B11 L36 E.P. Village,Brgy Pinagsama, Taguig City
Contact Nos. 02-710-3769 / 02-838-8209/0922-9450012
Email : nicolsons08@yahoo.com

Nov. 21, 2017


Rehabilitation of LMS Pedestals and Wastewater Collection System
Light Rail Manila Corp. ( LRMC)
Aug. 17, 2017 to Nov. 21, 2017
ACCOMPLISHMENT REPORT No. 11

Item Description

PREAMBLE
The unit rates "Total" for items in the bills shall be split into two sub-unit rates as follows:
(a) Unit rates for "Materials" shall include for the cost of materials (including all
wastage and for taxes, overheads and profit in connection with the ordering
of such materials) per unit of the items delivered to street level of site.
Sundry materials for fixing such as adhesives, mortar for bedding and
jointing, grouting materials, tying wire, bolts, nails, screws, ties and the like
are to be included in "Others".
(b) Unit rates for "Others" shall include for:-
(i) Labor and all costs in connection therewith
(ii) Taking delivery, unloading, storing, returning
packing handling, hoisting, lowering, etc. of materials
(iii) Fitting and fixing materials and goods in position including all sundry
materials for fixing such as adhesives, mortar for bedding and jointing,
grouting materials, tying wire, bolts, nails, screws, ties and the like
and for painting and finishing as specified.
(iv) Use of equipment, plant and tools
(v) All cutting
(vi) Establishment charges, overheads and profit
All prices shall be exclusive of 12% VAT.
The quantities given are indicative only and do not
represent a final bill of quantities.

PRELIMINARIES AND GENERAL REQUIREMENTS


Note : Contractor shall provide the detailed breakdown of costs in separate sheet.
Mobilization
Allow for mobilization of all necessary construction plant and
equipment, manpower and field facilities to site
Demobilization
Allow for demobilization of construction tools and equipment, manpower and field
facilities from site after completion of the work.
Temporary Facilities (as applicable)
This item represents provision, installation, maintenance and dismantling costs
of temporary facilities such as offices, warehouses, workshops, including
furniture, utilities, toilets and sanitary facilities, temporary access, fencing, etc.
Safety Requirements (as applicable)
Allow for the full compliance of the local and international safety, health &
environment provisions including all necessary and required protective equipment
for all workmen carrying out the works, safety sign boards, caution tapes, blue
sheets and all necessary protections to prevent access for others during
construction and after working hours.
Construction Equipment (as applicable)
Allow for the provision of necessary construction equipment including, but not limited
to, normal and special construction equipment and vehicles, instruments,
lifting devices, ventilating machines as required for the completion of the works.
Bonds & insurances, and warranties (as applicable)
Allow for the provision of all insurances, security and bank guarantees, and
warranties as required in the contract.
Permits and Licenses (as applicable)
Allow for the provision of necessary work permits and clearances and other permits
required for the completion of the work.
Drawings (as applicable)
Allow for the provision of all shop, as-built drawings and designs including all
necessary Professional Indemnity insurances.
Designs and PI Insurances (as applicable)
Allow for the provision of design services incuding all necessary
Professional Indemnity Insurances. ( Note: 5 Million Coverage)
Samples and Test Panels (as applicable)
Allow for the provision of samples and test panels as required by relevant
specifications for the proper execution of the works.
Brochures and Manuals (as applicable)
Allow for the provision of necessary manuals and brochures
for all but not limited to equipment supplied and installed.
Test and inspection (as applicable)
Allow for the provision of necessary site test and inspection works as required
by the relevant specification, in accordance with the test and inspection procedure,
using his own personnel and testing devices.
Security (as applicable)
Security of all materials, equipment, tools and all related works shall be included.
All works should be secured until completion of the works.
Scaffoldings (as applicable)
Allow for the provision of all scaffolding for the execution
and completion of the works.
Site Supervisory and Administrative Staff
Allow for the provision of adequate and competent site supervisory and
administrative staff for the proper execution of the works. Provide table of rates.
Taxes and duties (as applicable)
Allow for the provision of all applicable taxes and duties necessary for the
execution of the works except for the direct materials.
Disposal of Waste (as applicable)
Allow for the provision of disposal of all construction waste
and debris on the designated dumping area by LRMC.
Others (as applicable)
Other obligations not listed above but are contingently required for complying
with the requirements and provisions in the Contract.
a. Workers House Rentals
b. Safety Officer and PCO
c. Lorry Truck Rentals
PEDESTALS
A. Minor Cracks Repair
Number of pedestals with minor crack defects: 325 of 520
Percentage: 62.50%
1 Chipping of cracked area
2 Concrete binder (Structural Epoxy)
3 Concrete 4000Psi (Non Shrink Grout Cement @ 6000 psi)
4 Sawn Cut
5 Formworks
6 Painting of Concrete Pedestal
Note: See Drawings, Figures and Photographs

B. Major Cracks Repair


Number of pedestals with major crack defects: 60 of 520
Percentage: 12.00%
1 Chipping of cracked area
2 Cement Grout (Non Shrink Grout @ 6000 psi or Epoxy Injection)
3 Steel Reinforcement 12mm dia, Grade 40
4 Formworks
5 Painting of Concrete Pedestal
Note: See Drawings, Figures and Photographs

C. Repair of Corroded Structural Steel


Number of pedestals with steel corrosion: 130 of 520
Percentage: 25.00%
1 Surface Cleaning and Preparation
2 Application of Pimer (2 coats)
3 Application of Epoxy Enamel Finish Coat (2 coats)
Note: See Drawings, Figures and Photographs

D. Painting of Existing Column & Remaining Pedestal


1 Painting of Concrete Pedestal (Number of remaining Pedesals: 135 of 520)
2 Painting of Steel Column with Epoxy Paint(Number of remaining Pedesals: 390 of 520).

E. Removal of Existing Steel Column (Mid-Support)

F. Others
1. Chamferings of all Concrete pedestal Top Corners

Waste Water Collection System

Degreasing
Degreasing and removal of sludge shall perform as described regardless of the character
of sediments encountered, within the limits of work, to the lines and grade indicated
in the drawings & depths indicated, as specified.
Degreasing and Removal of sludge
7 Areas:
*Sump pits: LMS A, B, Rectifier Substation, Truck cleaning plant area & Paint Shop
* Oil & water Separator: LMS North and South

Clear up clogged pipelines


8 Areas:
*Sump pits: LMS A, B, Rectifier Substation, Truck cleaning plant area & Paint Shop
*LMS Drainage system (Trench)
*Oil & water Separator: LMS North and South
Unit Rate (Php)
Unit Qty Amount
Materials Others Total (M+O)

Lot 1.00 230,000.00 - 230,000.00 230,000.00

Lot 1.00 45,000.00 - 45,000.00 45,000.00


Lot 1.00 80,000.00 - 80,000.00 80,000.00

Lot 1.00 253,000.00 - 253,000.00 253,000.00

Lot 1.00 419,750.00 - 419,750.00 419,750.00

Lot 1.00 85,000.00 - 85,000.00 85,000.00

Lot 1.00 - - - N/A

Lot 1.00 8,000.00 - 8,000.00 8,000.00

Lot 1.00 246,000.00 - 246,000.00 246,000.00

Lot 1.00 10,000.00 - 10,000.00 10,000.00

Lot 1.00 - - - Included

Lot 1.00 51,200.00 - 51,200.00 51,200.00

Lot 1.00 - - - Included

Lot 1.00 10,000.00 - 10,000.00 10,000.00

Lot 1.00 138,000.00 - 138,000.00 138,000.00

Lot 1.00 30,000.00 - 30,000.00 30,000.00

Lot 1.00 50,000.00 - 50,000.00 50,000.00


- - -

Lot 1.00 24,000.00 - 24,000.00 24,000.00


Lot 1.00 276,000.00 - 276,000.00 276,000.00
Lot 1.00 253,000.00 - 253,000.00 253,000.00

cu.m 113.75 - 681.05 681.05 77,469.44


sq.m 121.55 963.75 321.25 1,285.00 156,191.75
cu.m 3.41 55,512.00 706.75 56,218.75 191,705.94
lm 260.00 - 192.75 192.75 50,115.00
sq.m 93.60 514.00 218.45 732.45 68,557.32
sq.m 425.75 192.75 173.48 366.23 155,920.29

cu.m 11.32 - 706.75 706.75 7,997.58


cu.m 9.43 55,512.00 578.25 56,090.25 529,043.24
kg 996.00 38.55 10.28 48.83 48,634.68
sq.m 160.80 514.00 218.45 732.45 117,777.96
sq.m 157.20 192.75 173.48 366.23 57,570.57

- - - -
sq.m 161.20 64.25 141.35 205.60 33,142.72
sq.m 161.20 64.25 70.68 134.93 21,749.91
sq.m 161.20 192.75 102.80 295.55 47,642.66

sq.m 176.85 192.75 173.48 366.23 64,766.89


sq.m 483.60 257.00 179.90 436.90 211,284.84

nos. 64.00 - 642.50 642.50 41,120.00

l.m. 1,064.00 - 102.80 102.80 109,379.20

-
lot 1.00 750,000.00 - 750,000.00 750,000.00

lot 1.00 612,000.00 - 612,000.00 612,000.00