Process Status
1 Sourcing of New Materials New
2 Accreditation of Suppliers Update of existing
3 Purchasing Process of Local Materials Split from PM: Purchasing Process
4 Purchasing Process of Imported Materials Split from PM: Purchasing Process
5 Outsourcing of Requirements New
Work Instruction
1 Petty Cash Issuance, Liquidation and Reimbursement Update of existing
2 Monitoring Deliveries of Requirements Update of existing
3 Issuance of Notice of PO Changes Update of existing
4 Sourcing New Contractors Update of existing
5 Sourcing New Suppliers Update of existing
6 Imported Materials Payment New
a. Processing Letter of Credit (LC) New
b. Advance Payment for Imported Materials New
7 Assigning a Forwarder and Broker New
8 Processing a Purchase Return Slip New
9 Contractor's Purchase for Components New
Sourcing of New Materials
Update: December 14, 2016
Objective:
To source sustainable materials and services at the best value and quality.
Scope:
From receiving sourcing direction, evaluation of gathered information, approval of the material to evaluation of delivery and qu
Definition of Terms:
1 PMS - System used to create the Purchase Order.
2 MOQ - Minimum Ordering Qaantity
3 MCQ - Minimum Color Qaantity
Forms Used:
No standard forms
Sequence
Number Procedure Person Responsible
Purchasing Manager /
1 Receive material direction Purchaser
Purchasing Manager /
2 Canvass and identify atleast 3 possible Suppliers Purchaser
Purchasing Manager /
3 Engage with the Suppliers and conduct inquiry Purchaser
Purchasing Manager /
4 Request for initial sample Purchaser
Purchasing Manager /
5 Request quotation Purchaser
Purchasing Manager /
6 Receive sample and conduct visual evaluation Purchaser
Purchasing Manager /
7 Receive quotation and create comparison Purchaser
Purchasing Manager /
8 Conduct negotiation as needed Purchaser
Purchasing Manager /
9 Request for a larger sample lot Purchaser
Product Developer,
10 Submit material samples for testing and evaluation Merchandiser
Purchasing Manager /
11 Finalize results and recommendation Purchaser
Purchaser, Purchasing
12 Seek approval Manager
1. Sourcing New
Suppliers
2. Sourcing New
Referrals, internet, existing Suppliers Contractors
Objective:
To ensure the Supplier's is credibility to serve a the Company’s requirement through evaluation.
Scope:
From sourcing candidates Suppliers, evaluation of the qualifications, recommendation and approval up to reviewing performance after a trial order.
Definition of Terms:
1 Certificate of Registration (COR) - Issued by the Bureau of Internal Revenue (BIR) Philippines
2 Company profile - A document containing the Supplier's product offering, capabilities, customers, address and contact information
3 Master List - Directory of accredited suppliers including their contact details
4 Supplier Code - A unique 6 digits alpha numeric code to identify the Supplier, generated upon accreditation
Forms Used:
No standard forms
Sequence
Number Procedure Person Responsible Details Work Instruction
1. Sourcing New
Suppliers
Purchasing Manager / 2. Sourcing New
1 Source candidate Supplier Purchaser Referral, internet Contractors
Requiremens:
1. Company profile
2. Certificate of Registration (COR)
Require candidate Supplier to submit accreditation Purchasing Manager / 3. Supplier comprison form if any
2 requirements Purchaser 4. Quotation if any
6 Submit COR for creation of Supplier code Purchaser Update Master List when the code is received
9 Review performance and implement improvements Purchasing Manager Refer to Performance Indicators
Purchasing of Local Materials
Update: December 14, 2016
Objective:
To ensure accurate, complete and on timely delivery of required locally purchased raw materials at best value and of required quality for customer satisfaction.
Scope:
From receiving of the requisition to monitoring and recording of delivered items.
Definition of Terms:
1 PMS - System used to create the Purchase Order.
2 MOQ - Minimum Ordering Qaantity
3 MCQ - Minimum Color Qaantity
Forms Used:
1 Purchae Order (PO)
2 Notice of PO Change (NPC)
3 Purchase Return Slip (PRS)
Sequence
Number Procedure Person Responsible Details Work Instruction
Regular
4 Route PO for sigh-off Purchaser Purchaser and Purchasing Manager signs
Seasonal
Purchaser, Purchasing Manager and President signs
7 Enter PO details in Monitoring Report Purchaser Purchasing Monitoring Report (Excel internal control)
Monitoring
Deliveries of
Monitor delivery timeliness and/or respond to any change Requirements PM-
8 in requirements Purchaser Daily communications with the Supplier or customers. WI 07-02.09
1. Issuance of
1. Update Purchasing Monitoring Report Notice of PO
2. Issue Notice of PO Change (NPC) if any change in the Changes
date, quantity or price 2. Issuance
3. Issue Purchase Return to Supplier (PRS) if there are Purchase Return to
11 Close PO Purchaser substandard materials for return Supplier
12 Review performance and implement improvements Purchasing Manager Refer to Performance Indicators
Purchasing of Imported Materials
Update: December 14, 2016
Objective:
To ensure accurate, complete and on timely delivery of required imported raw materials at best value and of required qua
Scope:
From receiving of the requisition to monitoring and recording of delivered items.
Definition of Terms:
1 PMS - System used to create the Purchase Order.
2 MOQ - Minimum Ordering Qaantity
3 MCQ - Minimum Color Qantity
4 Telegraphic Transfer (TT) - Mode of payment where transaction is done from a local bank to a foreign bank
5 Proforma Invoice (PI) - A document showing the intended materials, price, amount, original and consignee or receiver.
6 PMS - System used to create the Purchase Order.
7 Dollar Allocation - Memo format in excel summarizing the required amount in Pesos for actual payment in US Dollars.
8 Sworn Statement with TAN entry number - One of the requirements in opening an LC. This form was formatted by our L
9 Temporary Assessment Notice (TAN) and Single Administrative Documets (SAD) - Requirements for opening an LC. A tem
10 Import Entry Declaration (IED) - Documents from the Broker after lodgement.
11 Shipping Documents - Packing List, Commercial Invoice, Bill of Lading, Form D or E, Marine Insurance
Forms Used:
1 Purchae Order (PO)
2 Notice of PO Change (NPC)
3 Purchase Return Slip (PRS)
4 Letter of Credit Form (LC)
5 Distribute PO Purchaser
Purchaser, IMPEX
7 Enter PO details in Monitoring Report Officer
12 Request shipping invoice and packing list from Supplier IMPEX Officer
IMPEX Officer,
14 Request to send original shipping docs from supplier Purchaser
Seq# Procedure Person Responsible
Purchaser, IMPEX
20 Close PO and update Monitoring Reports Officer
Work
Details Instruction
Seasonal
Purchaser, Purchasing Manager and President signs
1. LC Process
1. Request dollar allocation 2. Advance
2. Flll-up LC form if required Payment
3. Prepare payment instruction if needed Process
Monitoring
Deliveries of
Requirements
PM-WI 07-
Daily communications with the Supplier or customers 02.09
Mode of payment:
1. Bureau of Customs by bank debit
2. If by TT to Supplier is 30 days from B/L date Payment
3.If by LC, opening depending on bank conditions Process