Note: Start dates must be calculated from Tilos through links, except the project
start, dated 15.03.13.
Templates could be found under sub-folders in the preset tool bar. Example:
Earth Works and Canalisation.
Following you will find the relationships between tasks.
Predecessors Sucessors Link and lag
ID Name ID Name
00 Start 10 Trenching FS
10 Trenching 40 Trenching FS
10 Trenching 20 Pipe installation SS + 200 mts
(1)
Note 1.- This kind of lag (distance) keeps a distance of 200 mts in the production
sequence between one activity and another.