Detailed Estimate

2017/48101 : 8­പശുെതാഴു് നിർೱാണംസുഭദ അജി, ഇരുനൂ ിപുതുവൽ

1 ­ clearing
1 2.32 ­­ Clearing grass and removal of the rubbish up to a distance of 50 m outside the
periphery of the area cleared.
Sl No Description No L B D CF Quantity Remark
­
1 ­ 1 8.000 5.000 1.0 40.0000 ­
Total Quantity 40.0000 sqm
Total Deducted Quantity 0.0000 sqm
Net Total Quantity 40.00 sqm
Say 40.0000 sqm @ Rs 0.0 / sqm 0.00

2 ­ earth work excavation
1 80.2  ­­  Earthwork  in  excavation  by  manual  means  over  areas  (exceeding  30cm  in
depth, 1.5m in width as well as 10 m2 on plan) including disposal of excavated earth
lead upto 50m and lift upto 1.5m disposed earth to be levelled and neatly dressed For
foundation 
All kinds of soil
Sl No Description No L B D CF Quantity Remark
foundation
1 ­ 1 21.200 0.600 0.400 1.0 5.0880 ­
ramp
2 ­ 1 3.400 0.200 0.250 1.0 0.1700 ­
urine tank
3 ­ 1 1.000 1.000 0.200 1.0 0.2000 ­
Total Quantity 5.4580 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 5.46 cum
Say 5.4580 cum @ Rs 0.0 / cum 0.00

3 ­ P C C
1 4.1.8 ­­ Providing and laying in position cement concrete of specified grade excluding
the cost of centering and shuttering ­ All work up to plinth level:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
Sl No Description No L B D CF Quantity Remark
­
1 ­ 1 21.200 0.600 0.1000 1.0 1.2720 ­
ramp
2 ­ 1 3.400 0.300 0.100 1.0 0.1030 ­
urine tank
3 ­ 1 1.000 1.000 0.100 1.0 0.1000 ­
Total Quantity 1.4750 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 1.48 cum
Say 1.4750 cum @ Rs 0.0 / cum 0.00

4 ­ brick masonry
1 50.6.2.1  ­­  Solid  block  masonry  using  pre  cast  solid  blocks  (Factory  made)  of  size
30x20x15  cm  or  nearest  available  size  confirming  to  IS  2185  part  I  of  1979  for
foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement :6 coarse sand) etc
complete
Sl No Description No L B D CF Quantity Remark
foundation
1 ­ 1 21.200 0.400 0.300 1.0 2.5440 ­
basement
2 ­ 1 21.200 0.300 .4 1.0 2.5440 ­
trough wall
3 ­ 1 15.800 0.200 0.400 1.0 1.2650 ­
urine tank
4 ­ 1 3.200 0.200 0.800 1.0 0.5130 ­
ramp
5 ­ 2 1.000 0.200 0.200 1.0 0.0810 ­
Total Quantity 6.9470 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 6.95 cum
Say 6.9470 cum @ Rs 0.0 / cum 0.00

5 ­ filling basement
1 60.2.1 ­­ EARTH WORK FILLING­ Supplying contractors own earth including cost of
conveyance  and  royalty  and  filling  (excluding  rock)  in  trenches,  plinth,  sides  of
foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited
layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Sl No Description No L B D CF Quantity Remark
­
1 ­ 1 7.100 3.100 0.400 1.0 8.8040 ­
Total Quantity 8.8040 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 8.80 cum
Say 8.8040 cum @ Rs 0.0 / cum 0.00

6 ­ flooring
1 4.1.8 ­­ Providing and laying in position cement concrete of specified grade excluding
the cost of centering and shuttering ­ All work up to plinth level:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
Sl No Description No L B D CF Quantity Remark
­
1 ­ 1 7.100 3.100 0.100 1.0 2.2010 ­
ramp
2 ­ 1 0.800 1.000 0.200 1.0 0.1610 ­
Total Quantity 2.3620 cum
Total Deducted Quantity 0.0000 cum
Net Total Quantity 2.36 cum
Say 2.3620 cum @ Rs 0.0 / cum 0.00
7 ­ plastering
1 13.1.1 ­­ 12 mm cement plaster of mix:
1:4 ( 1 cement : 4 fine sand)
Sl No Description No L B D CF Quantity Remark
basement
1 ­ 1 22.000 .4 1.0 8.8000 ­
trough wall inside
2 ­ 1 15.000 0.400 1.0 6.0000 ­
outside
3 ­ 1 16.600 0.400 1.0 6.6410 ­
urine tank inside
4 ­ 1 2.400 0.800 1.0 1.9200 ­
outside
5 ­ 1 4.000 0.700 1.0 2.8000 ­
Total Quantity 26.1610 sqm
Total Deducted Quantity 0.0000 sqm
Net Total Quantity 26.16 sqm
Say 26.1610 sqm @ Rs 0.0 / sqm 0.00

8 ­ steel work
1 10.2 ­­ Structural steel work riveted, bolted or welded in built up sections, trusses and
framed work, including cutting, hoisting, fixing in position and applying a priming coat
of approved steel primer all complete.
Sl No Description No L B D CF Quantity Remark
42mm dia GI
1 ­ 10 2.500 2.46 61.5000 ­
­
2 ­ 5 2.500 2.46 30.7500 ­
20*40mm
3 ­ 3 7.700 2.03 46.8930 ­
­
4 ­ 3 3.500 2.03 21.3150 ­
Total Quantity 160.4580 kg
Total Deducted Quantity 0.0000 kg
Net Total Quantity 160.46 kg
Say 160.4580 kg @ Rs 0.0 / kg 0.00

9 ­ roofing
1 12.51.1 ­­ Providing and fixing precoated galvanised steel sheet roofing accessories
0.50  mm  (+  0.05%)  total  coated  thickness,  zinc  coating  120  grams  per  sqm  as  per
IS:mm(+0.05%)  total  coated  thickness,  Zinc  coating  120  grams  per  sqm  as  per  IS:
277, in 240 mpa steel grade, 5­7 microns epoxy primer on both side of the sheet and
polyester top coat 15­18 microns using self drilling/self tapping screws complete:
Ridges plain (500­600 mm)
Sl No Description No L B D CF Quantity Remark
­
1 ­ 18 1.200 1.0 21.6000 ­
Total Quantity 21.6000 metre
Total Deducted Quantity 0.0000 metre
Net Total Quantity 21.60 metre
Say 21.6000 metre @ Rs 0.0 / metre 0.00

10 Sharpening charges 1500.00
11 Display Board 2000.00
Total Rs :
Rounded Total Rs : .00
( Rupees Only)
Unskilled Manpower wages 0.00
Materials 0.00
Skilled 4944.21
SemiSkilled 12235.18
No of Person days 0.00
No of Person days(Say) 0
 