CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY REPORTS

CLIENT: Abu Dhabi Sewerage Services Company Date: 30 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sectors W2, W4, W6 & W7
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
* Sector W2 –Backfilling bet H25 to H25/1 and Bet H25/1 to H25/6 . Reinstatement of Tiles Near H25 , H25/1 , H25/6 ,
H25/3 .

* Sector W4,– Dewatering for line 4, 6 and 10 2)removal of asphalt for line 1 and excavation exposing of existing sewer
pipe length is 6.0m from the chamber 3)trial pit excavation for dewatering and excavation at road crossing for line 4
4)installation for 3 cover of new chamber for line 6 and preparation for deflection test and excavation and breaking of
concrete encased street light duct obstruction for construction of d53/13/26n/1 5)excavation to formation level and
removed existing pipe from ch1.35 to 7 from d53/23/1 to d53/23 for line 10

* Sector W6– at line 2 : Sheet Pilling and Excavation at h13/8C BD , at Line 3 : Excavation and expose Ext Pipe Bet H13/17/6
to H13/17/3A to H13/17/3 , at Line 4 : Reinstatement of Ceramic Tiles Bet H13/12/3 to 2 , At line 8 : Isolating of work
place Bet h19 to H18 , At line 9 : Excavation works .
*Sector W7 – Excavation works at H9 BD location , Bet H9/2 to H9/1 Excavation and exposing of Ext Pipe .
Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Secretary 01 Charge Hand* 07
Project Manager 01 Time keeper 01 Asst. Surveyor* 01
Dy. Project Manager 01 CAD Technician 04 Mason* 03
Construction Manager 01 HSE Engineer 01 Operator* 11
Site Agent 01 Office boy 02 Pipe Fitter* 03
QS 01 Site Engineer* 03 Welder* 02
PRO 01 Foreman* 01 Carpenter* 04
Accountant 01 Safety Officer* 04 Steel Fixer* 00
QA/QC 01 Surveyor* 04 Laminator* 02
Planning Engineer 01 Chainman* 04 Watchman 05
Supervisor 01 Driver* 05 Others: (SOP) 10
Material Engineer 01 Labors* 82 Asst. Welder 01
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type Mod No. WG IL BD
Pick Up (3T) 03 03 Bob Cat 02 02
DC Pick Up 00 00 Dewatering Pumps:
Mini Bus (14 Seat)* Electrical Pumps 01 01
01 01 (Submersible)
Mini Bus (65 Seat)* 01 01 Diesel Pumps (6" & 05 05
Car (Salon) 03 03 Jetting Pumps 00 00
JCB 03 03 Overpumping Pumps:
Asphalt Cutter Elec’l Pumps 08 08
02 02 (Submersible)
Compressor Jack Hammer 03 03 Diesel Pumps (6" & 00 00
Excavator 06 06 Welding Machine 02 02
Plate Compactor 03 03 Shovel 00 00
Crane * 00 00 Jack Hammer Exc. 00 00
Tipper 03 03 Generator 00 00
Drill Excavator 00 00 Vibrator 00 00
Remarks: Common equipment with mark of “*” being utilized for the whole project.
For Contractor: Checked by (DC):

Date: Date: