BAR CHART

Waktu Kegiatan Hari ke-


Kegiatan
(hari) sebelum 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 1 -
B 2 A
C 3 A
D 4 B,C
E 2 D
F 2 F
G 5 D
H 1 F,G
I 1 H

3
NET WORK PLANNING 3
4
B
2 I
8 E 10 F 14 15
0 A 1 C 4 D
4 5 6 9 10
1 2 4 8 2 11 2 14 1 15
0 1 3 4
1
H
G
CRITICAL PATH = A - C - D - G - H - I 1
5 13
8
13

TABULASI NWP
Waktu Kegiatan
Kegiatan ES LS EF LF TF
(hari) sebelum
A 1 - 0 0 1 1 0
B 2 A 1 1 3 4 1
C 3 A 1 1 4 4 0
D 4 B,C 4 4 8 8 0
E 2 D 8 8 10 11 1
F 2 F 10 11 13 13 1
G 5 D 8 8 13 13 0
H 1 F,G 13 13 14 14 0
I 1 H 14 14 15 15 0