D.C.N –CO3/MM/ ISO 9001 : 2008 (7.5.1) / ISO 14001 : 2004 Issue / Rev. No. Effective Date–
WI 9 (4.3.1,4.3.1,4.4.6) / BS OHSAS 18001 : 2007 1/1 26-Mar-12
(4.3.1,4.3.1,4.4.6)
TITLE :- WORK INSTRUCTION FOR REPLACEMENT CALIBRATION OF
PRESSURE GAUGE/TRANSMITTER / DP TRANSMITTER/SWITCH/DP SWITCH
Spares requirement:
Nil
Tools & tackles:
1. Spanners
2. Screw-drivers.
3. Calibrator.
7. SAFETY ASPECTS:
Work permit to be obtained from concerned department before starting
the work.
Conduct Tool box talk
Barricading the area
PPE s should be used by all working at site.
Operator should be informed before taking up the work.
In addition to the above any other safety measures with respect to the
department / area will be followed as displayed in that site.
Ambulance: 43111/44000/43333.
Fire & Safety control room: 9449598000.
7.1 LOTO Aspects:
LOTO is not applicable
7.2 WAH Aspects
WAH is not applicable
7.3 PTW Aspects:
PTW is applicable related documentation number is
PTW/SAFETY/STANDARD/010
8. ENVIRONMENTAL ASPECTS:
Oil/grease , cotton waste is collected and dispatched to incinerator.