PREVENTORES Y CSC

POZO PRIMER ETAPA SEGUNDA ETAPA TERCER ETAPA CUARTA ETAPA QUINTA ETAPA

DIVERTER DE 30" 500 PSI STRING DE 20 3/4" 3 K STRING DE 16 3/4" 10 K STRING DE 13 5/8" 10 K STRING DE 11" 15 K
TR 20" TR 16" TR 13 5/8" X 13 3/8" TR 9 7/8" X 9 5/8" LINER Y COMPLEMENTO DE 7"
VALERIANA 1
PERFORAR 50 MTS 100% PERFORAR 2200 MTS 100%PERFORA A 4029 MTS 75% PERFORAR 4958 MTS 0%PERFORAR 6462 MTS 0%
CAMBIO DE RAM´S 7/01/16 APROX TERMINACION
DIVERTER DE 20 3/4" 3 K STRING DE 13 5/8" 10 K STRING DE 13 5/8" 10 K
TR 13 3/8" TR 9 5/8" TR 7"
AYOCOTE 101
PERFORAR 950 MTS 75% PERFORAR 3420 MTS 0% PERFORAR A 4340MTS 0%
DESMANTELACION APROX 6/01/16 INST.APROX 7/01/16 TERMINACION
PENDIENTE PENDIENTE PENDIENTE PENDIENTE PENDIENTE
SE ESTIMA TRANSPORTAR ENTRE EL 20/01/16
TEOTLECO 101
AUN NO SE CUENTA CON ESTADO MECANICO DEL POZO, SE TRABAJA EN BASE EN HABILITACION DE PREVENTORES Y CSC.