LOAD SUMMARY

PROJECT : NATIONAL PARKING COMPANTY (G+4+ROOF) OWNER : AREA: DUBAI AIRPORT TERMINAL - 01
PLANNED COMPLETION DATE : CONSULTANT : CAPITAL ENGINEERING CONSULTANCY LOCATION :
DESIGNATION : FED FROM : DEWA PLOT:
CIRCUIT RATING -AMPS FAULT PVC / CABLE SIZE ECC CONNECTED LOAD (kW) KWH METER
FEEDER SP TP ISO MCB / ACB DUTY XLPE 2/4 x 1C 2/3/4C SIZE 1C R-PHASE Y-PHASE B-PHASE TOTAL 1-F 3-F 3-F CT REMARKS
DB NO. MCCB DOT kA SWA/PVC MM2 MM2 MM2 (kW) (kW) (kW) KW (1) (2) (3) (4)
INCOMER 4P 1000A 55 XLPE DEWA 2x1C,150 1 400/5A
OUTGOING:-
60 KVAR
MDB-01 TP 350A 50 XLPE 4C,240 1C,120 56.03 55.13 53.72 164.87
MDB-02 TP 400A 50 XLPE 4C,300 1C,150 63.71 61.67 61.66 187.03
MDB-03 TP 400A 50 XLPE 4C,300 1C,150 78.26 75.03 69.96 223.24
EMDB TP 300A 50 XLPE 4C,185 1C,120 48.29 48.29 48.28 144.86

NOTE:- TOTAL CONNECTED LOAD PER PHASE 246.28 240.11 233.61 720.00

ENSURE THAT F/S DOES NOT ALLOW


REPLACEMENT OF FUSE RATED HIGHER THAN TCL : 720.00
THAT 'SPECIFIED FOR' THE CIRCUIT CABLES MAX. DEMAND AT 0.9 DIVERSITY
MAX. DEMAND 3 PHASE IN KW
648.00 PROVIDE CT-METER ABOVE MAX. DEMAND > 160A/80kW

(1) 60 A (2) 100 A (3) 125-160 A (4) 400 / 5A