Coiled Tubing Equipment

Printed July 2007


Coiled Tubing Equipment

Coiled Tubing Unit Schematic

Wellhead Configuration

Blowout Preventers (BOPs)


Gooseneck:
Rig Up Configuration

Coiled Tubing
Guides Coiled Tubing into Injector

Slings: Connection For Crane


Wellhead Schematic
Injector: Runs CT In and Out of Well

Equalizer Valves: Equalize pressure


Above and Below BOP Rams Stuffing Box: Seals CT Annulus
Indicator Pins: Shows Position of Blind Rams: Seals well without CT
BOP Rams Cutter Rams: Cuts CT
Kill Port: Flow Entry for Kill Fluid in Slip Rams: Keeps CT from Moving Up/Down
an Emergency Tubing Rams: Seals CT Annulus Emergency
Flow Tee: Directs Returns to 2X2 Hamer Valve: Isolates Flowback
Flowback Iron and Tanks Iron from Wellhead
Flange or Quick Union X-over Connection
for CT Rig Up
Swab valve: Allows well to be shut in
Wing Valves: Isolates Production Flow
while flowing through production
to pipeline (or process plant)
lines
Top Master Valve: Shuts in Well Under
Normal Conditions
Emergency Master Valve: Shuts in Well in
an Emergency, ie. Top Master failure
Casing Valve: Allows Access to Production
Tubing Annulus Tubing Hanger: Hangs and Isolate
Production Tubing
Surface Vent: Allows Surface Casing to
Casing Flange: Connection for Wellhead Breath
Casing Bowl: Adapter for Casing Surface Casing: Supports Wellhead
to Wellhead & isolates surface zones
Injector Head

Stuffing Box

Riser

Power Reel
BOP
Injector
Injector
Coiled Tubing Unit Schematic

Reel
Reel Unit
Unit
Stripper
Stripper
Packer
Packer Control
Control Cab
Cab

BOP
BOP Power
Power Pack
Pack
B O P STANDARDS

Minimum 10,000 psi working pressure


Minimum 3 1/16” ID
All shall be H2S compatible
Quad Ram B.O.P.
Top Equalizing
Valve

BLINDS

SHEARS
Kill Port

SLIPS Bottom
Equalizing Valve

PIPES

Well Head
Quad Ram B.O.P.

Blind Rams
Shear Rams
Slip Rams
Tubing Rams

“Kill” Line

Wellhead
Internal BOP Parts

!!
Texas Oil Tools
Quad BOP Ram Inserts

!
Texas Oil Tools
Quad BOP for Coiled Tubing

!
Ram Position Indicator

!
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Run coiled tubing


into hole and
perform treatment !
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Close Slips to secure


coiled tubing !
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Close Pipe Rams to


isolate Annulus !
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Close Shear Rams to


cut off coiled tubing
!
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Pull coiled tubing


out of B.O.P.’s !
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Close Blind Rams


to isolate live well
pressure from
Stuffing Box
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Equalize pressure
before opening the
Blind Rams !
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Open Blind Rams


Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Open Shear Rams Run in


with overshot
Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Open Pipe Rams


Quad Ram B.O.P. Operations

BLINDS

SHEARS

SLIPS

PIPES

Open Slips and recover


tubing
BOPs

150,000 ft (50 km) Running Feet Major


Inspection or After Acid or H2S Job
Regular Maintenance, Inspection and
Function Testing
Always Check Travel Indicators to Ensure
Ram Activation
Always Manually Lock Rams & “Flag”
Setting Slips Shortens Life of Coiled
Tubing at that Point
Slip Ram Inserts
Interrupted Style
BOPs (cont.)

Never Rig up to Take Wellbore Flow


Through BOP
Rig up ‘Back Flow’ When Dealing With
Elastomer Attacking Chemicals or High
Temperature Wells
Ensure Shear Ram Capabilities -
Especially When Running Stiff Wireline or
Concentric Coiled Tubing
MAXIMUM Closure Time 15 seconds For
Each Ram
Cutter Rams w/Boosters
Combination BOP
“Combi”
Texas Oil Tools
Combi Ram Inserts

Shear Seal Ram Insert

Pipe Slip Ram Insert

!
BOP Inserts
Shear Seal Blades

Top View

Below View