Anda di halaman 1dari 7

Carpentry

Door 1
V = (No. of Doors) (Perimeter) (Jamb)
Perimeter = 17.03’ + 1.33 = 18.39 m
D= 1
Jamb= (2 x 2 / 12)

V= (1)(18.39)(2 x 2 / 12)= 19 bdft (2” x 6” x 4”)

Door 2
V= (No. of Doors) (Perimeter) (Jamb)
Perimeter = 16.41’ + 1.33 = 17.73 m
D= 1
Jamb= (2 x 2 / 12)
V= (1)(17.73)(2 x 2 / 12) = 18 bdft(2” x 6” x 4”)

Door 3
V= (No. of Doors) (Perimeter) (Jamb)
Perimeter = 16.08’ + 1.33 = 17.41 m
D= 2
Jamb= (2 x 2 / 12)
V= (2)(17.41) (2 x 2 / 12) = 35 bdft (2” x 6” x 4”)

Door 4
V= (No. of Doors) (Perimeter) (Jamb)
Perimeter = 16.51’ + 1.33 = 17.9 m
D= 3
Jamb= (2 x 2 / 12)
V= (3) (17.9) (2 x 2 / 12) = 54 bdft (2” x 6” x 4”)

Door 5
V= (No. of Doors) (Perimeter) (Jamb)
Perimeter = 16.08’ + 1.33 = 17.41 m
D= 2
Jamb= (2 x 2 / 12)
V= (2) (17.41) (2 x 2 / 12) = 35 bdft (2” x 6” x 4”)

Door 6
V= (No. of Doors) (Perimeter) (Jamb)
Perimeter = 16.08’ + 1.33 = 17.41 m
D= 2
Jamb= (2 x 2 / 12)
V= (2) (17.41) (2 x 2 / 12) = 35 bdft (2” x 6” x 4”)
Column
P = 2(0.15 + 0.3) + 0.2 = 1.1 m
A= PHQ= (1.1)(9.4)(16)
= 165.44 m2

Q= A / U= 165.44 / 2.88
= 57.44

W= (V+H)(No.of columns)(2x2/12)

V= H x 3 x 4 = 9.4 x 3 x 4
= 370.08

H= P x 2 = 1.1 x 2
= 2.2

Total = 377.3
58 pcs of plywood

Typical Beams
P= 2 (0.4 + 0.2) + 0.1 = 0.7 m

A= PHQ = (0.7)(81.44)(1)
= 57.008 m2

Q= A / U = 57.008 / 2.88
= 19.79

W= (V+H)(No. of column)(2x2/12)
V= H x 3 x 4 = 81.44 x 3 x 4
= 977.28

H= P x 65= 0.7 x 65
= 45.5

Total = 3355.58’
20 pcs of plywood

Tie Beams
P= 2(0.4+ 0.2) + 0.1= 0.7 m

A = PHQ = (0.7)(48.6)(1)
= 34.02 m2

Q = A / U = 34.02 / 2.88
= 11.81

W= (V+H)(No. of column)(2x2/12)

V = H x 3 x 4 = 48.6 x 3 x 4
= 583.2

H= P x 36 = 0.7 x 36
= 82.68

Total= 1996.07’
12 pcs of plywood

Roof Beams
P = 2 (0.3+0.2) + 0.1 = 1.1 m

A = PHQ = (1.1)(67.125)(1)
= 73.8375 m2

Q = A / U = 73.8375 / 2.88
= 25.63

W= (V+H)(No. of column)(2x2/12)

V = H x 3 x 4 = 73.8375 x 3 x 4
= 604.125

H = P x 53 = 1.1 x 53
= 191.27

Total= 2173.31’
26 pcs of plywood

Slab
Q = A / U = 93.815 / 2.88
= 33 pcs of plywood

Column
P = 2 (0.15 + .3) + 0.2 = 1.1 m

W= (V+H)(No. of column)(2x2/12)

V = H x 3 x 4 = 9.4 x 3 x 4
= 370.08

H = P x 2 = 1.1 x 2
= 2.2

Total= 377.3’

W= (16)(377.3’)(2 x 2 / 12)
= 2013 bdft (2” x 2” wood)

Typical Beams
P = 2(.4+.2) + 0.1 = 0.7 m

W= (V+H)(No. of column)(2x2/12)
V = H x 3 x 4 = 81.44 x 3 x 4
= 977.28

H= P x 65 = 0.7 x 65
= 45.5

Total= 3355.58’

W= (1)(3355.58’)(2 x 2 / 12)
= 1119bdft (2” x 2” wood)

Tie Beams
P= 2(0.4+ 0.2) + 0.1 = 0.7 m

W= (V+H)(No. of column)(2x2/12)

V = H x 3 x 4 = 48.6 x 3 x 4
= 583.2

H = P x 36 = 0.7 x 36
= 82.68

Total= 1996.07’

W= (1)(1996.07’)(2 x 2 / 12)
= 666 bdft (2” x 2” wood)

Roof Beams
P = 2 (0.3+0.2) + 0.1 = 1.1 m

W= (V+H)(No. of column)(2x2/12)

V = H x 3 x 4 = 73.8375 x 3 x 4
= 604.125

H = P x 53 = 1.1 x 53
= 191.27

Total= 2173.31’

W= (1) (2173.31’)(2 x 2 / 12)


= 725 bdft (2” x 2” wood)

Slab
S= AF =(93.815)(6.10)
= 573bd ft (2” x 2” wood)