BRIDGE OVER SIRSA NADI ON LINK ROAD FROM

HARRAIPUR TO CHUNARI AT RD 1/100

HYDRAULIC CALCULATIONS

CLIENT: CONSULTANT:
HIMACHAL PRADESH PUBLIC GEO GLOBE CONSULTANTS, PLOT
WORKS DEPT., NALAGARH NO. 528, PHASE 9, IND. AREA,
DIVISION MOHALI
BRIDGE OVER SIRSA NADI ON LINK ROAD FROM HARRAIPUR TO CHUNARI AT RD 1/100

Waterway Calculation

HFL = 101.39 m
Bed profile :-
The bed profile is plotted in AutoCad and flow characteristics are calculated
from there.

Area of river section, A = 449.55 m2


(From AutoCad)
Wetted Perimeter of river section, P = 255.26 m
(From AutoCad)
River slope, S = 0.007
Hydraulic radius, R = A/P = 1.76 m
Manning's rugrosity coefficient, n = 0.033
From Manning's formula,
Flood Discharge, Qf = 1678.71 m3/s
2/3 1/2
(Qf = 1/n. R . S )
For four spans of 45m each,
Total width of waterway, (W) = 170.00 m
Now, From IRC:5-1998,

=> W required = 4.8 X √Q


=> = 196.67
W provided = 170.00 m
< Waterway required
XXX

However if 5 spans of 45m each are proposed,


Then total regime width = 212.5 m
> Waterway required
OK
Hence 5 Spans are required.
Bed Levels as provided in the Survey Drawing

-13 101.422 -70


-12 101.226 -65
-11 101.035 -60
-10 100.701 -55
-9 100.217 -50
-8 99.733 -45
-7 99.744 -40
-6 99.463 -35
-5 99.181 -30
-4 99.987 -25
-3 99.094 -20
-2 99.187 -15
-1 99.281 -10
0 99.59 -5
1 100.147 0
2 100.253 5
3 100.376 10
4 100.229 15
5 100.083 20
6 99.937 25
7 99.827 30
8 99.713 35
9 99.65 40
10 99.689 45
11 99.729 50
12 99.768 55
13 99.678 60
14 99.503 65
15 99.302 70
16 99.084 75
17 99.851 80
18 99.582 85
19 98.708 90
20 99.122 95
21 99.583 100
22 99.69 105
23 99.905 110
24 99.828 115
25 99.787 120
26 99.65 125
27 99.514 130
28 99.507 135
29 99.404 140
30 99.192 145
31 98.676 150
32 98.766 155
33 98.655 160
34 98.635 165
35 98.65 170
36 98.664 175
37 98.875 180
38 101.446 185
5182.519