I. PROJECT DESCRIPTION
 Project Title: “Earthquake 101”
 Type of Project: Safety
 Number of Beneficiaries: Whole Barangay
 Area of Project Implementation: Lodlod, Lipa City Batangas.
 Budget Requirement:

II. BACKGROUND/SITUATION ANALYSIS

 What prompted the project?


To give proper knowledge to the people incase of an earthquake.

 Is there an existing concern or potential problem that you want to


address?
To teach or refresh the minds of the people who knows what to do to be
assure on doing it in-case of an earthquake.

III. PROJECT OBJECTIVES

OBJECTIVES STRATEGIES
The Project aims to teach disaster Giving Brochures and discussing the
awareness, preparedness, contents through the seminar and
prevention, recovery and teaching the proper way with
rehabilitation demonstration.
IV. DESIRED IMPACT AND OUTCOME OF THE PROJECT
 What are the long term effects of the project?
To broaden and strengthen the knowledge of residents regarding disaster
awareness and also teach the next generation (their sons/daughters) to
help in the spreading of knowledge as well.
 What are the various ways to sustain/maintain the project?
The willingness of the residents to cooperate and learn new things.

V. RISK MANAGEMENT PLAN


 Unwillingness of the residents, insufficient money, lack of space for the
event if there are a lot of residents that will come, and the execution of
the allotted time and schedule.

VI. DETAILED BUDGET REQUIREMENT


Budget line item Description Amount needed Proposed Source’s
Food Jollibee Chicken P700,000 Jollibee
rice meal
Transportation Service vehicles P300,000
Emergency Kit Bandage, Gauze P700,000 Red Cross
Pad, alcohol,
Radio, vitamins
Sound system Speakers, P500,000 R&M Lights and
Microphone sounds
Guest Speakers Nurses,Doctors P400,000 Mary mediatrix
medical center
Educational Brochures, P80,000
materials Letters

VII. ATTACHMENTS