Anda di halaman 1dari 136

Arahan Teknik (Jalan) 16/03; (Pindaan 2008)

JKR 21300-0002-09

JABATAN KERJA RAYA

A PRACTICAL GUIDE FOR


ENVIRONMENTAL PROTECTION &
ENHANCEMENT WORKS

Cawangan Kejuruteraan Jalan & Geoteknik


Ibu Pejabat JKR Malaysia
Peti Surat 18 & 19, Menara Tun Razak
Jalan Raja Laut
50350 Kuala Lumpur
GREEN MISSION

Being the key implementing agency for governments‟ projects, Jabatan Kerja Raya (JKR)
is committed and dedicated to steer the organization and safeguard the environment by
adopting the following principles:-

 Natural resources protection and enhancement


 Resource efficiency
 Sustainable consumption
 Sustainable construction
 Adherence to relevant laws and regulations

In doing so, Jabatan Kerja Raya (JKR) is guided by their environmental management
system (ISO 14001 EMS) particularly during the construction stage to minimize and
mitigate impacts to the environment through controlled site clearing, protection and
maintenance of slopes, waste minimization and management and compliance to legal
requirements.

In moving forward, JKR is committed in ensuring that all projects are developed in a
sustainable manner, focus shall be given at planning stage in order to take into account the
need to identify and mitigate environmental impacts for developments in Environmentally
Sensitive Areas (ESAs) or within its vicinity. Protection of ESA is one of the key steps
towards protecting our country‟s natural resources.

i
PREFACE

In line with the MS: ISO 14001 requirement, a continual improvement of the system must
be done to ensure success and effectiveness of environmentally sustainable approach in
construction. To produce a clear and comprehensive tender document, revision of JKR
Tender Documents on environment protection and enhancements has been done by
itemising the environmental works into the Bill of Quantities to allow contractors to tender
a realistic price. Arahan Teknik (Jalan) 16/03, produced in 2004, provided changes to the
items in the Tender Document with regards to the Condition of Contracts, Instruction to
Tenderers, Specification to Environmental Protection and Enhancements, Preamble to Bill
of Quantities, Need Statement, Bill of Quantities and Drawings.

In 2006, a committee comprising multi-disciplinary personnel was set up to revise the


Arahan Teknik (Jalan) 16/03. Changes have been made in accordance to problems
encountered and inadequacies of the previous Arahan Teknik. The overall improvement is
aimed to ensure contractors understand the application of the environment protection
works that they have tendered in the Bill of Quantities. Notwithstanding the importance of
other technical agencies requirements to protect the environment, some parts have been
added such as the preparation of Erosion and Sediment Control Plan (ESCP) and
management of disposal site for surplus material as part of the latest EIA requirements.
Drawings of mitigation works have been revised and amended. The revised Arahan
Teknik (Jalan) 16/03 is made applicable, not only to road projects, but to all projects in
JKR. It is important that all parties involved in the construction industry, be made aware of
the latest government requirements in environment protection to ensure our nation has the
capacity to be sustainable in the long term future.

ii
ACKNOWLEDGEMENT
This revised Arahan Teknik (Jalan) 16/03 was prepared by a sub-committee comprising
thirty-seven (37) multi-disciplinary personnel as listed below:-

(1) Ir. Cheong Pui Keng Pengarah, JKR Cawangan Alam


Sekitar dan Tenaga (CAST)
(2) Dato‟ Ir. Dr. Hj. Roslan bin Md Taha Pengarah, JKR Negeri Sembilan
(3) Ir. Hj. Abu Harith bin Shamsuddin KPPK, JKR Cawangan
Kejuruteraan Senggara
(4) Ar. Cik Lee Bee Chew Retired, (formerly Pengarah, JKR
Cawangan Alam Sekitar dan
Tenaga.
(5) En. Meor Mohamed Haris bin Meor Hussein KPP, JKR Perak (Jalan).
(6) En. Muhamad Rahimi b Abdullah KPPK, Cawangan Kej. Jalan &
Geoteknik
(7) Pn. Hjh. Sujatiah binti Tamrin PPK, Cawangan Jalan
(8) Pn. Hjh. Faridah binti Abdul Rashid KPP, Kementerian Kewangan
(formerly JKR Cawangan Kontrak
dan Ukur Bahan)
(9) Tn. Hj. Abdul Rahman bin Idris KPP, JKR WPKL
(10) Pn. Nor Shahrene binti Mohd Ibrahim KPP (Arkitek). JKR Cawangan
Pengurusan Korporat
(11) En. Amran bin Majid Juruukur Bahan, Cawangan
Kejuruteraan Ukur Bahan
(12) Pn Emmy Sherina binti Ismail Hashim Jurutera Senggara, JKR Daerah
Kuala Terengganu
(13) En. Nasrollah bin Mohamad PP, (ECER)
(14) En. Hamizan bin Husain PP, Cawangan Kej Mekanikal
(15) En. Mohd Nor Rashidi bin Abd Jalil PP, Cawangan Pengurusan
Korporat
(16) En. Mohd Aznan Shukri b Mohamed Safian Jurutera Bangunan, JKR Hilir
Perak
(17) Pn. Nurazaini binti Mokhtar PPK, Jabatan Pengairan dan
Saliran
(18) YM Raja Nur Ashikin binti Raja Zainal ERE Consulting Group Sdn. Bhd.
(19) Pn. Geetha P. Kumaran Europasia Eng. Services Sdn.
Bhd. & ENSEARCH
(20) En. Romzi bin Mat Zainul ATZ Consult Sdn. Bhd. (formerly
HSSI S/B)
(21) En. Shamsul Azhar bin Ismail Wiranda (M) Sdn. Bhd.
(22) En. Mohd Zikri bin Azmi Wiranda (M) Sdn. Bhd.
(23) En. Mohd. Khusairi b. Mohd. Isa KPP, CAST
(24) Cik Siti Nor bt. Othman PP, CAST
(25) Pn. Siti Noor Aiza bt. Abd. Aziz PP, CAST
(26) Cik Nurazura bt. Ali PP, CAST
(27) En. Azizul b. Hashim PP, CAST
(28) Pn. Hawa Liza bt. Zahari PP, CAST
(29) En. Khairol Nazri b. Abdul Khaiyom PP, CAST

iii
(30) En. Mohd. Fauzie b. Ismail PP, CAST
(31) Cik Aida Elyana bt. Jamil PP, CAST
(32) En. Khairul Amir b. Isahak PP, CAST
(33) En. Mohd. Amir b. Hashim PP, CAST
(34) Pn. Noor Azizah bt. Majid PP, CAST
(35) En. Mohd. Eikmal b. Ahmad PP, CAST
(36) Pn. Zuraiha bt. Zainuddin@Abd Aziz PP, CAST
(37) Pn. Izmazurin bt. Ramli PP, CAST

Finally, the publisher wishes to express its gratitude to the above committee members for
their valuable contributions and preparation of this guide.

Published by:-

Unit Standard & Spesifikasi


Bahagian Penyelarasan & Khidmat Sokongan
Cawangan Kejuruteraan Jalan & Geoteknik
Ibu Pejabat JKR Malaysia
Tingkat 14, Menara Tun Razak
Jalan Raja Laut
50350 Kuala Lumpur

Reproduction of any part from this publication may be made subject to due
acknowledgement of the source. However, the publisher does not accept any responsibility
for any consequences arising from the use of the information within this guide.

iv
A PRACTICAL GUIDE FOR ENVIRONMENTAL PROTECTION &
ENHANCEMENT WORKS

CONTENTS PAGE

CHAPTERS

1.0 Introduction 1
2.0 Environmental Requirements 5
3.0 Contractual Requirements 14
4.0 Specifications 16
5.0 Method of Measurement 35
6.0 Bill of Quantities 71
7.0 Best Management Practices 82
8.0 Standard Drawings and Figures 91

REFERENCES 104

APPENDIX 1 105

Standard Specifications for Building Works (2005 Edition):-


SECTION A: PRELIMINARIES AND GENERAL CONDITIONS
AND SECTION C: EXCAVATIONS AND EARTHWORKS

APPENDIX 2: Government Requirements (Need Statement) 111


(Term of Reference) (For Design and Build Projects Only)

APPENDIX 3: Standard Report Format for :- 120

(i) Environment Management Plan (EMP)


(ii) Environment Quality Report (EQR)
(iii) Environment Management Audit Report (EMAR)
(iv) Closure Audit Report (CAR)

v
CHAPTER 1

INTRODUCTION

1
CHAPTER 1.0: INTRODUCTION

1.0 Introduction

Environmental protection and conservation is gaining more significance in the long term
national development plan. In this regards, Malaysia as a country, has reaffirmed its
commitments towards the protection and conservation of its environment as stated in the
National Policy on Environment, National Physical Plan (NPP) and prevailing
Malaysia Plans.

In summary, the National Policy on Environment aims for continuous economic, social
and cultural progress and enhancement of the quality of life of Malaysians, through
environmentally sound and sustainable development.

The main goal of the NPP is to create an efficient, equitable and sustainable national
framework that will guide future development of the country. It is an important piece of
document as it provides the spatial element in development planning as well as spells out
policies that determine the direction of physical development and conservation areas
within Peninsular Malaysia. It also identifies areas that need to be conserved and protected
via a ranking system. These areas are called Environmentally Sensitive Areas (ESA).
Such identification will greatly assist any project proponent (government or private sector)
in evaluating and determining the feasibility of some projects at macro or national level.

In line with the nation‟s aspirations in protecting the environment, JKR has formulated
and implemented the “JKR Green Mission” and has an Accredited MS ISO 14001
since 5th November 2002. The main objective of the document is to protect and enhance
the environment by ensuring that projects are being implemented in a sustainable manner
and with the least impacts to the environment.

1.1 Objectives

This Revised Arahan Teknik shall aim to attain the following objectives:-

 To ensure that the “JKR EMS ISO 14001” requirements in terms of environmental
protection measures are properly incorporated in the preparation of the tender
document and subsequently implemented during the planning, construction and
operational stages of the project.

 To guide users on the requirements pertaining to environmental protection,


mitigation and enhancement measures in the preparation of tender document.

1.2 Method of Procurement

This document is applicable for both conventional and design and build contracts. A
typical example of the process flow for both types of contracts can be referred to in the
JKR‟s Quality Management System (QMS).

2
1.3 Limitation

This document may have limited use for costing and environmental protection
measures purposes in the preparation of Bill of Quantities (BQ) for Projects that are
subjected to the following:

 Detailed Environmental Impact Assessment Study (particularly for projects that


involve reclamation;
 Marine-related projects such as jetties, marina, coastal protection structures or any
structure that extends out into the sea; and
 Projects located within areas identified as Environmentally Sensitive Areas (ESAs)
such as wildlife sanctuary, wetlands, marine parks and national parks.

For projects identified above, more specific environmental protection measures may be
required in order to minimize impacts to the environment.

1.4 Format of Document

This Revised Arahan Teknik (Jalan) 16/03 has been divided into eight chapters addressing
the various components which form part and parcel of the tender document preparation
process.

In addition to the introductory material in this section, the document contains:-

Chapter 2.0 Environmental Requirements – in which environmental requirements


at various project development stages will be described. Relevant
guidelines are also tabulated for reference purposes.

Chapter 3.0 Contractual Requirements – in which environmental requirements


pertaining to different methods of procurement will be presented.

Chapter 4.0 Specifications – in which environmental protection works are


elaborated to assist users in preparing tender document as well as
ensuring compliance to the relevant legislations and regulations.

Chapter 5.0 Method of Measurement (MOM) – in which elaboration of methods


of measurement for items stated in the BQ will be measured. It
describes the items, unit and measurement for payment.

Chapter 6.0 Bill of Quantities (BQ) – in which environmental protection works


will be itemized in terms of unit, quantity, rate and cost. It will cover
both non-physical works and physical works.

Chapter 7.0 Best Management Practices (BMP) – in which samples of mitigating


measures that have been implemented successfully at site are shown.

Chapter 8.0 Standard Drawings and Figures – in which preliminary drawings and
figures of mitigating measures such as silt trap, sediment basins, check
dams and fuel storage skid tanks are shown.

3
APPENDIX 1

Standard Specifications For Building Works (2005 Edition):- SECTION A :


PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C :
EXCAVATIONS AND EARTHWORKS

Appendix 2 Government Requirements (Need Statement) (Term of Reference)


(For Design and Build Projects Only)

Appendix 3 Standard Report Format for Environmental Management Plan


(EMP), Environmental Quality Report (EQR), Environmental
Monitoring and Audit Report (EMAR) and Closure Audit Report
(CAR)

4
CHAPTER 2

ENVIRONMENTAL REQUIREMENTS

5
CHAPTER 2: ENVIRONMENTAL REQUIREMENTS

The legislation that is related to the prevention, abatement, control of pollution and
enhancement of the environment in Malaysia is stipulated in the Environmental Quality
Act 1974 (Amendment) 2007. To date, 40 sets of Regulations and Orders have been
introduced and enforced. Under this Act, an Environmental Impact Assessment (EIA) is
required for activities prescribed under the Environmental Quality (Prescribed
Activities (Environmental Impact Assessment) Order 1987. Those activities that are
not subject to the mandatory EIA requirement are nevertheless subject to various other
regulations under the Act. The standard regulations require evaluation for project siting,
pollution control, monitoring and self regulation via the audit process.

For the states of Sabah and Sarawak, the environmental requirements are clearly stipulated
in the Environment Protection (Amendment) Enactment 2004 and Natural Resources
and Environment Ordinance respectively.

Apart from compliance with the Environmental Quality Act (EQA) 1974 (Act 127) and
other related environmental legislations, the following Acts are also applicable based on
its relevancy to the planning, design, construction, equipping and commissioning of any
project.

(a) National Land Code (Act 56 of 1965)


(b) Town and Country Planning Act 1976, (Act 172)
(c) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978
(d) Protection of Wildlife Act, 1972 (Act 76)
(e) Forestry Act 1984 (Act 313)
(f) Land Conservation Act 1960 (Act 385)
(g) Occupational Safety and Health Act 1994 (Act 514)
(h) Solid Waste and Public Cleansing Management Act 2007 (Act 672)
(i) Federal Territory (Planning) Act 1982 (Act 267)
(j) Workers Minimum Amenities Act 1990 (Act 446)
(k) Local Government Act 1976 (Act 171)

6
2.1 Planning/Design Stage

Environmental requirement during planning or design stage is clear whereby if the said
project has been classified as a “prescribed activity” according to the Environmental
Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987 and
Section 34A of the Environmental Quality (Prescribed Activities)(Environmental
Impact Assessment) Order 1987, an Environmental Impact Assessment (EIA) study
needs to be carried out and submitted to Department of Environment for approval prior to
project implementation.

Under the Act, there are a total of nineteen (19) categories of prescribed activities which
include agriculture, airport, drainage and irrigation, land reclamation, fisheries, forestry,
housing, industry, railways, transportation, resort and recreation development, waste
treatment and disposal, and water supply projects. Additionally, a Detailed Environmental
Impact Assessment (DEIA) study is required for thirteen (13) different types of projects
which include steel mill, pulp and paper mill, cement plant, coal-fired power plant, dams
(hydroelectric and water supply), coastal land reclamation, incinerators (scheduled wastes
and solid wastes, solid wastes disposal sites, projects involving land clearance where more
than 50% of the area has slope>250) and logging (>500 hectares). It is to be noted that for
projects in Sabah and Sarawak, specific local legislations pertaining to EIA requirements
need to be adhered to.

For the state of Sabah, lists of prescribed activities are contained in First Schedule and
Second Schedule of the Environment Protection (Prescribed Activities) (Environment
Impact Assessment) Order 2005. For projects in Sabah, an environmental impact
assessment report is required for any prescribed activities specified in the Second
Schedule of the Environment Protection (Prescribed Activities) (Environment Impact
Assessment) Order 2005. In addition, a proposal for mitigation measures is required for
any prescribed activities specified in the First Schedule.

For projects in Sarawak, an environmental impact assessment report is required for any
prescribed activities specified in the First Schedule of the Natural Resources and
Environment (Prescribed Activities) Order 1994.

Apart from the legislative requirement, EIA may be prepared taking into consideration the
sensitivity of the project in terms of its location, site conditions and magnitude of impacts.
In some cases, preparation of EIA study is required by the local authorities or form part of
the contractual requirement of a project.

Findings from the study are intended to provide input in the planning of the Project,
particularly in minimizing environmental impacts during the construction and operational
stages. An EIA is considered as a planning tool to assist the Project Initiator in
anticipating impacts of the development, both beneficial and adverse, with an aim to
maximize the beneficial impacts and minimize the adverse impacts on the environment.

For better understanding of the EIA process and procedures, an EIA flow chart for both
Preliminary EIA and Detailed EIA are shown in Figures 1 and 2. Similarly, a simple EIA
flow chart for Sarawak and Sabah are shown in Figures 3 and 4.

7
Figure 1: Flowchart for Preliminary EIA Process in Malaysia

Source: Department of Environment, Malaysia

8
Figure 2: Flowchart for Detailed EIA Process in Malaysia

Source: Department of Environment, Malaysia

9
Figure 3: Flowchart for EIA Process in Sarawak

Source: Natural Resources and Environment Board, Sarawak

10
Figure 4: Flowchart for Preliminary EIA Process in Sabah

Source: Environment Protection Department, Sabah

11
2.2 Implementation/ Construction Stage

In order to monitor Project‟s compliance with the general requirements of the Client‟s
needs and relevant environmental legislation, an Environmental Management Plan
(EMP) shall be prepared as detailed herein. The EMP shall be prepared in accordance to
the format or guidelines recommended by the Department of Environment (DOE) and/or
other relevant government departments‟ requirements. These guidelines shall provide the
framework for the preparation of the environmental management and mitigation measures
to mitigate on-site impacts to acceptable limits as stipulated by the DOE.

The EMP is not intended as a rigid planning document but an active document that shall
be revised and improved, as and when required, throughout the implementation stage.
Proper execution of the EMP is expected to result in minimal adverse impacts on the
surrounding environment and its natural resources.

The plan shall outline the responsibilities of the various parties involved in the Project,
the environmental requirements for the Project and specifies mitigation measures and
environmental monitoring and audit that must be implemented during construction
stage. The EMP shall be prepared and implemented to ensure compliance to the JKR EMS
ISO 14001.

Integral to EMP is the establishment of a monitoring program that serves as a


quantitative feedback mechanism on the effectiveness of the mitigation measures.
Essentially, the monitoring program is a set of procedures targeted towards periodical
measurement of environmental indicators that provides a platform to evaluate
environmental performance through comparisons against baseline and compliance levels.
Selection of environmental components to monitor, their locations, parameters and
frequency of monitoring are governed by the EIA approval conditions or by a Registered
Environmental Consultant (if no EIA was carried out for the project). As a norm,
monitoring is centered on the issues of water, noise and air qualities likely to be impacted
upon by the Project.

The auditing procedure and schedule shall be detailed out in the EMP. The audit shall
focus on the implementation of the EMP and/or other environmental management
elements. The environmental auditor shall have the necessary expertise and experience to
execute the tasks diligently and professionally in accordance with the requirements of JKR
EMS: MS ISO 14001 and shall undertake the following tasks:-

(a) To carry out environmental compliance audits quarterly and closure audit on
completion of the project;

(b) To evaluate monitoring data for water, air, noise qualities and if applicable
vibration qualities;

(c) To verify implementation of corrective and preventive action findings on adequacy


of compliance to the EMP and/or JKR EMS ISO 14001;

(d) To prepare a comprehensive environmental auditing report in compliance to


elements as stated in the EMP and/or JKR EMS ISO 14001;

12
2.3 Operational/Post Construction Stage

Upon submission and acceptance of the closing audit at the end of the construction period,
monitoring of operational activities in compliance to the necessary laws and regulations is
encouraged to be continued during the post construction stage in order to ensure that the
operational stage of the project does not cause any environmental damage. The impact of
generated wastewater has been deemed to be the more significant residual impact that
requires further monitoring. The quality of any wastewater discharged must comply with
the limits as stipulated by the Environmental Quality (Sewage) Regulations 2009.

2.4 Applicable Guidelines

The use of the relevant Guidelines in the planning/design stage of the project is deemed
necessary in order to ensure the project activities do not violate any applicable laws and
regulations. The guidelines need to be used in respect to the project site specific
conditions.

The General guidelines applicable are as follows:-

Area to be developed
Applicable Guidelines

 Guidelines for the Environmental Impact Assessment


of Highway/Road Projects, JKR Malaysia
 Environmental Impact Assessment Guidelines for
Housing and New Township Development Project,
DOE 2003
General Sites  Urban Storm Water Management Manual for Malaysia
(Manual Saliran Mesra Alam Malaysia), JPS 2000
 Guidelines for Prevention and Control of Soil Erosion
and Siltation in Malaysia, DOE 1996
 Environmental Audit Guidance Manual, DOE 2009
 Submission checklist for stormwater management in
Malaysia, DID 2008
 Cabinet Committee Guidelines on Hill slope
development;
Hill slope and Sensitive
 KPKT Guidelines for Development of Hilly Areas,
Sites
JPBD 2009;
 JKR Manual on Slope Maintenance

 JPS Guidelines 1/97 Erosion Control for Coastal


Development Area, 1997;
 Planning Standards for Coastal Areas, JPBD
Coastal Sites
 Planning Standards for the Physical Development of
Islands, JPBD

Note: The above guidelines are not exhaustive.

13
CHAPTER 3

CONTRACTUAL REQUIREMENTS

14
CHAPTER 3: CONTRACTUAL REQUIREMENTS

Environmental protection and enhancement works for conventional contract projects are to
be specified in the Instructions to Tenderer (ITT) and Conditions of Contracts. These
shall form part of the pre bid document to be prepared for Conventional Contract projects.

3.1 Instructions to Tenderer (ITT)

As stated in the Contract Specification issued by JKR on behalf of the Government of


Malaysia, the Contractor shall comply with all legal duties and obligations regarding the
protection of the environment as laid down in the Environmental Quality Act 1974 (Act
127). Before the commencement of works Contractor shall submit to the Superintendent
Officer (S.O.), an Environmental Management Plan (EMP), detailing the Contractor‟s
proposed arrangement for the abatement and mitigation measures for environmental
protection, environmental monitoring, testing programmed and reporting, and his
organisation chart.

3.2 Conditions of Contract

Within forty-five (45) days from the Letter of Acceptance, the successful tendered shall
submit for the S.O.‟s approval an Environmental Management Plan (EMP) as specified. In
the event if the contractor fail to submit such plan, then the government deserves the right
to prepare such plan and the cost incurred shall be deducted from the contract sum. The
cost of preparing the EMP shall include the cost involved in obtaining the services of a
Registered Environmental Consultant and is deemed to be borne by the Contractor.

The Environmental Impact Assessment (EIA) report and the Conditions of Approval given
by the Department of Environment (DOE), where possible, will be made available by the
Government to assist the Contractor and the environmental consultant in preparing the
EMP.

3.3 Design and Build Contract

For design and build contract, reference shall be made to the need statement pertaining to
environmental protection and enhancement requirements. The need statement is as
appended in appendix 2 of this document.

15
CHAPTER 4

SPECIFICATIONS

16
CHAPTER 4: SPECIFICATIONS

This section contains the specification relating to environmental matters in the execution
of JKR projects in line with JKR EMS: MS ISO 14001 and shall be read in conjunction
with the Standard Specification for Buildings, Road Works and JKR Green Mission.
However where these matters appear also in other sections of the Contract Document, this
specification shall take precedence.

4.1 Legislation and Regulations

The Contractor shall at all times adhere to all existing statutes regarding the protection
of the Environment.

Prior to the execution of the project, the Contractor shall comply with the Environmental
Quality Act (EQA) 1974 (Act 127) and other related environmental legislation including,
but not limited to:

(a) National Land Code (Act 56 of 1965)


(b) Town and Country Planning Act 1976, (Act 172)
(c) Street, Drainage and Building Act, 1974: Act 133 and Amendment, 1978
(d) Protection of Wildlife Act, 1972 (Act 76)
(e) Forestry Act 1984 (Act 313)
(f) Land Conservation Act 1960 (Act 385)
(g) Occupational Safety and Health Act 1994 (Act 514)
(h) Solid Waste and Public Cleansing Management Act 2007 (Act 672)
(i) Federal Territory (Planning) Act 1982 (Act 267)
(j) Workers Minimum Amenities Act 1990 (Act 446)
(k) Local Government Act 1976 (Act 171)

The Contractor shall be liable for and shall indemnify the Government against any
damages, expenses, liability, losses, claims, prosecution, proceedings, fines and penalties
caused by any non-compliances or contraventions of the above legislation and regulations.

4.2 Environmental Impact Assessment (EIA)

In line with EQA 1974, Act 127, Section 34A (1-8), the Contractor shall submit a report
on project‟s impact on the environment if the project is listed as prescribed activities in the
Environmental Quality (Prescribed Activities) (EIA) Order, 1987. The report should be
prepared in accordance with the requirements as per the latest “A Handbook of EIA
Guidelines” by the Department Of Environment.

17
4.3 Environmental Management Plan (EMP) & Applicable Elements

4.3.1 Objectives

The main objective of the Environmental Management Plan (EMP) is to set


out a comprehensive programmed which will form the basis for
implementing environmental mitigation measures, environmental
monitoring and environmental auditing of the construction works by the
Contractor as listed below:-

(i) To set out various environmental protection / conservation measures


that conform to the environmental conditions stipulated in the
Specifications, EIA report and by other relevant authorities (e.g. the
Department of Environment (DOE);

(ii) To ensure that the Contractor comply with all applicable


environmental standards and guidelines, legislative requirements and
other relevant conditions related to the environment;

(iii) To specify a detailed environmental monitoring and auditing


programmed to ensure that the Contractor and all his Sub-contractors
comply with all stipulated requirements throughout the duration of the
project; and

(iv) To streamline the different functions of various sections and


authorities related to the environmental matters during construction.

4.3.2 Preparation of the EMP

The Contractor shall submit an EMP prepared by a registered


environmental consultant and approved prior to commencement of any
works on site. The EMP shall be submitted to the S.O. for endorsement
within 45 days from the date of Letter of Acceptance in compliance with
the Conditions of Contract and/or in compliance with the requirements of
the conditions of approval of the EIA report by the Department of
Environment. For design and build projects, the need statement shall
prevail.

The EMP shall make reference to the following but not limited to:-

(a) DOE Format for the Preparation of EMPs


(b) JKR Environmental Management System (EMS)
(c) The approved EIA report
(d) EIA Approval Conditions from DOE (attached if any).

It should be clearly noted the EMP is a document for practical use on site
by nominated personnel and thus should be concise, up to date and site
specific.

18
The execution of the EMP is a joint responsibility of the Contractor,
consultant and appointed Environmental officer (EO) for the project. The
EO‟s primary responsibility is to ensure the implementation of the EMP
and JKR‟s EMS and to monitor and report on the site compliance on a daily
basis.

4.3.3 Scope of EMP

Scope of EMP is as per DOE Guidelines on Preparation of EMP.

4.3.4 Deliverables

The following documents shall be submitted by the Contractor:-

Table 1: Deliverables to be submitted by the Contractor to the S.O./P.D.


Documents No. of Reporting Frequency Timing
Copies

Environmental 5 Once only Within 45 days from


Management Plan (However, EMP should the date of the Letter of
(EMP) be updated when Acceptance and/or as
necessary) compliance to the
conditions of approval
of the EIA report

Environmental Quality 5 Monthly 4 weeks after


Report (EQR) monitoring

Environmental 5 Quarterly 2 weeks after audit


Monitoring and Audit
Report (EMAR)

Closure Audit Report 5 Once Only 2 weeks prior to


(CAR) issuance of Certificate
of Practical Completion
(CPC)

Note: To ensure consistency, a standard reporting format for EMP, EQR, EMAR and CAR
is provided in Appendix 3.

19
4.4 Site Office and Facilities

4.4.1 Site office, workshop, canteen and store

(a) The Contractor shall provide and maintain on site, suitable and
sufficient offices for the S.O., his representatives and the Contractor
own use.

(b) The Contractor shall also provide and maintain on site suitable
workshops and stores with impervious flooring including grease
traps.

(c) The Contractor is prohibited from discharging oil and grease to any
watercourses. Any spilled oil and grease shall be promptly removed
and this contaminated waste shall be kept in proper containers. Used
oil and grease shall be kept in separate containers for recycling. All
containers shall be stored in secured areas prior to disposal by a
licensed contractor as per the Environmental Quality (Scheduled
Wastes) Regulations 2005.

4.4.2 Accommodation for Workmen

(a) The Contractor shall provide and maintain on site, suitable and
sufficient accommodation and camps for his workmen and
supervisory staff as required in the Contract.

(b) The location of the workmen‟s accommodation shall be agreed


beforehand with the S.O. and shall be such as to avoid obstruction
and nuisance to the Works and public and shall be laid out in an
approved and orderly manner.

(c) The construction and habitation of the accommodation shall comply


with the requirements of all government and local authorities.

(d) All accommodation for workmen shall be properly ventilated and


lighted with sufficient toilet and bathing facilities and waste and
refuse collection bins/disposal. Cooking is prohibited in sleeping
quarters.

(e) The Contractor shall also provide adequate supply of water for
canteen usage and allowable cooking areas.

(f) The Contractor shall be wholly responsible for the workmen at the
accommodation provided. Activities such as hunting/ trapping of
wildlife should be strictly forbidden and fines/ penalties shall be
imposed on the Contractor by the relevant Government
Departments.

20
4.4.3 Utilities

(a) Water Supply

(i) The Contractor shall provide and maintain a potable water


supply system to all facilities required in the construction area.
The supply shall be taken from sources approved by the S.O.

(ii) The Contractor shall submit his plans for the water supply and
reticulation system, including filtration, chlorination and other
proposed treatment where required, to the S.O. for approval, not
less than thirty (30) days prior to the provision of water supply.

(iii) Potable water shall comply with the requirements of Ministry of


Health Standards.

(b) Sanitation

(i) The Contractor shall provide and maintain sufficient toilets at


appropriate locations on site as approved by the S.O. Toilets
shall be complete with adequate water closets, urinals and hand-
basins, and proper sanitary system.

(ii) The Contractor shall maintain all toilets in a clean and sanitary
condition and shall comply with requirements of the Ministry of
Health.

(iii) All wastewater must be treated such that its discharged effluent
meets the requirements of all existing legislation and
regulations.

(c) Solid waste disposal

(i) The Contractor shall undertake the collection and disposal of


solid waste such as litter, kitchen and canteen refuse, non-
hazardous solid waste including office, workshop and
accommodation waste. Solid waste collection shall be made at
least twice a week or as and when directed by the S.O.

(ii) Solid waste shall be stored in proper bins and containers,


collected and disposed off at designated site(s) approved by the
S.O. or to a locally available landfill by a licensed contractor.

(iii) A waste management schedule shall be set up to ensure that


licensed contractors carry out the collection and disposal of
waste materials at regular intervals. Proper facilities for the
temporary collection of solid waste shall be established at the
site office for construction debris and solid waste.

21
(iv) The Contractor should adopt ways to minimize waste such as
reduce, reuse and recycle of waste. Example of waste
minimizations is to reduce the amount of waste from concrete
usage, first is by ordering the correct quantity and batch or by
using concrete panels. Excess concrete can then be recycled as
concrete blocks and bench or reused as hardcore materials.

4.5 Site Clearing and Earthworks

No site clearing and earthworks shall be carried out prior to EMP approval by
relevant parties/authorities.

4.5.1 Site Clearing

(a) Site clearing shall be done in stages and within construction limit. No
burning of cleared vegetation and debris shall be allowed unless prior
approval has been obtained from the Director General of the
Department of Environment.

(b) Erosion mitigating measures shall be installed or constructed before


commencement of site clearing and earthworks. This includes
planning for „work in stages‟ and also plans for diverting as much as
possible surface runoff from the work areas.

(c) For road projects, site clearing should be from the centre of the road
outwards towards the construction limit to enable escape of wildlife
into neighbouring jungles.

(d) Cleared vegetation and debris should be disposed off to approve


designated spoil tips. The Contractor shall be responsible for
identifying these disposal areas (unless stated otherwise). The
approved disposal areas shall be prepared before any site clearing is
allowed to commence.

(e) Cleared vegetation, debris and spoils should on no account be


deposited or pushed into water-courses, streams and rivers.

(f) Trees and vegetation identified for conservation must be protected by


the Contractor at all costs.

(g) Other clearing activities such as access road construction, site office
and work-camp construction, etc shall be carried out with minimal
cutting of trees and site clearing. The intended area shall be marked
out for the S.O.‟s inspection and approval prior to any site clearing
works.

22
(h) Holes and cavities resulting from clearing, grubbing, de-stumping and
de-rooting shall be backfilled with acceptable materials and
compacted to approximate densities of adjacent areas.

(i) The Contractor shall provide all necessary temporary drainage for
keeping the site and other areas free of standing water. Efforts must
be made to channel the surface runoff as much as possible away from
the work areas.

(j) If due to unforeseen circumstances turfing cannot be carried out


immediately to the slope exposed areas, temporary protection/cover
(e.g. plastic sheet or equivalent) shall be applied over exposed
surfaces by the Contractor at his own cost.

(k) Should the Contractor fail to ensure compliance with any of the
above, the S.O. without prejudice to any other rights or remedies
available to the Government under this Contract may employ and pay
other persons to execute the work and all costs incurred in connection
with such employment shall be recoverable from the Contractor as
stipulated in the Conditions of Contract.

4.5.2 Earthworks

(a) All silt traps, sedimentation basins, erosion control measures and
drainage system as shown in drawings must be constructed in stages
and maintained by the Contractor. The location of these mitigating
measures shall be detailed and shown on plan in the EMP for the
approval of the S.O

(b) The Contractor shall provide all necessary temporary drainage for
keeping the site and other areas free of standing water before the
commencement of any earthworks. Effort must be made to channel
the surface runoff as much as possible away from the work areas.

(c) All temporary drainage, mitigation measures (e.g. silt traps and silt
fence) must be constructed before the commencement of any
earthworks and shall be maintained throughout the construction
period to ensure their effectiveness.

(d) Unsuitable materials and surplus earth shall be disposed off in


designated spoil tips, within the site or off site. Unless otherwise
stated, the Contractor shall be responsible for identifying these
disposal areas. The dump site/ disposal areas shall be identified and
approved by the S.O. before commencement of any earthworks. In
the event additional disposal areas (spoil tips) are required, the
Contractor shall also be responsible for identifying these disposal
areas which shall be approved by the S.O.

(e) The method of depositing the unsuitable materials and surplus earth to
the spoil tips must be properly engineered designed and must be

23
sufficiently graded, leveled, compacted, properly drained, revegetated
and approved by the S.O. End-tipping shall not be allowed.

(f) The Contractor shall schedule for earthworks to be carried out as


much as possible during dry weather periods. This is to ensure that
the earthwork activities being carried out are done in a
systematic/orderly manner in order to minimise earth surfaces from
being exposed for long periods during wet weather periods. Turfing
or hydro seeding must be carried out immediately after earthworks
and before work on other beam/lift commences. If due to unforeseen
circumstances turfing cannot be carried out immediately, temporary
protection/cover (e.g. plastic sheets or equivalent) shall be applied to
the exposed slopes.

(g) Should the Contractor fail to ensure compliance with any of the
above, the S.O. without prejudice to any other rights or remedies
available to the Government under this Contract may employ and pay
other persons to execute the work and all costs incurred in connection
with such employment shall be recoverable from the Contractor as
stipulated in the Conditions of Contract.

4.6 Access Roads and Existing Road

(a) All access roads to the site shall be built away from the existing
watercourses, streams and rivers with proper drainage system and be paved
for a distance of at least 10 meters from where these access roads join
existing roads.

(b) The Contractor shall maintain all access roads including the drainage
system throughout the construction period to the satisfaction of the S.O.

(c) Where the Contractor uses existing/private roads as his access, he shall be
responsible for any damage to the existing roads, bridges, drains, culverts,
roadside furniture, and all other appurtenances and services on such roads
caused by any work carried out by him throughout the construction period.
The Contractor shall repair any damages and reinstate the same to their
original condition to the satisfaction of the S.O.

(d) All temporary diversion affecting public/private roads must be approved by


the Government, private landowner and the S.O. All such diversions must
be equipped with temporary diversion signs and comply with the
requirements of Arahan Teknik (Jalan) 2C/85 of JKR. Adequate workmen
for controlling traffic diversion must be provided.

24
4.7 Pollution Control

4.7.1 Water quality

(a) All silt fence, silt traps, sedimentation basins and other erosion and
sediment control measures as shown in drawings must be
constructed and maintained by the Contractor.

(b) Water quality standards and monitoring schedule from the silt traps/
sedimentation basin/rivers/stream/water bodies shall comply as
specified in Table 2 or as directed by the S.O. Silt traps and
sediment basin discharges shall be monitored monthly and shall be
collected within 30 minutes after a rainfall event of more than
20mm depth or more.

(c) The Contractor is prohibited from discharging oil and grease to any
watercourse. Any spilled oil and grease shall be promptly removed
by the Contractor. The Contractor shall collect, keep in proper
containers, label and store all used oil and grease and other
scheduled wastes according to Environmental Quality (Scheduled
Wastes) Regulations, 2005.

(d) The Contractor shall carry out water quality monitoring at locations
on existing water bodies as indicated in the EMP. Parameters to be
tested are as specified in Table 2.

4.7.2 Noise Control

(a) All work shall be carried out with least disturbance and noise. The
Contractor shall ensure all his equipments and machineries are in
proper working condition so as to minimize the amount of noise
generated. The S.O. may require the Contractor to replace any
machinery that to his discretion is emitting excessive noise.

(b) The Contractor shall comply with the general recommendations set
out in DOE Interim Planning Guidelines for Construction Noise
together with any specific requirements described in the Contract.

(c) The Contractor shall indemnify and keep indemnified the


Government, S.O. and the S.O.‟s Representatives against any
liability for damages on account of noise or other disturbances
created while or in carrying out of the works and from and against
all claims, demands, proceedings, damages, costs charges and
expenses whatever in regard or in relation to such liability.

25
4.7.3 Air Quality

(a) Open burning of cleared vegetation, debris and construction waste


etc, shall not be allowed unless prior approval is obtained from the
Director General of the Department of Environment.

(b) The Contractor shall provide suitable spraying equipment for


regular spraying of water over the existing roads, tracks and access
roads, near settlements, completed as well as incomplete road and
other barren areas of the site used by the contractor especially
during the dry season or as and when directed by the S.O.

(c) When the Contractor‟s trucks or equipment utilizes public or private


roadways, all dirt and materials shall be removed from the trucks/
equipments by hosing, lorry wash-trough, etc. before leaving the
site.

(d) The Contractor shall provide for the prompt removal of all dirt and
other materials spilled from his or his sub-contractor‟s vehicles on
public or private roadways.

(e) For Contractor‟s trucks carrying sand, aggregates, earth and other
loose construction materials liable to spillage, tarpaulin must be
used to cover such open trucks when passing through villages and
settlements or on all roadways.

(f) The Contractor shall also ensure dust control at quarry / batching
plant (if any) complies with environmental requirement as
stipulated in the Environmental Quality (Clean Air) Regulations,
1978.

4.7.4 Vibration control

(a) All works shall be carried out with least vibration disturbance. The
Contractor shall ensure that at any time, the vibration levels
resulting from his works at or across real property boundary should
not exceed the Recommended Limit as Specified in Table 2 of this
document. No person unless duly authorized by law or carrying our
legitimate duties shall use explosives or results in explosions which
create a vibration disturbance across a real property boundary or on
a public space or right of way.

(b) The Contractor shall comply with the general recommendations set
out in DOE Interim Planning Guidelines for Vibration Limits and
Control in the Environment together with any specific requirements
described in the Contract.

26
(c) The Contractor shall indemnify and keep indemnified the
Government, S.O. and the S.O.‟s Representatives against any
liability for damages on account of vibration disturbance created
while or in carrying out of the works and from and against all
claims, demands, proceedings, damages, costs charges and expenses
whatever in regard or in relation to such liability.

27
Table 2: Environmental Quality Standards to be complied with by the Contractor
Environment Quality National Water Quality
(Sewage) Regulations, Standards (NWQS)
2009
Aspects Parameter JKR EMS
Set Target Standard Standard B Class IIA Class IIB
A
Soil loss Minimum
earthwork
Phase
construction
 6
Soil berms/bench
es for slopes
( 6m per
berm)
Reuse
topsoil
Turbidity ≤ 200 NTU - - ≤ 50 NTU ≤ 50 NTU
Suspended ≤ 100 mg/l ≤ 50 mg/l ≤ 100 mg/l ≤ 50 mg/l ≤ 50 mg/l
Solid

Biochemical ≤ 50 mg/l ≤ 20 mg/l ≤ 50 mg/l ≤ 3 mg/l ≤ 3 mg/l


Oxygen
Demand 5 @
20°C (BOD)5

Chemical ≤ 100 mg/l ≤ 120 mg/l ≤ 200 mg/l ≤ 25 mg/l ≤ 25 mg/l


Oxygen
Demand
(COD)

Water 1,2 pH 5.5 – 9 6–9 5.5 – 9 6-9 6-9

E-Coli ≤ 400 - - ≤ 100 counts ≤ 400


counts / 100 / 100ml counts /
ml 100ml

Dissolved ≥ 4 mg/l - - 5-7 mg/l 5-7 mg/l


Oxygen (DO)

Oil and ≤ 10 mg/l ≤ 5 mg/l ≤ 10 mg/l ≤ 40 µg/l, N ≤ 40 µg/l, N


Grease

Ammoniacal - ≤ 10 mg/l ≤ 20 mg/l ≤ 0.3 mg/l ≤ 0.3 mg/l


Nitrogen
(river)
Total Suspended Particulate ≤260 µg/m3/day
(TSP) (24hr)
Air3
Particulate Matter (PM10) ≤150 µg/m3/day
(24hr)

28
Receiving Land Use (residential)
Equivalent Noise Level
(Leq), L10, L90 Day time (7.00 am – 7.00 pm )
L90 ≤ 60 dBA; L10 ≤75 dBA; Lmax ≤ 90 dBA;

Evening (7.00 pm – 10.00 pm)


L90 ≤55 dBA; L10 ≤70 dBA; Lmax ≤ 85 dBA;
Noise4
Night time (10.00 pm – 7.00 am)
Noise Sensitive Areas : LAeq ≤40 dBA
Suburban Areas : LAeq ≤ 45 dBA
Urban Areas : LAeq ≤ 50 dBA

Vertical Vibration Peak Not more than 3 mm/s at receiver location or across real
Vibration5 Velocity (mm/s) property boundary.

Reference:

(1) 2nd Schedule (Regulation 7), Environmental Quality (Sewage) Regulations 2009,
Environmental Quality Act 1974.

Standard A: For location with downstream water intake


Standard B: For location with no downstream water intake

(2) National Water Quality Standards for Malaysia

Class IIA: Water Supply II – conventional treatment required


Fishery II – sensitive aquatic species
Class IIB: Recreational use with body contact

(3) Recommended Malaysian Guidelines on Ambient Air Quality

(4) Schedule 1 & Schedule 6, Planning Guidelines for Environmental Noise Limits &
Control, (Department of Environment, 2004)

(5) Planning Guidelines for Vibration Limits and Control of the Environment
(Department of Environment, 2004)

Note: N – No visible floatable materials or debris or no objectionable odour, or no


objectionable taste.

29
4.8 Preservation of Flora and Fauna

4.8.1 Flora

(a) Prior to site clearing, the forester and/or botanist engaged by JKR or
Contractor shall assist the surveyor to identify any trees of rare,
endemic or endangered species which need to be conserved or
relocated. Trees which are classified as rare, endemic and
endangered shall be conserved and marked (crossed) red. Similarly,
trees having girth of 800mm and above shall be conserved and
marked (crossed) red. Trees which are rare, endemic or endangered
and required to be relocated shall be marked (crossed) white.
Should relocation be required, trees shall have girth of 300mm and
below.

(b) The Contractor shall be responsible for the transportation of trees to


nearby sites, arboretum or other alternatives, as advised by the
forester. The Contractor shall ensure all relocated trees are well
kept.

(c) The botanist/ forester shall produce a report on the effectiveness of


the tree conservation, preservation and action plan as proposed in
the EMP as directed by the S.O. The report shall also cover aspects
of new findings not covered during the earlier investigation and
proposal of any rectification plan required.
(d) The felling of trees shall be confined within the construction limit.

(e) The Contractor shall prohibit all his and his sub-contractor‟s
employees from destroying, removing or clearing trees, timber,
shrub and other flora to any extent greater than that approved by the
S.O. as being necessary for the execution of the contract.

(f) The Contractor is prohibited from disposing waste materials


amongst vegetation within or outside the work site.

4.8.2 Fauna (Wildlife)

(a) The Contractor and his employees are prohibited from the
following:-

(i) Hunting, disturbing, capturing, endangering or destroying


such wildlife by any means (e.g. poison, baits, bird line or
net) as may be protected by relevant statutes including
removing or damaging bird nests and eggs.

(ii) Housing, confining or breeding any wildlife

30
4.9 Requirements In Relation To Waterways

(a) The Contractor and/or JKR shall seek approval from Jabatan Pengaliran &
Saliran (JPS) for any works related to natural waterways including
diversions, modifications replacements and/or relocation of rivers,
watercourses and related structures during execution of the works.

(b) The Contractor shall coordinate all operations and make adjustments to his
programmed resulting from JPS requirements pertaining to changes made
to the natural waterways.

(c) The Contractor shall ensure that temporary diversions of rivers and/or
waterways shall be capable of sustaining flows throughout the year as
specified by the JPS.

4.10 Erosion and Sediment Control (Temporary works)

4.10.1 Erosion Control

(a) Natural

(I). Bioengineering

Vetiver

The plant, Vetiver Zizanioodes (Rumput Wangi) shall be


non-seeding types tillers derived from tissue culture or
micro propagation method. The plantlets to be supplied shall
be at least an aggregate of 5 plantlets with roots at least 3 cm
long.

The Contractor shall plant Vetiver Zizanioodes in rows as


specified in the drawings or as directed by the S.O. In
difficult soil types, borrowed topsoil may be required to
refill trenches for planting the vetiver. The Contractor shall
ensure and maintain the growth of the vetiver.

Creepers

The Contractor shall plant creepers either through seeds or


saplings. Commonly used creepers are of the species
Centrusemo pubscens, Ficus pumila and Parthenocissus
himalayana. Ficus pumila and Parthenocissus himalayana
are suitable on concrete/gunited slopes and rock surfaces.

Creepers shall be planted into a planter bed previously


prepared with drainage layer/weep holes and topsoil.
Creepers should be planted individually immediately at the
toe of wall/slopes at approximately 0.3m centre to centre.

31
(II) Mulching

Mulch is a protective cover placed over the soil to protect


soil from rain, preserve moisture and slows runoff velocity.
A variety of materials can be used as mulch such as grass
clippings, leaves, hay, straw, shredded bark, sawdust, wood
chips, shredded newspaper, cardboard and wool.

(b) Proprietary products

The Contractor may also use proprietary or any man-made products


available in the market to control erosion on slopes, subject to
JKR‟s approval. The suitability of the products used shall follow the
manufacturer‟s specifications including method of installation and
maintenance. Examples of propriety products are geotubes, ENKA
mat, geocells/geoweb, fibromat and coir logs.

4.10.2 Sediment Control

The specification as described under this Section shall be read together with
other related sections of the Standard Specification for Road Works or
Standard Specification for Buildings and the drawings shall refer to the
Chapter 8 - Standard Drawings of this document.

(a) Silt Fence

Silt fence shall consist of geotextile supported by poles at regular


interval. The geotextile shall be made of non-woven material with
minimum properties of 200 g/m² or tensile strength 15 kN/m. shall
be constructed as close as possible, parallel to the contours of the
site with a setback of at least 0.9 m (3 ft0 from the toe of the slope.

The silt fence

The fence shall be inspected after every rain. The silt accumulated
behind the fence shall be removed when it has reached 2/3 of the
fence filter height and disposed at designated site. The geotextile
shall be checked for rips, tears and other types of deterioration and
replaced as needed.

(b) Silt Trap/Sediment Basin

Silt trap/sediment basin comprises rocks in gabions, shall be


constructed in respective catchment area to collect and store
sediment prior to entering natural waterways.

The silt traps/sediment basins shall be inspected regularly especially


after heavy rain and any damages shall be rectified. The sediment

32
accumulated in the silt traps/sediment basins shall be removed when
it has reached 2/3 of its depth and disposed at designated site.

(c) Gabion Wall

A gabion wall which comprises rocks in gabions but of smaller


nature compared to silt trap, shall be constructed in difficult terrains
such as on slopes and narrow valleys for the purpose of collecting
and storing sediment prior to entering natural waterways.

(d) Check Dam

A check dam which is a small, temporary or permanent dam shall


be constructed across a drainage ditch, swale or channel for the
purpose of lowering the speed of concentrated flows.

The check dams shall be inspected regularly especially after heavy


rain and any damages shall be rectified. The sediment accumulated
behind the check dams shall be removed when it has reached 2/3 of
its height and disposed at designated site. The height of the check
dam shall be maintained to be the same at all time.

(e) Silt Curtain

Silt curtain shall be used to mitigate sediments by confining


sediments and prevent dispersal and contamination of the water
body especially in lakes and riverbanks. Silt curtain shall also be
used as a divider to prevent sediment laden-water from migrating to
the rest of the water body.

Silt curtain shall be checked for rips, tears and other types of
deterioration and replaced as needed. The suspended sediments
trapped behind silt curtain shall be allowed to settle for a minimum
of 24 hours, prior to removal of the silt curtain.

(f) Sand bag barrier

A sandbag barrier is a series of sand-filled bags placed on a level


contour to intercept sheet flows. Sandbag barriers pond sheet flow
runoff, allowing sediment to settle out.

Sandbag barriers are suitable as a linear sediment control measure


which includes below the toe of slopes and erodible slopes, as
sediment traps at culvert/pipe outlets, down slope of exposed soil
areas, around temporary stockpiles and spoil areas, as check dams
across mildly sloped construction roads and parallel to a roadway to
keep sediment off paved areas.

Sand bag barrier shall be checked daily before and after rain events,
In addition, sandbags exposed to sunlight will cause degradation

33
and need to be replaced immediately. Sediment should be removed
when the sediment accumulation reaches one-third of the barrier
height and disposed at designated site.

NOTES: Other items not specified above shall be referred to


the Standard Specification for Road Works
JKR/SPJ/1988 of Section 1 – General, Section 2 –
Earthworks and Section 3 – Drainage Works

REFER TO APPENDIX 1 : Standard Specifications


For Building Works (2005 Edition):- SECTION A :
PRELIMINARIES AND GENERAL CONDITIONS
AND SECTION C : EXCAVATIONS AND
EARTHWORKS

4.11 Permanent Works

4.11.1 Noise Barrier

(a) Noise barrier shall be provided in sensitive areas such as housing,


schools and hospitals situated beside busy roads or highways.

(b) The type of noise barrier used shall be either absorptive, reflective,
dispersive or mixed depending upon the noise level survey
conducted or recommendations made by the relevant Consultant.

(c) The Contractor shall supply and install noise barrier including
maintenance until the expiry of the defects liability period.

(d) For concrete noise barrier, creepers shall be planted and maintained
to cover the said noise barrier until the expiry of the defects liability
period.

34
CHAPTER 5

METHOD OF MEASUREMENT

35
CHAPTER 5: METHOD OF MEASUREMENT

Non-Physical Work

5.1 Environmental Impact Assessment (EIA) (If Applicable)

5.1.1 EIA Report

Unit

The unit of measurement for preparation of EIA Report shall be Lump Sum
(sum).

Measurement

The measurement for payment shall be the preparation and approval of the
EIA report in accordance to the format in the Guidelines for EIA of
Highway/Road Projects and A Handbook of EIA Guidelines prepared by
Department of Environment (DOE).

Pricing Factors

The item for preparation of the EIA Report shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Cost of any study required, literatures, references, consultation in


the production of the EIA Report;

(b) Cost for the engagement of a registered environmental consultant


required for carrying out the respective study and preparation of the
said report;

(c) Submission of twenty one (21) hard copies and one (1) digital copy
of the approved and accepted report to S.O. The copyright of the
said documents shall be transferred and become the absolute
property of the Government.

5.2 Environmental Management Plan (EMP)

5.2.1 Preparation and acceptance of EMP

Unit

The unit of measurement for preparation and acceptance of EMP shall be


Lump Sum (sum) and include:

(a) Erosion and Sediment Control Plan (ESCP)

36
Pricing Factor

The item for preparation of ESCP shall be in accordance with the


Preambles to Bill of Quantities:-

(a) all cost associated in the preparation of a complete report on


drainage system, erosion control plan and course of action to be
taken;

(b) additional cost for the engagement of a professional engineer


required for the preparation of the ESCP;

(c) Submission of five (5) copies of ESCP for endorsement by the S.O.

(d) Flora Management Plan for tree conservation including method of


preservation and course of action to be taken

(e) Wildlife Management Plan for translocation animal to approved


location by Jabatan Perhilitan.

Measurement

The measurement for payment shall be made upon submission and


acceptance of the EMP prepared in accordance to the format as stipulated
in the DOE General Checklist for Preparing EMP as follows:-

(a) 60% upon submission of draft EMP to S.O.;

(b) 40% upon approval of EMP by DOE/JKR

Pricing Factor

The item for preparation of EMP including updating and revision shall be
in accordance with the Preambles to Bill of Quantities:-

(a) Cost of literatures, references, consultation and all that is required


and specified for the production of the EMP;

(b) cost for the engagement of the registered environmental consultant


required for the preparation of the EMP including its updating and
revision;

(c) Submission of five (5) copies and one (1) digital copy of the
approved and accepted EMP for endorsement by the S.O. The
copyright of the said documents shall be transferred and become the
absolute property of the Government.

37
5.3 Environmental Officer (E.O.)

5.3.1 Environmental Officer

Unit

The unit of measurement for provision of E.O. shall be Lump Sum (sum).

Measurement

The measurement for payment shall be made in each interim payment in


proportion of the total period lapsed to the Contract Period (excluding
Defects Liability Period).

The measurement for payment shall be the man-month basis throughout the
contract period (excluding Defects Liability Period).

Pricing Factors

The item for provision of E.O., assigned to be responsible for


environmental management works only, shall be in accordance with the
Preambles to Bill of Quantities:-

(a) The wages and other emoluments paid to the E.O.;

(b) Working outside the Contractor‟s normal working hours if so


required by the S.O.;

(c) The Contractor, with the approval of the S.O., shall employ a
competent E.O. (A Graduate in science and/or engineering field
with a minimum of one year experience in the environmental
sector);

(d) Costs and expenses incurred consequent upon the employment or


hiring of a competent full time E.O. throughout the contract period
including payment of Employee Provident Fund, insurance, medical
and hospitalization;

(e) Costs and expenses incurred for the training/awareness briefing by


the E.O. to site personnel whose activities have impact on the
environment;

(f) Replacement of incompetent E.O. to the equivalent level or higher


to the approval of the S.O.;

(g) Any substitution when the appointed E.O. is absent or on leave for
more than three (3) consecutive days.

38
5.4 Environmental Monitoring, Audit And Training

5.4.1 Environmental Monitoring

5.4.1 (i) Water Quality Monitoring


5.4.1 (ii) Air Quality Monitoring
5.4.1 (iii) Noise Monitoring
5.4.1 (iv) Vibration Monitoring

Unit

The unit for measurement to conduct the above monitoring shall be


Lump Sum (sum) for the whole duration of the contract.

Measurement

The measurement for payment shall be the number of samples taken


for monitoring, tested and accepted by the S.O.

Pricing Factor

The item to conduct environmental monitoring (water, air, noise and


vibration) shall be in accordance with the Preambles to Bill of
Quantities:-

(a) Provision of all necessary equipments as specified;

(b) Carrying out calibration of all necessary equipments prior to


use;

(c) Taking samples according to the intervals, parameters and


for the duration specified at approved sampling locations by
trained laboratory personnel;

(d) Recording and noting of specified data;

(e) Sending samples collected, testing and analysis at approved


independent accredited laboratory. The analysis report shall
be signed by a registered chemist;

(f) Submission of analysed results for purpose of reporting


(preparation of monitoring report is measured separately).

5.4.1 (v) Environmental Quality Report

Unit

The unit of measurement for the preparation of submission of the


Environmental Quality Report shall be Lump Sum (sum) for the
whole duration of the contract.

39
Measurement

The measurement for payment shall be the number of reports


prepared based on monitoring carried out and accepted by the S.O.

Pricing Factor

The item for preparation of the monitoring report shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Cost associated in the preparation of a comprehensive


report;

(b) Submission of five (5) copies of report to S.O.

5.4.2 Environmental Audit and Closure Audit

Unit

The unit of measurement to conduct environmental audit and preparation of


environmental monitoring and audit report shall be Lump Sum (sum) for
the whole duration of the contract.

Measurement

The measurement for payment shall be the number of reports prepared


based on audits carried out and accepted by the S.O.

Pricing Factor

The item to conduct environmental audit and preparation of report


including the Closure Audit Report shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Cost and expenses incurred consequent upon the engagement of a


competent, independent environmental auditor, registered with
DOE and/or have attended courses on ISO 14001 auditing with a
minimum of auditing experience for at least 3 sites;

(b) Cost of carrying out quarterly audits or at any other intervals


deemed necessary due to the nature of works on site, evaluation of
monitoring data and verifying implementation of corrective and
preventive actions;

(c) Cost associated in the preparation of a comprehensive report


including recommendations for improvement in accordance with the
Standard Report Format as specified in Appendix 2 of this
Document;

40
(d) Submission of five (5) copies of report (per audit) with colour
photographs to S.O.

5.4.3 Training

Unit

The unit of measurement for training shall be in number (no).

Measurement

The measurement for payment shall be the number of training sessions


carried out for the duration of the contract.

Pricing Factor

The item for training JKR personnel shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Cost associated in organizing and conducting training of JKR


personnel locally pertaining to Environmental Management, EIA,
Safety and Health, Environmental related legal and other
requirements.

Physical Work

5.5 Dust and Mud Control

5.5.1 Water Bowser Truck

Unit

The unit of measurement for provision, operation and maintenance of water


bowser truck shall be in number (no).

Measurement

The measurement for payment shall be the number of water bowser truck
provided on site and shall be made as follows:-

(a) 60% on complete provision of vehicle and equipment to the


satisfaction of the S.O.;

(b) 40% for operation and maintenance which shall be made in each
interim payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

41
Pricing Factor

The item for provision, operation and maintenance of bowser truck shall be
in accordance with the Preambles to Bill of Quantities:-

(a) All cost associated with the provision and operation of trucks
including operators, water supply, pumping of water, water tank and
all other necessary equipments needed to carryout water spraying;

(b) Carrying out water spraying minimum 3 times a day along


haul/access roads, existing road and nearby settlement zone or other
affected areas or as directed by S.O.;

(c) Maintenance in a roadworthy condition of trucks and associated


equipments;

(d) Provision of suitable replacement including equipment when the


regular truck is not available or unserviceable for more than 24
hours;

(e) Removal of truck and equipment from site on completion of the


works.

5.5.2 Tyre Washing Facilities

5.5.2 (i) Portable Water Jet

Unit

The unit of measurement for provision, operation and maintenance


of portable water jet shall be in number (no).

Measurement

The measurement for payment shall be the number of portable


water jet provided on site and shall be made as follows:-

(a) 60% on complete construction of structure, platform,


provision and installation of all equipments to the
satisfaction of the S.O.;

(b) 40% for operation and maintenance which shall be made in


each interim payment in proportion of the total period lapsed
to the Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for provision, operation and maintenance of portable water


jet shall be in accordance with the Preambles to Bill of Quantities:-

42
(a) cost of construction and maintenance of the structure for the
elevated water tank and the supply of the water tank;

(b) cost for the construction of the tyre washing concrete


platform;

(c) provision of portable water jet including operator and


other necessary equipment deemed required for the
successful washing operation;

(d) carrying out cleaning of all vehicle tyres at various exits of


worksites;

(e) maintenance of all cleaning facilities and associated


equipments;

(f) provision of replacement when the regular equipment is not


available or unserviceable for more than 24 hours;

(g) demolition, and disposal of all rubbish, debris and surplus


material including removal of all equipment from site on
completion of the works to the satisfaction of the S.O.
including reinstatement of the site.

5.5.2 (ii) Wash Trough

Unit

The unit of measurement for construction and maintenance of wash


trough shall be in number (no).

Measurement

The measurement for payment shall be the number of wash trough


constructed on site as shown in Drawing and shall be made as
follows:-

(a) 80% on complete construction to the satisfaction of the S.O.;

(b) 20% for maintenance which shall be made in each interim


payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for construction and maintenance of wash trough shall be


in accordance with the Preambles to Bill of Quantities:-

(a) Preparation of site and approaches including excavation and


disposal of surplus excavated material;

43
(b) Construction of wash trough including concrete, formwork,
reinforcement, hardcore complete as shown in Drawing;

(c) Filling and regular maintaining of water during the course of


the works;

(d) Maintenance of wash trough and surrounding areas clean


including desalting and disposal of material;

(e) Demolition and disposal of all rubbish, debris and surplus


material from the site to the satisfaction of the S.O.
including reinstatement of the site.

5.5.3 Water Sprinkler

Unit

The unit of measurement for provision and maintenance of water sprinkler


shall be in number (no)

Measurement

The measurement for payment shall be the number of water sprinkler


installed at quarry/batching plant and shall be made as follows:-

(a) 40% on complete installation;

(b) 60% for operation and maintenance which shall be made in each
interim payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for provision and maintenance of water sprinkler shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Supply and installation of water sprinkler system including all other
necessary equipments and facilities;

(b) Maintenance of water sprinkler system and associated equipments;

(c) Removal of all installation on site to the satisfaction of the S.O.

44
5.6 Erosion Control

5.6.1 Creepers

Unit

The unit of measurement for planting and maintenance of creepers shall be


square metre (m²).

Measurement

The measurement for payment shall be made of the plan area placed to the
lines, level grades and dimensions shown in Drawing or as directed by the
S.O.

Pricing Factor

The item for planting and maintenance of creepers shall be in accordance


with the Preambles to Bill of Quantities:-

(a) Removal of debris from the surfaces of earthwork to be turfed;

(b) The preparation of the areas to be turfed including if appropriates


the amount of topsoil to be used and its method of application;

(c) The details and results of investigations to determine which types of


grass and legume are compatible with the soil in the areas to be
turfed;

(d) The types of grass and legume (if any) and strains of seed to be
used, and the function, root and growth characteristics of each type;

(e) The rates of application of the grass and legume seeds;

(f) The type of mulch to be used and its method and rate of application;

(g) The amount of lime or other chemicals (if any) to be applied to


improve the soil before, during and after turfing;

(h) The equipment and methods to be used in preparing and placing the
turf mix and other materials;

(i) The cultivation and after – care of the turfed areas, including rates
and frequencies of watering, fertilising, grass cutting and general
maintenance for 1 year after turfing;

(j) An estimate of the time required after turfing for establishment of a


permanent dense growth of grass which will require minimal
maintenance.

45
5.6.2 Artificial Erosion Control Items

Unit

The unit of measurement for installation and maintenance of artificial


erosion control items shall be square metre (m²).
Measurement

The measurement for payment shall be made of the plan area placed to the
lines, level grades and dimensions shown in Drawing or as directed by the
S.O.

Pricing Factor

The item for installation and maintenance of artificial erosion control items
shall be in accordance with the Preambles to Bill of Quantities:-

(a) Removal of debris from the surfaces of earthwork to be artificially


controlled;

(b) The preparation of the areas to be artificially controlled including (if


any) the amount of topsoil to be used and its method of application;

(c) The details and results of investigations to determine which types


artificial erosion control items used are compatible with the soil in
the areas to be artificially controlled;

(d) The types of artificial erosion control items (if any) and strains of
artificial erosion control items to be used, and the function, root and
growth characteristics of each type;

(e) The type of artificial erosion control items to be used and its method
and rate of application including equipments and maintenance
required.

5.7 Sediment Control

5.7.1 (i) Construction of Silt Fence

Unit

The unit of measurement for construction of silt fence shall be


linear metre (m).

Measurement

The measurement for payment shall be the length of complete fence


constructed as shown in Drawing and shall be made as follows:-

46
(a) 80% on complete construction to the satisfaction of the S.O.

(b) 20% on removal

Pricing Factor

The item for construction of silt fence shall be in accordance with


the Preambles to Bill of Quantities:-

(a) Clearing of site for base preparation;

(b) Construction of silt fence complete as shown in drawing;

(c) Removal and disposal of all rubbish, debris and surplus


material from the site

(d) To the satisfaction of the S.O. including reinstatement of the


site

5.7.1 (ii) Maintenance of Silt Fence

Unit

The unit of measurement for maintenance of silt fence shall be


linear metre (m).

Measurement

The measurement for payment shall be made in each interim


payment in proportion of the total period lapsed to the Contract
Period (excluding Defects Liability Period).

Pricing Factor

The item for maintenance of silt fence shall be in accordance with


the Preambles to Bill of Quantities:-

(a) Inspection at regular interval and after heavy rain of


geotextile and other components for rips, tears and other
types of deterioration and replacement if required;

(b) Removal of silt and sediment accumulated to approximate


2/3 of filter height including its disposal.

47
5.7.2 Sand bag barrier

5.7.2 (i) Installation of sand bag barrier

Unit

The unit of measurement for Installation of sand bag barrier


shall be in number (no).

Measurement

The measurement for payment shall be the number of sand


bag barrier constructed as shown in Drawing and approved
by the S.O. and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;

(b) 20% on removal

Pricing Factor

The item for construction of installation of sand bag barrier


shall be in accordance with the Preambles to Bill of
Quantities:-

(a) Labour required for installation purposes;

5.7.2 (ii) Maintenance of sand bag barrier

Unit

The units of measurement for maintenance of sand bag


barrier shall be in number (no).

Measurement

The measurement for payment shall be maintenance of the


completed sand bag barrier and shall be made in each
interim payment in proportion of the total period lapsed to
the Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for maintenance of sand bag barrier shall be in


accordance with the Preambles to Bill of Quantities:-

48
(a) Sand bag barrier shall be checked daily before and
after rain events, weekly during the rainy season, and
at two-week intervals during the non-rainy season.

(b) Sediment should be removed when the sediment


accumulation reaches to approximate 1/3 of the
barrier height and it has to be incorporated into
earthwork on the site or disposed at an appropriate
location.

5.7.3 Silt Trap & Sediment Basin

5.7.3 (i) Gabion

Unit

The unit of measurement for construction of gabion units in


silt traps or sediment basins shall be in number (no)

Measurement

The measurement for payment shall be the number of


specified size gabion unit constructed as shown in Drawing
and approved by the S.O. and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;

(b) 20% on removal

Pricing Factor

The item for construction of gabion units in silt traps and


sediment basins shall be in accordance with the Preambles to
Bill of Quantities:-

(a) Excavation for preparation of the silt trap and


disposal of surplus excavated material;

(b) Construction of gabion overflow including cage,


geotextile and rock fill complete as shown in
Drawing;

(c) Assembling, tying and staking for the positioning of


the gabion units. ;

(d) Removal and disposal of all rubbish, debris and


surplus material from the site to the satisfaction of
the S.O. including reinstatement of the site

49
5.7.3 (ii) Sand Bedding

Unit

The unit of measurement for sand bedding in silt traps or


sediment basins shall be in cubic meter (m3).

Measurement

The measurement for payment shall be the volume of sand


bedding constructed as shown in Drawing and approved by
the S.O. and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;

(b) 20% on removal

Pricing Factor

The item for construction of sand bedding in silt traps and


sediment basins shall be in accordance with the Preambles to
Bill of Quantities:-

(a) Excavation for construction of the sand bedding and


disposal of surplus excavated material;

(b) Maintenance of the sand bedding to effectively


control siltation and sedimentation.

5.7.3 (iii) Stone Filling

Unit

The unit of measurement for construction of stone filling in


silt traps or sediment basins shall be in cubic meter (m3).

Measurement

The measurement for payment shall be the volume of stone


filling constructed as shown in Drawing and approved by the
S.O. and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;

(b) 20% on removal

50
Pricing Factor

The item for construction of stone filling in silt traps and


sediment basins shall be in accordance with the Preambles to
Bill of Quantities:-

(a) Excavation for construction of stone filling and


disposal of surplus excavated material;

(b) Maintenance of the stone filling to effectively control


siltation and sedimentation.

5.7.3 (iv) Mortared Rip Rap

Unit

The unit of measurement for construction of mortared rip


rap in silt traps or sediment basins shall be in cubic meter
(m3).

Measurement

The measurement for payment shall be the volume of


mortared rip rap constructed as shown in Drawing and
approved by the S.O. and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;

(b) 20% on removal

Pricing Factor

The item for construction of mortared rip rap in silt traps and
sediment basins shall be in accordance with the Preambles to
Bill of Quantities:-

(a) Excavation for construction of the mortared rip rap


and disposal of surplus excavated material;

(b) Maintenance of the mortared rip rap to effectively


control siltation and sedimentation.

5.7.3 (v) Excavation for silt trap construction

Unit

The unit of measurement for excavation of earth for silt


traps or sediment basin shall be in cubic meter (m3).

51
Measurement

The measurement for payment shall be the volume of earth


excavated as shown in Drawing and approved by the S.O.
and made as follows:-

(a) 80% on complete construction to the satisfaction of


the S.O.;
(b) 20% on removal

Pricing Factor

The item for excavation of earth for silt traps or sediment


basin shall be in accordance with the Preambles to Bill of
Quantities:-

(a) Excavation for preparation of the silt trap and


disposal of surplus excavated material;

5.7.3 (vi) Maintenance of Silt Trap or Sediment Basin

Unit

The units of measurement for maintenance of silt trap or


sediment basin shall be lump sum (sum).

Measurement

The measurement for payment shall be maintenance of the


completed silt trap or sediment basin and shall be made in
each interim payment in proportion of the total period lapsed
to the Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for maintenance of silt trap or sediment basin shall


be in accordance with the Preambles to Bill of Quantities:-

(a) Regular inspection and maintenance throughout the


construction period as directed by the S.O. and make
good and replace any damaged component;

(b) Removal of silt and sediment accumulated to


approximate 2/3 of filter height including disposal;

(c) Inspection at regular interval and after heavy rain for


damage and other types of deterioration and
replacement if required

52
5.7.3 (vii) Temporary Drainage

Unit

The unit of measurement for provision and maintenance of


temporary earth drain shall be cubic metre (m3).

Measurement

The measurement shall be the volume of the void formed


from the surface of the ground after clearing and excavation
of top soils to the lines, levels, grades and dimensions as
shown in Drawings or as directed by the S.O.

Pricing Factor

The item for provision and maintenance of temporary earth


drain shall be in accordance with the Preambles to Bill of
Quantities:-

(a) Preparation of site, excavation, leveling, trimming,


shaping and compacting surface of excavation to the
required lines, levels, grade and dimensions and
disposal of surplus excavated material;

(b) Reinstatement of site on completion of the work, to


the satisfaction of the S.O.

(c) Inspection at regular interval and after heavy rain to


check for clogs and sediment-laden;

(d) Removal of accumulated sediment to disposal site


and reshaping of temporary drainage;

5.7.4 Gabion Wall

5.7.4 (i) Construction of Gabion Wall

Unit

The unit of measurement for construction of gabion wall


shall be in number (no).

Measurement

The measurement for payment shall be the number of


specified size gabion constructed as shown in Drawing and
approved by the S.O. and made as follows:-

53
(a) 80% on complete construction to the satisfaction of
the S.O.;

(b) 20% on removal

Pricing Factor

The item for construction of gabion wall shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Excavation for preparation of bed and disposal of


surplus excavated material;
(b) Construction of gabion overflow including cage,
geotextile and rockfill complete as shown in
Drawing;

(c) Assembling, tying and staking for the positioning of


the gabion units;

(d) Removal and disposal of all rubbish, debris and


surplus material from the site to the satisfaction of
the S.O. including reinstatement of the site.

5.7.4 (ii) Maintenance of Gabion Wall

Unit

The unit of measurement for maintenance of gabion shall be


in number (no).

Measurement

The measurement for payment shall make in each interim


payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for maintenance of gabion wall shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Regular inspection and maintenance throughout the


construction period as directed by the S.O. and make
good and replace any damaged component;

(b) Removal of accumulated silt and sediment when full


including disposal.

54
5.7.5 Check Dam

5.7.5 (i) Construction of Check Dam

Unit

The unit of measurement for construction of check dam shall


be cubic metre (m3).

Measurement

The measurement for payment shall be the volume of rock


constructed as shown in drawing and approved by the S.O.
and made as follows:-
(a) 80% on complete construction to the satisfaction of
the S.O.;

(b) 20% on removal.

Pricing Factor

The item for construction of check dam shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Excavation for preparation of bed and disposal of


surplus excavated material;

(b) Construction of rock check dam including overflow


complete as shown in Drawing;

(c) Removal and disposal of check dam, all rubbish,


S.O. including reinstatement of the site.

5.7.5 (ii) Maintenance of Check Dam

Unit

The unit of measurement for maintenance of check dam


shall be cubic metre (m3).

Measurement

The measurement for payment shall be maintenance of the


completed check dam and shall be made in each interim
payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

55
Pricing Factor

The item for maintenance of check dam shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Regular inspection and maintenance throughout the


construction period as directed by the S.O. and make
good and replace any damaged component;

(b) Removal of silt and sediment accumulated to


approximate 2/3 of filter height including disposal.

5.7.6 Silt Curtain

5.7.6 (i) Installation of Silt Curtain

Unit

The unit of measurement for installation of silt curtain shall


be square metre (m2).

Measurement

The measurement for payment shall be the area of curtain


constructed as shown in drawing and approved by the S.O.
and made as follows:-

(a) 80% on complete installation to the satisfaction of


the S.O.;

(b) 20% on removal

Pricing Factor

The item for installation of silt curtain shall be in accordance


with the Preambles to Bill of Quantities:-

(a) Installation of silt curtain complete as shown in


drawing;

(b) Removal including of all rubbish, debris and surplus


material from the site to the satisfaction of the S.O.

5.7.6 (ii) Maintenance of Silt Curtain

Unit

The unit of measurement for maintenance of silt curtain


shall be square metre (m2).

56
Measurement

The measurement for payment shall be maintenance of the


completed silt curtain and shall be made in each interim
payment in proportion of the total period lapsed to the
Contract Period (excluding Defects Liability Period).

Pricing Factor

The item for maintenance of silt curtain shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Inspection at regular interval and after heavy rain for


rips tears and other types of deterioration and
replacement if required.

5.8 Topsoil and Finished Slope Temporary Protection

5.8.1 Plastic Sheeting

Unit

The unit of measurement for plastic sheeting to temporarily cover topsoil


and finished slope shall be square metre (m2).

Measurement

The measurement for payment shall be the area of sheeting laid (laps shall
not be measured for payment) as approved by the S.O. and made as
follows:-

(a) 90% on complete installation to the satisfaction of the S.O.;

(b) 10% on maintenance and removal

Pricing Factor

The item for installation of plastic sheeting shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Supply and placing of sheeting to cover topsoil stockpile.

5.8.2 Silt Fence

Unit

The unit of measurement for construction of silt fence shall be linear metre
(m).

57
Measurement

The measurement for payment shall be the length of complete fence


constructed as shown in drawing and shall be made as follows:-

(a) 80% on complete construction to the satisfaction of the S.O.

(b) 20% on removal

Pricing Factor

The item for construction of silt fence shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Clearing of site for base preparation;

(b) Construction of silt fence complete as shown in drawing;

(c) Removal and disposal of all rubbish, debris and surplus material
from the site

(d) To the satisfaction of the S.O. including reinstatement of the site

5.9 Fuel Spillage Management

5.9.1 Containment Bund for Bulk Fuel Tank

Unit

The unit of measurement for skid tank bund shall be in number (no).

Measurement

The measurement for payment shall be the number constructed as shown in


drawing and approved by the S.O. and made as follows:-

(a) 70% on complete construction to the satisfaction of the S.O.;

(b) 20% on maintenance;

(c) 10% on removal.

Pricing Factor

The item for construction of containment bund shall be in accordance with


the Preambles to Bill of Quantities:-

(a) Excavation for preparation of base and disposal of surplus


excavated material;

58
(b) Construction of concrete base, brick wall including grease trap with
oil and grease separator overflow complete as shown in Drawing;

(c) Regular cleaning and maintenance of grease trap, bund and


surrounding areas to prevent surface corrosion;

(d) Installation of proper drainage to bund and surrounding area;

(e) Demolition, removal and disposal of bund and all rubbish, debris
and surplus material from the site to the satisfaction of the S.O.
including reinstatement of the site.

5.10 Waste Management

5.10.1 Scheduled Waste Disposal

5.10.1 (i) Storage Shed

Unit

The unit of measurement for construction of storage shed


shall be Lump Sum (sum)

Measurement

The measurement for payment shall be the shed constructed


as shown in Drawing and approved by the S.O. and made as
follows:-

(a) 90% on complete construction to the satisfaction of


the S.O.;

(b) 10% on maintenance and removal

Pricing Factor

The item for construction of containment bund shall be in


accordance with the Preambles to Bill of Quantities:-

(a) All cost associated with the construction,


maintenance and removal of suitable storage shed for
the purpose of housing scheduled wastes

5.10.1 (ii) Scheduled Wastes

Unit
The unit of measurement for disposal of scheduled waste
shall be Lump Sum (sum).

59
Measurement

The measurement for payment shall be the number of


consignment of scheduled waste disposed from the project
site.

Pricing Factor

The item for disposal of scheduled waste shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Identifying the category of scheduled waste


generated from the project site as per the 1st
Schedule;

(b) Treating and recovering of scheduled waste


generated on site according to the regulations and
specification;

(c) Storing and labeling of scheduled waste as per


regulations;

(d) Delivering of scheduled waste by licensed contractor


to prescribed premises for treatment;

(e) Training of all relevant employees involved in


identification, handling, transportation, storage and
response to spillage or release of scheduled wastes.

5.10.2 Grease Trap

Unit

The unit of measurement for grease trap shall be in number (no).

Measurement

The measurement for payment shall be the number of grease trap


constructed as shown in drawing.

Pricing Factor

The item for construction of grease trap shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Construction and maintenance of grease trap at kitchen areas,


sharing and workshop;

60
(b) Skimming of oil and grease from the trap for disposal as scheduled
waste;

(c) Removal of grease traps to the satisfaction of S.O.

5.11 Management of Disposal Site for Surplus Material

5.11.1 Earthworks

5.11.1 (i) Close Turfing

Refer to Earthworks Method of Measurement

5.11.1 (ii) Hydroseeding with fibromat or equivalent

Refer to Earthworks Method of Measurement

5.11.1 (iii) Vertiver Z

Unit

The unit of measurement for planting and maintenance of vertiver Z


shall be square metre (m²).

Measurement

The measurement for payment shall be made of the plan area placed
to the lines, level grades and dimensions shown in Drawing or as
directed by the S.O.

Pricing Factor

The item for planting and maintenance of vertizer Z shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Removal of debris from the surfaces of earthwork to be


turfed;

(b) The preparation of the areas to be turfed including if


appropriates the amount of topsoil to be used and its method
of application;

(c) The details and results of investigations to determine which


types of grass and legume are compatible with the soil in the
areas to be turfed;

61
(d) The types of grass and legume (if any) and strains of seed to
be used, and the function, root and growth characteristics of
each type;

(e) The rates of application of the grass and legume seeds;

(f) The type of mulch to be used and its method and rate of
application;

(g) The amounts of lime or other chemicals (if any) to be


applied to improve the soil before, during and after turfing;

(h) The equipment and methods to be used in preparing and


placing the turf mix and other materials;

(i) The cultivation and after – care of the turfed areas, including
rates and frequencies of watering, fertilising, grass cutting
and general maintenance for 1 year after turfing;

(j) An estimate of the time required after turfing for


establishment of a permanent dense growth of grass which
will require minimal maintenance;

5.11.1 (iv) Creepers

Unit

The unit of measurement for planting and maintenance of creepers


shall be square metre (m²).

Measurement

The measurement for payment shall be made of the plan area placed
to the lines, level grades and dimensions shown in Drawing or as
directed by the S.O.

Pricing Factor

The item for planting and maintenance of creepers shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Removal of debris from the surfaces of earthwork to be


turfed;

(b) The preparation of the areas to be turfed including if


appropriates the amount of topsoil to be used and its method
of application;

62
(c) The details and results of investigations to determine which
types of grass and legume are compatible with the soil in the
areas to be turfed;

(d) The types of grass and legume (if any) and strains of seed to
be used, and the function, root and growth characteristics of
each type;

(e) The rates of application of the grass and legume seeds;

(f) The type of mulch to be used and its method and rate of
application;

(g) The amount of lime or other chemicals (if any) to be applied


to improve the soil before, during and after turfing;

(h) The equipment and methods to be used in preparing and


placing the turf mix and other materials;

(i) The cultivation and after – care of the turfed areas, including
rates and frequencies of watering, fertilising, grass cutting
and general maintenance for 1 year after turfing;

(j) An estimate of the time required after turfing for


establishment of a permanent dense growth of grass which
will require minimal maintenance;

5.11.2 Drainage

Taken from Drainage Works Method of Measurement:-

4.8 Surface Drain

Unit

The unit of measurement for surface drain shall be linear metre (m).

Measurement

The measurement for payment shall be length measured along the


centre line of the drain as shown on the drawings or as directed by
the S.O between any of the following:

(a) The external faces of manholes, sump, chambers, and like


the like;

(b) The external faces of headwalls, inlet and outlet structures


and the like;

(c) The intersections of the centre at drain/pipe junctions;

63
(d) The position of terminations as shown on the drawings; and

(e) The point of change of stage depth.

In the case of cascade drains, the length shall be measured along the
centre line of the projected horizontal plane. No allowance shall be
made foe laps.

The depth of drains shall be the vertical measurement between the


invert and the lowest of the following:

(a) Lower existing ground level at sides;

(b) Lower formations level at sides;

(c) At slopes, for the lower finished earthwork level at sides


prior to top soiling measured perpendicular to the invert;

(d) Lower finished earthworks level at sides

The average depth to invert shall be calculated arithmetic means of


the depths taken at intervals of 10 metres along the drains starting
from the outfall end. For terminal lengths of drains less than 10
metres long, the measurement of depths shall be taken at their ends.

Where the depth of drains are not stated, the Contractor shall
establish the depth of excavation required from the information
provided in the Contract and allow their costs in the rates.

Item Coverage

The item for the drain shall be in accordance with the Preambles to
the Bill of Quantities General Directions and shall include:

(a) Locating existing drains;

(b) Breaking into existing drains, chambers and the like, dealing
with existing flow and making connections unless otherwise
measured separately;

(c) Hand or machine excavation in any material except rock,


dewatering upholding the sides, keeping the excavation free
of water, backfilling with approved material from any source
and compaction;

(d) Taking precautions to avoid damage to existing works


including providing temporary supports;

(e) Excavation and filling of soft spot with granular backfilling


material and compaction;

64
(f) Brickworks (including rendering), stonework, filter
materials, pipes and fittings including cutting, laying,
stepping and jointing;

(g) Building in drains to sumps, chambers, headwalls and the


like;

(h) Blinding and bedding;

(i) Concrete bedding hunching and surround and cement


mortar;

(j) Formwork and reinforcement;

(k) Trimming of sides‟ slopes and inverts, leveling and


compaction;

(l) Stepping of inverts;

(m) Double handling and disposal of material to dumping site off


site provided by the Contractor;

(n) Movement joints to concrete beds surrounds and the like;

(o) Reinstatement of surfaces;

(p) Taking precautions to prevent siltation and desalting prior to


handling over;

(q) Checking and cleaning;

(r) R.C struts for blocks to drain with brick sides, precast
concrete covers (where specified, mild steel gratings, frame
and bedding);

(s) Additional excavation the contractor may require for


working space and its subsequent backfilling; and

(t) Transport, unload, storage and multiple handling of precast


concrete drain sections.

4.10 Sumps

Unit

The unit of measurement for sump shall be number (no).

65
Measurement

The measurement shall be the number of the completed sump (walls


and base) as shown on the Drawing or as directed by the S.O. The
depth shall be the distance between the top surface or the structure
and the invert if the main channel or upper most surface of the base
slab.

Item Coverage

The item of the sump shall be accordance with the Preambles to the
Bill of Quantities General Directions and shall include:

(a) Excavation in any material except rock, upholding the sides,


keeping excavation free of water, backfilling with approved
material from any source and compaction, double handling
and disposal of material;

(b) Taking precautions to avoid damage to existing works


including providing temporary supports;

(c) Trimming of side slopes and inverts, leveling and


compaction;

(d) Excavation and filling of soft spots with granular backfilling


material and compaction;

(e) Blinding and bedding, hunching and surround material;

(f) Concrete, formwork and reinforcement;

(g) Brickworks and rendering for brick sumps;

(h) Channels, fittings, benching and building, in drains and


pipes;

(i) Steps iron, safety chains, ladders, handholds, anchor irons,


bearers support and the like;

(j) Mild steel grating to suit including frame;

(k) Reinstatement of surfaces;

(l) Cleaning and desalting prior to handing over;

(m) Additional excavation for working space and its subsequent


backfilling;

(n) Movement joints;

66
(o) Joint filler, sealant and water stops.

5.11.3 Retaining Wall

Unit

The unit of measurement for construction and maintenance of


retaining wall shall be in number (no).

Measurement

The measurement for payment shall be the number of specified size


of the retaining wall as shown in drawing and approved by the S.O.
and made as follows:-

(a) 60% on complete construction to the satisfaction of the S.O.;

(b) 30% for maintenance

(c) 10% on removal

Pricing Factor

The item for construction and maintenance of retaining wall shall be


in accordance with the Preambles to Bill of Quantities:-

(a) Excavation for preparation of bed and disposal of surplus


excavated material;

(b) Construction of gabion overflow including cage, geotextile


and rockfill complete as shown in Drawing;

(c) Assembling, tying and staking for the positioning of the


gabion units;

(d) Removal and disposal of all rubbish, debris and surplus


material from the site to the satisfaction of the S.O.
including reinstatement of the site.

(e) Regular inspection and maintenance throughout the


construction period as directed by the S.O. and make good
and replace any damaged component;
(f) Removal of accumulated silt and sediment when full
including disposal.

67
5.12 Flora Management

5.12.1 Flora Survey

Unit

The unit of measurement to conduct Flora Survey shall be Lump Sum


(sum).

Measurement

The measurement for payment shall be the submission and acceptance of


the report by the S.O.

Pricing Factor

The item for conducting flora survey shall be in accordance with the
Preambles to Bill of Quantities:-

(a) The costs of literatures, references and consultation in the


production of the floral survey report.

5.12.2 Relocation, Transportation and Maintenance of Trees

Unit

The unit of measurement for relocation, transportation and maintenance of


trees with conservation value shall be in number (no).

Measurement

The measurement for payment shall be upon the completion of the


relocation process and acceptance by the S.O.

Pricing Factor

The item for relocation, transportation and maintenance of trees shall be in


accordance with the Preambles to Bill of Quantities:-

(a) Trees relocation to approved site and/or arboretum as required by


Jabatan Perhutanan;

(b) Handling, storing and maintaining packages of salvaged trees in


well kept condition including safety during relocation and
transportation;

(c) Watering;

(d) Fertiliser required and nurturing until the flora is established at the
temporary nursery and at the final place of relocation.

68
5.13 Wildlife Management

15.13.1 Fauna survey

Unit

The unit of measurement to conduct fauna survey shall be Lump Sum


(sum).

Measurement

The measurement for payment shall be based on the number of surveys


scheduled for the project.

Pricing Factor

The item to conduct fauna survey shall be in accordance with the


Preambles to Bill of Quantities:-

(a) Fauna survey prior to site clearing, during middle and end of
construction period;

(b) Preparation and submission of fauna status report.

5.13.2 Wildlife Translocation

Unit

Allow as provisional sum.

5.14 Noise Control (For permanent works only)

5.12.1 Noise Barrier

Unit

Allow as provisional sum.

The unit of measurement shall be square metre (m²).

Measurement

The measurement for payment shall be the exposed plain surface area on
the traffic side of noise barrier installed according to the specification and
approved by the S.O.

69
Pricing Factor

The item for construction of noise barrier shall be in accordance with the
Preambles to Bill of Quantities:-

(a) Site clearing and base preparation;

(b) Supply and driving of poles;

(c) Replacement of defective materials and components

70
CHAPTER 6

BILL OF QUANTITIES

71
PROJECT:

BILL NO 10: ENVIRONMENTAL PROTECTION WORKS

ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT


NO
(RM) SEN
NON - PHYSICAL WORKS
10.1 ENVIRONMENTAL IMPACT ASSESSMENT
(EIA)
10.1.1 Preparation, submission and approval of EIA Report sum
by environmental consultant registered with
Department Of Environment (DOE)

10.2 ENVIRONMENTAL MANAGEMENT PLAN


(EMP)
10.2.1 Preparation, submission and approval of EMP by sum
environmental consultant registered with DOE
including :-
(i) Erosion and Sediment Control Plan
(ii) Flora Management Plan *
(iii) Wildlife Management Plan *

10.3 ENVIRONMENTAL OFFICER (E.O.)


10.3.1 Provision of a full time E.O. for environmental
management works only, throughout the contract sum
period for the implementation of EMP and/or JKR
EMS : MS ISO 14001

10.4 ENVIRONMENTAL MONITORING, AUDIT AND


TRAINING
10.4.1 Environmental Monitoring
i) Water Quality Monitoring
a) Conduct monthly river/stream/other water bodies* sum
water quality monitoring as specified and as shown
on drawing for the following parameters or as
directed by the S.O./P.D.* through out the contract
period :-
1. Turbidity;
2. pH;
3. Total Suspended Solids (TSS);
4. Biochemical Oxygen Demand (BOD);
5. Chemical Oxygen Demand (COD);
6. Dissolved Oxygen (DO);
7. Oil & Grease;
8. E. Coli;
9. Ammoniacal Nitrogen (NH3-N)

Carried to Collection
72
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
NON – PHYSICAL WORKS (cont’d)
10.4 ENVIRONMENTAL MONITORING, AUDIT AND
TRAINING (cont‟d)

10.4.1 Environmental Monitoring (cont‟d)


i) Water Quality Monitoring (cont‟d)
sum
b) Conduct monthly water quality monitoring of the
effluent discharge at accommodation, workshop and
canteen area as specified for the following parameters
or as directed by the S.O./P.D.* through out the
contract period :-
1. Turbidity;
2. pH;
3. Total Suspended Solids (TSS);
4. Biochemical Oxygen Demand (BOD);
5. Chemical Oxygen Demand (COD);
6. Dissolved Oxygen (DO);
7. Oil & Grease;
8. E. Coli;
9. Ammoniacal Nitrogen (NH3-N)

c) Conduct monthly water quality monitoring at sum


discharge outlet of silt trap, sediment pond, sediment
basin as specified for Total Suspended Solid (TSS) or
as directed by the S.O./P.D.* through out the contract
period.

ii) Air Quality Monitoring


Conduct quarterly air quality monitoring for Total sum
Suspended Particulates (TSP) for 24-hour period
including wind velocity and direction as specified or
as directed by the S.O./P.D.* through out the
contract period.

iii) Noise Monitoring


Conduct quarterly noise monitoring (12 hours sum
average) including Leq, L10 and L90 as specified or as
directed by the S.O. /P.D.* throughout the contract
period.

iv) Vibration Monitoring


Conduct vibration monitoring as specified or as sum
directed by the S.O. /P.D.* through out the contract
period.
Carried to Collection

73
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN

NON – PHYSICAL WORKS (cont’d)


10.4 ENVIRONMENTAL MONITORING, AUDIT AND
TRAINING (cont'd)
10.4.1 Environmental Monitoring (cont'd)

v) Environmental Quality Report


Preparation of five (5) copies (per month) of the
following report through out the contract period :-

a) Monthly environmental quality report sum

10.4.2 Environmental Audit

i) Conduct quarterly audit as specified including sum


preparation of five (5) copies of Environmental
Monitoring and Audit Report (per audit) throughout
the contract period

ii) Conduct closure audit prior to issuance of no 1


certificate of practical completion including
preparation of five (5) copies of the report

10.4.3 Training

i) Local Training

Conduct environmental training on site for JKR no


personnel once a year.

PHYSICAL WORKS

10.5 DUST AND MUD CONTROL

10.5.1 Water Bowser Truck

Provision, operation and maintenance of bowser no


truck including operator, pumping of water, water
tank and other necessary equipments as specified for
carrying out water spraying along haul/access roads,
existing roads and near settlements or as directed by
the S.O./P.D

Carried to Collection

74
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN

PHYSICAL WORK (cont’d)

10.5 DUST AND MUD CONTROL (cont‟d)

10.5.2 Tyre Washing Facilities

i) Portable Water Jet

Provision, operation and maintenance of portable no


water jet including operator, water tank and other
necessary equipments as specified for carrying out
cleaning of vehicle tyres at various exits of the
worksites or as directed by the S.O./P.D

ii) Wash Trough


Construction and maintenance of wash trough no
including excavation, backfill and disposal of surplus
materials, formwork, reinforcement, hardcore and
placement of aggregate layer as specified and shown
in the drawing or as directed by the S.O./P.D.*

10.5.3 Water Sprinkler

Provision and maintenance of water sprinkler for no


controlling dust at quarry/ batching plant as directed
by S.O./P.D.*

10.6 EROSION CONTROL

10.6.1 Natural Control

Creepers
Planting and maintenance of creepers until fully
established as specified or as directed by the
S.O./P.D.*

I) Centrusemo Pubscens m2
II) Ficus Pumila m2
III) Parthenocissus Himalayana m2
IV) ……………… (any other suitable species) m2

Carried to Collection

75
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN

PHYSICAL WORK (cont'd)

10.7 SEDIMENT CONTROL

10.7.1 Silt Fence


i) Construction of 1.0m high silt fence including non- m
woven geotextile and wooden post with dimension as
specified and shown in the drawing or as directed by
the S.O./P.D.*

ii) Maintenance of silt fence as specified or as m


directed by the S.O./P.D.*

10.7.2 Sand Bags

i) Supply and lay gunny sack (or equivalent) filled no


with sand as specified and shown in the drawing or as
directed by the S.O./P.D.*

ii) Maintenance of sand bags as specified or as no


directed by the S.O./P.D.*

10.7.3 Silt Trap and Sediment Basin


i) Gabion cage with rock fill and geotextile including
excavation, jointing, backfilling and disposal of
surplus materials as specified and shown in the
drawing or as directed by the S.O./P.D.*
a) 1.0m x 1.0m x 1.0m gabion no
b) 2.0m x 1.0m x 1.0m gabion no
c) 2.0m x 1.0m x 0.5m gabion no
d) 2.0m x 1.0m x 0.3m gabion no

ii) Sand bedding for silt traps m3


iii) Stone filling at outlet m3
iv) 300 mm thick mortared rip-rap m2
v) Excavation to form silt trap m3

Carried to Collection

76
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
PHYSICAL WORK (cont'd)
SEDIMENT CONTROL (cont‟d)
vi) Maintenance as specified or as directed by the
S.O.
a) silt trap sum
b) sedimentation basin sum
vii) Provision and maintenance of temporary m3
earth drain

10.7.4 Gabion Wall


i) Construction of 1.0m x 1.0m x1.0m gabion cage no
with rock fill, sand bed and geotextile including
excavation, jointing, backfilling and disposal of
surplus materials as specified and shown in the
drawing and as directed by the S.O./P.D.*

ii) Maintenance of gabion wall as specified or as no


directed by the S.O./P.D.*

10.7.5 Check Dam

i) Construction of check dam using rocks as specified m3


and as shown in the drawing or as directed by the
S.O.
ii) Maintenance of check dam as specified or as no
directed by the S.O./P.D.*

10.7.6 Silt Curtain

i) Installation of silt curtain including non-woven m2


geotextile and floats as specified and as shown in the
drawing or as directed by the S.O./P.D.*
ii) Maintenance of silt curtain as specified or as
directed by the S.O./P.D.*

10.8 TOPSOIL PROTECTION

10.8.1 Provision and maintenance of plastic sheeting to m2


immediately cover topsoil stockpile for turfing and
landscaping

10.8.2 Construction of 1.0m high silt fence including non- m


woven geotextile and wooden post with dimension as
specified and shown in the drawing or as directed by
the S.O./P.D.*
Carried to Collection

77
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
PHYSICAL WORK (cont'd)
10.9 FUEL SPILLAGE MANAGEMENT

10.9.1 Containment Bund for Bulk Fuel Tank


Construct impervious concrete base as per drawing to no
contain 110% volume of stored fuel including grease
trap

10.10 WASTE MANAGEMENT

10.10.1 Scheduled Wastes Disposal

i) Construction of storage shed to temporary house sum


scheduled wastes as specified and as shown in the
drawing
ii) Disposal of scheduled waste to designated and sum
approved premises

10.10.2 Grease Trap

Provision and maintenance of grease traps at kitchen no


areas, sharing and workshop

10.11 MANAGEMENT OF DISPOSAL SITE FOR


SURPLUS MATERIAL

10.11.1 Earthworks

Protective Vegetation for Erosion Control

Plant and maintain until fully establish as specified or


as directed by the S.O./P.D.*
i) Closed turfing m2
ii) Hydroseeding with fibromat or equivalent m2
iii) Vertiver Z m
iv) Creepers m2
10.11.2 Drainage

i) Embankment Sump Outlet

Reinforced concrete class 25/20 embankment sump


outlet including excavation, concrete, reinforcement,
leveling, blinding, formworks, RCP, backfilling and
all incidentals necessary as shown in drawings or as
directed by the S.O./P.D.*
Carried to Collection

78
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
PHYSICAL WORK (cont’d)

MANAGEMENT OF DISPOSAL SITE FOR


SURPLUS MATERIAL (cont‟d)

a) Sump Type S3 internal size 400mm x 600mm x no


700mm depth
b) ………………………………………… no

ii) Drains
Reinforced insitu concrete class 25/20 in drains at
any inclination including excavation, junction,
reinforcement, formworks where necessary, joints,
stepping, backfilling and disposal of surplus material
and all incidental necessary as specified and as shown
in Drawings or as directed by the S.O./P.D.*

a) Toe Drain Along Toe of Embankment


- 450mm invert width, 450mm deep m
- 600mm invert width, 600mm deep m

b) Berm Drain Along Berm of Embankment


- 400mm deep m

c) Embankment Shoulder Block Drain m


- 300mm half round concrete drain

d) Slope Drain Down Embankment Slope


(Spillway)
- 600mm invert width, 500mm deep m

10.11.3 Gabion Retaining Wall

Construction and maintenance of gabion retaining


wall inclusive of geotextile filter and sand drainage
blanket and necessary works as specified and as
shown in drawings or as directed by S.O./P.D.*

i) 2.0m x 1.0m x 1.0m gabion no

ii) 2.0m x 1.0m x 0.5m gabion no

iii) 2.0m x 1.0m x 0.3m gabion no

Carried to Collection

79
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
PHYSICAL WORK (cont'd)

10.12 FLORA MANAGEMENT

10.12.1 Conduct Flora Survey as specified. no 2

10.12.2 Relocate, transport and maintain trees with


conservation value of girth 300mm and above :
i) to nearby sites approved by forester or botanist no

ii) to arboretum no

10.13 WILDLIFE MANAGEMENT

10.13.1 Conduct Fauna Survey as specified. no 2

10.14 NOISE CONTROL (Permanent Works)


10.14.1 Noise Barrier

Supply and install noise barrier type as approved by m2


SO/PD* at specified locations as directed by the
S.O./P.D.*

Carried to Collection

80
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO
(RM) SEN
PHYSICAL WORK (cont'd)

10.15 EROSION CONTROL (cont‟d)


10.15.1 Artificial Control
Proprietary Products
Allow a Provisional Sum of Ringgit PS
______________________ for the supply,
installation and maintenance of proprietary products
to be used and expended as directed by the S.O./P.D.*
in part or whole or entirely omitted

10.16 WILDLIFE MANAGEMENT

10.16.1 Allow a Provisional Sum of Ringgit PS


___________________ to translocation wildlife to
sites approved by Jabatan Perhilitan to be used and
expended as directed by the S.O./P.D.* in part or
whole or entirely omitted

Carried to Collection

81
CHAPTER 7

BEST MANAGEMENT PRACTICES

82
CHAPTER 7: BEST MANAGEMENT PRACTICES

Soil Erosion and Sedimentation Control Measures

Silt Traps

Courtesy of: Pn.Geetha (Europasia Eng. Services)

Sediment Basins

83
Sediment Basins Outlets

Silt Marker & Desilting Works

Source : Projek Lebuhraya Pantai Timur Fasa 2, Pakej 2

Sand Bag & Grease Trap

84
Silt Fence

Source ::Projek Lebuhraya Pantai Timur Fasa 2, Pakej 2

Silt Curtain

Courtesy of: Wiranda (M) Sdn. Bhd

Gabion Wall

Courtesy of: Pn.Geetha (Europasia Eng. Services)

85
Turfing

Hydroseeding

Sources: Projek Membina dan Menyiapkan Jalan Pos Betau Lembah Bertam, Pahang

86
SCHEDULED WASTE MANAGEMENT

Courtesy of: Pn.Geetha (Europasia Eng. Services)

87
FLORA AND FAUNA MANAGEMENT

EXAMPLES OF ANIMAL VIADUCT

Courtesy: Wiranda (M) Sdn Bhd. – Projek Simpang Pulai Lojing – Gua Musang

FLORA SALVAGING

Protected endemic species Rafflesia, found only


in Hutan Simpan Belum, Endau Rompin and
Taman Kinabalu

88
EXAMPLES OF ENVIRONMENTAL MONITORING
1. Examples of Water / Effluent Quality Monitoring

Source: Projek Trans-Eastern Kedah Interland Highway

89
2. Examples of Air Quality Monitoring

Source: Projek Trans-Eastern Kedah Interland Highway

3. Example of Noise Monitoring

Source: Projek Trans-Eastern Kedah Interland Highway

90
CHAPTER 8

STANDARD DRAWINGS AND FIGURES

91
92
93
Drawing 1: Containment Bund For Skid Tank

94
Drawing 2: Silt Traps

95
Drawing 3: Wash Trough For Construction Site At Urban Area

96
Drawing 4: Wash Trough For Construction Site At Rural Area

97
Drawing 5: Silt Fence

98
Drawing 6: Check Dam

99
Drawing 7: Scheduled Waste Storage Shed

100
Drawing 8: Disposal of Suitable Cut Materials

101
WATER LEVEL
JOINT TO SUIT
SITE CONDITION
GEOTEXTILE SEPARATOR

CONCRETE ANCHORAGE
EVERY 6000mm CURTAIN

WIRE ROPE

HARD WOOD PICKET

TYPICAL CONCRETE ANCHOR

NOTES :
CURTAIN ARRANGEMENT ALL DIMENSION ARE IN MILIMETRE UNLESS OTHERWISE STATED

Drawing 9: Silt Curtain

102
Drawing 10: Unsuitable Material Disposal Embankment

103
REFERENCES

(1) Environmental Quality Act 1974 (Act 127) & Subsidiary Legislations
(2) Department of Environment, 2007: A Handbook of Environmental Impact
Assessment Guidelines (4th Edition)
(3) Environmental Impact Assessment Guidelines for Highway/Road Project
(4) Canter, L.W. (1996). Environmental Impact Assessment. McGraw Hill, Boston.
(5) Protection of Wild Life Act 1972 (Act 76).
(6) National Forestry Act 1984 (Act 313).
(7) Fisheries Act 1985 (Act 317)
(8) Town and Country Planning Act 1976 (Act 172)
(9) Occupational Safety and Health Act 1994 (Act 514)
(10) Street, Drainage and Building Act 1974 (Act 133)
(11) Jabatan Kerja Raya EMS ISO 140001 Environmental Manual and Procedure
(12) Nota Teknik (Jalan) 22/01 : A Practical Guide to Prepare Bill of Quantities for
Environmental Protection and Enhancement
(13) Cawangan Jalan, Ibu Pejabat JKR, 50582 Kuala Lumpur, Standard Specification
for Road Works : JKR/SPJ/1988
(14) Manual Mesra Alam Malaysia, Jabatan Pengairan dan Saliran Malaysia, 2000
(15) Department of Environment, 1986 : Water quality Criteria and Standards for
Malaysia. Ministry of Science, Technology and the Environment, Malaysia
(16) Flood Estimation for Urban Areas in Peninsular Malaysia (Hydrological Procedure
No. 16), 1976, JPS Malaysia
(17) Planning guidelines for the Preservation of Natural Topography in Physical
Planning and Development in Accordance with the Town and country Planning
Act 1976 (Act 172), the Federal Department of Town and country Planning,
Malaysia
(18) EIA Guidelines for Forestry, Department of Environment, 2000
(19) EIA Guidelines for Housing and New Township Development Project, Department
of Environment, 2003
(20) Department of Environment Guidelines for Soil Erosion and Siltation Malaysia,
1996
(21) Guidelines of Slope Maintenance in Malaysia
(22) Morgan, R.P.C., 1987. Soil Erosion and conservation Ed. D.A. Davidson.
Longman UK.
(23) Corner, E.J. H., 1988. The Wayside Trees of Malaya, 3rd Edition (2 vols).
Malayan Nature Society, Kuala Lumpur.
(24) David T.J.,1993. Flora of Malaysia. Illustrated. Oxford University Press,
Singapore.
(25) Giles, R.H. (ed),1969. Wildlife Management Techniques, 3rd Edition. The
wildlife Society Washington
(26) Henderson, Murry & R, 1974. Malayan Wild Flowers (2 vols). Malayan Nature
Society, Kuala Lumpur
(27) IUCN, 1994. IUCN Red List Categories. IUCN Special Survival Commission,
IUCN Gland
(28) John, B. 1993. A Birdwatchers Guide to Malaysia. Wymark Publ.
(29) Junaide, P. C.M. Francis & K. Phillips, 1985. A Field Guide to the Mammals of
Borneo. The Sabah Society and WWF Malaysia

104
APPENDIX 1

Taken From Section 2.2.8 – Protective Vegetation for Erosion Control of Standard
Specification for Roadworks JKR/ SPJ/1988:-

Standard Specifications For Building Works (2005 Edition):- SECTION A :


PRELIMINARIES AND GENERAL CONDITIONS AND SECTION C :
EXCAVATIONS AND EARTHWORKS

105
Hydroseeding/Turfing

Taken from From Section 2.2.8 – Protective Vegetation for


Erosion Control of Standard Specification for Roadworks
JKR/ SPJ/1988:-

Topsoil

Topsoil stockpiled for the Works in accordance with Sub-


Sections 2.1.1.3 and 2.1.2.3 (of Section 2.2.8 – Protective
Vegetation for Erosion Control of Standard Specification for
Roadworks JKR/ SPJ/1988) shall be spread and lightly
compacted to an even thickness of 50 mm as directed by the
S.O. in areas to be turfed and/or seeded, or used as the S.O.
shall otherwise direct for tree planting and other purposes.

Turfing

(i) Turfing shall be carried out as soon as practicable on


all earth slopes and other areas as shown on the
Drawings and/or where directed by the S.O.

(ii) The type of turf shall be as indicated on the


Drawings or other alternative type as approved by
the S.O. and shall be free of „lalang‟ and essentially
free of weeds.

(iii) Turf shall be obtained in unbroken sods with a


substantial amount of topsoil and shall be
approximately 250 mm x 250 mm in size and 100
mm thick, from an approved source, and shall be
placed in position as soon as practicable after cutting.

(iv) Turf sods shall be stacked and watered when they


cannot be laid immediately after cutting. The
surfaces to be turfed shall be trimmed and
thoroughly wetted. The turf shall then be carefully
laid to form a complete and uniform cover as shown
on the Drawings.

(v) Turf lay on slopes steeper than 1 (vertical) and 3


(horizontal) shall be pegged down with bamboo
stakes approximately 250 mm in length.

(vi) Approved fertiliser shall be applied after lacing of


turf at suitable times and at rates of application
approved by the S.O. All turf shall be regularly
watered and fertilised to the satisfaction of the S.O.
until the vegetation is satisfactorily established.

106
(vii) Any dead turf shall be replaced with new turf at the
Contractor's own expense.

Seeding

Seeding or hydroseeding shall be carried out as soon as


practicable on slopes and other areas as shown on the
drawings and/or directed by the S.O. The contractor shall
submit to the S.O. for his consideration and approval, at
least four (4) weeks in advance of the proposed work, full
details of his proposed method of seeding or hydroseeding.
The information submitted shall include, but not necessarily
be limited to, a full description of the following aspects of
the work:-

(i) The preparation of the areas to be seeded or


hydroseeded, including if appropriate the amount of
top soil to be used and its method of application;

(ii) The details and results of investigations to determine


which types of grass and legume are compatible with
the soil in the areas to be seeded;

(iii) The types of grass and legume (if any) and strains of
seed to be used, and the function, root and growth
characteristics of each type;

(iv) The rates of application of the grass and legume


seeds;

(v) The composition of fertiliser to be used at the time of


seeding and its rate of application;

(vi) The composition of fertiliser to be used after seeding,


the times of application after seeding, and the rates
of application;

(vii) The type of mulch to be used and its method and rate
of application;

(viii) The amounts of lime or other chemicals (if any) to be


applied to improve the soil before, during and/or
after seeding;

(ix) The type and amounts of binding agent to be applied


with the seeds, mulch, fertiliser, etc., as appropriate;

(x) The proportions and methods of preparation of the


seeding mix;

107
(xi) The equipment and methods to be used in preparing
and placing the seeding mix and other materials;

(xii) The cultivation and after-care of the seeded areas,


including rates and frequencies of watering,
fertilising, grass cutting and general maintenance for
at least 1 year after seeding;

(xiii) The time after seeding required for establishing


permanent, dense growth of grasses, which will
require minimal maintenance;

(xiv) Guarantees of the success of the seeding work. All


grass shall be regularly watered until the vegetation
is satisfactorily established to the satisfaction of the
S.O. Any dead grass shall be replaced at the
Contractor's own expense.

SECTION A – Preliminaries and General Conditions

22. Drainage of Site and Erosion Control

22.1 The Contractor shall make proper provision for the


drainage of surface water from the work site
including rainwater from surrounding areas which
drain on to the Site.

22.2 The Contractor shall at his own cost, provide, form,


fix and maintain such pumps, chutes, walls, drains,
bunds and other temporary works necessary for the
proper drainage of the Site so that no flooding or
other damage or disturbance is caused to areas
surrounding the Works or to the Works throughout
the duration of the Contract.

22.3 Silt trap shall be constructed as shown in the


Drawings. The silt trap shall be maintained regularly
throughout the contract period, including desalting
when full or as directed by the S.O and making good
of any damaged portions during the course of the
works. The desalted material shall be transported to
disposal site approved by the S.O.

22.4 The Contractor shall, if and where directed by the


S.O, install silt fences as shown in the drawings for
trapping silt and sediment from disturbed area during
construction. The silt fence shall be constructed of a
vertical barrier of geotextile supported by poles at
regular intervals. The geotextile shall be made of

108
non-woven material with minimum weight of
200g/m2 and tensile strength 15 kN/m. The fence
shall be inspected after every rain and when a
sediment accumulation of approximately two third
(⅔) of the fence height is observed; the silt shall be
removed and disposed of properly. The geotextile
shall be checked for rips, tears and other types of
deterioration and replaced as needed.

22.5 The Contractor shall, if and where directed by the


S.O, construct gabion walls which shall consist of
layers of gabion as shown in the Drawings for
trapping sediments in catchment area.

22.6 The Contractor shall, if and where directed by the


S.O, construct sediment pond or basin as shown in
the Drawings for collecting and trapping sediments
before the water leaves the Site. The sediment basin
shall be maintained such that the silt shall be
removed when a sediment accumulation of
approximately one third (⅓) the basin depths is
observed.

SECTION C – Excavations and Earthworks;

16. Temporary Drainage Channels and Bunds

16.1 As earthwork progresses, the Contractor shall


provide and maintain efficient drainage of the Site as
specified under SECTION A: PRELIMINARIES
AND GENERAL CONDITIONS, until such time as
the permanent surface water drainage is installed.

17. Clearing of Existing Ditches, Drains, Rivers, etc.

17.1 During the execution of the earthwork, the


Contractor shall take all necessary precautions to
prevent blockage or obstruction, and to ensure free-
flow of existing drains, ditches, streams and the like.

18. Protection and Maintenance of Earthworks

18.1 The Contractor shall provide all necessary protection


and maintenance of earthwork, particularly from the
damaging effects of water entering the works from
rainfall, runoff, springs, rivers or streams. Damage to
finished or partly completed work arising from the
lack of such protection and maintenance work, shall

109
be made good by the Contractor at his own cost and
expense.

18.2 Where turfing is required for slope protection, they


shall be planted immediately after the embankment is
formed.

18.3 If due to unforeseen circumstances turfing cannot be


carried out immediately, temporary protection/cover
(e.g. plastic sheets or equivalent) shall be laid on
exposed slopes by the Contractor.

110
APPENDIX 2

GOVERNMENT REQUIREMENTS (NEED STATEMENT)


(TERM OF REFERENCE) (FOR DESIGN AND BUILD PROJECTS
ONLY)

111
(Please insert this document into the prebid document)

GOVERNMENT REQUIREMENTS
(NEED STATEMENT)
(TERM OF REFERENCE)

ENVIRONMENTAL PROTECTION AND ENHANCEMENT REQUIREMENTS

(FOR DESIGN AND BUILD PROJECTS ONLY)

112
Fill in Name of Project

ENVIRONMENTAL PROTECTION AND ENHANCEMENT REQUIREMENTS

CONTENTS

GENERAL

1.0 Scope of Works


2.0 Special Requirements
3.0 Legal Requirements
3.1 Compliance with the Legal Requirements
3.2 Environmental Impact Assessment (EIA)
3.3 Environmental Protection Works
4.0 Safety and Health Requirements
5.0 Waste Management and Disposal System
6.0 Stormwater Management
7.0 Environmental Management Plan
7.1 Erosion and Sediment Control Plan (ESCP)
8.0 Environmental Monitoring, Auditing and Training
8.1 Monitoring
8.2 Auditing
8.3 Reports
8.4 Training

113
GENERAL

1.0 Scope of Works

1.1 The works shall cover planning, design, construction, monitoring, auditing,
reporting, training and maintenance of environmental protection and
enhancement works.

1.2 The Contractor is deemed to have visited the site to familiarize himself with
site and local conditions that pertain to the necessary programme, design and
execution of this work. The Contractor shall take all necessary action and
precaution during construction and maintenance works so as not to affect the
surrounding environment.

2.0 Special Requirements

2.1 Forty five (45) days prior to site possession, the Contractor shall submit for
the P.D/S.O approval a detailed EMP based on the Arahan Teknik (Jalan)
16/03 – Pindaan 2008. For projects subjected to EIA requirements, the EMP
shall be submitted 45 days after the approval of the EIA. No site clearing and
earthworks shall be carried out prior to EMP approval by relevant
parties/authorities.

2.2 The Contractor shall need to include the environmental activities in the
program (CPM) to be submitted to the P.D/S.O. These activities shall contain
all the necessary actions and interactions in detail.

2.3 The onus of obtaining timely approval from each relevant Local Approving
Authority on environment shall be the Contractor‟s responsibility. Untimely
receipt of approvals which may affect the Contractor‟s design/construction
program shall not in any way be a basis/cause for consideration of time
extension or variation to the contract.

2.4 The Contractor must take serious and urgent actions on all findings and
recommendations toward protecting the environment as in the report or/and as
instructed by the P.D/S.O.. Failure to do so, the P.D/S.O shall appoint other
party and all cost will be borne by the contractor.

2.5 The Contractor shall provide turbidity measuring equipment to determine


direct in-situ measurement on water quality for immediate rectification should
pollution occur.

3.0 Legal Requirements

3.1 Compliance with the Legal Requirements

Prior to the execution of the project, the Contractor shall comply with the
Environmental Quality Act 1974, Act 127 and other related environmental
legislations including, but not limited to:

114
(a) National Land Code (Act 56 of 1965)
(b) Town and Country Planning Act 1976, (Act 172)
(c) Street, Drainage and Building Act, 1974: Act 133 and Amendment,
1978
(d) Protection of Wildlife Act, 1972 (Act 76)
(e) Forestry Act 1984 (Act 313)
(f) Land Conservation Act 1960 (Act 385)
(g) Occupational Safety and Health Act 1994 (Act 514)
(h) Solid Waste and Public Cleansing Management Act 2007 (Act 672)
(i) Environmental Quality Act 1974 (Act 127 & Subsidiary Legislation)
(j) Federal Territory (Planning) Act 1982 (Act 267)
(k) Workers Minimum Amenities Act 1990 (Act 446)
(l) Local Government Act 1976 (Act 171)

3.2 Environmental Impact Assessment (EIA)

Where EIA is required by the said Act, the Contractor shall prepare, submit
and obtain approval from the Department of Environment (DOE). The
Contractor shall incorporate in his Works all the abatement and mitigation
measures for environmental protection and enhancement including
monitoring and auditing.

3.3 Environmental Protection Works

The Contractor shall identify the significant environmental aspects and


impacts of the projects and execute all mitigating measures proposed in the
Conditions of Approval by the Approving Authority and in the EMP.
Reference shall be made to the Arahan Teknik (Jalan) 16/03 – Pindaan 2008
for a more comprehensive understanding of the scope of works. The
contractor shall also observe / carry out the following:

(i) Limit and control site clearing works to construction areas only.
Existing trees of 80cm diameter at breast height are to be retained as
much as possible and only minimum tree cutting is allowed unless
they impose danger to the public and traffic after completion of the
project.

(ii) Transport and stockpile topsoil to designated areas approved by the


P.D./S.O for reuse during turfing, hydroseeding and landscaping.

(iii) Turf or hydroseed slopes immediately upon reaching their formation


levels. For cut slopes, hydroseeding shall be carried out together with
supportive materials. Landscaping works shall commence early as
directed by the P.D. /S.O.

(iv) Take necessary precautions to prevent deposition of debris, rubbish,


silt, waste materials, polluted water, chemicals, etc. during execution
of the works from entering existing streams/waterways.

115
(v) Construct berm/bench drains, interceptor drains and other related
drainage works to slopes which have reached the required formation
levels. Provide temporary cover, for example, polythene or plastic
sheet to exposed slopes.

(vi) Provide and maintain sediment control measures namely silt fences,
silt traps, sediment basins, gabion walls, check dams, silt curtains, etc.
Upon completion, reinstate site including landscaping where sediment
basins were located and remove other measures which are not
required as directed by the P.D. /S.O.

(vii) Take necessary precautions to ensure that tyres of all vehicles leaving
the site are free of mud.

(viii) Not to carry out open burning on site unless with written approval
from the DOE.

(x) Supply and lay immediately at least to binder course layer on roads
which have reached the required formation levels including the
required drainage system.

(xi) Preserve mangrove areas on site unless deemed necessary for


construction. However, the clearing of mangroves shall be limited to
construction infrastructural area only and with approval from P.D.
/S.O.

(xii) Bakau piles are not allowed to be used.

4.0 Safety and Health Requirements

The Contractor shall provide and maintain suitable accommodations for workmen by
carrying out the following:

(i) Locate suitable workmen's accommodation to be agreed by the P.D./S.O.


(ii) Provide sufficient toilet facilities to the satisfaction of the P.D./S.O.
(iii) Provide proper disposal for waste and refuse.
(iv) Provide adequate supply of water for washing, cooking and drinking.
(v) Maintain site in a clean and sanitary condition and that complies with all
requirements of Government, Health and Sanitary Authorities.
(vi) Prohibit activities such as hunting/trapping of wildlife. Fines/penalties
imposed by the relevant Government Departments due to such activities shall
be borne by the Contractor.

5.0 Waste Management and Disposal System

5.1 All types of waste i.e. Solid waste, Liquid waste, Domestic waste (non-
hazardous) and Scheduled wastes are to be segregated, stored and disposed
in accordance with the Ministry of Health requirements , the DOE
requirements and other approving Authority requirements (e.g. the Local
Authority).

116
5.2 Wastes with sharp edges are to be stored in specially designed containers
and specially manufactured for that purpose.

5.3 Scheduled waste shall be kept in labeled containers/ drums and stored in
storage shed which shall both be maintained and removed in accordance
with the DOE requirements. Schedule waste shall be disposed by a licensed
contractor to approved prescribed premises for treatment.

5.4 The disposal of Liquid or Solid waste and scheduled wastes must be
properly designed and programmed to abide with the Authorities‟
Requirements.

6.0 Stormwater Management

Stormwater management design and construction works shall conform with the
requirements of Jabatan Kerja Raya „Drainage System‟, „Erosion and Sedimentation
Control Plan (ESCP), Jabatan Pengairan dan Saliran „Urban Stormwater Management
Manual (MSMA) and Local Authorities requirement.

Stormwater drainage shall be designed for least maintenance cost, effective initial
cost and serves its function. There shall be no flooding, ponding/silting up and
erosion during construction and after completion of the works.

7.0 Environmental Management Plan (EMP)

The Contractor shall submit for prior approval by the government, an


environmental consultant registered with DOE, for preparation of a site specific
EMP. The EMP shall be submitted to the S.O. for endorsement 45 days prior to
site possession in compliance with the Conditions of Contract and/or in compliance
with the requirements of the conditions of approval of the EIA report by the
Department of Environment.

The EMP shall make reference to the following but not limited to:
(a) DOE Format for the Preparation of EMPs.
(b) JKR Environmental Management System (EMS).
(c) The approved EIA report.
(d) EIA Approval Conditions from DOE (attached if any).

It should be clearly noted the EMP is a document for practical use on site by
nominated personnel and thus should be concise, up to date and site specific.

The Contractor shall engage the following qualified personnel (degree holder in
related fields) on site:

(i) Environmental Officer (Full Time).


(ii) Safety and Health Officer (Full Time).
(iii) Horticulturist / Plant / Tree Expert (Part Time), if required.
(iv) Fauna Expert (Part Time), if required.

117
7.1 Erosion and Sediment Control Plan (ESCP)

The Contractor shall prepare an ESCP. This document which is to be prepared


and certified by a Professional Engineer shall be submitted to the P.D. / S.O
and Environment Branch, JKR Malaysia 30 days prior to commencement of
any earthwork activity at project site.

The P.D. / S.O shall then submit the ESCP document to the Drainage and
Irrigation Department (D.I.D) for approval upon document review by the
Environment Branch, of JKR Malaysia.

The following items apply to an ESCP document:

(a) The document shall be prepared in accordance with the Storm water
Management Manual (MSMA) published by D.I.D.
(b) It must be amended whenever a change in the design, construction,
operation or maintenance at the construction site has a significant
effect on the discharge of pollutants to the waters at project site not
previously addressed in the document
(c) It must be amended if discharges are causing water-quality
“exceedances” or the Best Management Practice (BMP) are
ineffective in minimizing pollutants in storm water discharging from
the construction site.
(d) The document must be revised within 7 calendar days following an
inspection when additions and/or modifications to BMPs are
necessary to correct observed problems.

8.0 Environmental Monitoring, Auditing and Training

8.1 Monitoring

The Contractor shall monitor water and air quality, noise and vibration, if
required. All samples taken must be tested by an accredited laboratory. The
Contractor shall produce and submit monthly and quarterly environmental
quality reports consisting in-situ and laboratory results, sampling photographs
with weather charts and analyses of the monitoring data in terms of
environmental performance. Reference to the contents of the reports can be
made to the Standard Report Format attached in Appendix 2.

8.2 Auditing

The Contractor shall engage a registered Environmental Auditor to audit all


activities on site as per JKR EMS: MS ISO 14001 requirements. The tasks of
the Auditor among others are:

(i) To carry out environmental compliance of JKR EMS: MS ISO 14001


audits quarterly.
(ii) To interpret monitoring data in terms of environmental performance.
(iii) To verify effectiveness of corrective and preventive action
implemented.

118
(iv) To recommend requirement and improvement of mitigating measures.
(v) To produce and submit a comprehensive environmental auditing
report.

8.3 Reports
The Contractor shall submit environmental quality and audit reports to JKR
Environment Branch and Portfolio Branch, DOE HQ/State and P.D./S.O.
Contents of the report must be in accordance with the Standard Report Format
as attached in Appendix 2 of this document.

8.4 Training

The contractor shall provide training for relevant JKR personnel in the field
of environment. This training shall include Environmental Conservation,
Post EIA and Environmental Monitoring, Environmental Management
System in Project Construction, Safety and Health Courses, and Technical
visits. The training shall be conducted and given by an established
organization with reputable track records in environmental protection
during project management and construction with opportunity for transfer
of technology in enhancing such development. The Contractor‟s EO shall
also provide training/awareness briefing for site personnel involved in
works that have impact on the environment.

119
APPENDIX 3

STANDARD REPORT FORMAT FOR EMP, EQR, EMAR AND CAR

120
TITLE OF DOCUMENT: ENVIRONMENTAL MANAGEMENT PLAN (EMP)
STANDARD REPORT FORMAT FOR JKR PROJECTS

1.0 Definition of EMP

An EMP is basically a documentation of administrative environmental


management and coordination procedures for onside management in order to
ensure that all development activities complies with the EIA approval conditions as
stipulated by DOE. It must show the commitment of the project proponent in terms
of accountability and availability of resources. An EMP should be improved and
adapted throughout the life of the project to reflect changing conditions. It must
also be subjected to periodic review to ensure it‟s continues relevance and validity.

2.0 Objectives of EMP

The main objectives of the Environmental Management Plan (EMP) is to set out a
comprehensive programme which will form the basis for implementing
environmental mitigation measures, environmental monitoring and environmental
auditing of the construction works by the Contractor as listed below:

(a) To set out various environmental protection / conservation measures that


conform to the environmental conditions stipulated in the Specifications,
EIA report and by other relevant authorities (e.g. the Department of
Environment (DOE);

(b) To ensure that the Contractor comply with all applicable environmental
standards and guidelines, legislative requirements and other relevant
conditions related to the environment;

(c) To specify a detailed environmental monitoring and auditing programme to


ensure that the Contractor and all his Sub-contractors comply with all
stipulated requirements throughout the duration of the project; and

(d) To streamline the different functions of various sections and authorities


related to the environmental matters during the construction.

3.0 General Information about the Project

The following details are needed to help commence the preparation of the EMP:-

(i) Project Contractor


(ii) Project Title
(iii) Condition of Contract
(iv) Project Cost
(v) Duration of Contract

121
4.0 Information on EMP

The type of EMP that is being prepared can be divided into:-

(i) Compliance to EQA 1974


(ii) Compliance to JKR MS ISO 14001

5.0 Cover Page Information

The cover has to include the following information:-

(i) Project & Document Title


(ii) JKR Logo
(iii) Contractor‟s Logo
(iv) Contractor‟s Registration
(v) DOE Approval Reference (if applicable);
(vi) Insertion page for document verification

6.0 Executive Summary

The executive summary must manage to summarise the key elements of the
project:-

(i) Site Features


(ii) Project Description
(iii) Identified Impacts
(iv) Proposed Mitigation
(v) Conclusion

7.0 Chapter 1: Introduction

Key information needed to be detailed in Chapter 1 is:-

(i) Project Title


(ii) Details of Project Proponent
(iii) Site Description
 Topography
 Drainage
 Flora
 Fauna
 Land use
 Geology & Soils
 Socio Economy

122
(iv) Project Description
 Concept
 Components
 Activities
 Scheduling

8.0 Chapter 2: Environmental Requirement

This chapter has to outline the need for the EMP and has to detail the following:-

(i) Listing of all Environmental Requirements including any approval obtained


for the ESCP, MASMA, disposal site etc.
(ii) EIA approval conditions (if applicable)

9.0 Chapter 3: Environmental Policy

Chapter 3 has to state in the Policy in relation to Environment of the Project


Proponent and elaborate on the objectives of the EMP:-

(i) Objectives of the EMP


(ii) Environmental Policy of the PP

10.0 Chapter 4: Organisation Chart and Budget

Chapter 4 has to detail the aspects related to the Environmental Management Unit
(EMU) and the allocations provided for Environmental Protection:-

(i) Organisation chart of EMU


(ii) Contact details of EMU
(iii) Job description of EMU
(iv) Training proposed
(v) Budget for EMP implementation

11.0 Chapter 5: Monitoring Program

Detailing of the environmental monitoring proposal for the project:-

(i) Baseline information


 Monitoring locations and justification of locations
 Validity of data
 Verification of data
 Frequency of monitoring
 Sampling methodology and Accreditation of laboratory

123
(ii) Proposed monitoring programme

 Monitoring locations and justification of locations


 Frequency of monitoring
 Accreditation of laboratory to be used for sampling
 Report to be submitted

12.0 Chapter 6: Auditing Programme

This chapter has to detail the auditing programme for the project:-

(i) Audit elements


(ii) Frequency of audit
(iii) Reports to be submitted
(iv) Types of forms used
(v) Registration details of auditor
(vi) Follow up action on audit

13.0 Chapter 7: Identification of Aspect, Impact and Recommended Mitigation


Measures

This chapter has to detail the identified significant aspects, impacts and their
corresponding site specific mitigation measures:-

(i) Site Cleaning and Biomass Management


(ii) Wildlife Protection Plan
(iii) Social Acceptance Plan
(iv) Earthworks Description
(v) ESCP Description
 Elements
 Staging
 Plans
 Implementation Schedule

(vi) Stockpile Management


(vii) Slope Protection
(viii) Drainage
(ix) Logistics
(x) Site Facilities
(xi) Solid Waste Management
(xii) Scheduled Wastes Management
 Type of waste generated
 Estimated volume
 Storage, Collection and Disposal Plan
(xiii) Safety
(xiv) Traffic Control
(xv) Site Abandonment/Closing Plan

124
14.0 Chapter 8: Environmental Contingency Plan

This chapter has to detail the contingencies related to the project:-

(i) Issued identified


 Flooding
 Landslide
 Fire
 Medical Emergencies
 Spillages

(ii) Action Plan and Line of Communication


(iii) Contact Numbers of relevant Agencies

15.0 Chapter 9: Performance Evaluation and Project Review

This chapter has to detail the analysis used to determine performance of the
environmental Protection Measures and the recommendations for improvement:-

(i) Description of Analytical Methodology Used


(ii) Forms Used
(iii) Recommendations for Improvement

16.0 Chapter 10: Conclusion

This chapter has to conclude the findings of the EMP:-

(i) Concluding Statements on site related issues and their corresponding


mitigation measures.

17.0 Appendices

Items to include in the appendix are:-

(i) Data sources


(ii) Consultations held
(iii) Approvals obtained
(iv) References
(v) Calculations
(vi) Plans

125
18.0 Figures

The following figures are mandatory to be included in the EMP:-

(i) Location plan


(ii) Layout of site and facilities
(iii) Organisation chart of EMU
(iv) Location of water, air and noise monitoring stations (baseline)
(v) Location of water, air and noise monitoring stations (proposed)
(vi) ESCP
 Earth drain network
 Diversion channels
 Silt traps/sediment basins locations
 Final discharge outlets
 Silt fence
 Gabions
 Check dams

(vii) Overall Mitigation Plan


 Location of solid waste storage
 Location of scheduled wastes storage
 Toilets
 Stockpile area
 Boundary of site clearing
 Septic tanks
 Grease traps
 Wash trough

(viii) Emergency Response chart for any Non-compliances observed/identified

126
REPORT: ENVIRONMENTAL QUALITY REPORT (EQR)

TABLE OF CONTENTS
EXECUTIVE SUMMARY

1.0 INTRODUCTION

1.1 Introduction to Project


1.2 Progress of works to date
1.3 Monitoring Period

2.0 WATER QUALITY MONITORING

2.1 Sampling and analysis procedures


2.2 Results
2.3 Comparison with baseline quality and Previous results
2.4 Discussion on water quality results
2.5 Conclusion of findings on water quality
2.6 Photos

3.0 SILT TRAP/SEDIMENT BASIN MONITORING

3.1 Sampling and analysis procedures


3.2 Results
3.3 Comparison with previous results
3.4 Discussion on results
3.5 Conclusion of findings on discharge quality
3.6 Photos

4.0 SITE OBSERVATION DETAILS


Photos to verify site observations

5.0 NON-CONFORMANCE REPORTS

5.1 Details

6.0 CONCLUSION

APPENDIX: Certified Monitoring Results

127
REPORT: ENVIRONMENTAL MONITORING AND AUDIT REPORT
(EMAR)

TABLE OF CONTENTS
EXECUTIVE SUMMARY

1.0 INTRODUCTION

1.1 Introduction to Project


1.2 Project Development Concept
1.3 Project Environmental Management Unit
1.4 Progress of works to date
1.5 Auditing Period

2.0 SCOPE OF MONITORING WORKS

2.1 Summary of Monitoring Programme


2.2 Sampling Methodology
2.3 Water Quality Results
2.4 Silt trap/Sediment Discharge Results
2.4.1 Comparison with Baseline/Previous Results
2.4.2 Findings/Observations
2.5 Air Quality Results
2.5.1 Comparison with Baseline/Previous Results
2.5.2 Findings/Observations
2.6 Noise Quality Results
2.6.1 Comparison with Baseline/Previous Results
2.6.2 Findings/Observations

3.0 STATUS OF COMPLIANCE

3.1 Regulation of Earthworks


3.2 Drainage and Surface runoff control
3.3 Slope Protection
3.4 Air Pollution Control
3.5 Noise Pollution control
3.6 Biomass Management
3.7 Sewage Management
3.8 Solid Waste Management
3.9 Scheduled Wastes management
3.10 Contingency and Emergency Response Plan
3.11 Housekeeping

128
4.0 RECOMMENDATIONS

4.1 NCR Issued/Closed Out


4.2 Action Plan for Rectification/Improvement works
4.3 Recommendations for Identified/Predicted Issues

5.0 CONCLUSION

APPENDIX:

 PROJECT PHOTOGRAPHS

 ENVIRONMENTAL PROTECTION AND ENHANCEMENT MONITORING


CHECKLIST DURING CONSTRUCTION: Ref: ER/4.5.2/1/1

 CERTIFIED LABORATORY RESULTS

129
REPORT: CLOSURE AUDIT REPORT (CAR)

TABLE OF CONTENTS
EXECUTIVE SUMMARY

1.0 INTRODUCTION

1.1 Background details of Project


1.2 Project Description
1.3 Any changes to Project Activities throughout duration of Contract
1.4 Summary of Monitoring Program
1.5 Summary of Audit Program

2.0 EVALUATION OF PROJECT PERFORMANCE

2.1 Description and evaluation of environmental monitoring results


2.2 Description and evaluation of mitigating measures
2.3 Achievement of environmental performance as compared to JKR Corporate
Objectives
2.4 Achievement of environmental performance compared against JKR ISO
14001 EMS, the EMP and other environmental requirements

3.0 LESSONS LEARNED AND RECOMMENDATIONS


3.1 Detailing of any problems encountered on-site
3.2 Suggestions for improvement

APPENDIX:

 PROJECT PHOTOGRAPHS

 HANDING OVER AUDITING CHECKLIST: Ref: ER/4.5.5/1/9

130

Anda mungkin juga menyukai