SCHOOL OF
ARCHITECTURE,
URBAN PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Master of Science in Architecture
Architecture
Course of Project Appraisal – Section A & B
Politecnico di Milano – School of Architecture, Urban planning and Construction Engineering
Milan, 11th March 2016
KEY FACTS ABOUT
THE COURSE
• How Earned Value Management fits into a Program and Project ENGINEERING
Master of Science in
environment Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
– Are from the internal system the contractor uses to manage Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Why use Earned Value? For one, it is mandated by some key DOE SCHOOL OF
ARCHITECTURE, URBAN
directives and guidance that Earned Value will be implemented. The PLANNING AND
CONSTRUCTION
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Traditional Management vs. Earned Value THE COURSE
Management
Module 1 -
Introduction
To better understand Earned Value Management, let’s take a look at
how earned value management compares with traditional
management.
Following pages will discuss and contrast the different between the two SCHOOL OF
ARCHITECTURE, URBAN
management approaches. PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Traditional Management
In Traditional management, there are two data sources, the budget (or
planned) expenditures and the actual expenditures. The comparison of Module 1 -
budget versus actual expenditures merely indicates what was planned Introduction
to be spent versus what was actually spent at any given time. But how
much has been produced?
As you can see, with this approach there in no way to determine the
physical amount of work performed. It does not indicate anything about
what has actually been produced for the amount of money spent nor
whether it is being produced at the rate, or according to the schedule,
originally planned. In other words, it does not relate the true cost
performance of the project.
70
As the graph shows, 60
SCHOOL OF
this comparison 50 ARCHITECTURE, URBAN
PLANNING AND
only represents the 40 CONSTRUCTION
ENGINEERING
relationship of what 30 Master of Science in
was budgeted 20 Architecture
Time Now
(planned) versus 10 Project Appraisal
spent. Budget 5 10 15 20 25 30 35 40 45 50 55 60
11th March 2016
Earned Value takes these three data sources and is able to compare the
SCHOOL OF
budgeted value of work scheduled and compare it to the “earned value of ARCHITECTURE, URBAN
PLANNING AND
physical work completed” and the actual value of work completed. CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Let’s take a closer look at how earned value appears in a graph. Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
the earned value of the production (in black). Note how the budget line is below
both the actual expenditures and the earned value lines. What does this
indicate?
First, it is obvious that the project is expending more (blue line) than it was
budgeted to spend, to date
(red line). Given the 150
125
progression of each line, it is
100
also apparent that this trend 75
has occurred since the 50 SCHOOL OF
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
By comparing the budget line (in red) to the earned value line (in black), it is
immediately apparent that the project is producing more than it was budgeted
to produce to date. Additionally, by comparing the actual expenditures (in blue)
to the earned value line (in black), it is immediately apparent that the project is
spending more then it was budget to date. So while the project is expending
more (blue line) than budgeted (red line), it is also producing more (black line)
than budgeted.
So what conclusions can be drawn from this graph? Let’s find out on the next
page. 150
SCHOOL OF
125 ARCHITECTURE, URBAN
PLANNING AND
100 CONSTRUCTION
ENGINEERING
75
Master of Science in
50 Architecture
25 Project Appraisal
Time Now
0
J F M A M J J A S O N D Milan
Budget 5 10 15 20 25 30 35 40 45 50 55 60 11th March 2016
Actuals 10 20 30 40 50 60
Earned 8 15 25 30 35 45 prof. Barrese
Forecast 70 80 90 100 110 120 prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
150
125
100 SCHOOL OF
ARCHITECTURE, URBAN
75 PLANNING AND
CONSTRUCTION
50 ENGINEERING
25 Master of Science in
Time Now
Architecture
0
J F M A M J J A S O N D
Project Appraisal
Budget 5 10 15 20 25 30 35 40 45 50 55 60
Actuals 10 20 30 40 50 60 Milan
Earned 8 15 25 30 35 45 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Summarizing Traditional Management vs. THE COURSE
• How much money and time a particular job is likely to require prior to starting
and once stated, how much money was spent at any given time.
• How much money and time a particular job is likely to require prior to starting
and once stated, how much money was spent at any given time.
SCHOOL OF
ARCHITECTURE, URBAN
Plus PLANNING AND
CONSTRUCTION
ENGINEERING
• Once started, what work has been accomplished to date for the funds Master of Science in
Architecture
expended (what you got for what you spent) Project Appraisal
Milan
11th March 2016
• Once started, what the total job will cost at completion, and how long it will
take to complete prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Understanding how Earned Value fits into the program and project
management environment is also essential.
On the following page we will discuss and define items such as project
vs. program, project management, program management and the
relationship between them.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
“Triple Constraint”
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Milan
11th March 2016
• To obtain benefits not available from managing them individually ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value Management vs Program/Project THE COURSE
Management
Earned Value is a Program/Project management technique used to objectively evaluate Module 1 -
cost and schedule efficiency, thereby facilitating better management of customer needs Introduction
and expectations.
Management
PLANNING AND
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Framework for an Earned Value Management THE COURSE
System (EVMS)
Module 1 -
Introduction
So far, we have discussed what Earned Value is, why to use it, and how it
fits into a program and project management environment. Next, we
need to discuss the framework needed to implement earned value.
Project Appraisal
On the following pages these three phases for developing an Earned Milan
11th March 2016
Value Management System (EVMS) will be discussed in more detail.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Inputs needed for Earned Value Management THE COURSE
System (EVMS)
As you recall, the first phase of Earned Value is inputs. The inputs required Module 1 -
for an EVMS include: Introduction
Project Appraisal
If any of these items are not completed or are not completed appropriately,
the use of Earned Value will be compromised and your outputs will not Milan
11th March 2016
Project
Schedule
Resource Planning
Define/Assign
Schedule/Budget
Performance Measurement
These Items are covered in Modules 5 Establish Baseline
Early Warning & Detection
Project Appraisal
Once again, if any of these items are not completed or are not completed
appropriately, the use of Earned Value will be compromised and your outputs Milan
11th March 2016
will not properly represent the program/project current and future status.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Outputs needed for Earned Value Management THE COURSE
System (EVMS)
The last phase of Earned Value is the outputs. The outputs required for an Module 1 -
EVMS include: Introduction
• Reporting requirements
• Proper Analysis of Reports
WBS/OBS
• Correct Action taken Project
Schedule
Resource Planning
Define/Assign
Schedule/Budget
Performance Measurement
Establish Baseline
Early Warning & Detection
These Items are covered in Modules Earned Value
Informed Management Decisions
Management
9,10 & 12 System
Corrective Actions
Recovering Planning SCHOOL OF
ARCHITECTURE, URBAN
Accounting PLANNING AND
System CONSTRUCTION
ENGINEERING
$$$
Master of Science in
Architecture
Even if the first two phases are completed appropriately, improper Project Appraisal
analysis of the outputs could cause inappropriate or inadequate
actions to be taken against the program/project and could either create Milan
11th March 2016
problems that otherwise would not exist or fail to fix the real problem
prof. Barrese
that does exist. prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review of Module 1
Module 1 -
“You cannot manage what you cannot measure…and what gets Introduction
measured gets done.”
--- Bill Hewlett, Hewlett Packard
Traditional Management does not allow for analysis of the physical amount ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
of work performed. Earned Value Management allows for both schedule ENGINEERING
and cost analysis against physical amount of work performed Master of Science in
Architecture
• EVMS can be divided into three phases (Inputs, Earned Value method, Milan
outputs) and all three most be completed appropriately for proper 11th March 2016
The objective is to introduce you to Work Breakdown Structure (WBS) and other
supporting documents.
This module will include defining and illustrating the following topics:
• WBS dictionary
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Over the years, it was determined that project managers needed a tool to help SCHOOL OF
capture and control their project scope. This led to the development of a ARCHITECTURE, URBAN
PLANNING AND
Master of Science in
Architecture
On the following pages we will define and discuss a WBS. Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
all the work and products 1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3 1.1.1.3.2
prof. Barrese
necessary to produce the book. prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
BEST Management
Books
1.
Master of Science in
Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
details and distinguish one project’s needs from others within the company or
ENGINEERING
Master of Science in
organization. Why is distinguishing one project from another important? It Architecture
enables you to identify resource requirements and allocate resources more Project Appraisal
effectively. Milan
11th March 2016
Preparing a WBS
In preparing a WBS there are a number of steps that need to be taken to make
sure the WBS developed will help manage your project. Below and on the
following pages we will discuss these steps.
1. Identify final project products necessary for achieving project success. The
WBS should assist the project manager in developing a clear vision of the end
product. You need to answer the following question:
– What must be delivered to achieve project success?
• You may need to review the project scope documents for guidance.
SCHOOL OF
2. Identify the major deliverables necessary for project success. ARCHITECTURE, URBAN
PLANNING AND
– These are items that by themselves do not satisfy the project need but CONSTRUCTION
ENGINEERING
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
– Remember that no matter how detailed a WBS is, there are planning Project Appraisal
Preparing a WBS
Let’s use the BEST Management Books’ WBS we looked at earlier. Assume that
the WBS was only planned down to the chapters level (see graph below, left),
but after the first month of work, the stakeholder wants reporting at the
subchapter level (see graph below, right). Without restructuring the WBS and
changing the other supporting systems, like cost tracking and reporting, it is
impossible for the project manager to meet the stakeholder’s request.
Writing Writing
Text Book Text Book
1.1.1 1.1.1 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Chapter 2 Chapter 2 ENGINEERING
Chapter 1 Chapter 1
1.1.1.1 1.1.1.2 1.1.1.1 1.1.1.2
Master of Science in
Architecture
Project Appraisal
Project Project Project Budget & Scheduling
Scheduling Project
Not Planned to this level Selection
1.1.1.1.1
Organization
Organization
1.1.1.1.2
Planning
1.1.1.1.3
Cost
1.1.1.2.1
1.1.1.2.2 Controls
1.1.1.2.3
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
Now let’s reverse the situation. Assume WBS was planned down to the
subchapter level (see graph below, left), but after the first month of work, the
stakeholder wants reporting at the chapter level (see graph below, right). Is
there any restructuring needed to the WBS? The answer is “No”. Since you
planned the work at a level below what is now the stakeholder’s requirement,
you can “roll-up” and meet the stakeholder’s request.
Do you still see a problem with the project WBS? Let’s take a look.
Master of Science in
Architecture
Milan
11th March 2016
.
Project
Selection
Project
Organization
Organization
Project
Planning
Budget &
Cost
Scheduling
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.1.2 1.1.1.2.1
1.1.1.1.1 1.1.1.1.3 1.1.1.2.3
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
Actually, there is not a problem with the WBS structure, but a problem with the
idea of time and cost. The project manager spent time and resources to
define the WBS down to a level that he determined was appropriate. The
only benefit could be that the project manager wishes to manage the project
at the lower level and will roll-up reporting for the stakeholder.
In review, always get stakeholders to agree with the level of project planning and
reporting.
Master of Science in
Architecture
Milan
11th March 2016
Project Project Project Budget & Scheduling
Scheduling Project
Selection Organization
Organization Planning Cost 1.1.1.2.2 Controls
1.1.1.1.2 1.1.1.2.1
1.1.1.1.1 1.1.1.1.3 1.1.1.2.3
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
In developing a WBS, one must realize that there are multiple ways to develop a
WBS for any given project. Some ways might be better than others, but the
two most important item to remember are that the WBS must contain all
approved scope and the Project Manager must develop the WBS to reflect
the way he/she intends to manage the project.
Master of Science in
Architecture
On the following two pages are examples of alternative WBS structures for the Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
This WBS structure is designed to control scope by
chapters, unlike the original WBS which was
developed to control scope by writing and
editing.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Preparing a WBS
This WBS structure is taking into consideration that
the writing and editing will be executed by a
contractor. It still requires the contractor to
control scope by writing and editing by chapter.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Building a WBS
Armed with the basics of the WBS, it is time to examine them in more detail and
to begin to understand how to build one. To do this, let’s look at building a WBS
for the construction of a single family home. First, take a moment to familiarize
yourself with some background information about the construction company,
which appears on the next page.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS: Structure
The ACME Housing Corporation, which you own, has been contracted to build its
first house. You want to be able to manage your projects effectively and
efficiently, so you charge your project managers to develop an appropriate
WBS. You decide to manage the project by the individual tasks necessary to
complete the house.
You hope that this is the first of many houses that ACME will build, so you start
the WBS with ACME in the highest position, or Level 1. Accordingly, Level 1 is
given a WBS code of 1. You assign the WBS code of 1 to the highest level
because all future projects (houses) will be summarized at Level 1.
Level 1
ENGINEERING
• Inspection happens
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS: Structure
With Level 1 established, you can begin to complete the WBS. But what should
the next level be?
The logical next level for ACME is the project level. Level 2 is the level for each
individual project, or house, that ACME undertakes. As the chart shows below,
Level 2 is identified at the project level: House.
Appropriately, the code for Level 2 corresponds to Level 1. In this case, the code
is 1.1.
Level 1 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS: Structure
Now the WBS for the housing project is complete, right? Actually, no, the WBS is
not complete. At this point you determine that you want to divide the work into
the major elements needed to build a house. You choose to divide Level 3 into
six elements: concrete, framing, plumbing, electrical, interior and roofing. You
realize that these are both major deliverables and milestones for managing the
project. They also enable you to get to your goal of managing the project by
task.
Notice the WBS codes at level 3. Each is unique to the project and starts with the
WBS code from the level above (11.11.1.1). Now lets look and see if
another level is needed.
Level 1 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Project Appraisal
Milan
Level 3
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS: Structure
The ACME WBS is taking shape, but it does not quite define the project at a level
that shows needed tasks for completion. To do this, one more level needs to
be included.
Level 4 of the WBS will enable us to manage
the project as desired. All of our contractors
fit into specific elements at level 4, and so
do all specific departments. As with the Level 1
previous Levels, note the WBS codes that
have been assigned to the tasks and their Level 2
relationship to the previous Level.
SCHOOL OF
Master of Science in
Architecture
Level 4 Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS: Structure
What do you think? Is the WBS complete? Does it enable the manager to
manage at the task level?
After a review to make sure that only approved scope is included, our WBS is
complete. It does include the necessary components to manage the project by
task.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
the Levels in the Tree format mirror the 1.1.5.1 Install Drywall
Master of Science in
1.1.5.2 Install Carpets
graphical format. The content has not Architecture
Now that you understand the WBS and how to assemble one, let’s examine how
it relates to earned value.
In Module 1, we discussed that in implementing earned value, a project manager
must have control of the project’s “triple constraint” (scope, schedule and cost).
Unlike traditional management, which tracks two components (budget and
expenditures), earned value considers three and provides a more robust
understanding of a project’s overall progress and health.
The WBS is the most important item in defining and controlling the project scope.
How does it control the scope? If the WBS is not developed correctly and does
not capture all the project scope and only the project scope, then the “earned
value” system built using the WBS will be inaccurate. The project manager will SCHOOL OF
ARCHITECTURE, URBAN
Master of Science in
Now that you have your WBS, let’s take a look on the next page at the other item
Architecture
Project Appraisal
needed to properly organize your project.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
WBS Dictionary
Once the WBS is complete, the WBS dictionary needs to be the next item
developed. The WBS dictionary is a narrative documentation of the effort
needed to accomplish all work defined in the WBS. The WBS dictionary is
developed for the lowest level element in the WBS only.
To better understand how a WBS and a WBS dictionary work, let’s compare it to
a book and the book’s table of contents:
– The WBS is the table of contents for the project. It captures the
contents in an organized fashion (chapters, subchapter).
– The WBS dictionary is the book itself. It tells the story. In our case the
story is what work will be accomplished and what outputs will be SCHOOL OF
ARCHITECTURE, URBAN
produced in each of the WBS elements. The total of these descriptions PLANNING AND
CONSTRUCTION
is how a house will be built and what is needed to build the house. ENGINEERING
Master of Science in
Architecture
The WBS dictionary will often lead to the development of the statements of work Project Appraisal
(SOW) for the project. SOWs will be discussed in later modules. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
CIVIL STRUCTURAL ELECTICAL PLUMBING ARCHITECTURE, URBAN
With the relationships RESP DEPT RESP DEPT RESP DEPT RESP DEPT PLANNING AND
R. Kelly P. Tate J. Sims R. Lee CONSTRUCTION
and responsibilities ENGINEERING
CONSTRUCTION
R. Oriely
PLUMBING
RESP DEPT
K. Wells
GAS
ENGINEERING
R. Lee
Master of Science in
PERF DEPT 4010
Architecture
HOOKUP/TIE-IN
Responsibility
S. Johnson
RESP DEPT
ELECTICAL
WIRING
P. Ottis
J. Sims
Project Appraisal
PROJ ECT OFFICE
Assignment Matrix
B. Smithers
RESP DEPT
DRYWALL
ROOFING
D. Smith
Y. Taylor
R. Sites
Milan
RESP DEPT
P. Tate
prof. Barrese
CONCRETE
M. Manning
MASONRY
T. Greams
RESP DEPT
TEST
R. Kelly
CIVIL
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review
Take some time to review the major items of this module:
• The Work Breakdown Structure (WBS) is a tool that defines a project and
groups the projects elements in a way that helps organize and define the
total work scope of the project
• In preparing a WBS there are a number of steps that need to be taken
including:
– identifying the final project product
– identifying the major deliverables
– incorporating the appropriate levels of detail
– obtaining stakeholder agreement
• WBS Dictionary is a narrative description of the lowest level for each WBS SCHOOL OF
ARCHITECTURE, URBAN
• Responsibility Assignment Matrix (RAM) merges the WBS and OBS to Milan
11th March 2016
identify the specific responsibility for specific project tasks
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Scheduling
The objective is to introduce you to Project Scheduling.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• In Module 2 we discussed
– the first steps in the planning process
– development of the work breakdown structure (WBS)
– organizational breakdown structure (OBS)
– the integration of WBS and OBS in creating the responsibility assignment
matrix (RAM) SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
• The next step in this process is to develop the project schedule. So the first Master of Science in
Architecture
question we need to ask is what is scheduling?
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
What is Scheduling?
There are multiple ways of defining scheduling. Scheduling is:
…Forming a network of activities and event relationships that portrays the sequential
relations between the tasks in a project…
…Planned completion of a project based on the logical arrangement of activities,
resources…
…Placing the project and its activities in a workable sequenced timetable…
…A detailed outline of activities/tasks with respect to time…
While scheduling is all of these things, the main thing to remember is that SCHOOL OF
ARCHITECTURE, URBAN
scheduling is the development of planned dates PLANNING AND
CONSTRUCTION
Master of Science in
Architecture
Project Appraisal
By looking at the aforementioned definitions of scheduling, do you see a
difference between planning and scheduling? Let’s take a look on the next Milan
11th March 2016
page.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
“I keep six honest serving men (they taught me all I knew); their names are
What and Why and When and How and Where and Who.”
--- Rudyard Kipling
Planning involves making decisions with the objective of influencing the future.
Another way to consider planning is as the “thinking” phase. Defining
activities, their logical sequence, and their relationship to each other are all
planning functions. In planning you answer the following questions:
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
With five main questions answered, only one last question remains: when. This
question involves scheduling.
Scheduling determines the timing of operations in the project. The schedule will
determine the specific start and completion dates for the project and all project
activities. Another way to look at scheduling is to consider it the “action” or
“doing it” phase. In scheduling you answer the question:
Master of Science in
Equipped with an understanding of the difference between planning and Architecture
scheduling, let’s look on the next page at the scheduling requirement needed Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Scheduling
To satisfy the earned value management system (EVMS) criteria, the schedule
must:
On the following pages, we will discuss the process for developing a project CONSTRUCTION
ENGINEERING
schedule, including how to ensure it is logical and how to ensure that it Master of Science in
Architecture
includes all key milestones and deliverables.
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Scheduling
Project scheduling in the earned value management system involves a clear, five
step process. This process aids managers in determining the project schedule
and, eventually, the project schedule baseline. The process steps are:
the end of the process will will look at the outcome of using this process on the Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling - Step 1. Develop a List of Project THE COURSE
Activities
Developing a list of project activities is as simple as it sounds: list all activities
that are needed to complete the project. Do not order or rank them yet, as this
step comes later. This list needs to be as complete as possible. You can add
and subtract activities throughout the process, but the more complete the list is
now, the easier the process will be.
BEST Management
Using the BEST Management Book example from Books
1.
Master of Science in
on the following page. Chapter 1 Chapter 2 Chapter 3 Editing Editing Editing
Architecture
1.1.1.1 1.1.1.2 1.1.1.3 Chapter 1 Chapter 2 Chapter 3
1.1.2.1 1.1.2.2 1.1.2.3 Project Appraisal
Milan
Project Project Project Budget & Scheduling Project Auditing Administrative 11th March 2016
Selection Organization Planning Cost 1.1.1.2.2 Controls 1.1.1.3.1 Closeout
1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3 1.1.1.3.2
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling – Step 1. Develop a List of Project THE COURSE
Activities
Here is the initial list of activities for the BEST Project Management book. There
are two things to remember at this stage of the process.
1. The activity list is not a complete list; additions and subtractions will be
made from it.
2. As you develop your list, you may see the need to update the WBS.
Remember the WBS is a dynamic tool, revisions may be needed and
should be expected as the scheduling of activities progresses.
1.1.1.1.3 Writing Project Planning section for Chapter 1 no revision to the WBS is needed. PLANNING AND
CONSTRUCTION
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 ENGINEERING
1.1.1.2.2 Writing Scheduling section for Chapter 2
Master of Science in
1.1.1.2.3 Writing Project Controls section for Chapter 2 Architecture
1.1.1.3.1 Writing Auditing section for Chapter 3
Project Appraisal
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
1.1.2.1 Editing Chapter 1
1.1.2.2 Editing Chapter 2 Milan
11th March 2016
1.1.2.3 Editing Chapter 3
1.1.3 Publishing Project Management Book
1.1 Finished Development of the Project Management Book prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling – Step 2. Sequence the List of Project THE COURSE
Activities
With the activity list complete, we need to “sequence” or develop “logic” between
activities. To complete this process we need the WBS activities list and a
pencil.
This process requires the project manager, subject matter experts (SME), and
other project team members who are familiar with the nature of the specific
activities to meet, discuss and develop the sequencing of the project activities.
This process is known as “a pencil to paper” process.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Continuing to use our BEST Management book example, we will take a look at CONSTRUCTION
ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling – Step 2. Sequence the List of Project THE COURSE
Activities
1. Start with the WBS… BEST Management
Books
1.
…2. Develop the Activity List….
WBS Activity List
1.1 Start Development of Project Management Book
Project Management 1.1.1.1.1 Writing Project Selection section for Chapter 1
- An Introduction
1.1 1.1.1.1.2 Writing Project Organization section for Chapter 1
1.1.1.1.3 Writing Project Planning section for Chapter 1
1.1.1.2.1 Writing Budget and Cost section for Chapter 2
Writing Editing Publishing 1.1.1.2.2 Writing Scheduling section for Chapter 2
Text Book Text Book Text Book
1.1.1 1.1.2 1.1.3
1.1.1.2.3 Writing Project Controls section for Chapter 2
1.1.1.3.1 Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
Chapter 1 Chapter 2 Chapter 3 Editing Editing Editing 1.1.2.1 Editing Chapter 1
1.1.1.1 1.1.1.2 1.1.1.3 Chapter 1 Chapter 2 Chapter 3
1.1.2.1 1.1.2.2 1.1.2.3 1.1.2.2 Editing Chapter 2
1.1.2.3 Editing Chapter 3
1.1.3 Publishing Project Management Book
Project Project Project Budget & Scheduling Project Auditing Administrative
Selection Organization Planning Cost 1.1.1.2.2 Controls 1.1.1.3.1 Closeout 1.1 Finished Development of the Project Management Book
1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3 1.1.1.3.2
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling - Step 3. Determine the Relationship THE COURSE
Sequencing is the order of how things will happen. First, second, third, etc. . .
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Scheduling - Step 3. Determine the Relationship THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Let’s take a closer look at the first three scheduling dependencies. We will not ENGINEERING
Master of Science in
discuss the last dependence, as it is never used. Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Start
Chapter 1
ARCHITECTURE, URBAN
Master of Science in
You must “Finish” writing the Project Organization section of Chapter 1 before Architecture
you can “Start” writing the Project Planning section for Chapter 1.
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Let’s look at this relationship using the BEST Management Books example:
Start-To-Start
Start BEST
Management
Books Project
SCHOOL OF
Selection section
CONSTRUCTION
ENGINEERING
Project Appraisal
You can “Start” writing the Project Selection section for Chapter 1 as soon as you Milan
11th March 2016
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Finish
FF
Editing Chapter 3
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Books Project
Architecture
Project Appraisal
You cannot “Finish” the project, Finish BEST Management Book Project, until
Milan
11th March 2016
Project Activities
Using the relationships we have just described, the BEST Management Books
project activities and the logical relationships among them is diagrammed
below. This is formally known as a Network Diagram.
Start BEST
Finish BEST
Management Book
Management Book
Project
Project
Writing Project FS Writing Project Planning FS
Organization Section for Section for Chapter 1 Editing Chapter 1 FF
SS FS
Chapter 1
FS
Publishing Project
Writing Project Management Book
Selection Section for
FS
Chapter 1
SCHOOL OF
FS
FS ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Writing Auditing Section FS Writing Administrative FS
Closeout Section for ENGINEERING
for Chapter 3 Editing Chapter 3
Chapter 3
Master of Science in
Architecture
With the relationships defined, we now need to establish the duration for each Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling - Step 4. Establish the THE COURSE
Establishing the duration of each project activity involves determining the work
periods needed to complete each identified activity. Work periods can be
– hours
– days
– weeks
SCHOOL OF
– months, etc.. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Regardless of the exact work period chosen, the period must be consistent for all Master of Science in
Architecture
activities in the schedule. The project manager and team member(s) must Project Appraisal
decide which work period is right for the project.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
formula is CONSTRUCTION
(P + 4M + O) / 6 Master of Science in
Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Methods for Determining Activity Duration: an THE COURSE
Example
For the activity “Editing Chapter 1,” the following estimates are determined:
– (O) Optimistic estimate = 6 days
– (P) Pessimistic estimate = 18 days
– (M) Most Likely = 9 days
Legend
SCHOOL OF
ARCHITECTURE, URBAN
Time Estimates PLANNING AND
CONSTRUCTION
• Optimistic (O) ENGINEERING
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling - Step 4. Establish the THE COURSE
Master of Science in
Architecture
Project Appraisal
The work period is weeks (wks). Remember the selected work period must be Milan
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
So far in this module, we have covered four of the five steps related to project
scheduling:
The final step in this process is to determine the project duration (start and ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
completion dates) and the start and finish dates for each individual activity. ENGINEERING
Take a closer look at this step on the following page. Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Usually the project duration and activity start and completion dates are mapped
in a typical scheduling software application. The activities are placed in the
software tool, and the relationships are identified. The software calculates the
dates.
To better understand how the software calculates the dates, we will take a look
at the process known as Forward and Backward Pass.
The Forward Pass determines the early The Backward Pass determines the late
start (ES) and the early finish (EF) of each start (LS) and late finish (LF) of each
activity. activity.
Together, these processes give the total project duration, including the start and SCHOOL OF
ARCHITECTURE, URBAN
finish dates for each activity. Additionally, the process will determine the PLANNING AND
CONSTRUCTION
• critical path, which tells you the activities that cannot slip without increasing ENGINEERING
Master of Science in
the total duration of the project or moving the project completion date, and Architecture
• float, which tells you how much certain activities can slip without impacting Project Appraisal
We will look at critical path and float later in the module. 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
To start this process, let’s look at the Forward Pass.
The Forward Pass calculates the earliest date that each activity can start and
finish according to the logical sequence of work and the duration of each
activity. The Forward Pass yields the project duration.
appropriate dates. SS
Writing Project
Organization Section for
Chapter 1
FS
SCHOOL OF
Writing Project
Chart Selection Section for
ARCHITECTURE, URBAN
PLANNING AND
Chapter 1 CONSTRUCTION
WBS Activity Duration ES EF LS LF
ENGINEERING
FS Writing Budget and Cost
Section for Chapter 2 Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
To begin the Forward Pass process, determine a project start date. Looking at
the BEST project, we will use January 1 as the project start date.
Start BEST
The first activity that appears in the Network Diagram Management Book
Project
is “Start BEST Management Books project.” SS
Writing Project
Organization Section for
Chapter 1
Accordingly, the information appears in the FS
Writing Project
corresponding chart. Selection Section for
Chapter 1
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
The early start (ES) is 1/1 since this is the First activity and the start date for the Master of Science in
Architecture
project is 1/1. The early finish (EF) for this activity is also 1/1 since it is a Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Using the Network Diagram, the next activity is “Writing Project Selection section
of Chapter 1.” This activity is start to start (SS) with the previous activity, thus
its early start date is 1/1 (see chart). The early finish is determine by the
duration of the activity itself. This activity has a duration of 8 weeks, which
translates to a early finish date of 2/25.
Start BEST
Management Book
Project
Writing Project
SS Organization Section for
Chapter 1
FS
Writing Project
Selection Section for
Chapter 1
SCHOOL OF
FS Writing Budget and Cost
ARCHITECTURE, URBAN
WBS Activity Duration ES EF LS LF Section for Chapter 2
PLANNING AND
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 CONSTRUCTION
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The next activity is “Writing the Project Organizational section of Chapter 1.” It is
finish to start (FS) with the previous activity. With the FS relationship in mind,
what is the early start date for this activity?
Start BEST
Management Book
Because you must finish writing the Project Project
Writing Project
Selection section before you start writing the SS Organization Section for
Chapter 1
FS
Project Organizational section, the early start Writing Project
date for the current activity is 2/26. The early Selection Section for
Chapter 1
finish is once again calculated by using the FS Writing Budget and Cost
Section for Chapter 2
duration of the activity, giving you a early
SCHOOL OF
completion of 5/6. ARCHITECTURE, URBAN
PLANNING AND
WBS Activity Duration ES EF LS LF CONSTRUCTION
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 ENGINEERING
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 Master of Science in
Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The next activity is “Writing the Project Budget and Cost section of Chapter 2.” It
is finish to start (FS). Can you determine the activity that must finish, before
this activity can start?
Start BEST
It is finish to start (FS) with Writing the Project Selection Management Book
Project
Writing Project
section: because you must finish writing the project SS Organization Section for
Chapter 1
FS
selection section before you start writing the project
Writing Project
budget and cost section (same as Writing Project Selection Section for
Chapter 1
Selection section), the early start date is also 2/26. The FS Writing Budget and Cost
Section for Chapter 2
early finish is once again calculated by using the duration
SCHOOL OF
of the activity, giving you an early completion of 4/29. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
WBS Activity Duration ES EF LS LF ENGINEERING
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 Master of Science in
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 Architecture
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
Project Appraisal
This process is used to determine each activity’s ES and EF. On the page next is
Milan
11th March 2016
Duration
By looking at the chart below, can you determine the project duration, start and
completion dates?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 SCHOOL OF
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 ARCHITECTURE, URBAN
PLANNING AND
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 CONSTRUCTION
ENGINEERING
Master of Science in
Project Duration: 41 weeks or 205 days. Architecture
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
With the Forward Pass complete, let’s look at the Backward Pass. The Backward
Pass calculates the latest date that each activity can start and finish in order
to meet the project end date.
Again, using the BEST Management Books example, let’s now address the
Backward Pass. The chart below contains the Forward Pass information.
Unlike the Forward
Pass, which started 1.1
WBS Activity
Start Development of Project Management Book
Duration
0 wks
ES
1/1
EF
1/1
LS LF
with the first activity, 1.1.1.1.1 Writing Project Selection section for Chapter 1
1.1.1.1.2 Writing Project Organization section for Chapter 1
8 wks
10 wks
1/1
2/26
2/25
5/6
the Backward Pass 1.1.1.2.1 Writing Budget and Cost section for Chapter 2
1.1.1.1.3 Writing Project Planning section for Chapter 1
9 wks
9 wks
2/26
5/7
4/29
7/8
will start at the 1.1.1.2.2 Writing Scheduling section for Chapter 2
1.1.1.2.3 Writing Project Controls section for Chapter 2
5 wks
7 wks
4/30
6/4
6/3
7/22 SCHOOL OF
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The process works the same as the Forward Pass but in the opposite direction.
Once again using the Network Diagram, the last activity is “Finish the
Development of the Project Management Book” (see below). The late finish
(LF) and the late start (LS) will be the same as the early start (ES) and early
finish (EF) since it is the final activity. Finish BEST
Management Book
Project
Editing Chapter 1 FF
FS
Publishing Project
WBS Activity Duration ES EF LS LF Management Book
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 FS
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
Editing Chapter 2 FS
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 FS
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 SCHOOL OF
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 Editing Chapter 3 ARCHITECTURE, URBAN
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 PLANNING AND
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 CONSTRUCTION
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 ENGINEERING
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 Master of Science in
Architecture
The next activity is “Publishing Project Management Book,” and it is finish to Project Appraisal
finish (FF) with the “Finish Development” activity. Thus, the LF and LS are
Milan
also the same as the ES and EF. 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Looking at the Network Diagram on the previous page, you see that there are
three activities that have a relationship with Publishing Project Management
Book:
– Editing Chapter 1
– Editing Chapter 2
– Editing Chapter 3
Also note that the relationships are all finish to start (FS). With this in mind, what
is the LF and LS for each activity?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 SCHOOL OF
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 ARCHITECTURE, URBAN
PLANNING AND
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
CONSTRUCTION
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 ENGINEERING
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
Master of Science in
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 Architecture
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 Project Appraisal
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Because “Publishing
WBS Activity Duration ES EF LS LF
Project Management 1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
Book” has an LS of 1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
9/17 and all three 1.1.1.1.3
1.1.1.2.2
Writing Project Planning section for Chapter 1
Writing Scheduling section for Chapter 2
9 wks
5 wks
5/7
4/30
7/8
6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
activities are finish to 1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
start (FS), the late 1.1.2.1
1.1.2.2
Editing Chapter 1
Editing Chapter 2
8 wks
8 wks
7/9
7/23
9/2
9/16
7/23
7/23
9/16
9/16
1.1.2.3
finish (LF) for each 1.1.3
Editing Chapter 3
Publishing Project Management Book
4 wks
4 wks
8/13
9/17
9/9
10/14
8/20
9/17
9/16
10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
must be 9/16.
SCHOOL OF
How do you determine the late start (LS) for each activity? Subtract the duration ARCHITECTURE, URBAN
PLANNING AND
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Here is the completed list of all the activities, including the early starts (ES), early
finishes (FS), late starts (LS) and late finishes (LF). What can you determine
about the project from this data?
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 Master of Science in
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
From the Forward Pass information, we know the Project duration, Project Start,
and Completion date.
Project Appraisal
Now it is time to use the information from the Backward Pass to determine the
Milan
project’s critical path. 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The Critical Path tells you the activities that cannot slip a day without increasing
the total duration of the project or moving the project completion date. The
critical path is the longest path of logically related activities through the
network which cannot slip without impacting the total project duration.
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12
SCHOOL OF
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 ARCHITECTURE, URBAN
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 PLANNING AND
CONSTRUCTION
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 ENGINEERING
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
Master of Science in
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
Architecture
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Let’s look at calculating the critical path on the following page.
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The Critical Path is calculated as follows:
• If the result is a number greater the zero, then the activity is not on the critical
SCHOOL OF
path and has float. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
To better understand critical path, look at the chart. Note a column was added
to calculate float and determine the critical path. From reviewing the chart,
what activities are on the critical path?
Project Appraisal
All the activities with zero float are on the Critical Path!!!! But what exactly does
this mean? Take a look on the next page. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
The Critical Path tells management the activities that are critical or essential in
completing the project on time. It is also important for management to look at
activities with minor float because any delays in those activities could cause
them to be on the critical path.
WBS Activity Duration ES EF LS LF Float
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1 0
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25 0
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20 14
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29 0
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22 14
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3 0
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22 0
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12 7
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 7
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 14 SCHOOL OF
ARCHITECTURE, URBAN
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 0 PLANNING AND
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16 7 CONSTRUCTION
1.1.3 ENGINEERING
Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 0
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 0 Master of Science in
Architecture
Lets look at the table above in a PERT chart format. Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Below is the PERT chart layout of the project. The boxes in red indicate those
activities on the critical path. The blue boxes are for all other activities.
Notice the information in the boxes, it shows the activity name, duration, early
start and finish, and late start and finish. See the legend below for details.
Writing
Writing Project
Project
Organization
Organization section
section Duration
for Chapter 1
Start Development Early Start 10wks
10 wks Early Finish
of Project
Management Book 2/26/2002 5/6/2002
2/26/2002 5/6/2002
0 days 3/12/2002 5/20/2002
3/12/2002 5/20/2002
1/1/2002 1/1/2002 Late Start Late Finish
1/1/2002 1/1/2002
Milan
Editing Chapter 2
8 wks 11th March 2016
7/23/2002 9/16/2002
7/23/2002 9/16/2002
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Project Scheduling – Step 5. Determine Project THE COURSE
Duration
Now that we have covered the entire process with the BEST Management
project in detail, lets apply it to the ACME House Building project from Module
2. It reveals the following information:
Activity Duration ES EF LS LF Float
Start House Construction 0 days 1/15 1/15 1/15 1/15 0
Pour foundation 6 days 1/15 1/22 1/15 1/22 0
Install Patio 6 days 1/23 1/30 3/21 3/28 57
Pour stairway 2 days 1/31 2/1 3/29 4/1 59
Concrete Complete 0 days 2/1 2/1 4/1 4/1 59
Frame exterior walls 13 days 1/23 2/8 1/23 2/8 0
Frame interior walls 7 days 2/11 2/19 2/11 2/19 0
Project Duration: 55 Install roofing trusses 4 days 2/20 2/25 2/20 2/25 0
Framing Complete 0 days 2/25 2/25 2/26 2/26 1
days Install waterlines 7 days 2/20 2/28 2/25 3/5 5
Install gas lines 3 days 2/22 2/26 3/1 3/5 7
Install B/K fixtures 5 days 3/1 3/7 3/26 4/1 25
Plumbing Complete 0 days 3/7 3/7 4/1 4/1 25
Project Start:
SCHOOL OF
Install wiring 5 days 2/20 2/26 2/27 3/5 7 ARCHITECTURE, URBAN
Install outlets/switches 4 days 3/22 3/26 3/22 3/26 0 PLANNING AND
At this point, we have examined the first two bullets; the next step in our process
SCHOOL OF
is to reflect the schedule baseline. Take a moment now to familiarize yourself ARCHITECTURE, URBAN
PLANNING AND
with this step on the next page. CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Schedule Baselining
Baseline is the original approved plan that consists of both schedule and cost.
The baseline is used as the foundation for measuring project performance. In
an Earned Value Management System (EVMS), the schedule and cost
baseline are essential.
The Schedule Baseline is the standard that all schedule performance will be
measured against. It should be approved by the project manager and other
appropriate individuals. Once the project manager approved the project start,
logic, relationships and project duration, the schedule is then “baselined” to
measure schedule performance.
SCHOOL OF
ARCHITECTURE, URBAN
The final step, integrating with the cost baseline, will be discussed in detail in the PLANNING AND
CONSTRUCTION
next module. For now, take a look at the types of scheduling formats on the ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Schedule Formats
In reporting and displaying your schedule, there are multiple formats that have
and can be used. We focus on three major formats:
SCHOOL OF
ARCHITECTURE, URBAN
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review
Take some time now to review the major items:
Master of Science in
– Determine project duration (start and completion dates) Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review
• The Critical Path tells you the activities that can not slip a day without
increasing the total duration of the project or moving the project completion
date. It is the longest path of logically related activities through the network
which cannot slip without impacting the total project duration, termed zero
float.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Summary
At this point we have examined the basics for developing a project schedule
and schedule baseline. The Schedule Baseline is one of the two most
important items in an earned value management system (EVMS). In the
next module you will examine the other important item in an earned value
management system (EVMS): the cost baseline.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics for developing a project schedule.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Module 4: Budgeting
• Welcome to Module 4. The objective of this module is to introduce Prepared by:
you to Budgeting Concepts and Definitions. Booz Allen
Hamilton
• Cost/Schedule Baselines
• WBS Levels: Control Accounts, Work Packages, Planning Packages
• Elements of an Earned Value Contract Baseline
SCHOOL OF
ARCHITECTURE, URBAN
Project Appraisal
• Review
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Let’s review the steps required to establish a cost and schedule baseline ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
ACME Project X
1.0
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Design Procurement Construction Project Mgmt CONSTRUCTION
1.1 1.2 1.3 1.4 ENGINEERING
Master of Science in
Architecture
Prelim Design Title I Design Final Design
Project Appraisal
1.1.1 1.1.2 1.1.3
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
1.0
Prepared by:
Booz Allen
Design Procurement Construction Project Mgmt Hamilton
1.1 1.2 1.3 1.4
Master of Science in
1.1.1.3 Review Preliminary Design Architecture
Project Appraisal
1.0
Prepared by:
Booz Allen
Design Procurement Construction Project Mgmt Hamilton
1.1 1.2 1.3 1.4
1.0
Prepared by:
Booz Allen
Design Procurement Construction Project Mgmt Hamilton
1.1 1.2 1.3 1.4
• Let’s discuss these three key elements in more detail, starting with
Control Accounts, on the next page. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Control Accounts
• A Control Account is an assigned WBS Level used to monitor the cost Prepared by:
and schedule performance of a significant element of the work. Booz Allen
Hamilton
Control Accounts are also referred to as Cost Accounts. These terms
are interchangeable, however, we will use the term Control Accounts.
• A Control Account is a major management control point for:
• Cost Summarization
• Variance Analysis and Reporting
• Responsibility Assignment
• Scope Description
• Corrective Action Planning SCHOOL OF
ARCHITECTURE, URBAN
Statement of Work associated with their assigned Control Account(s). Master of Science in
• The illustration on the following page depicts the ACME House Architecture
Project Appraisal
Project WBS down to the Control Account Level.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Control Accounts
• For the ACME House project, it was determined that the performance
Prepared by:
measurements for the project will be taken at Level 3 (see graphic Booz Allen
below). The project manager and the stakeholders must determine the Hamilton
Level 3 Concrete
1.1.1
Framing
1.1.2
Plumbing
1.1.3
Electrical
1.1.4
Interior
1.1.5
Roofing
1.1.6
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Work Packages
• The detail that builds up to the Control Account Level is contained in
Prepared by:
Work Packages and Planning Packages. Take a moment now to review Booz Allen
Work Packages. Hamilton
Master of Science in
span of time (normally, but not limited to, six months or less). Project Appraisal
Milan
11th March 2016
Planning Packages
• Planning Packages reflect a future segment of work within a Control
Prepared by:
Account that is not yet broken down into detailed work packages. A Booz Allen
planning package has a firm budget, estimated start and complete dates, Hamilton
requirements are defined, and at a minimum, are scheduled to start at ARCHITECTURE, URBAN
PLANNING AND
House Building
Level 2 Project
1.1
Control Account Level
Concrete Framing Plumbing Electrical Interior Roofing
Level 3 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Frame Exterior Install Water CONSTRUCTION
Pour Foundation Install Wiring Install Drywall Install Felt
Walls Lines
1.1.1.1 1.1.4.1 1.1.5.1 1.1.6.1 ENGINEERING
1.1.2.1 1.1.3.1
Review
• At this point, you should have a comfortable understanding of the
following: Prepared by:
Booz Allen
Hamilton
• The budgeting process establishes a means for documenting and
tracking the cost goals for all contractually authorized work.
Master of Science in
• If you are unsure about any of these concepts, please go back and review, Architecture
otherwise let’s move on to discuss the key elements used to develop, Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Performance Measurement Baseline (PMB) Management Reserve (MR) Architecture
Project Appraisal
Distributed Budgets Undistributed Budget (UB)
Work Packages
prof. Barrese
Planning Packages
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
Distributed Budgets Undistributed Budget (UB) ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Control Accounts ENGINEERING
Master of Science in
Work Packages Architecture
Project Appraisal
Planning Packages
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
Distributed Budgets Undistributed Budget (UB) ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Control Accounts ENGINEERING
Master of Science in
Work Packages Architecture
Project Appraisal
Planning Packages
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Profit/Fee
Prepared by:
Profit/Fee is the estimated profit or fee realized by executing the contract or Booz Allen
Hamilton
project. Profit/Fee is not part of the Contract Budget Base (CBB), as
defined on the next page.
Planning Packages
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Work Packages
prof. Barrese
Planning Packages prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Management Reserve.
Work Packages
prof. Barrese
Planning Packages prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Management Reserve
• Once the CBB is established, the Program Manager establishes a Management
Reserve (MR) prior to distributing budgets to the performing organizations.Prepared by:
Booz Allen
The purpose of MR is to have a budget for the Program Manager to allocateHamilton
for unforeseen problems.
SCHOOL OF
Contract Budget Base (CBB) ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Performance Measurement Baseline (PMB) Management Reserve (MR) ENGINEERING
Master of Science in
Distributed Budgets Undistributed Budget (UB) Architecture
Project Appraisal
Control Accounts
Milan
Work Packages 11th March 2016
Planning Packages
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Distributed Budgets
• Distributed Budgets reflect the contractually authorized efforts allocated to
Prepared by:
the WBS elements. Booz Allen
Hamilton
SCHOOL OF
Contract Budget Base (CBB) ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Performance Measurement Baseline (PMB) Management Reserve (MR) ENGINEERING
Master of Science in
Distributed Budgets Undistributed Budget (UB) Architecture
Project Appraisal
Control Accounts
Milan
Work Packages 11th March 2016
Planning Packages
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Undistributed Budget
• Undistributed budget (UB) applies to contractually authorized efforts not Prepared
yet by:
allocated to WBS elements. The UB consists of a budget for authorized Booz Allen
changes for which there has not been adequate time to plan the change at Hamilton
the
control account level. Undistributed budget is an element of the
Performance Measurement Baseline, but it is not time-phased.
• Every effort should be taken to distribute budgets in a timely manner and to
minimize undistributed budgets. Undistributed budgets are controlled by the
Program Manager, and all changes must be documented using an
Undistributed Budget Log. Total Contract Price
Work Packages
prof. Barrese
Planning Packages prof. Pandolfi
KEY FACTS ABOUT
Proposed Costs and the Contract Budget Base THE COURSE
Relationship
• To better understand the key elements of the Contract Budget Base, lets
walk through the Proposal Development, Negotiations, and Contract Prepared by:
Booz Allen
Award Phases. To begin, first ensure you understand the relationship Hamilton
between the proposed cost and the established Contract Budget Base.
• A proposed cost estimate and a Contract Budget Base are developed in SCHOOL OF
ARCHITECTURE, URBAN
the same manner. The resources required to complete each defined PLANNING AND
CONSTRUCTION
element of work are developed in terms of hours. These hours are ENGINEERING
converted to Labor Dollars by applying Direct Labor Rates and Indirect Master of Science in
Architecture
Burdens (Direct and Indirect Costs are discussed on the following page). Project Appraisal
Direct Costs – Costs applicable to, and identified specifically with, the
program contract Statement of Work.
Examples of Direct Costs: Labor, Travel, Material, Subcontractor
Charges
Master of Science in
Example of Indirect Costs: Fringe Benefits, Overhead, Material Handling, Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
– Assign Labor, Material, ODC, and Subcontractor Resources to the Master of Science in
Architecture
– Apply Burdens and Fee to derive the Total Cost and Price. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
House Building
Project
1.1
Master of Science in
Architecture
Install Roofing Install B/K
Stairway Install Fixtures Install Painting Install Vents
Trusses Fixtures
1.1.1.3 1.1.4.3 1.1.5.3 1.1.6.3 Project Appraisal
1.1.2.3 1.1.3.3
Milan
11th March 2016
• This insures that we develop cost for only approved project scope. prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• This process is used to price each WBS element. On the next page is
the completed price for the ACME House.
WBS 1.1.1.2 Install Patio SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
RES CODE Hours Rate/Hour Prime Overhead G&A COM Fee Total Price CONSTRUCTION
Carpenter 40 $ 25.00 $ 1,000 $ 1,666 $ 422 $ 2 $ 618 $ 3,707 ENGINEERING
Drywall 40 $ 15.00 $ 600 $ 1,000 $ 253 $ 1 $ 371 $ 2,224
ELEC 4 $ 40.00 $ 160 $ 267 $ 67 $ 0 $ 99 $ 593 Master of Science in
Architecture
ENGE 20 $ 30.36 $ 607 $ 825 $ 226 $ 1 $ 332 $ 1,991
Material 0 $ 2,000 $ 109 $ - $ 1 $ 422 $ 2,531 Project Appraisal
Other 0 $ 500 $ 27 $ - $ 0 $ - $ 527
Total 104 $ 4,867 $ 3,894 $ 968 $ 5 $ 1,840 $ 11,574
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
House Building
Project 1.1
$231,894
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$59,094 $57,905 $25,018 $61,826 $20,447 $7,605
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1 CONSTRUCTION
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$3,259 ENGINEERING
$28,452 $22,026 $8,257 $24,642 $9,312
Master of Science in
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles Architecture
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$11,574 $14,699 $8,339 $12,353 $2,500 $3,259 Project Appraisal
Install Roofing Install B/K Install Fixtures Install Painting Install Vents Milan
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3 11th March 2016
$19,067
$21,180 $8,421 $24,831 $8,635 $1,086
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$47,200 $57,905 $25,018 $61,826 $20,447 $7,605
SCHOOL OF
ARCHITECTURE, URBAN
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall PLANNING AND
Install Felt 1.1.6.1 CONSTRUCTION
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$3,259 ENGINEERING
$20,523 $22,026 $8,257 $24,642 $9,312
Master of Science in
Architecture
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
Project Appraisal
$10,781 $14,699 $8,339 $12,353 $2,500 $3,259
Milan
Install Roofing Install B/K Install Fixtures Install Painting Install Vents 11th March 2016
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$15,895
$21,180 $8,421 $24,831 $8,635 $1,086
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The Negotiated Total Cost, without Profit/Fee, for the ACME House equals
$183,852. This will be the basis for developing the Contract Budget
Baseline (CBB). Again, remember that this amount is exclusive of Fee.
Milan
Control Accounts 11th March 2016
Work Packages
prof. Barrese
Planning Packages prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• All of the PMB will be distributed, therefore Distributed Budgets will equal
$165,467, and Undistributed Budget will remain zero.
Total Contract Price
$219,999
SCHOOL OF
Total Contract Cost Profit/Fee ARCHITECTURE, URBAN
$183,852 $36,147 PLANNING AND
CONSTRUCTION
Contract Budget Base (CBB) ENGINEERING
$183,852
Master of Science in
Architecture
Performance Measurement Baseline (PMB) Management Reserve (MR)
$165,467 $18,385
Project Appraisal
Work Packages
• For example, remember the ACME House Proposal? Control Account 1.1.1
Concrete, had a proposed Total Price of $59,094, however, based on final
contract negotiations, the negotiated price was $47,200. The negotiated cost,
without Profit Fee was $39,424.
• The following table summarizes the proposed vs. negotiated price for the
Concrete effort. Remember, in establishing target budgets, Profit/Fee is not
included.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Control Account 1.1.1 Concrete CONSTRUCTION
ENGINEERING
Master of Science in
Total Dollars Profit/Fee Total Price Architecture
Milan
Negotiated $39,424 $7,776 $47,200 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• The target budget released to the Control Account Manager for 1.1.1
Concrete is $35,482 ($39,424 – $3,942 = $35,482).
Master of Science in
MR (10%) -$3,942 Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• In the case of the Concrete Control Account, the Control Account Manager
has accepted the budget of $35,482.
• Once the budgets have been allocated to the Control Accounts, the Control
Account budgets are further subdivided into work packages and planning SCHOOL OF
ARCHITECTURE, URBAN
packages.
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$35,482 $43,432 $18,765 $46,373 $15,711 $5,704
SCHOOL OF
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1 ARCHITECTURE, URBAN
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$2,445 PLANNING AND
$15,394 $16,521 $6,194 $18,483 $6,984
CONSTRUCTION
ENGINEERING
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2 Master of Science in
$8,166 $11,025 $6,255 $9,265 $2,250 $2,445 Architecture
Project Appraisal
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$11,922
$15,887 $6,317 $18,625 $6,477 $815 Milan
11th March 2016
• The development of detail planning for the control account and ultimate
approval of the budget, schedule, and associated Work Authorization
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Document (WAD) is accomplished through an iterative process. CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
• A Work Authorization Document (WAD) authorizes and documents the Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• The sum of the work packages and planning package budgets are equal to the
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
total budget assigned to the CAM on the work authorization form. The total
CONSTRUCTION
ENGINEERING
budget for the control account is time-phased in hours and dollars. Master of Science in
Architecture
• Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Baseline Documentation
• Summaries of schedules and budgets at the work package level are integrated
Prepared by:
using a Control Account Plan (CAP). A CAP is a low level detail plan Booz Allen
prepared by the CAM showing time phased planning of tasks and their Hamilton
associated budget for a Control Account. The CAP also provides brief work
package and milestone descriptions that enable the CAM to clarify and
differentiate the unique content of each work package.
•
• The CAM and Program Control develop the cost and schedule database by
using the control account planning documentation and other data. A series
of checks and balances are performed to ensure the data is consistent. Upon
completion of the baseline development, reports displaying the planning data
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
as it appears in the system are reviewed and verified for accuracy. CONSTRUCTION
ENGINEERING
• Master of Science in
Architecture
• The baselining process is complete when all Work Authorization Document Project Appraisal
(WADs) have been issued and accepted, and all CAPS have been developed Milan
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
Master of Science in
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall Architecture
Install Felt 1.1.6.1
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$2,445
$15,394 $16,521 $6,194 $18,483 $6,984
Project Appraisal
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$8,166 $11,025 $6,255 $9,265 $2,250 $2,445 Milan
11th March 2016
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$11,922
$15,887 $6,317 $18,625 $6,477 $815
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Work Packages (WP) contain a discrete segment of work below the Control
Account level and provide detailed planning for accomplishing the work
within a Control Account.
ACME Housing Corporation
Level 1 1
Planning Packages
House Building
account.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Management Reserve: The amount of the contract budget withheld by Master of Science in
Architecture
Milan
11th March 2016
• If you have a firm grasp of the concepts covered in these first four modules,
feel free to progress to the next module. Otherwise, review the modules to
ensure you have a solid understanding of the basics.
SCHOOL OF
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• In Module 4 we discussed the development of the project budget and the cost
ENGINEERING
Master of Science in
baseline Architecture
Project Appraisal
Now lets discuss the basic Earned Value concepts and methods. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
EVMS Criteria
Before we start discussing the Earned Value concepts and methods, let’s look at
an overview of the criteria needed for EVMS. There are numerous EVMS
guidelines that have been developed in both the government and commercial
industry.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
EVMS Criteria
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
EVMS Criteria
The criteria are divided into five categories:
Industry Standard
• Organization Earned Valueof
Department
• Planning and Budgeting Department Standard
Industry
Management
Defense of
Earned
Defense Valueof
Department
• Accounting System
5000.2-R
Department of
Management
5000.2-R
Defense
• Analysis and Management Reporting Defense
System
5000.2-R
5000.2-R
• Revisions and Data Maintenance
SCHOOL OF
On the followings pages we provide a summary level review of the criteria. As ARCHITECTURE, URBAN
PLANNING AND
mentioned earlier there are 32 criteria but for the purpose of a summary CONSTRUCTION
ENGINEERING
review, the criteria were combined. For a complete list of the criteria and the
Master of Science in
guideline go to the frequently asked questions (FAQ) section or reference Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
• Ensure that the Contract Budget Base (CBB) is reconciled with the Total Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Establish process for reporting Material, Other Direct Costs, and Subcontractor SCHOOL OF
Master of Science in
• Provide full accounting of all material purchased for the project Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
EVMS Criteria – Analysis and Management THE COURSE
Reports
The fourth category is Analysis and Management Industry Standard Earned Value
Reports. Within Analysis and Management Management System
Project Appraisal
• Develop revised estimates (EACs, LREs) based on performance to date and Milan
11th March 2016
estimates of future performance
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
EVMS Criteria – Revisions and Data THE COURSE
Maintenance
The final category is Revisions and Data Industry Standard Earned Value
Management System
Maintenance. Within Revisions and Data
• Organization
Maintenance the criteria require the following: • Planning & Budgeting
• Accounting
• Analysis & Management Reporting
• Establish Change Management System • Revisions & Data Maintenance
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
EVMS Criteria – Revisions and Data THE COURSE
Maintenance
In modules 1 through 4, we discussed the criteria in the first 3 categories:
Organization, Planning and Budgeting, and Accounting.
In this and succeeding modules we will cover the criteria in the final two
categories: Analysis and Management Reporting, and Revisions and Data
Maintenance.
•
ARCHITECTURE, URBAN
Organization PLANNING AND
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Understanding how the three components work in earned value is explained on ENGINEERING
Master of Science in
the following pages. Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
weeks, months,etc.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Planned Value (PV) consists of a 5 step THE COURSE
process…
PV, also known as Budget Cost of Work Scheduled (BCWS), can be defined as:
4. Budget Scope: develop cost (budget) for all approved scope (Performance
Measurement Baseline) SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
5. Baseline: Snap-shot in time, frozen. What performance measurement will be
Master of Science in
based on. Architecture
Project Appraisal
Now let’s look at an example of Planned Value on the next page. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The Cumulative PV is the total for the elapsed months: January – March. The
cumulative PV is $9,000.
The Current PV is the budget for the current month, March, and equals $3,000.
This example uses dollars as units of measure, but note that you can use any
Milan
unit of measurement: hours, days, dollars, etc. 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
–
ARCHITECTURE, URBAN
The Project BAC must always equal the Project Total PV. If they are not equal, PLANNING AND
your earned value calculations and analysis will be inaccurate. CONSTRUCTION
ENGINEERING
Master of Science in
Let’s examine BAC using our previous example. Take a look on the next page.
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Yes, BAC = $15,000. And, in keeping with the previous points about BAC, the PLANNING AND
CONSTRUCTION
project BAC equals the Project Total PV. The Earned Value calculations are ENGINEERING
Master of Science in
correct. Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Now let’s turn our attention on the following pages to the second, Actual
Charges.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The Cumulative AC is the total for the elapsed months: January – March. The Master of Science in
Architecture
cumulative AC is $3,200.
Project Appraisal
Milan
The Current AC is the actual cost for the current month, March, and equals 11th March 2016
Now let’s turn our attention on the following pages to the last of the three
components, Actual Charges.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
In other words, EV tells you, in physical terms, what the project has
accomplished. As with PV and AC, EV can be presented in a Cumulative
and Current fashion. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
the budget for the activities budget for the activities Master of Science in
Architecture
accomplished to date. accomplished in a given period. Project Appraisal
Milan
11th March 2016
The Cumulative EV is the sum of the budget for the activities accomplished to date: Master of Science in
Architecture
January – March. The cumulative EV is therefore $3,100. Project Appraisal
The Current EV is the sum of the budget for the activities accomplished in the current Milan
11th March 2016
Master of Science in
Project Appraisal
Cum AC = $3,200 Current AC = $1,200
Cum EV = $3,100 Current EV = $1,000 Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review
At this point, you should have a solid understanding of the three key earned
value components. Let’s review them now.
• Actual Cost (AC) is determined by the actual cost incurred on the project
• Earned Value (EV) tells you, in physical terms, what the project
accomplished. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Master of Science in
Actual Charges (expenditures) Architecture
Project Appraisal
Reported accomplishments or
“Earned Value” Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
•
PLANNING AND
Milestone Weights CONSTRUCTION
ENGINEERING
• Percent Complete
Milan
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
0/100 - Nothing is earned when activity starts but 100% of budget is earned
when completed
SCHOOL OF
50/50 - 50% is earned when activity starts and the balance is earned on ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
completion ENGINEERING
Master of Science in
Architecture
25/75 - 25% is earned when activity starts and the balance is earned on Project Appraisal
completion
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Advantages: Works well for short term work packages, and requires minimal
effort to status.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Weighting
The next method of calculating EV that Earned Value Methods
we will discuss is Milestone Weights.
The Milestone Weighting method assigns Fixed Formula
budget value to each milestone. Not until Milestone Weights
full completion of each milestone is the • Milestone Weights with % Complete
budget earned. Milestone Weighting is • Units Complete
used as a method for work packages with • Percent Complete
• Level of Effort
long term durations and ideally should have
milestones each month or accounting period.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Weighting
Below is an example of the Milestone Weighting method. For the purposes of
this and future examples, we will assume that the Building Design is the
Control Account Level and the activities are at the Work Package level.
Below are the activities and milestones in the Control Account for completing
a building design. The dates for each milestone are given, along with the
value for each milestone upon completion.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Let’s use this example and see how Milestone Weighting is applied.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Weighting
For this example, assume that all activities begin and complete as scheduled.
With this in mind, can you determined the earned value as of January 31th?
As you can see by the schedule the project has started (1/7). The “Start
PLANNING AND
CONSTRUCTION
Inspection milestone” has been completed, but no value appears for that
ENGINEERING
milestone. The “Site Inspection Complete” milestone has also been Master of Science in
Architecture
completed, and its value is 100. There are no more milestones completed Project Appraisal
through January, so our Current EV is 100. Because it is the first month for
the control account, the Cumulative EV is also 100. Now lets look at what Milan
11th March 2016
Weighting
As you can see by looking at the schedule below, there are no milestones
scheduled for February (remember we assumed all activities will start and
complete as scheduled), but we have started the Phase 1 Design. What are
the Current EV and Cumulative EV as of February 28th?
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
The Current EV is 0. Remember we can only take “earned” if milestone is Master of Science in
February, we have earned no value under the milestone weighting approach. Project Appraisal
The Cumulative EV is 100, which includes the 100 from January and the 0 Milan
Weighting
Two milestones are scheduled for March. What is are Current EV and
Cumulative EV as of March 31th?
The Current EV is 350. Completion of Phase 1 Design (150) and Phase 2 Design
PLANNING AND
CONSTRUCTION
(200). ENGINEERING
Master of Science in
The Cumulative EV is 450, which includes the Site Inspection Complete fromArchitecture
January (100), February (0), plus the current March EV (350). Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Weighting
The advantages and disadvantages of Milestone Weighting are:
Disadvantages: Does not allow partial credit for in-process work, and requires
detailed milestone planning.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Take a look on the following pages at how using Milestone Weighting with Master of Science in
Project Appraisal
previously using simple Milestone Weighting.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
Time Now
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Time Now
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Time Now
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
Time Now
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Milestone THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
PV EV AC Master of Science in
Units 10 12 12 Architecture
Units ($) $10,000 $12,000 $12,000
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Advantages: An objective and easy way of determining the earned value for an
activity.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Subjective THE COURSE
Percent Complete
The fifth method of EV calculation that we will Earned Value Methods
review is Subjective Percent Complete. The
Subjective Percent Complete method applies Fixed Formula
a percent complete to a budget value to Milestone Weights
Milestone Weights with % Complete
determine what is earned. The percent
Units Complete
complete value is determined by the Control
Percent Complete
Account Manager or other designated • Level of Effort
individuals. The percent complete is applied
to the Budget at Completion (BAC) for a
given activity to determine the current and
cumulative EV. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
Take a look on the next page at how Subjective Percent Complete is used. CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Subjective THE COURSE
Percent Complete
To use the Subjective Percent Complete method, the value is placed on the work
activity, not the milestone (as in the Milestone Weighting method). Using the
Building Design Project from earlier, this becomes more clear.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Subjective THE COURSE
Percent Complete
Looking at the Site Inspection activity in the schedule below, the start date is
January 7th with a scheduled completion date of January 30th. Let’s status the
activity as of January 15th.
To determine the percent complete for January 15th, the control account
manager (CAM) must use an educated guess to determine the percent
complete of the activity. The CAM must maintain the logic for assessing each
activity’s percent complete.
In this example, the CAM decides that the activity is 45% complete as of January
15th. Given this, the EV for Site Inspection as of January 15th is 45. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value (EV) Methods – Subjective THE COURSE
Percent Complete
The advantages and disadvantages of Subjective Percent Complete are:
SCHOOL OF
Note: Milestones do not apply to this method. Labor and non-labor must be ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
identified in separate work packages if this method is applied. This method ENGINEERING
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Advantages: This EVM does not require statusing, and is appropriate for
sustaining tasks like Program Management.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review
At this point, you should have a firm grasp of the EV methods of calculation.
• Fixed Formula
• Milestone Weights
• Milestone Weights with % Complete
• Units Complete
• Percent Complete
• Level of Effort SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Now that we are finished reviewing the EV methods, let’s take a look at our Master of Science in
ACME House Building project using the concepts discussed in this module. Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Status as of 1/31
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Status as of 1/31
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Status as of 1/31
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Activity EV Method
Pour Foundation Fixed Formula: 0/100
Install Patio Subjective % Complete
Frame Exterior Walls Subjective % Complete
Pour Stairway Fixed Formula: 25/75 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Now that we understand what activities need statusing and what method of EV Architecture
will be used for each activity, it is time to status the project activities. Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The first activity is Pour Foundation. This activity was scheduled to start on 1/15
and finish on 1/22 (see schedule below). It’s actually started on 1/15 and
finished on 1/22 (see status report below). Thus this activity was on
schedule and is 100% complete. What is its Planned Value (PV), Earned
Value (EV), and Actual Cost (AC)?
Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
Control Account Activity Start Finish Complete Completion
Concrete Pour Foundation 1/15 1/22 100%
Install Patio 1/23 1/30 100%
Pour Stairway 1/31 25% 2/1
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The Earned Value (EV) is what was actually done as of 1/31. The activity is
100% complete and its EV is $15,394 (100% of PV). Remember you cannot
earn more then was planned. Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
The Actual Cost (AC) is what was Control Account
Concrete
Activity
Pour Foundation
Start
1/15
Finish
1/22
Complete
100%
Completion
obtained from the accounting Framing Frame Exterior Walls 1/23 40% 2/8
SCHOOL OF
ARCHITECTURE, URBAN
system. The AC is $15,850. Plumbing No activities scheduled PLANNING AND
CONSTRUCTION
Electrical No activities scheduled ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Let’s take a look at the activity, Frame Exterior Walls first. Check out this activity
on the next page.
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The activity is schedule from 1/23 to 2/8, which is 17 calendar days or 13 working
days. We will use calendar days in our example calculation. Remembering
the assumption that all costs are spent uniformly across each activity, we
need to determine what the PV is as of 1/31. Let’s take a look at the
calculations on the next page. Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
Control Account Activity Start Finish Complete Completion
Concrete Pour Foundation 1/15 1/22 100%
Install Patio 1/23 1/30 100%
Pour Stairway 1/31 25% 2/1
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
In summary:
Monthly Status Meeting
January 31th, 2002
PV = $8,748 Actual Actual % Forecast
Control Account Activity Start Finish Complete Completion
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
AC = $3,100 (from accounting system) Framing Frame Exterior Walls 1/23 40% 2/8
SCHOOL OF
ARCHITECTURE, URBAN
Plumbing No activities scheduled PLANNING AND
CONSTRUCTION
Electrical No activities scheduled
ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
These questions and others will be answered in the next module, Module 6 – Milan
Metrics, Performance Measures and Forecasting where the value of EVM 11th March 2016
The Estimate at Completion (EAC) is the actual cost to date plus an objective
estimate of costs for remaining authorized work. The objective in preparing
an EAC is to provide an accurate projection of cost at the completion of the
project. There are multiple ways and varying degrees of detail to calculate
EAC, and they will be covered in a future module. The most common is:
The Estimate to Complete (ETC) is the cost of completing the authorized SCHOOL OF
remaining work. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review of Module 5
Take some time to review the major items of this module
• There are three key components to earned value: Planned Value, Earned
Value and Actual Cost.
– PV (BCWS) is the physical work scheduled or “what you plan to do”.
– EV (BCWP) is the quantification of the “worth” of the work done to date or
“what you physically accomplished”.
– AC (ACWP) is the cost incurred for executing work on a project or “what
you have spent”.
SCHOOL OF
ARCHITECTURE, URBAN
• There are numerous EV methods used for measuring progress. PLANNING AND
CONSTRUCTION
– Milestone Weights
Master of Science in
Architecture
Master of Science in
• Define Estimate at Completion (EAC) and Latest Revised Estimate (LRE) Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• There are three key components to earned value: Planned Value, Earned
Value and Actual Cost.
– PV is the physical work scheduled or “what you plan to do”.
– EV is the quantification of the “worth” of the work done to date or “what
you physically accomplished”.
– AC is the cost incurred for executing work on a project or “what you
have spent”.
The next step is to stand back and monitor the progress against the PerformanceMaster of Science in
Architecture
Measurement Baseline (PMB). Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
To answer this question, consider the ACME House Building project. You have
two major stakeholders on this project, the Buyer and the Builder. Do you
think they both measure success on the project identically or do you believe
their definition of project success may be different? Let’s take a look on the
next page. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Buyer Builder
Project Appraisal
Can you see how different parties or individuals can have conflicting views of Milan
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The Cost Management focuses on the cost performance of the project. It looks
at the relationships between the Earned Value (EV) and the Actual Cost (AC).
The Schedule Management focuses on the schedule performance of the project. SCHOOL OF
It looks at the relationships between the Earned Value (EV) and the Planned ARCHITECTURE, URBAN
PLANNING AND
Value (PV). CONSTRUCTION
ENGINEERING
Master of Science in
Now let’s look at these relationships in more detail on the following pages.
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Earned Value: Metrics and Performance THE COURSE
Measurements
Earned value performance measurements look at the project cost and
schedule performance by analyzing the cost and schedule variance along
with cost and schedule efficiency. The formulas used are as follows:
Variance Analyses
Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)
Performance Indices
SCHOOL OF
Cost Performance Index = Earned Value (EV)/Actual Cost (AC) ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Schedule Performance Index = Earned Value (EV)/Planned Value (PV)
Master of Science in
Architecture
Project Appraisal
Let's take a look at the Variance Analyses on the next page. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Variances
The Cost Variance (CV) is the difference between the earned value of work
performed and the actual cost. CV tells you the earned value of work
performed for each dollar’s worth of work scheduled.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250
Cost
Stairway $5,961 $2,981 $3,100
Project Total $38,269 $33,149 $32,400
CV = EV – AC
Cost SCHOOL OF
CV = $33,149 - $ 32,400 Variance
ARCHITECTURE, URBAN
PLANNING AND
CV = $749 CONSTRUCTION
ENGINEERING
Master of Science in
Project Appraisal
on the next page.
1/31 Milan
Time 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
To date the project has a Cost Variance of $749 or 2.3% Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Variances
The Schedule Variance (SV) is the difference between the earned value of
work performed and the work scheduled. SV tells you the value of work
performed less value of work scheduled.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250 Cost
Stairway $5,961 $2,981 $3,100
Project Total $38,269 $33,149 $32,400
Schedule
Variance
SV = EV – PV
SV = $33,149 - $38,269 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
SV = -$5,120 CONSTRUCTION
ENGINEERING
Master of Science in
Project Appraisal
on the next page.
1/31 Milan
Time 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Cost
Using the graph to right, you can see that
on 1/31 the EV line (green) is below the
PV line (blue). This means that what was Schedule
Variance
earned to date is less then what was
planned to be accomplished. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
•
ENGINEERING
indicate the cost needed to regain schedule Master of Science in
Architecture
Project Appraisal
Let's look at another Schedule Variance calculation on the next page. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
To date the project has a Schedule Variance of -$5,120 or -13.4% Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Variances: Review
You should have a solid understanding of the cost and schedule variance
calculations and what they mean. Let's review them now.
SCHOOL OF
as of 1/31 PV EV AC SV CV ARCHITECTURE, URBAN
PLANNING AND
Foundation $15,394 $15,394 $15,850 0 -456 CONSTRUCTION
ENGINEERING
Patio $8,166 $8,166 $7,200 0 966
Master of Science in
Exterior Walls $8,748 $6,608 $6,250 -2,140 358 Architecture
Performance Indices
The Cost Performance Index (CPI) is a measure of Cost Efficiency. The CPI
measures the value of work performed against the actual cost.
$900 $1200
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Cost Performance Index THE COURSE
example
Using the ACME Home Building project information, let's calculate the Cost
Performance Index (CPI) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250 Cost
Stairway $5,961 $2,981 $3,100
Project Total $38,269 $33,149 $32,400
CPI = EV/AC
CPI= $33,149/$32,400 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CPI = 1.02 CONSTRUCTION
ENGINEERING
Master of Science in
Project Appraisal
on the next page.
1/31
Milan
Time 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Cost Performance Index THE COURSE
example
A Cost Performance Index (CPI) of 1.02 tells you that your actual costs are less
then what was budgeted.
You are getting $1.02 worth of work for every $1.00 spent.
1.2
1.15
1.1
1.05
CPI1.02
1
SCHOOL OF
0.95 CPI 1.02 ARCHITECTURE, URBAN
PLANNING AND
0.9 CONSTRUCTION
ENGINEERING
0.85
Master of Science in
Architecture
0.8
Project Appraisal
Now let's look at some causes of favorable and unfavorable cost performance. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Cost Performance Index THE COURSE
example
Potential Causes of Unfavorable (-) Potential Causes of Favorable (+)
Cost Performance Cost Performance
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Performance Indices
The Schedule Performance Index (SPI) is a measure of Schedule Efficiency.
The SPI measures the value of work performed against the work scheduled.
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Schedule Performance THE COURSE
Index example
Using the ACME Home Building project information, let's calculate the
Schedule Performance Index (SPI) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250 Cost
Stairway $5,961 $2,981 $3,100
Project Total $38,269 $33,149 $32,400
SPI = EV/PV
SPI = $33,149/$38,269 SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
SPI = .87 CONSTRUCTION
ENGINEERING
Master of Science in
Project Appraisal
on the next page.
1/31
Time Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Schedule Performance THE COURSE
Index example
A Schedule Performance Index (SPI) of .87 tells you that you are behind
schedule. It can be defined in two ways:
1.2
1.15
1.1
1.05
CPI 1.02 SCHOOL OF
1 ARCHITECTURE, URBAN
PLANNING AND
0.95 CPI 1.02 CONSTRUCTION
ENGINEERING
0.9
Master of Science in
0.85
SPI 0.87 Architecture
Project Appraisal
0.8
Now let's look at some causes of favorable and unfavorable schedule Milan
11th March 2016
performance on the following page.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Performance Indices: Schedule Performance THE COURSE
Index example
Potential Causes of Unfavorable (-) Potential Causes of Favorable (+)
Schedule Performance Schedule Performance
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
The ACME Home Building Project is 13% behind schedule (SPI = .87) but is
ahead on cost by 2% (CPI = 1.02). In review of the activities, Installation of the
Stairway and Framing the Exterior Walls are the activity causing the project to
be behind (SPI = .50 and .76) schedule. On the cost side, the Installation of
the Patio is costing less then budgeted (CV =$966) and is the main reason for SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
the project underrunning its budget. CONSTRUCTION
ENGINEERING
Master of Science in
What is the standard reporting variance threshold for a project? Find out on the Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Reporting Variances
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
So far we have only looked at how to analyze what has happened on a project
(CV,SV, CPI, SPI). Take some time to review the formulas below.
Tells you what percentage cost varies Tells you what percentage schedule varies from
from what has been earned to date. what has been planned to date.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Cost Performance Index (CPI) = EV/AC Schedule Performance Index (SPI) = EV/PV
Master of Science in
Architecture
If result is less than 1.0, cost is If result is less than 1.0, project is
Project Appraisal
GREATER than budgeted “BEHIND” schedule
If the result greater than 1.0, cost is If the result greater than 1.0, project is Milan
LESS than budgeted “AHEAD of schedule 11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Estimate at Completion
Now it is time to learn how to analyze the future or what is expected to happen
on a project given the progress measurements reported to date. Anticipating
future progress requires determining when the project will be completed and
how much it will cost to complete it.
To complete our analysis, we will look at the Estimate at Completion (EAC) and
the Budget at Completion (BAC).
The Estimate at Completion (EAC), which was defined in Module 5, is the actual
cost to date plus an objective estimate of costs for remaining authorized work.
The objective in preparing an EAC is to provide an accurate projection of cost
at the completion of the project.
SCHOOL OF
ARCHITECTURE, URBAN
The Budget at Completion (BAC) is the sum of all budgets allocated to a projectPLANNING AND
CONSTRUCTION
scope. The Project BAC must always equal the Project Total PV. If they are ENGINEERING
not equal, your earned value calculations and analysis will be inaccurate. Master of Science in
Architecture
Project Appraisal
The chart on the following page lists the parameters of the BAC and EAC along
with the other EVM items we have covered. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Estimate at Completion
Item Questions
Planned Value (PV) How much work should be done?
Earned Value (EV) How much work was done?
Actual Cost (AC) How much did the work cost?
Budget at Completion (BAC) What is the total job budgeted to cost?
Estimate at Completion (EAC) What do we expect the total job to cost?
Another term you may hear is Latest Revised Estimate (LRE). The LRE is equal
to the EAC.
SCHOOL OF
ARCHITECTURE, URBAN
Estimate At Completion = Latest Revised Estimate PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
For the remainder of the Modules, we will refer to Estimate at Completion as Project Appraisal
“EAC”.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Estimate at Completion
The EAC is the best estimate of the total cost at the completion of the project.
The EAC is a periodic evaluation of the project status, usually on a monthly
basis or when a significant change happens to the project.
EACs are developed with varying degrees of detail and supporting documents. A
comprehensive EAC is usually prepared annually or if there are any major
changes in the project. The EAC should be reviewed on a monthly basis by
the Control Account Manager (CAM) or those responsible. The EAC is
developed for projects as well as Control Accounts and Work Packages.
There are multiple ways to develop an EAC. The technique selected is based
upon the dollar value of the project, the risk, accounting system available and
SCHOOL OF
the accuracy of the estimates. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Let's take a look on the following pages at the most frequently used EAC Master of Science in
formulas. Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Now let's look use the EAC formula for our ACME Home Building project. Take a Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
When using this formula to calculate EAC, you can also include expert opinion,
project and industry trends and other forms of objective analysis.
ACTUALS ETC EAC
Activity January February March April Total
1.1.1.1 Pour foundation $15,850 $15,850
1.1.1.2 Install Patio $7,200 $7,200
1.1.1.3 Pour stairway $3,100 $8,942 $12,042
1.1.2.1 Frame exterior walls $6,250 $9,913 $16,163
1.1.2.2 Frame interior walls $11,025 $11,025
1.1.2.3 Install roofing trusse $15,887 $15,887 SCHOOL OF
1.1.3.1 Install waterlines $6,194 $6,194 ARCHITECTURE, URBAN
PLANNING AND
1.1.3.2 Install gas lines $6,255 $6,255
CONSTRUCTION
1.1.3.3 Install B/K fixtures $6,317 $6,317 ENGINEERING
1.1.4.1 Install wiring $18,483 $18,483
1.1.4.2 Install outlets/switches $9,265 $9,265 Master of Science in
1.1.4.3 Install fixtures $13,969 $4,656 $18,625 Architecture
As mentioned earlier, EAC is the best estimate of the total cost at the completion
of the project. It is also used to determine the Variance at Completion (VAC)
for the project. The VAC is calculated as follows:
Now let's determine the VAC for our project as shown on the next page. Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
In other words, the project is now forecasted to overrun by $102 using this form
of EAC. Remember, this is only one method of forecasting the performance of
the project. Several other methods can be used. Let’s consider those on the
following pages.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
This calculation uses the Actual cost, Earned value and Budget at Completion for
the project.
This formula is the easiest to use, but it assumes that the “burn-rate” will be the
same for the remainder of the project.
Let's use our ACME Home Building project to calculate the EAC using this
formula. Take a look on the next page. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
as of 1/31 PV EV AC BAC
VAC = BAC – EAC Foundation $15,394 $15,394 $15,850 $15,394
VAC = $165,467 - $162,158 Patio $8,166 $8,166 $7,200 $8,166
Frame exterior Walls $8,748 $6,608 $6,250 $16,521
VAC = 3,309 Stairway $5,961 $2,981 $3,100 $11,922
Frame interior walls $0 $0 $0 $11,025
Install roofing trusse $0 $0 $0 $15,887
Using this EAC calculation, our project Install waterlines $0 $0 $0 $6,194
is projected to underrun by $3,309. Install gas lines $0 $0 $0 $6,255
SCHOOL OF
Install B/K fixtures $0 $0 $0 $6,317
ARCHITECTURE, URBAN
PLANNING AND
Install wiring $0 $0 $0 $18,483
CONSTRUCTION
Now let's look at the next EAC formula Install outlets/switches $0 $0 $0 $9,265
ENGINEERING
EAC = BAC/CPI
This calculation uses the Budget at Completion (BAC) and the Cost Performance
(CPI) Index to calculate EAC.
This formula is also easy to use and assumes that the “burn-rate” remains
constant for the remainder of the project.
This formula is derived from the previous formula and thus should result in the
same EAC figure. Note that with this formula you need additional information SCHOOL OF
ARCHITECTURE, URBAN
than the previous formula. PLANNING AND
CONSTRUCTION
ENGINEERING
Let's use our ACME Home Building project and calculate the EAC using this Master of Science in
Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
This formula assumes that the work not yet begun will be completed as planned.
Let's use our ACME Home Building project and calculate the EAC using this
formula. Take a look on the next page.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Now let's look on the next page at our final EAC formula. Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
This calculation uses the Actual Cost (AC) Budget at Completion (BAC), Earned
Value (EV) and the Cost Performance (CPI) Index to calculate EAC.
Let's use our ACME Home Building project and calculate the EAC using this
formula. Check it out on the next page.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
If you need to review these techniques, please pay close attention to the Project Appraisal
assumptions of each.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review Module 6
At this point, you have covered all of the content in Module 6. Take some time
now to review the major items:
– Cost Performance Index (CPI) is a measure of Cost Efficiency. The CPI Project Appraisal
measures the value of work performed against the actual cost.
– Schedule Performance Index (SPI) is a measure of Schedule Efficiency. The Milan
11th March 2016
SPI measures the value of work performed against the work scheduled.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
• There are multiple methods for determining EAC. Each project needs to be
evaluated to determine which EAC formula best fits the project’s size and
complexity.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
At this point we have examined the basic metrics and performance measures
used in EVMS. In the next module you will examine the concepts of Integrated
Baseline Review (IBR), Rebaselining, and Change Control.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics metrics and performance measures
used in EVMS.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Module 7: Integrated Baseline Review and THE COURSE
Change Control
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• In Module 3 we discussed the development of the project schedule and the ENGINEERING
Master of Science in
schedule baseline Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
– assess the accuracy of the related resources (budgets) and schedules ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Remember the discussion on PMB from Module 4? Let’s quickly review. The
Performance Measurement Baseline (PMB) is the time-phased budget plan
against which contract performance is measured.
Now that we’ve reviewed the PMB and defined the purpose of an IBR, let’s
SCHOOL OF
discuss when an IBR is conducted. ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
When a major event occurs within the life of a program such as a Critical Design
Review (CDR), and a significant shift in the content and/or time-phasing of
the PMB occurs, the Program Manager may conduct a review of the
associated resources and schedules affected by the changes.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
The IBR is intended to be a continuous part of the Program Management CONSTRUCTION
ENGINEERING
Project Appraisal
Now let’s review the specific IBR objectives, on the next page.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Ensure that the technical content of Control Account, Work Packages, and
Planning Packages is consistent with the Contract Work Breakdown Structure
(CWBS) and the Contract Statement of Work (SOW)
and time-phasing
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
• Understand the earned value methods for measuring accomplishment and to Project Appraisal
technical accomplishment
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• Verify that cost, schedule, and technical systems are integrated SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
• Establish a forum through which the government program manager and the
ENGINEERING
Master of Science in
Milan
11th March 2016
Now that we’ve reviewed the IBR objectives, let’s review some of the key prof. Barrese
documents required at an IBR. Check these out on the next page. prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Integrated Baseline Review (IBR) THE COURSE
Responsibilities
Now that we’ve discussed the key objectives for conducting an IBR and
reviewed the IBR Checklist, let’s review the responsibilities.
The Program Office Technical Team assesses the PMB and identifies risk areas.
The Control Account Managers are responsible for the integrity and SCHOOL OF
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• The IBR is conducted within six months of the award of a new contract or as
required due to a major change to an existing contract.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
• The responsibility for conducting the IBR lies with the Program Manager and
CONSTRUCTION
ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Now that we’ve discussed the Integrated Baseline Review Process, let’s
discuss what happens when there are changes made to the PMB and the SCHOOL OF
ARCHITECTURE, URBAN
Change Control Process used to track baseline changes. Take some time to
PLANNING AND
CONSTRUCTION
ENGINEERING
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
The Change Control Process is used to establish, analyze, communicate, and Project Appraisal
prof. Barrese
Now let’s discuss the specific objectives of a Change Control Process. prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
would change previously reported amounts for actual costs, earned value, orARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
budgets. Adjustments should be made only for correction of errors, routine ENGINEERING
changes, or to improve the baseline integrity and accuracy of performance Project Appraisal
prof. Barrese
• Prevent revisions to the program budget except for authorized changes prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
We will examine each of these in more detail on the following pages, but first,
Project Appraisal
take a look on the next page at the types of documentation that must be
completed for these changes.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
the PMB within 60 days of cost of money, is entered in UB using PLANNING AND
CONSTRUCTION
organizations. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
The distribution of UB must be identified in the Contract Budget Base (CBB) ARCHITECTURE, URBAN
PLANNING AND
and Undistributed Budget (UB) Log for each authorized contract CONSTRUCTION
ENGINEERING
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Base (CBB) and Management Reserve (MR) Log. This is a requirement as Master of Science in
Architecture
part of a Change Control Process. Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Re-planning should be accomplished within the constraints of the previously Master of Science in
Architecture
established Control Account schedule and budget.
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
cost, schedule or technical issues have caused the original plan to become ARCHITECTURE, URBAN
PLANNING AND
unrealistic. The contract target cost remains unchanged. The ground rules CONSTRUCTION
ENGINEERING
for re-baselining the remaining effort are submitted to the procuring agency Master of Science in
Architecture
prior to implementation, and all baseline changes must be documented and
Project Appraisal
tracked.
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
The procuring agency must be consulted prior to reprogramming. The change Architecture
to the budget and schedule are recorded as though the contractual scope Project Appraisal
had been changed. Changes to the baseline budget are fully documented Milan
11th March 2016
and traceable per the change control process.
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review Module 7
At this point, you have covered all of the content in Module 7. Take some time
now to review the major items:
• Reconcile current budgets to prior budgets in terms of changes to the Project Appraisal
authorized work and internal re-planning in the detail needed by management Milan
• Prevent revisions to the program budget except for authorized changes prof. Barrese
prof. Pandolfi
• Document changes to the Performance Measurement Baseline
KEY FACTS ABOUT
THE COURSE
Summary of Module 7
At this point we have examined the basic metrics and performance measures
used in EVMS. In the next module you will examine EVMS Reporting.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics metrics and performance measures
used in EVMS.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
• In Module 4 we discussed the development of the project budget and the cost
ENGINEERING
Master of Science in
baseline Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Now let’s look at the Government reporting requirements for earned value. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Generally, all five formats are applied to a contract requiring EVMS. However, SCHOOL OF
ARCHITECTURE, URBAN
the customer may not require all the reports and may delete one or more. PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Most customers will require at least the CPR Format 1 (WBS) and Format 5 Architecture
Project Appraisal
(Variance Analysis Report).
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
All reported changes to the project baseline, management reserve (MR) and
contingency should be traceable through the formal Earned Value
Management System (EVMS) and CPR reports.
On the following pages, we will look at examples of the five CPR reports using
the ACME House Building Project.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
First let’s quickly review the projects current status that will be used in the
example reports.
ACME Home Building Project
Project Start date: January 15th as of 1/31 PV EV AC SV CV SPI CPI
Foundation $15,394 $15,394 $15,850 0 -456 1.00 0.97
Patio $8,166 $8,166 $7,200 0 966 1.00 1.13
Status Date: January 31th Exterior Walls $8,748 $6,608 $6,250 -2,140 358 0.76 1.06
Stairway $5,961 $2,981 $3,100 -2,980 -119 0.50 0.96
Project Total $38,269 $33,149 $32,400 -5,120 749 0.87 1.02
EAC calculations used for the ACTUALS ETC EAC
Activity January February March April Total
example will be based on the 1.1.1.1 Pour foundation $15,850 $15,850
assumptions discussed on 1.1.1.2 Install Patio
1.1.1.3 Pour stairway
$7,200
$3,100 $8,942
$7,200
$12,042
Page 35 and 36 of Module 6. 1.1.2.1 Frame exterior walls
1.1.2.2 Frame interior walls
$6,250 $9,913
$11,025
SCHOOL OF
$16,163
ARCHITECTURE, URBAN
$11,025
See the charts to the right for 1.1.2.3 Install roofing trusse
1.1.3.1 Install waterlines
$15,887
$6,194
PLANNING AND
$15,887
CONSTRUCTION
$6,194
an overview. 1.1.3.2 Install gas lines
1.1.3.3 Install B/K fixtures
$6,255
$6,317
ENGINEERING
$6,255
$6,317
1.1.4.1 Install wiring $18,483 Master of Science in
$18,483
Architecture
1.1.4.2 Install outlets/switches $9,265 $9,265
This report also contains data about budget, price, Management Reserve
(MR), Undistributed Budget (UB), and MEAC cases.
A copy of the CPR Format 1 for the ACME Home Building project is on the
following page. Please review the entire report but pay close attention to
the lower section (highlighted red) of the report. This is the Performance
data section that contains the current and cumulative cost and schedule SCHOOL OF
ARCHITECTURE, URBAN
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
1.1.1 Concrete 9,670 8,757 26,150 -912 -17,393 9,670 8,757 26,150 -912 -17,393 11,485 28,873 -17,388
SCHOOL OF
1.1.2 Framing 7,089 5,355 6,250 -1,734 -895 7,089 5,355 6,250 -1,734 -895 27,147 28,041 -893
ARCHITECTURE, URBAN
PLANNING AND
1.1.3 Plumbing 0 0 0 0 0 0 0 0 0 0 5,704 5,704 0
CONSTRUCTION
1.1.4 Electrial 0 0 0 0 0 0 0 0 0 0 14,070 14,070 ENGINEERING
0
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 2 – THE COURSE
Organizational Categories
The Cost Performance Report (CPR) Format 2 includes current period,
cumulative, and at complete values for each Organization (Performing or
Responsible), It also contains header data showing quantity, targets,
ceilings, and MEAC cases.
This report also contains data about budget, price, Management Reserve
(MR), Undistributed Budget (UB), and MEAC cases.
The reporting details in CPR Format 2 are the same as on the CPR Format 1
accept that it is structured by organization.
SCHOOL OF
ARCHITECTURE, URBAN
A copy of the CPR Format 2 for the ACME Home Building project is on PLANNING AND
CONSTRUCTION
following page. Please review the entire report but pay close attention to
ENGINEERING
the lower section (highlighted red) of the report. This is the Performance
Master of Science in
Architecture
data section that contains the current and cumulative cost and schedule Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 2 – THE COURSE
Organizational Categories
COST PERFORMANCE REPORT Form Approved
FORMAT 2 - ORGANIZATIONAL CATEGORIES OMB No. 0704-0188
1. CONTRACTOR 2. CONTRACT 3. PROGRAM 4. REPORT PERIOD
a. NAME: ACME Construction a. NAME: ACME Housing a. NAME: ACME Housing a. FROM: 01-JAN-02
b. LOCATION: Denver, CO b. NUMBER: ACME - 1000 b. PHASE (X one) b. TO: 31-JAN-02
c. TYPE: FFP [ ] RDT&E [X] PRODUCTION
d. SHARE RATIO:
5. PERFORMANCE DATA CURRENT PERIOD CUMULATIVE TO DATE AT COMPLETION
BUDGETED COST ACTUAL VARIANCE BUDGETED COST ACTUAL VARIANCE
ITEM COST COST
WORK WORK WORK WORK WORK WORK
SCHED PERF PERF SCHED COST SCHED PERF PERF SCHED COST BUDGET EST VAR
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14)
Construction
Construction 12,116 9,560 10,300 -2,556 -740 12,116 9,560 10,300 -2,556 -740 17,226 17,965 -739
Management
Project Management 7,503 5,668 6,250 -1,835 -582 7,503 5,668 6,250 -1,835 -582 19,475 20,057 -582
SubCont
Subcontractor Mgmt 13,203 13,203 15,850 0 -2,647 13,203 13,203 15,850 0 -2,647 36,272 38,919 -2,647
SCHOOL OF
SUBTOTAL 32,821 28,430 32,400 -4,391 -3,970 32,821 28,430 32,400 -4,391 -3,970 72,973 76,941 ARCHITECTURE,
-3,969 URBAN
b. COST OF MONEY 19 17 0 -3 17 19 17 0 -3 17 82 65 PLANNING
17 AND
c. GEN & ADMIN 5,429 4,702 0 -726 4,702 5,429 4,702 0 -726 4,702 23,237 18,537 CONSTRUCTION
4,700
d. UNDISTRIBUTED BUDGET 0 0 ENGINEERING
0
e. SUBTOTAL (PM Baseline) 38,269 33,149 32,400 -5,120 749 38,269 33,149 32,400 -5,120 749 165,467 165,569 -102
f. MANAGEMENT RESERVE 18385 Master of Science in
g. TOTAL 38,269 33,149 32,400 -5,120 749 38,269 33,149 32,400 -5,120 749 183,852 Architecture
6. RECONCILIATION TO CONTRACT BUDGET BASE
a. VARIANCE ADJUSTMENT 0 0 Project Appraisal
b. TOTAL CONTR VARIANCE 0 0 0 0 0
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 3 – THE COURSE
Baseline
Cost Performance Report (CPR) Format 3 displays a forecast of monthly
changes to the Baseline, Management Reserve, and Undistributed Budget
for the entire project, and contains header data showing schedule dates for
the contract and the project.
COST PERFORMANCE REPORT Form Approved
FORMAT 3 - BASELINE DOLLARS IN THOUSANDS OMB No. 0704-0188
1. CONTRACTOR 2. CONTRACT 3. PROGRAM 4. REPORT PERIOD
a. NAME: ACME Construction a. NAME: ACME Housing a. NAME: ACME Housing a. FROM: 01-JAN-02
b. LOCATION: Denver, CO b. NUMBER: ACME - 1000 b. PHASE (X one) b. TO: 31-JAN-02
c. TYPE: FFP [ ] RDT&E [X] PRODUCTION
d. SHARE RATIO:
5. CONTRACT DATA
a. ORIGINAL NEGOTIATED COST b. NEGOTIATED CONTRACT
c. CURRENT NEGOTIATED d. ESTIMATED COST e. CONTRACT BUDGET f. TOTAL ALLOCATED g. DIFFERENCE
CHANGE COST (A + B) AUTH UNPRICED WORK BASE (C + D) BUDGET (E - F)
$0 $0 $0 $0 $0 $0 $0
h. CONTRACT START DATE i. DEFINITIZATION DATE j. PLANNED COMPL DATE k. CONT COMPLETION DATE l. EST COMPLETION DATE
01-JAN-01 31-DEC-01
6. PERFORMANCE DATA BUDGETED COST FOR WORK SCHEDULED (NON - CUMULATIVE)
BCWS BCWS SIX MONTH FORECAST
ITEM CUM FOR
TO REPORT +1 +2 +3 +4 +5 6+ UNDISTRIB TOTAL
DATE PERIOD FEB02 MAR02 APR02 MAY02 JUN02 JUL02 AUG02 SEP02 OCT02 NOV02 DEC02 BUDGET BUDGET
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
a. PM BASELINE
(BEGIN OF PERIOD) 165 0 0 0 0 0 0 0 0 0 0 0 0 0 165 SCHOOL OF
b. BASELINE CHANGES AUTH ARCHITECTURE, URBAN
DURING REPORT PERIOD
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
c. PM BASELINE
(END OF PERIOD) 38 73 49 5 0 0 0 0 0 0 0 0 0 165
7. MANAGEMENT RESERVE 18
8. TOTAL 184
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 4 – THE COURSE
Staffing
The Cost Performance Report (CPR) Format 4 displays a forecast of hours and
person-months by Organization (Performing/Responsible), and contains
header data showing schedule dates for the contract and the project. This
report also contains program variance thresholds for month, cumulative, and
at-complete percents and values.
COST PERFORMANCE REPORT Form Approved
FORMAT 4 - STAFFING OMB No. 0704-0188
1. CONTRACTOR 2. CONTRACT 3. PROGRAM 4. REPORT PERIOD
a. NAME: ACME Construction a. NAME: ACME Housing a. NAME: ACME Housing a. FROM: 01-JAN-02
b. LOCATION: Denver, CO b. NUMBER: ACME - 1000 b. PHASE (X one) b. TO: 31-JAN-02
c. TYPE: FFP [ ] RDT&E [X] PRODUCTION
d. SHARE RATIO:
5. PERFORMANCE DATA FORECAST (NON - CUMULATIVE)
ACTUAL
END OF SIX MONTH FORECAST BY MONTH
ORGANIZATIONAL ACTUAL CURRENT
CATEGORY CURRENT PERIOD +1 +2 +3 +4 +5 +6 AT
PERIOD (CUM) FEB02 MAR02 APR02 MAY02 JUN02 JUL02 AUG02 SEP02 OCT02 NOV02 DEC02 COMPL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
Construction
Hours 0 0 121 0 0 0 0 0 0 0 0 0 0 343
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 2
SCHOOL OF
Project Management ARCHITECTURE, URBAN
Hours 0 0 134 0 0 0 0 0 0 0 0 0 0 134 PLANNING AND
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 1 CONSTRUCTION
Subcontractor Mgmt
ENGINEERING
Hours 0 0 138 0 0 0 0 0 0 0 0 0 0 305
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 2
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
6. TOTAL DIRECT
Hours 0 0 393 0 0 0 0 0 0 0 0 0 0 781
Man Months 0 0 2 0 0 0 0 0 0 0 0 0 0 5 prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 5 – THE COURSE
The variance reporting thresholds are pre-determined prior to the start of the
program. Explanations and problem analysis reporting is only required for
those variances that breech the pre-set threshold(s). The report will
indicate those variances needing explanation.
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
Cost Performance Report (CPR) Format 5 – THE COURSE
TASK/PROJECT IMPACT:
Task/Project Impact: SCHOOL OF
Framing the exterior walls will be completed on schedule and no delay will occur to the project complete. This section is used to explain the impact toARCHITECTURE, URBAN
the Control Account and overall Project. PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
CORRECTIVE ACTION PLAN: Architecture
The current skill mix will be adjusted to complete this activity as scheduled. The ACME project
Corrective Action Plan:
management team is conducting a review of all future work to determine if resource availability will an issue. This section provides the recovery and risk Project Appraisal
mitigation plan.
Milan
Preparer: Dept: Initials: Date: 11th March 2016
This report includes cumulative and at complete summaries for each WBS
element, and contains header data showing contractor and contract
information, and MEAC calculations.
This report also contains data about contract price, budget, Management
Reserve (MR), Undistributed Budget (UB), and MEAC cases. SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
It is very similar to the CPR Format 1 except that the C/SSR has only CONSTRUCTION
ENGINEERING
A copy of the C/SSR for the ACME Home Building project in on the following Project Appraisal
page. Milan
11th March 2016
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
6. CONTRACT DATA
a. ORIGINAL CONTRACT TARGET COST b. NEGOTIATED CONTRACT CHANGES c. CURRENT TARGET COST (A + B) d. EST COST OF AUTH UNPR WORK
$0 $0 $0 $0
e. CONTRACT BUDGET BASE (C + D) f. MGMT ESTIMATE AT COMPLETION g. VARIANCE AT COMPLETE (E - F) h. OVER TARGET BASELINE DATE
$0 $0 $0 01-JAN-02
7. PERFORMANCE DATA CUMULATIVE TO DATE AT COMPLETION
BUDGETED COST ACTUAL VARIANCE
ITEM COST
WORK WORK WORK
SCHEDULED PERFORMED PERFORMED SCHEDULED COST BUDGET ESTIMATE VARIANCE
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1.1.1 Concrete 9,670 8,757 26,150 -912 -17,393 11,485 28,873 -17,388
1.1.2 Framing 7,089 5,355 6,250 -1,734 -895 27,147 28,041 -893
SCHOOL OF
ARCHITECTURE, URBAN
1.1.3 Plumbing 0 0 0 0 0 5,704 5,704 0
PLANNING AND
CONSTRUCTION
1.1.4 Electrical 0 0 0 0 0 14,070 14,070 0
ENGINEERING
Project Appraisal
OVERHEAD 16,062 14,317 0 -1,745 14,317 75,684 61,371 14,313
b. COST OF MONEY 19 17 0 -3 17 82 65 17
c. GEN & ADMIN 5,429 4,702 0 -726 4,702 23,237 18,537 4,700
d. UNDISTRIBUTED BUDGET 0 0 Milan0
e. SUBTOTAL (PM Baseline) 38,269 33,149 32,400 -5,120 749 165,467 165,569 11th
-102March 2016
f. MANAGEMENT RESERVE 18,385
g. TOTAL 38,269 33,149 32,400 -5,120 749 183,852
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
THE COURSE
Review Module 8
At this point, you have covered all of the content in Module 8. Take some time
now to review the major items:
Master of Science in
Project Appraisal
prof. Barrese
prof. Pandolfi
KEY FACTS ABOUT
If you have a firm grasp of the concepts covered in this module, along with all
provide modules, you have completed the EVMS tutorial. Otherwise, review
this or any other module to ensure you have a solid understanding of the
Earned Value Management.
SCHOOL OF
ARCHITECTURE, URBAN
PLANNING AND
CONSTRUCTION
ENGINEERING
Master of Science in
Architecture
Project Appraisal
Milan
11th March 2016
prof. Barrese
prof. Pandolfi