GP 04-30
Applicability Group
Date Draft 1 August 2005
GP 04-30
BP GROUP
ENGINEERING TECHNICAL PRACTICES
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Foreword
Copyright 2005, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organization. None of the information
contained in this document shall be disclosed outside the recipient’s own organization
without the prior written permission of the Director of Engineering, BP Group, unless the
terms of such agreement or contract expressly allow.
Page 2 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Table of Contents
Page
Foreword.......................................................................................................................................... 2
1. Scope...................................................................................................................................... 5
2. Normative references.............................................................................................................. 5
3. Symbols and abbreviations.....................................................................................................5
4. General................................................................................................................................... 6
5. Loading................................................................................................................................... 7
5.1. General........................................................................................................................ 7
5.2. Normal loading............................................................................................................. 7
5.3. Blast loading................................................................................................................. 7
5.4. Traditional methods......................................................................................................7
6. Blast risk assessment.............................................................................................................. 8
7. Cost benefit analysis (CBA)....................................................................................................9
7.1. General........................................................................................................................ 9
7.2. Options for blast protections.........................................................................................9
7.3. Costs............................................................................................................................ 9
7.4. Benefits (loss reduction)...............................................................................................9
7.5. Cost benefit ratio........................................................................................................10
8. Load combinations................................................................................................................ 11
9. Analysis and design of structures..........................................................................................11
9.1. Analysis/design procedure..........................................................................................11
9.2. Dynamic analysis........................................................................................................11
9.3. CIA method................................................................................................................12
9.4. Equivalent static method............................................................................................12
9.5. Existing buildings.......................................................................................................12
10. Considerations for toxic and fire risks....................................................................................12
10.1. Toxic risk.................................................................................................................... 12
10.2. Fire Risk..................................................................................................................... 13
Annex A (Normative) Design of blast resistant buildings................................................................17
A1. General................................................................................................................................. 17
A2. Definition............................................................................................................................... 17
A3. Excluded materials................................................................................................................ 17
A4. Dynamic design methods......................................................................................................17
A5. Loads.................................................................................................................................... 17
A5.1 Normal building loads.................................................................................................17
A5.2 Positive blast pressures and durations.......................................................................17
A5.3 Negative blast loadings..............................................................................................18
Page 3 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
List of Tables
Table A1 - Positive blast pressures and durations for various structural elements..........................25
Table A2 - Average uniform loading for frames...............................................................................25
List of Figures
Page 4 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
1. Scope
This GP provides guidance for the design of land based buildings in areas subject to blast risks,
including how costs and benefits of protection may be established.
2. Normative references
The following normative documents contain requirements that, through reference in this text,
constitute requirements of this technical practice. For dated references, subsequent amendments to, or
revisions of, any of these publications do not apply. However, parties to agreements based on this
technical practice are encouraged to investigate the possibility of applying the most recent editions of
the normative documents indicated below. For undated references, the latest edition of the normative
document referred to applies.
BP
GP 44-70 Guidance on Practice for Plant Layout.
Guideline on the Use of Quantified Risk Assessment (QRA) and
Development of Risk Criteria, BP Corporate HSE Team. Draft Issued
October 1992.
Other
Structural Design for Dynamic Load Norris et al, McGraw-Hill ,1959.
Introductory to Structural Dynamics J.M. Biggs, McGraw-Hill, 1964.
Structures to Resist the Effects of Accidental Explosions Dept. of Army Manual, TM5-1300, 1969.
For the purpose of this GP, the following symbols and abbreviations apply:
Page 5 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
4. General
a. This GP may refer to certain local, national, or international regulations. The responsibility
to ensure compliance with legislation and any other statutory requirements lies with the
user. The user should adapt or supplement this GP to ensure compliance for specific
application.
b. This GP should be used by BP businesses that own or operate land based buildings in areas
subject to blast risks.
c. This GP may be applied to all types of buildings and is not restricted to control buildings.
d. The purpose of this GP is to provide guidance on:
1. Methods available to determine blast loading.
2. How costs and benefits of protecting buildings may be determined.
3. Methods available and principles of structural design for buildings exposed to blast
loading.
4. Upgrading of existing buildings.
e. Determination of blast loading and design of buildings subject to blast should be
performed by a team of experienced civil/structural engineers, process engineers, and
safety risk analysts.
f. This GP is based on a four step approach that should be applied to design of new buildings
and upgrading of existing buildings. The steps are:
1. Determine blast risk.
2. Identify options for design/location of building.
3. Evaluate options.
4. Perform detailed structural design.
g. Approach is intended to determine incremental risks due to blast loading and ensure such
risks are kept within acceptable bounds.
h. Risk presented by plant is the major consideration in specifying blast resistant
requirements for a new building at a given location (or assessing an existing building).
i. Blast risk assessment should be conducted to evaluate nature, magnitude, and potential
consequences of potential hazards.
j. Location/strengthening options
1. For new buildings, various location options should be considered, subject to
operational requirements.
2. Different strengths of building structures may be required for each location.
3. For existing buildings, strengthening options should be considered.
Page 6 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
5. Loading
5.1. General
Buildings and structures are subjected to a wide range of normal loadings. In
addition, a building may also be subjected to blast loading.
Page 7 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
a. Blast risk assessment studies shall examine plant containing hazardous inventories and use
methods, such as fault tree analysis, to identify series of events that could lead to release
and/or an explosion.
b. Each identified event should be assigned associated frequency of occurrence.
c. Overpressure versus distance relationship
1. Consequences of events identified in blast risk assessment should be modelled to
obtain overpressure versus distance relationship.
2. This relationship should be drawn as a set of contours on plot plan.
3. Contours may be either overpressure contours plotted for given frequency or
frequency contours for given level of overpressure.
4. Contours should be used to compare various options for locating new building.
d. Once building location is established, a further consequence model should be run to
determine duration of blast impulse. This should be similarly applied to an existing
building, the location of which is fixed.
e. Blast consequence modelling should be based on multi energy method developed by The
Netherlands Organisation for Applied Research (TNO).
Two methods available for blast consequence modelling are the TNT equivalence
method and the multi energy method. Based on recent research, it is considered that
the multi energy method is superior to the TNT method for modelling hydrocarbon
vapour cloud explosions (the TNO model is available within the BP CIRRUS suite
of consequence models).
Page 8 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
7.1. General
a. CBA shall be used to evaluate:
1. Different location options (with appropriate degree of blast protection) for new
buildings.
2. Proposed upgrading projects for existing buildings.
b. Individual national Health Safety and Environment (HSE) authorities or BP businesses
may have prescribed requirements/procedures for design of buildings or criteria for risk to
personnel. These requirements shall be taken into account and may override results of
CBA.
For guidance, see BP Corporate HSE Team Guidelines.
c. Costs and benefits of various options should be evaluated as described in 7.2 through 7.5.
7.3. Costs
Incremental cost (IC) beyond base case associated with protecting building against blast load
should be determined for each option considered. It may consist of a combination of the
following items:
a. New building
1. Structure designed to resist blast.
2. HVAC system protected against blast.
b. Existing building
1. Strengthened/modified to resist blast.
2. HVAC system modifications.
c. Building relocated to lower blast risk area - relocation costs for occupants/equipment.
d. Plant modification to reduce blast risk.
Typical structural schemes associated with varying levels of design blast load are
given in Figure 3. It is assumed blast loading duration is of the order of 50 to 100
ms (which is typical for a hydrocarbon vapour cloud explosion). Note that, for new
buildings, the strengthening is designed in, whereas existing buildings may need to
be modified.
Page 9 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
b. Incremental benefit (IB) beyond base case associated with protecting building should be
expressed in monetary terms by valuing reduced risk of losses that would be incurred if
building collapsed.
c. Such losses may consist of the following elements:
1. Personnel.
2. Business interruption.
3. Property damage.
4. Loss of reputation.
5. Loss of licence to operate.
d. Losses should be expressed in monetary units/year.
e. Guidance on value of these elements should be sought from relevant BP businesses.
f. Incremental benefit of providing new building or strengthening existing building to resist
blast can be expressed as:
B = L×Y×F
Where:
L = Loss per year as calculated above (e.g., 1+2+3+4+5)
Y = Design life of building/plant
F = Reduction of frequency of building collapse
Note: The blast risk assessment for a given plant will yield a range of frequencies
(F) and associated levels of overpressure. Y is a constant. The values of loss for
items 1, 2, and 3 (within L) should be estimated based on an overpressure versus
damage/personnel vulnerability relationship for the building.
Page 10 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
8. Load combinations
a. Buildings shall be capable of resisting normal load combinations before blast loading is
considered.
During the design of a structure, a number of load cases, e.g., the load cases
specified in BS 8110, are typically considered.
b. Blast loading shall be applied with dead and live loads as a particular load case.
In the absence of any national guidelines, the load case can be applied as 1,0 Dead
Load + 1,0 Live Load + 1,0 Blast Load using ultimate limit design, such as BS 8110
or BS 5950.
It should be noted that the blast load case does not necessarily govern the design of
all or any part of the structure, as other load combinations (e.g., seismic) may be
more severe.
Page 11 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Page 12 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Page 13 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Refer to Clause 6Blast risk Refer to Clause 7.3Incremental Costs Refer to Clause 7.4Value of risk
assessment resultsBlast (IC)Building structure reduction (Compared to base
pressure Location costs case)Occupants
Duration Special features (Doors, HVAC protection) Equipment
Frequency Loss of production
Building location
Plant life
(Years)
Relocate
Downgrade
SFrequency
(Events/year cumulativeDesign features
or modificationsIncremental costValue of risk
X
Plant life
Decreasing
X
frequency<1NoneBase case 0Base case 0OptimumNo blast load1 – 3Replace glass in windowsMinor modifications3 - 10Framed building design to national
code>10Design structure
Or
Strengthen to
resist blast
loadStrengthen existing building
or
Design new building to optimised blast load
or
Relocate
or
DowngradeRebuild
or
Relocate
or Page 14 of 26
Downgrade
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Figure 2 - Design procedure for buildings subject to blast loading
DL + LL +EQUIVALENT
EQUIVALENT STATIC LOAD STATIC METHODS
STATIC LOAD
NORMAL DESIGN TO
NORMAL LOAD NATIONAL CODES
LOADING ENVIRONMENTAL LOADS COMBINATIONS
(CLAUSE 5.2)
WIND
SNOW
SEISMIC
ETC.
END
Page 15 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Where:
Po = peak incident overpressure.
Pr = reflected overpressure.
Pa = atmospheric pressure.
2. 100 kN/m2 = 1 bar
Page 16 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Annex A
(Normative)
Design of blast resistant buildings
A1. General
a. This annex is based on the guidelines given in CIA publication, An Approach to the
Categorisation of Process Plant Hazard and Control Building Design, Appendix I.
b. This procedure should be limited to rectangular box shaped single story buildings.
It is recommended that a full blast risk assessment/CBA study be conducted to find
the design load. In the absence of this study, the loads given in A.5.2 may be used,
although they are likely to be conservative.
Note: If a blast risk assessment study exists for a similar plant, the loadings from
this study may be used, provided the influence of surrounding process units are
considered.
A2. Definition
a. Materials that form part of structure shall not display non ductile behaviour.
b. This shall include unreinforced concrete, masonry, and brickwork.
The use of prestressed concrete is not covered in this procedure.
A5. Loads
Page 17 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
a. Design load case shall be blast load + dead load + imposed load.
b. Walls shall be designed to resist reflected blast pressure.
c. Imposed load shall not be considered if it provides beneficial effect.
d. For reinforced concrete, partial safety factor for load (f) shall be 1,00.
Page 18 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
A7.2.1 Method
a. Design of structural element for blast effect shall be by method that takes into account its
dynamic responses, such as those provided in references listed in 2.
b. Structural elements shall be analysed for applicable dynamic loadings. Such loadings shall
be specified blast loads to which structural element may be directly exposed or dynamic
reactions from members that structural element supports.
c. Analysis may be most simply achieved by method given in A7.2.2. It should be noted that
formula in A7.2.2 is for discrete members only. Frames shall be checked for their dynamic
response with damping provided by plastic hinges.
2 - 1 2 - 1 t o
= +
to 2 t o + 0.77
=
to = duration of blast load
p = peak value of applied blast load
= fundamental period of vibration of structural element
Xm = maximum allowable dynamic displacement
Xy = effective yield displacement (based on equivalent elastic-plastic load deformation
relationship).
Note: If members, which are directly loaded by blast impulse (called primary members), are
supported by secondary structural elements, loads/impulses to be resisted by secondary
members should be determined from dynamic characteristics of primary members.
Page 19 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
4. Reinforced concrete panel subjected to simultaneous bending and shear wall or deep
beam action:
Xm £ 1,5 Xy
b. If steel or reinforced concrete beam forms part of rigid beam, check shall be made of
column stability if plastic deformation of beam is possible.
In the cases in a., Xy is the effective displacement at which plastic deformation
begins for the equivalent bilinear (elastic-plastic) resistance deflection (R-x) curve
that has the same energy absorbing capacity as the actual R-x curve for a structural
member. (See Figure A1).
For slender columns, this will be the displacement at which buckling begins.
a. Ability of structural element to resist dynamic load shall be determined in accordance with
plastic design method for structural steel and ultimate strength method for reinforced
concrete.
b. Recommended methodology using British Standards is proposed in c. Contractor may
nominate equivalent method to alternative standards. This should be reviewed by BP prior
to implementation.
c. Requirements are defined by BS 8110 and BS 5950 respectively, except as follows:
Page 20 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
1. For structural steel - for steelwork designed to BS 5950, partial safety factor for
strength m shall be taken as 1,0.
2. For reinforced concrete:
a) Reinforcing steel - strength for dynamic considerations should be taken as 120%
of values in BS 8110.
b) Partial safety factor for strength (m) shall be taken as 1,0.
3. Concrete - strength for dynamic considerations shall be taken as the following
percentages of values in BS 8110:
a) Compression: 120%.
b) Shear expressed as diagonal tension: 100%.
c) Bond: 100%.
4. In case of shear wall and deep beam design, direct shear stress at support shall not
exceed 10% of design compression strength for concrete. Partial safety factor for
strength (m) shall be taken as 1,30.
5. Calculations - Three sets of calculations shall be provided to show that conditions of
loading (A6) are met by final design.
A9.3 Joints
a. Construction joints shall be minimised and surfaces properly prepared.
b. In the case of shear walls, additional care shall be taken to form keys, or epoxy resin
bonding agents may be used in horizontal joints.
c. Contraction/expansion joints shall be avoided if possible.
Page 21 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
A11.1 General
a. The following points should be taken into account if designing/specifying non structural
building features. The objective is to ensure that these features perform in a safe manner
during a blast.
b. Building designer shall demonstrate that each of these features can either resist blast
without damage or fail in such a way that they do not increase risk to personnel or
equipment within or outside building.
A11.2 Location
Building location will be specified or shall be subject to BP approval in accordance with
GP 44-70.
A11.3 Orientation
If appropriate, orientation of building should be such that smallest area is presented to source of
hazard as defined.
A11.5.1 General
Openings, e.g., for ventilating systems, shall be designed to prevent entry of debris into
personnel or equipment areas by location, provision of attenuators, or other means.
Page 22 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Page 23 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
b. Distortion/movement of external walls/roof could cause equipment to break free from its
mountings and injure occupants/damage equipment.
Page 24 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Table A1 - Positive blast pressures and durations for various structural elements
Page 25 of 26
Draft 1 August 2005 GP 04-30
Guidance on Practice for Design of Buildings Subject to Blast Loading
Page 26 of 26