job Shop Scheduling Terminology
3. Make-span
 The make-span is the time required to complete a group of jobs (all n
jobs).
 Minimizing the make-span is a common objective in multiple-
machine sequencing problems.
Machines

M1 Job 1 Job 2 Job 3

M2 Job 1 Job 2 Job 3

Wating time Job 2 Time


Waiting time Job 2

Idle time machine 2


Job Shop Scheduling Terminology
4. Tardiness and lateness
 Tardiness is the positive difference between the completion time and the
due date of a job.
 Lateness refers to the difference between the job completion time and its
due date and differs from tardiness in that lateness can be either positive
or negative.
 If lateness is positive, it is tardiness; when it is negative, it is earliness
Tardiness Completion
Due date of Job i time of Job i
of Job i Lateness>0---
Tardiness

Completion Due date


Lateness<0---
time of Job i of Job i Earliness

When the completion of Job is earlier than due date, the tardiness is 0
Sequencing Rules

FCFS (first come-first served)


 Jobs are processed in the sequence in which they entered the shop;
 The simplest and nature way of sequencing as in queuing of a bank

SPT (shortest processing time)


 Jobs are sequenced in increasing order of their processing time;
 The job with shortest processing time is first, the one with the next
shortest processing time is second, and so on;

EDD (earliest due date)


 Jobs are sequenced in increasing order of their due dates;
 The job with earliest due date is first, the one with the next earliest due
date is second, and so on;
Sequencing Rules

CR (Critical ratio)
 Critical ratio is the remaining time until due date divided by processing
time;
 Scheduling the job with the shortest CR next;
Current time Remaining time of Job i Due date of Job i

Processing time of Job i

CRi=Remaining time of Job i/Processing time of Job i


=(Due date of Job i-current time)/Processing time of Job i

CR provides the balance between SPT and EDD, such that the task with
shorter remaining time and longer processing time takes higher priority;
CR will become smaller as the current time approaches due date, and more
priority will given to one with longer processing time..
For a job, if the numerator of its CR is negative ( the job has been already
later), it is naturally scheduled next;
If more jobs are later, higher priority is given to one that has shorter
processing time (SPT).
Sequencing Rules
Example 8.1
 A machine center in a job shop for a local fabrication company has five
unprocessed jobs remaining at a particular point in time. The jobs are labeled
1, 2, 3, 4, and 5 in the order that they entered the shop. The respective
processing times and due date are given in the table below.
Sequence the 5 jobs by above 4 rules and compare results based on mean
flow time, average tardiness, and number of tardy jobs

Job number Processing Time Due Date

1 11 61
2 29 45
3 31 31
4 1 33
5 2 32
Sequencing Rules——FCFS

Job number Processing Time Due Date

1 11 61
2 29 45
3 31 31
Mean Flow time=268/5=53.6
4 1 33
Average tardiness=121/5=24.2
5 2 No. of tardy jobs=3. 32

Job Completion Time Due Date Tardiness


1 11 61 0
2 40 45 0
3 71 31 40
4 72 33 39
5 74 32 42
Totals 268 121
Sequencing Rules——SPT

Job number Processing Time Due Date

1 11 61
2 29 45
3 31 31
Mean Flow time=135/5=27.0
4 1 33
Average tardiness=43/5=8.6
5 2 32
No. of tardy jobs=1.

Job Processing Time Completion Time Due Date Tardiness


4 1 1 33 0
5 2 3 32 0
1 11 14 61 0
2 29 43 45 0
3 31 74 31 43
Totals 135 43
Sequencing Rules——EDD

Job number Processing Time Due Date

1 11 61
2 29 45
3 31 31
Mean Flow time=235/5=47.0
4 1 33
Average tardiness=33/5=6.6
5 2 32
No. of tardy jobs=4.

Job Processing Time Completion Time Due Date Tardiness


3 31 31 31 0
5 2 33 32 1
4 1 34 33 1
2 29 63 45 18
1 11 74 61 13
Totals 235 33
Sequencing Rules——CR

Current time: t=0


Job number Processing Time Due Date Critical Ratio
1 11 61 61/11(5.545)
2 29 45 45/29(1.552)
3 31 31 31/31(1.000)
4 1 33 33/1 (33.00)
5 2 32 32/2 (16.00)
Current time should be reset after scheduling one job
Current time: t=31
Job number Processing Time Due Date-Current Time Critical Ratio
1 11 30 30/11(2.727)
2 29 14 14/29(0.483)
4 1 2 2/1 (2.000)
5 2 1 1/2 (0.500)
Sequencing Rules——CR

Current time=60 Mean Flow time=289/5=57.8


Average tardiness=87/5=17.4
Job number Processing Time DueNo.
Date- Critical Ratio
of tardy jobs=4.
Current Time
1 11 1 1/11(0.0909)
4 1 -27 -27/1<0
5 2 -28 -28/2<0

Both Jobs 4 and 5 are later, however Job 4 has shorter processing time
and thus is scheduled first;
Job number Processing Time Completion Tardiness
Time
3 31 31 0
2 29 60 15
4 1 61 28
5 2 63 31
1 11 74 13
Totals 289 87
Sequencing Rules——Summary

Rule Mean Flow Time Average Number of


Tardiness Tardy Jobs

FCFS 53.6 24.2 3


SPT 27.0 8.6 1
EDD 47.0 6.6 4
CR 57.8 17.4 4

Discussions
 SPT results in smallest mean flow time;
 EDD yields the minimum maximums tardiness (42, 43, 18, and 31 for
the 4 different rules);
 Always true? Yes!
Sequencing Theory for A Single Machine

Assuming that n jobs are to be processed through one machine.


For each job i, define the following quantities:
 ti=Processing time for job i, constant for job i;
 di=Due date for job i, constant for job i;
 Wi=Waiting time for job i, the amount of time that the job must wait before its
processing can begin.
 When all the jobs are processed continuously, Wi is the sum of the
processing times for all of the preceding jobs;

t1 t2 t3 t4

W4=t1+t2+t3 F4=W4+t4
 Fi=Flow time for job i, the waiting time plus the processing time: Fi= Wi+ ti;
 Li=Lateness of job i , Li= Fi- di, either positive or negative;
 Ti=Tardiness of job i, the positive part of Li, Ti=max[Li,0] ;
 Ei=Earliness of job i, the negative part of Li, Ei =max[- Li,0]
Sequencing Theory for A Single Machine

 Maximum Tardiness T max


 max{ T ,T
1
,...,T n}
2

n
1
 Mean Flow Time  F
'
F n i 1
i

 Suppose that 4 jobs J1, J2, J3, J4 need to be scheduled

 For example a schedule  Written as a permutation of


is J3-J2-J1-J4 integers 1, 2, 3, 4: 3, 2, 1, 4.

 For only a single machine, every schedule can be represented by a


permutation (ordering) of the integers 1, 2, 3, …, n.
 There are totally n! (the factorial of n) different permutations.

 A permutation of integers 1, 2, , n is expressed by [1], [2], ,


[n], which represents a schedule;
 In case of a schedule 3, 2, 1, 4, [1]=3, [2]=2, [3]=1, and [4]=4;
Sequencing Theory for A Single Machines

1. Shortest-Processing-Time Scheduling
 Theorem 5.1 The scheduling rule that minimizes the mean
flow time F’ is SPT
 Suppose a schedule is [1], [2],  [k], [k+1], 
k

F [k ]
 t
i 1
[i ]
[n], the flow time of the job that is scheduled in
position k is given by, say job in position 3:

t[1] (t2) t[2] (t1) t[3] (t4) t[4] (t3)

F[3]=t[1]+t[2]=t2+t1

n n k
1 1
 F   t
'
The mean flow time of all jobs on F n [k ]
n [i ]
i 1 k 1 i 1
the schedule is given by
Sequencing Theory for A Single Machines

1. Shortest-Processing-Time Scheduling
Theorem 5.1 The scheduling rule that minimizes the mean flow time F’ is
SPT
n n k
1 1
 F   t
'
The mean flow time is given by F n [k ]
n [i ]
i 1 k 1 i 1

 The double summation term may By summing down the column
be written in a different form. rather than across the row, we may
Expanding the double summation, rewrite F’ in the form
we obtain
k=1:t[1] ; nt[1]+(n-1)t[2]+…+t[n]
k=2:t[1]+ t[2];
…;
k=n:t[1]+ t[2 +…t[n] Clearly, it is minimized by setting

t [1]
 t[ 2]  ...  t[ n]

SPT sequencing rule: the job with shortest processing time t is set first
Sequencing Theory for A Single Machines

1. Shortest-Processing-Time Scheduling (Cont.)


Corollary 5.1 The following measures are equivalent:
 Mean flow time
 Mean waiting time
 Mean lateness
SPT minimizes mean flow time, mean waiting
time, and mean lateness for single machine
sequencing.
2. Earliest-Due-Date Scheduling: If the objective is to
minimize the maximum lateness, then the jobs should be
sequenced according to their due dates. That is, d[1] d[2]…
d[n].
Sequencing Theory for A Single Machines

3. Minimizing the number of Tardy Jobs: An algorithm from


Moore(1968) that minimizes the number of tardy jobs for the
single machine problem.
 Step1. Sequence the jobs according to the earliest due date to obtain the
initial solution. That is d[1] d[2],…,  d[n];
 Step2. Find the first tardy job in the current sequence, say job [i]. If none
exists go to step 4.
 Step3. Consider jobs [1], [2], …, [i]. Reject the job with the largest
processing time. Return to step2. (Why ?)
 Reason: It has the largest effect on the tardiness of the Job[i].
 Step4. Form an optimal sequence by taking the current sequence and
appending to it the rejected jobs. (Can be appended in any order?)
 Yes, because we only consider the number of tardiness jobs rather
than tardiness.
Sequencing Theory for A Single Machines

Example 8.3
Job 1 2 3 4 5 6
Due date 15 6 9 23 20 30
Processing time 10 3 4 8 10 6

Solution Longest processing time

Job 2 3 1 5 4 6
Due date 6 9 15 20 23 30
Processing time 3 4 10 10 8 6
Completion 3 7 17 27 35 41
time
Sequencing Theory for A Single Machines

Example 8.3 :Solution (Cont.) Longest processing time

Job 2 3 5 4 6
Due date 6 9 20 23 30
Processing time 3 4 10 8 6
Completion time 3 7 17 25 31

Job 2 3 4 6
Due date 6 9 23 30
Processing time 3 4 8 6
Completion time 3 7 15 21

The optimal sequence: 2, 3, 4, 6, 5, 1 or 2, 3, 4, 6, 1, 5. In each case the


number of tardy jobs is exactly 2.
Sequencing Theory for A Single Machines

Precedence constraints: Lawler’s Algorithm


g i ( Fi )  Fi  d i  Li Minimizing maximum
lateness
Objective min max g ( F ) i i
Function 1i  n

g i ( Fi )  max( Fi  d i ,0) Minimizing maximum


tardiness
gi is any non-decreasing function of the flow time Fi

The Algorithm
First schedules the job to be completed last, then the job to be completed
next to last, and so on. At each stage one determines the set of jobs not
required to precede any other. Call this set V. among the set V, choose the
job k that satisfies
g k ( )  min ( g i ( ))
iv

  i 1 t i
n The processing time of the current sequence
Sequencing Theory for A Single Machines

The Algorithm (Cont.)


Consider the remaining jobs and again determine the set of
jobs that are not required to precede any other remaining job.

The value of τ is reduced by tk and the job scheduled next to


last is now determined.

The process is continued until all jobs are scheduled.

Note: As jobs are scheduled, some of the precedence


constraints may be relaxed, so the set V is likely to change at
each iteration.
Sequencing Theory for A Single Machines

Example 8.4

Job 1 2 3 4 5 6
Processing 2 3 4 3 2 1
time
Due date 3 6 9 7 11 7
Sequencing Theory for A Single Machines

Example 8.4
Not predecessor
Step1: find the job scheduled last(sixth)

Job 1 2 3 4 5 6
Processing 2 3 4 3 2 1
time
Due date 3 6 9 7 11 7
3 5 6
τ =2+3+4+3+2+1=15
Tardines 15-9=6 15-11=4 15-7=8
Step2: find the job scheduled fifth s

Not predecessor
Job 1 2 3 4 6
Processing 2 3 4 3 1
time
Due date 3 6 9 7 7
3 6
τ =15-2=13 Tardines 13-9=4 13-7=6
Sequencing Theory for A Single Machines

Example 8.4
Not predecessor
Step3: find the job scheduled fourth

Job 1 2 4 6
Because job3 is no
Processing 2 3 3 1 longer on the list,
time job 2 now because
a candidate.
Due date 3 6 7 7
2 6
τ =13-4=9
Tardines 9-6=3 9-7=2
Step4: find the job scheduled third s
Not predecessor
Because job6 has
Job 1 2 4 been scheduled, so job 4
now because a candidate
Processing 2 3 3 along with job 2.
time
Due date 3 6 7
2 4
τ =9-1=8 Tardines 8-6=2 8-7=1
Sequencing Theory for A Single Machines

Example 8.4
Not predecessor
Step5: find the job scheduled second

Job 1 2
Processing 2 3 The optimal sequence: 1-2-4-6-3-5
time
Due date 3 6

Job Processing Flow Due date Tardiness


time time
1 2 2 3 0
2 3 5 6 0
4 3 8 7 1
6 1 9 7 2
3 4 13 9 4
Maximum
5 2 15 11 4 tardiness
Sequencing Theory for Multiple Machines

Assume that n jobs are to be processed through m


machines. The number of possible schedules is
staggering, even for moderate values of both n and m.
For each machine, there is n! different ordering of the
jobs; if the jobs may be processed on the machines in
any order, there are totally (n!)m possible schedules.
(n=5, m=5, 25 billion possible schedules)
Even with the availability of inexpensive computing
today, enumerating all feasible schedules for even
moderate-sized problems is impossible or, at best,
impractical.
Sequencing Theory for Multiple Machines

Gantt chart
Suppose that two jobs, I and J, are to be scheduled on
two machines, 1 and 2, the processing times are

Machine 1 Machine 2
Job I 4 1
Job J 1 4

Assume that both jobs must be processed first on


machine 1 and then on machine 2. There are four
possible schedules.
Sequencing Theory for Multiple Machines

Schedule Total flow time Mean flow time Mean idle time
1 9 (5+9)/2=7 (4+4)/2=4
2 6 5.5 1
3 10 8 5
4 10 9.5 5
Sequencing Theory for Multiple Machines
1. Scheduling n Jobs on Two Machines
Theorem 8.2 The optimal solution for scheduling n jobs on two machines
is always a permutation schedule.
A very efficient algorithm for solving the two-machine
problem was discovered by Johnson(1954).
 Denote the machines by A and B
 The jobs must be processed first on machine A and then on machine
B.
 Define
 Ai=Processing time of job i on machine A
 Bi=Processing time of job i on machine B
 Rule: Job i precedes job i+1 if min(Ai, Bi-1)<min(Ai+1,Bi)
 List the values of Ai and Bi in two columns.
 Find the smallest remaining element in the two columns. If it
appears in column A, then schedule that job next. If it appears in
column B, then schedule that job last.
 Cross off the jobs as they are scheduled. Stop when all jobs have
been scheduled.
Sequencing Theory for Multiple Machines

Job Machine A Machine B


Example 8.5 1 5 2
2 1 6
3 9 7
4 3 8
5 10 4

Optimal sequence : 2 4 3 5 1
Sequencing Theory for Multiple Machines

2. Extension to Three Machines


 The three-machine problem can be reduced to a two-machine problem if
the following condition is satisfied
min Aimax Bi or min Cimax Bi
It is only necessary that either one of these conditions be satisfied. If that is the
case, then the problem is reduced to a two-machine problem
 Define Ai’=Ai+Bi, Bi’=Bi+Ci
Solve the problem using the rules described above for two-machines,
treating Ai’ and Bi’ as the processing times.
The resulting permutation schedule will be optimal for the three-machine
problem.
If the condition are not satisfied, this method will usually give reasonable,
but possibly sub-optimal results.
Sequencing Theory for Multiple Machines

3. The Two-Job Flow Shop Problem: assume that two jobs are
to be processed through m machines. Each job must be
processed by the machines in a particular order, but the
sequences for the two jobs need not be the same.
 Draw a Cartesian coordinate system with the processing times
corresponding to the first job on the horizontal axis and the processing
times corresponding to the second job on the vertical axis.
 Block out areas corresponding to each machine at the intersection of
the intervals marked for that machine on the two axes.
 Determine a path from the origin to the end of the final block that
does not intersect any of the blocks and that minimizes the vertical
movement. Movement is allowed only in three directions: horizontal,
vertical, and 45-degree diagonal. The path with minimum vertical
distance corresponds to the optimal solution.
Sequencing Theory for Multiple Machines

Example 8.7
A regional manufacturing firm produces a variety of household products. One
is a wooden desk lamp. Prior to packing, the lamps must be sanded, lacquered,
and polished. Each operation requires a different machine. There are currently
shipments of two models awaiting processing. The times required for the three
operations for each of the two shipments are

Job 1 Job2
Operation Time Operation Time
Sanding(A) 3 A 2
Lacquering(B) 4 B 5
Polishing( C ) 5 C 3
Minimizing the flow time is the same as maximizing the time that both jobs are
being processed.that is equivalent to finding the path from the origin to the end of
block C that maximizes the diagonal movement and therefore minimizes either the
horizontal or the vertical movement.

or 10+6=16

or 10+(3+2)=15
Assembly Line Balancing

 The problem of balancing an assembly line is a classic


industrial engineering problem.
 The problem is characterized by a set of n distinct tasks that must be
completed on each item
 The time required to complete task i is a known constant ti.
 The goal is to organize the tasks into groups, with each group of tasks being
performed at a single workstation
 In most cases, the amount of time allotted to each workstation is determined
in advance, based on the desired rate of production of the assembly line.
Assembly Line Balancing

 Assembly line balancing is traditionally thought of as a facilities design and


layout problem.
 There are a variety of factors that contribute to the difficulty of the problem.
 Precedence constrains: some tasks may have to be completed in a particular
sequence.
 Zoning restriction: Some tasks cannot be performed at the same
workstation.
 Let t1, t2, …, tn be the time required to complete the respective tasks.
 The total work content (time) associated with the production of an item, say T,
is given by n
T  t
i 1
i

For a cycle time of C, the minimum number of workstations possible is


[T/C], where the brackets indicate that the value of T/C is to be rounded to
the next larger integer.
Ranked positional weight technique: the method places a weight on each
task based on the total time required by all of the succeeding tasks. Tasks are
assigned sequentially to stations based on these weights.
Assembly Line Balancing

Example 8.11
The Final assembly of Noname personal computers, a generic mail-order PC
clone, requires a total of 12 tasks. The assembly is done at the Lubbock,
Texas, plant using various components imported from the Far East. The
network representation of this particular problem is given in the following
figure.
Assembly Line Balancing
ti=70, and the production rate is a unit/15 minutes;
Precondition The minimum number of workstations = [70/15]=5
The job times and precedence relationships for this problem are summarized
in the table below.

Task Immediate Predecessors Time


1 _ 12
2 1 6
3 2 6
4 2 2
5 2 2
6 2 12
7 3, 4 7
8 7 5
9 5 1
10 9, 6 4
11 8, 10 6
12 11 7
Assembly Line Balancing

The solution precedence requires determining the positional


weight of each task. The positional weight of task i is defined as
the time required to perform task i plus the times required to
perform all tasks having task i as a predecessor.
t3+t7+t8+t11+t12=31
Task Positional Weight
1 70
2 58
3 31
4 27
5 20
6 29
7 25
8 18
9 18
10 17
The ranking
11 13
1, 2, 3, 6, 4, 7, 5, 8, 9, 10, 11, 12 7
12
Assembly Line Balancing

Profile 1 C=15
Station 1 2 3 4 5 6
Tasks 1 2, 3, 5, 6, 9 7, 8 10, 11 12
4
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
Task Immediate Time
Predecessors
1 _ 12
2 1 6
3 2 6
4 2 2
5 2 2
6 2 12
7 3, 4 7
8 7 5 The ranking
9 5 1
10 9, 6 4 1, 2, 3, 6, 4, 7, 5, 8, 9, 10, 11,
11 8, 10 6 12
12 11 7
Assembly Line Balancing

Profile 1 C=15
Station 1 2 3 4 5 6
Tasks 1 2,3,4 5,6,9 7,8 10,11 12
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
15
Evaluate the
Cycle Time=15 balancing results by
the efficiency
T1=12 T2=6 ti/NC;
T2=6 T3=6 T4=2 T5=2 The efficiencies
T5=2 T6=12 T9=1 for Profiles 1 ~ 3 are
77.7%, 87.5%, and
T7=7 T8=5 T10=4 89.7%. Thus the
T10=4 T11=6 T12=7 profile 3 is the best
T12=7 one.
Assembly Line Balancing

Alternative 1: Change cycle time to ensure 5 station balance


Profile 1: Increasing cycle time from 15 to 16

Station 1 2 3 4 5
Tasks 1 2,3,4,5 6,9 7,8,10 11,12
Idle time 4 0 3 0 3

Increasing the cycle time from 15 to 16, the total idle time
has been cut down from 20 min/units to 10; resulting in a
substantial improvement in balancing rate.
 However, the production rate has to be reduced from one
unit/15 minutes to one unit/16minute;
Assembly Line Balancing

Alternative 2: Staying with 6 stations, see if a six-station


balance could be obtained by cycle time less that 15 minutes

Profile 2 C=13

Station 1 2 3 4 5 6
Tasks 1 2,3 6 4,5,7,9 8,10 11,12
Idle time 1 1 1 1 4 0

 13 minutes appear to be the minimum cycle time with six


station balance.
 Increasing the number of stations from 5 to 6 results in a
great improvement in production rate;

Anda mungkin juga menyukai