OFFTAKE OPERATION FLOW CHARTS

(PLEASE TO READ OYONG MARINE TERMINAL HANDBOOK)

NO DESCRIPTION REFERENCE

1 TERMINAL REP INFO FOR PREPARED TIDE & CURRENT


DATE AND NOMINATION PREDICTION
STOWAGE PLAN

2 REVIEW Q88 OF NOMINATED


TERMINAL REP INFO
FOR TANKER(ESPECIALLY BOW
NOMINATED TANKER MOORING ARRANGEMENT)
ARRANGE MOORING MASTER
AND WEATHER REPORT

3 CARGO HEATING ABOVE 10⁰C


FSO MASTER PREPARED
TO DETERMINED DRY CRUDE POUR POINT (BOILER START
AT LEAST 4 DAYS BEFORE)

4 FSO MASTER PREPARED PROCEDURES AND JHA IN


OFFTAKE PROCEDURES AND JRA PLACE AT LEAST 2 DAYS BE
FORE OFFTAKE

5 FSO MASTER PREPARED MOORING BOLLARD PULL TEST FOR


OPERATION AND LOADING HOSE
CONNECTED SUPPORT VESSEL 2 DAYS
BEFORE OFFTAKE
CONNECT TO QRH
VISUAL INSPECTION FOR
EXPORT HOSE, MOORING
HAWSER, OFFTAKE TOOLS
2 DAYS BEFORE OFFTAKE

6 PRE OFFTAKE MEETING FSO MASTER LEAD THE


MEETING WITH OFFTAKE
TEAM IN 1 DAY BEFORE
PROCEDURES AND JRA IN
PLACE TO EXPLAIN
1 DAY BEFORE
TANKS INSPECTION FOR WA
TER CUT CHECK BY SKKMIGAS
AND SURVEYOR
FSO MASTER INFORM OFF-
7 OFFTAKE TAKE TEAM TO STAND BY
OPERATION 1 HR BEFORE( WILL BE PICK
UP BY SUPPORT VESSEL TO
GETHER WITH TOOLS) AND
ORGANIZED FSO PERSONNEL
ON DUTY
SKKMIGAS