ACTION PLAN PEKERJAAN PROJECT

Periode Tgl. 01 Januari 000 S/d Tgl. 30 Januari 000 STATUS PERIO STATUS PERIODE : 31-Dec-99 S/d 29-Jan-00

SATKER : PENGELOLAAN JARINGAN SUMBER AIR SULAWESI I


KEGIATAN : PRASARANA KONSERVASI SDA Timbunan 1,296.00 11,664.00 46.66 97.63 Gal. Lumpur 6,435.96 TARGET RENCAN TARGET RENCANA : 100.00 %
PEKERJAAN : REVITALISASI DANAU TONDANO THP II Galian 661.05 5,949.45 23.80 Cerucuk 3,367.00
LOKASI : KABUPATEN MINAHASA Bronjong 94.52 850.68 - Timb. 32,766.36 TARGET MIN TARGET MIN : 3.33 % / Rata-Rata per Hari
PELAKSANA : PT. SELARAS MANDIRI SEJAHTERA Matras 309.11 2,781.99 11.13 HARI 2,122.50 MINGGU
JANGKA WAKTU RENCANA 30.00 4.00

ACTION PLAN TARGET ACTION PLAN PERIODE 01 Januari S/D 30 JANUARI 000
HARGA PROGRESS VOLUME PROGRESS VOLUME SISA PROGRESS
JUMLAH RENCANA MC. REALISASI RENCANA Nilai
Bobot VOLUME SATUAN PERIODE BULAN TAHUN
NO URAIAN PEKERJAAN SAT HARGA KAPASITAS Ket
% KONTRAK WAKTU / KEBUTUHAN
( Rp. ) (%) PRODUKSI
( RP. ) Bobot- Bobot- HARI ALAT / PEKERJA (disesuaikan)
Volume Bobot-% Volume Volume 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
(%) (%)
Minggu ke I Minggu Ke II Minggu Ke III Minggu Ke IV

I. PEKERJAAN CONTOH 25,000,000 100.00

1 Galian Tanah Alat M3 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 - 5,000.00 20.00 - 7 1.13 Excavator 79.04 M3/Jam 2.86 2.86 2.86 2.86 2.86 2.86 2.86

2 Galian Tanah Manual M3 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 - 5,000.00 20.00 - 25 11.90 Orang 2.10 M3/Hr/Org 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80

3 Timbunan Tanah Borrow M3 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 - 5,000.00 20.00 - 22 5.68 Dump Truck 5.00 M3/Jam 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91

4 Pasangan Batu 1 : 4 M3 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 - 5,000.00 20.00 - 27 9.65 Orang 2.40 M3/Hr/Org 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74 0.74

5 Plesteran 1 : 3 M2 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 - 5,000.00 20.00 - 19 5.63 Orang 5.84 M2/Hr/Org 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05

JUMLAH HARGA KONTRAK / MC 100 25,000,000 100.00 0.00 100.00 Pekerja 27.182 Orang / Hari ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

Excavator 1.000 Unit / Hari 0.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

- Bulldozer Unit / Hari

- ACTION (Rp) REALISASI (Rp.) SISA (Rp.) Vibro Roller

Nilai ( Rp. ) 25,000,000 - 25,000,000 Dump Truck 6.000 Unit / Hari

RENCANA PENYERAPAN ANGGARAN PERHARI ( RAB ) 833,333 : Terbilang

Ret 14

15 3.5 52.5

25 10 250

40 3.6 144 10 1440


ACTION PLAN PEKERJAAN PROJECT
Periode Tgl. 01 Januari 000 S/d Tgl. 15 Januari 000 STATUS PERIO STATUS PERIODE : 31-Dec-99 S/d 14-Jan-00

SATKER : PENGELOLAAN JARINGAN SUMBER AIR SULAWESI I


KEGIATAN : PRASARANA KONSERVASI SDA Timbunan 1,296.00 11,664.00 87.66 183.44 Gal. Lumpur 6,435.96 TARGET RENCAN
TARGET RENCANA : 53.22 %
PEKERJAAN : REVITALISASI DANAU TONDANO THP II Galian 661.05 5,949.45 44.71 Cerucuk 3,367.00
LOKASI : KABUPATEN MINAHASA Bronjong 94.52 850.68 - Timb. 32,766.36 TARGET MIN TARGET MIN : 3.55 % Rata-rata/Hari
PELAKSANA : PT. SELARAS MANDIRI SEJAHTERA Matras 309.11 2,781.99 20.91 HARI 2,122.50 MINGGU
JANGKA WAKTU RENCANA 15.00 2.00

ACTION PLAN TARGET ACTION PLAN PERIODE 01 BULAN S/D 07 BULAN TAHUN
PROGRESS VOLUME PROGRESS VOLUME SISA PROGRESS
BOBOT HARGA RENCANA [AP] REALISASI RENCANA Nilai
VOLUME JUMLAH HARGA Target / PERIODE BULAN TAHUN
NO URAIAN PEKERJAAN SAT KONTRAK SATUAN Ket
KONTRAK ( Rp. ) WAKTU / KEBUTUHAN KAPASITAS Hari
% ( RP. ) (%)
Bobot- Bobot- HARI ALAT / PEKERJA PRODUKSI
Volume Bobot-% Volume Volume 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
(%) (%)
Minggu ke I

I. PEKERJAAN CONTOH 25,000,000 100.0

1 Galian Tanah Alat M3 20 5,000.00 1,000.00 5,000,000.00 5,000.00 20.00 4,000 16.0 1,000.00 4.00 80 7 1.13 Excavator 79.0 M3/Jam 0.57 0.57 0.57 0.57 0.57 0.57 0.57

2 Galian Tanah Manual M3 20 5,000.00 1,000.00 5,000,000.00 2,800.00 11.20 2,500 10.0 300.00 1.20 50 14 11.90 Orang 2.1 M3/Hr/Org 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09

3 Timbunan Tanah Borrow M3 20 5,000.00 1,000.00 5,000,000.00 2,045.45 8.18 2,045 8.2 - - 41 9 4.06 Dump Truck 7.0 M3/Jam - - - - - - - - -

4 Pasangan Batu 1 : 4 M3 20 5,000.00 1,000.00 5,000,000.00 2,407.41 9.63 2,407 9.6 - - 48 13 9.65 Orang 2.4 M3/Hr/Org - - - - - - - - - - - - -

5 Plesteran 1 : 3 M2 20 5,000.00 1,000.00 5,000,000.00 1,052.63 4.21 1,053 4.2 - - 21 4 5.63 Orang 5.8 M2/Hr/Org - - - -

JUMLAH HARGA KONTRAK / MC 100 25,000,000 53.22 48.02 5.20 Pekerja 27.182 Orang / Hari

Excavator 1.000 Unit / Hari

- Bulldozer Unit / Hari

- ACTION (Rp) REALISASI (Rp.) SISA (Rp.) Vibro Roller

Nilai ( Rp. ) 13,305,494 12,005,494 1,300,000 Dump Truck 4.000 Unit / Hari

RENCANA PENYERAPAN ANGGARAN PERHARI ( RAB ) : 887,033 Terbilang

Ret 7

15 3.5 52.5

25 10 250

40 3.6 144 10 1440


ACTION PLAN PEKERJAAN PROJECT
Periode Tgl. 16 Januari 000 S/d Tgl. 30 Januari 000 STATUS PERIO STATUS PERIODE : 15-Jan-00 S/d 29-Jan-00

SATKER : PENGELOLAAN JARINGAN SUMBER AIR SULAWESI I


KEGIATAN : PRASARANA KONSERVASI SDA Timbunan 1,296.00 11,664.00 89.76 187.83 Gal. Lumpur 6,435.96 TARGET RENCAN
TARGET RENCANA : 51.98 %
PEKERJAAN : REVITALISASI DANAU TONDANO THP II Galian 661.05 5,949.45 45.78 Cerucuk 3,367.00
LOKASI : KABUPATEN MINAHASA Bronjong 94.52 850.68 - Timb. 32,766.36 TARGET MIN TARGET MIN : 3.47 %
PELAKSANA : PT. SELARAS MANDIRI SEJAHTERA Matras 309.11 2,781.99 21.41 HARI 2,122.50 MINGGU
JANGKA WAKTU RENCANA 15.00 2.00

ACTION PLAN TARGET ACTION PLAN PERIODE 16 Januari S/D 30 JANUARI 000
HARGA PROGRESS VOLUME PROGRESS VOLUME SISA PROGRESS
JUMLAH RENCANA [AP]. REALISASI RENCANA Nilai
Bobot VOLUME SATUAN Target / PERIODE BULAN TAHUN
NO URAIAN PEKERJAAN SAT HARGA ( KAPASITAS Ket
% KONTRAK WAKTU / KEBUTUHAN Hari
( Rp. ) %) PRODUKSI
( RP. ) Bobot- Bobot- HARI ALAT / PEKERJA (disesuaikan)
Volume Bobot-% Volume Volume 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
(%) (%)
Minggu Ke III Minggu Ke IV

I. PEKERJAAN CONTOH 25,000,000 100.00

1 Galian Tanah Alat M3 20 5,000.00 1,000.00 5,000,000.00 1,000.00 4.00 - 1,000.00 4.0 2 0.8 Excavator 79.04 M3/Jam - -

2 Galian Tanah Manual M3 20 5,000.00 1,000.00 5,000,000.00 2,500.00 10.00 - 2,500.00 25.0 - 11 13.5 Orang 2.10 M3/Hr/Org 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27 2.27

3 Timbunan Tanah Borrow M3 20 5,000.00 1,000.00 5,000,000.00 2,954.55 11.82 - 2,954.55 34.9 - 13 5.7 Dump Truck 5.00 M3/Jam 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69

4 Pasangan Batu 1 : 4 M3 20 5,000.00 1,000.00 5,000,000.00 2,592.59 10.37 - 2,592.59 26.9 - 14 9.6 Orang 2.40 M3/Hr/Org 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92 1.92

5 Plesteran 1 : 3 M2 20 5,000.00 1,000.00 5,000,000.00 3,947.37 15.79 - 3,947.37 62.3 - 15 5.6 Orang 5.84 M2/Hr/Org 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16 4.16

JUMLAH HARGA KONTRAK / MC 100 25,000,000 51.98 0.00 51.98 Pekerja 28.806 Orang / Hari ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

100.00 Excavator 1.000 Unit / Hari 0.00 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

- Bulldozer Unit / Hari

- ACTION (Rp) REALISASI (Rp.) SISA (Rp.) Vibro Roller

Nilai ( Rp. ) 12,994,506 - 12,994,506 Dump Truck 6.000 Unit / Hari

RENCANA PENYERAPAN ANGGARAN PERHARI ( RAB ) 866,300 : Terbilang

Ret 8

15 3.5 52.5

25 10 250

40 3.6 144 10 1440