Board of Library Trustees Meeting

Capital Projects Report


January 24, 2018

Document #10C.1
Board of Library Trustees Meeting
January 24, 2018
Capitol View Library Project Information
Ward 7
Address 5001 Central Ave. SE
Councilmember Vincent Gray
Branch Manager Eboni Harris
Project Manager Jaspreet Pahwa

Project Budget $ 7,200,000


Additional funds added for Interior renovation $733,050
Project Milestones
Project Start Date May 2016
Library Close for Construction- Interior Renovation
Feb 9 2017
Exterior Phase: Interim Library Open, Library Close
Spring 2018
Interim Library Close Fall 2018
Library Opened after Interior Renovation Dec 18, 2017
Exterior Renovation projected completion Summer 2018
Active Contractor(s):
Broughton / R.McGhee & Associates
GDG Construction, Fabricator Steel River Building Systems

Project Description/Status

Project Scope funded at $4.5 for interior spatial re-configuration, new Mechanical, Electrical & Plumbing systems, new windows,
reconfigured front entrance, roof replacement, new furniture, finishes & equipment. New $2.7M FY 18 funding will be spent on exterior
renovation including the modular interim library being planned to go on the grounds of JC Nalle during the exterior renovation phase.
Exterior Concept design is slated for CFA approval during the February meeting.

Board of Library Trustees Meeting


January 24, 2018 Page 2
Cleveland Park Library Project Project Information
Ward 3
Address 3310 Connecticut Ave NW
Councilmember Mary Cheh
Branch Manager Barbara Gauntt
Project Manager Rauzia Ally

Project Budget $ 19,770,000

Project Milestones
Project Start Date March 2015
Library Close for Construction Fall 2016
Interim Library Open Fall 2016
Interim Library Close Summer 2018
New or Renovated Library Open Summer 2018

Active Contractors(s):
Gilbane/Perkins Eastman
A2 Services, Inc.
ECS Capitol Services, PLLC

Project Description/Status:
Exterior Framing, sheathing and air barrier, and most of the roofing are complete. Brick masonry is complete. Stone masonry is ongoing.
Most of the glazing is installed except for the bays and the tower. Interior MEP rough in and all stair structure is complete. Drywall is
being hung on both sides on all floors. Building will be dried-in in January. Security infrastructure is now starting. Permanent power is
scheduled. Gas tie in is awaiting the utility permit. Water tie in is awaiting warmer weather for water shut down. Bioretention walls on
the exterior are now being completed. Elevator installation is starting in the next week. Millwork wall panels will be installed in March.

Board of Library Trustees Meeting


January 24, 2018 Page 3
Lamond-Riggs Library Project Information
Ward 5
Address 5401 South Dakota Ave. NE
Councilmember Kenyan McDuffie
Branch Manager Robin Imperial
Project Manager Lisa Deanes

Project Budget $ 20,000,000

Project Milestones
Project Start Date 2018
Library Close for Construction Fall 2019
Interim Library Open Fall 2019
Interim Library Close Fall 2020
New or Renovated Library Open Early 2021

Active Contractor(s):
Brailsford and Dunlavey

Project Description/Status:

Project funded in October 2017. Due diligence review is underway. RFP for Design Build Services to be issued .

Board of Library Trustees Meeting


January 24, 2018 Page 4
Martin Luther King Jr. Memorial Library Project Information
Ward 2
Address 901 G Street NW
Councilmember Jack Evans
Library Manager TBD
Project Manager Rauzia Ally

Project Budget $ 211,000,000

Project Milestones
Project Start Date August 2014
Library Close for Construction Spring 2017
Interim Library Open Spring 2017
Interim Library Close Spring 2020
New or Renovated Library Open Summer 2020

Active Contractor(s):
Martinez+Johnson/Mecanoo
Jair Lynch Development
Smoot / Gilbane
Liberty Engineering

Project Description/Status:

Complete modernization of the downtown central library. Demolition is complete and hazardous materials abatement is ongoing. LEED kick off is
scheduled for mid January. Coordination with HPO on the removal/support of the existing brick exterior walls is ongoing. Glass samples for
exterior glazing is evaluated. Metal repairs at the north elevation are ongoing. The metal repairs have been completed in the Mock up area with a
projected time next week for the application of the finish coating. The architect is reviewing elevator shop drawings and submittals for other long

Board of Library Trustees Meeting


January 24, 2018 Page 5
Palisades Library Project Information
Ward 3
Address 4901 V Street, NW
Councilmember Mary Cheh
Branch Manager Karen Quash
Project Manager Lisa Deanes

Project Budget $ 7,500,000

Project Milestones
Project Start Date October 2015
Library Close for Construction March 2017
Interim Library Open N/A
Interim Library Close N/A
New or Renovated Library Open January 20 2018

Active Contractor(s):

Cox graae+spack / MCN Build

Project Description/Status:
Project Completed. Major renovation project that included green roof, and upgrades to mechanical, plumbing and electrical systems. Project
includes new furniture, fixtures and equipment. The façade has been modified to introduce more natural light and the new open floor plan
enables an intuitive library services experience for patrons.

Board of Library Trustees Meeting


January 24, 2018 Page 6
Southeast Library Project Information
Ward 6
Address 403 7th Street SE
Councilmember Charles Allen
Branch Manager Maria Escher
Project Manager TBD

Project Budget $ 23,500,000

Project Milestones
Project Start Date 2019
Library Close for Construction TBD
Interim Library Open TBD
Interim Library Close TBD
New or Renovated Library Open TBD

Active Contractor(s):
TBD

Project Description/Status:

Planned major renovation starting FY19. A due diligence study to analyze the addition of a new sublevel to the library under 7th St to
Eastern Market Metro Park has been completed. Informal Site Survey conducted September 20, 2017.

Board of Library Trustees Meeting


January 24, 2018 Page 7
Southwest Library Project Information
Ward 6
Address 900 Wesley Place SW
Councilmember Charles Allen
Branch Manager Kimberly Knight
Project Manager Jaspreet Pahwa

Project Budget * $ 18,000,000

Project Milestones
Project Start Date Summer 2017
Library Close for Construction Fall 2018
Interim Library Open Fall 2018
Interim Library Close Early 2020
New or Renovated Library Open Early 2020

Active Contractor(s):
Turner Construction / Perkins+Will

Project Description/Status:
Project is funded in FY2017 for a new LEED certified branch library. Design started in July 2017 with Perkins+ Will & Turner Construction. Two
community meetings held in July and September culminated in a successful concept design. The library is proposed to be all above ground
and is gearing up to go through the approval process of ANC, Zoning, and Commission of Fine Arts.

Board of Library Trustees Meeting


January 24, 2018 Page 8