Conto Penyusunan Rab Penawaran
Conto Penyusunan Rab Penawaran
JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp. )
Total 700,325,022.15
PPN 10 % 70,032,502.22
Jumlah 770,357,524.37
Dibulatkan 770,357,000.00
Terbilang : Tujuh Ratus Tujuh Puluh Juta Tiga Ratus Lima Puluh Tujuh Ribu Rupiah
HARGA SATUAN
JUMLAH SUB JUMLAH
NO URAIAN PEKERJAAN VOL SAT UPAH + BAHAN
( Rp ) ( Rp ) ( Rp. )
1 2 3 4 5 6 7
HARGA
NO. JENIS BAHAN SATUAN KET.
( RP )
1 Pekerja Hr / Org Rp 30,000
2 Mandor Hr / Org Rp 42,000
3 Tukang listrik Hr / Org Rp 40,000
4 Tukang kayu Hr / Org Rp 40,000
5 Kep. tk. kayu Hr / Org Rp 42,000
6 Tukang batu Hr / Org Rp 40,000
7 Kep. tk. batu Hr / Org Rp 42,000
11 K e p . t k . c a t Hr / Org Rp 42,000
12 T u k a n g p l i t u r Hr / Org Rp 40,000
13 T u k a n g j a l a n Hr / Org Rp 32,000
14 T u k a n g g a l i Hr / Org Rp 32,000
I BAHAN DASAR
1 BATU KALI Bulat Belah m3 50,000
Beton ,2/3 m 3
125,000
Pasang m 3 85,000
Beton / Muntilan m3 100,000
Balok/pesagen m 3
32,000,000
2 KAMPER Papan m 3
7,500,000
Balok/pesagen m 3
7,100,000
3 KRUING Papan m 3 4,500,000
Balok/pesagen m3 5,200,000
4 BENGKIRAI Papan m 3
8,700,000
Balok/pesagen m 3
8,000,000
40 x 40 cm m 2
50,000
2 Parquet Jati m2 160,000
V.BAHAN BESI
1 BESI BETON besi beton polos kg 10,000
2 BESI PLAT Besi Strip kg 13,700
- Kawat Kasa m 2
13,000
NO. J E N I S B A H A N SATUAN HARGA KETERANGAN
VI . B A H A N L A N G I T - L A N G I T
1 HARD BOARD-uk: 4'X 8' lbr 63,000
2 TRIPLEKS
. 120 X 240 X 6 mm lbr 72,500
VII . B A H A N F I N I S H I N G
1 KAYU
Menie kg 15,500
Dempul plamur kg 13,700
Ambril/amplas lbr 7,500
. Emco kg 42,000
. Plitur jadi ltr 70,000
2 TEMBOK
Plamur kg 5,000
Cat Tembok kg 11,500
Catylac 5 kg 125,000
Minyak cat ltr 5,500
VIII . B A H A N K A C A
1 ES KABUR 5 mm m2 85,000
2 RAY BAND 5 mm m2 72,000
IX . BAHAN SANITAIR
WASTAFEL bh 700,000
XI . PAVING BLOCK
STANDARD GRASS BLOCK ABU-ABU m2 72,000
1m 3 Urugan Pasir
1.2000 m3 Pasir Urug Rp. 50,000.00 Rp. 60,000.00
0.3000 Oh Pekerja Rp. 30,000.00 Rp. 9,000.00
0.0100 Oh Mandor Rp. 42,000.00 Rp. 420.00
Jumlah Rp. 69,420.00
1 m 1 Plesteran Sudut/Skoning
0.0125 Zak Semen Rp. 50,000.00 Rp. 625.00
0.0020 m3 Pasir Muntilan Rp. 100,000.00 Rp. 200.00
0.0570 Oh Pekerja Rp. 30,000.00 Rp. 1,710.00
0.0380 Oh Tukang Batu Rp. 40,000.00 Rp. 1,520.00
0.0380 Oh Kepala Tukang Batu Rp. 42,000.00 Rp. 1,596.00
0.0020 Oh Mandor Rp. 42,000.00 Rp. 84.00
Jumlah Rp. 5,735.00
1 m 2 Pas.Batu Candi
1.100 m2 Batu Candi Rp. 78,000.00 Rp. 85,800.00
0.130 Zak Semen Rp. 50,000.00 Rp. 6,500.00
0.031 m3 Pasir Mintilan Rp. 100,000.00 Rp. 3,100.00
0.188 Oh Pekerja Rp. 30,000.00 Rp. 5,625.00
0.225 Oh Tukang Batu Rp. 40,000.00 Rp. 9,000.00
0.038 Oh Kep. Tukang batu Rp. 42,000.00 Rp. 1,575.00
0.034 Oh Mandor Rp. 42,000.00 Rp. 1,419.60
Rp. 113,019.60
1 m 3 Lantai Kerja 1 Pc : 3 Kr ; 5 Ps t. 5 cm
0.2500 Zak Semen Rp. 50,000.00 Rp. 12,500.00
0.0260 m3 Pasir Beton Rp. 100,000.00 Rp. 2,600.00
0.0440 m 3
Split Pecah mesin 2/3 Rp. 125,000.00 Rp. 5,500.00
1.1500 Oh Pekerja Rp. 30,000.00 Rp. 34,500.00
0.0200 Oh Tukang Batu Rp. 40,000.00 Rp. 800.00
0.0020 Oh Kep. Tukang Batu Rp. 42,000.00 Rp. 84.00
0.0060 Oh Mandor Rp. 42,000.00 Rp. 252.00
Jumlah Rp. 56,236.00
1 m 2 Cat Kayu
0.1900 Kg Cat dasar Rp. 15,000.00 Rp. 2,850.00
0.2700 Kg Cat penutup Rp. 42,000.00 Rp. 11,340.00
0.1500 Kg Plamur kayu Rp. 5,000.00 Rp. 750.00
0.2000 Kg Meni kayu Rp. 15,500.00 Rp. 3,100.00
0.0090 Oh Tukang Cat Rp. 40,000.00 Rp. 360.00
0.0060 Oh Kepala Tukang Rp. 42,000.00 Rp. 252.00
0.0700 Oh Pekerja Rp. 30,000.00 Rp. 2,100.00
0.0025 Oh Mandor Rp. 42,000.00 Rp. 105.00
Rp. 20,857.00
1 m 2 Lantai keramik 30 x 30 Cm
11.3800 Kg Semen PC Rp. 1,250.00 Rp. 14,225.00
0.0450 m3
Pasir Muntilan Rp. 100,000.00 Rp. 4,500.00
1.0500 m2 Keramik 30/30 Rp. 40,000.00 Rp. 42,000.00
1.5000 Kg Semen warna Rp. 15,000.00 Rp. 22,500.00
0.6200 Oh Pekerja Rp. 30,000.00 Rp. 18,600.00
0.3500 Oh Tukang Batu Rp. 40,000.00 Rp. 14,000.00
0.0350 Oh Kepala Tukang Rp. 42,000.00 Rp. 1,470.00
0.0300 Oh Mandor Rp. 42,000.00 Rp. 1,260.00
Jumlah Rp. 118,555.00
1 m 2 Lantai keramik 40 x 40 Cm
11.3800 kg Semen Rp. 1,250.00 Rp. 14,225.00
0.0450 m3 Pasir Muntilan Rp. 100,000.00 Rp. 4,500.00
1.0500 m2 Keramik 40/40 Rp. 50,000.00 Rp. 52,500.00
1.5000 kg Semen warna Rp. 15,000.00 Rp. 22,500.00
0.5200 Oh Pekerja Rp. 30,000.00 Rp. 15,600.00
0.3500 Oh Tukang Batu Rp. 40,000.00 Rp. 14,000.00
0.0350 Oh Kepala Tukang Rp. 42,000.00 Rp. 1,470.00
0.0300 Oh Mandor Rp. 42,000.00 Rp. 1,260.00
Jumlah Rp. 126,055.00
1 m2 Daun pintu panel kayu
0.0400 m3 Kayu kamfer Rp. 7,100,000.00 Rp. 284,000.00
0.5000 Kg Lem Rp. 35,000.00 Rp. 17,500.00
1.0000 Oh Pekerja Rp. 30,000.00 Rp. 30,000.00
3.0000 Oh Tukang Kayu Rp. 40,000.00 Rp. 120,000.00
0.3000 Oh Kepala Tukang Rp. 42,000.00 Rp. 12,600.00
0.0500 Oh Mandor Rp. 42,000.00 Rp. 2,100.00
Jumlah 466,200.00
1 m 2 Bongkar Genteng
0.1500 Oh Pekerja Rp. 30,000.00 Rp. 4,500.00
0.0750 Oh Tukang Kayu Rp. 40,000.00 Rp. 3,000.00
0.0080 Oh Kepala Tukang Rp. 42,000.00 Rp. 336.00
0.0080 Oh Mandor Rp. 42,000.00 Rp. 336.00
Jumlah Rp. 8,172.00
1 m 2 Pasang Genteng Kembali
0.1500 Oh Pekerja Rp. 30,000.00 Rp. 4,500.00
0.0750 Oh Tukang Kayu Rp. 40,000.00 Rp. 3,000.00
0.0080 Oh Kepala Tukang Rp. 42,000.00 Rp. 336.00
0.0080 Oh Mandor Rp. 42,000.00 Rp. 336.00
Jumlah Rp. 8,172.00
1 m 2 Bongkar dan Pasang Genteng Kembali 16,344.00
1 m 2 Bongkar Reng
0.1000 Oh Pekerja Rp. 30,000.00 Rp. 3,000.00
0.1000 Oh Tukang Kayu Rp. 40,000.00 Rp. 4,000.00
0.0100 Oh Kepala Tukang Rp. 42,000.00 Rp. 420.00
0.0050 Oh Mandor Rp. 42,000.00 Rp. 210.00
Jumlah Rp. 7,630.00
1 m 2 Pasang Reng
0.1000 Oh Pekerja Rp. 30,000.00 Rp. 3,000.00
0.1000 Oh Tukang Kayu Rp. 40,000.00 Rp. 4,000.00
0.0100 Oh Kepala Tukang Rp. 42,000.00 Rp. 420.00
0.0050 Oh Mandor Rp. 42,000.00 Rp. 210.00
Jumlah Rp. 7,630.00
1 m 2 Bongkar dan Pasang Reng Kembali 15,260.00
BULAN I II III IV
NO URAIAN PEKERJAAN BOBOT SKALA KET
MINGGU 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5
E DINDING BENTENG 1.590501 0.159 0.159 0.159 0.159 0.159 0.159 0.159 0.159 0.159 0.159
F GEDUNG PERTEMUAN DEPAN 22.457 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604 1.604
G FASUM
1 PEK. PAVINGISASI 13.871 1.734 1.734 1.734 1.734 1.734 1.734 1.734 1.734
2 PEK. INSTALASI AIR BERSIH 1.142 0.571 0.571
3 PEKERJAAN PAGAR BELAKANG 2.661 0.333 0.333 0.333 0.333 0.333 0.333 0.333 0.333
4 PEKERJAAN SALURAN KELILING 1.676 0 0.186 0.186 0.186 0.186 0.186 0.186 0.186 0.186 0.186
RENCANA MINGGUAN 100.000 1.044 2.229 1.715 4.094 4.433 4.638 6.881 8.310 11.033 9.426 9.175 6.970 6.970 7.007 5.528 5.528 5.018
RENCANA MINGGUAN KOMULATIF 1.044 3.273 4.988 9.082 13.515 18.153 25.034 33.344 44.377 53.803 62.978 69.948 76.918 83.925 89.453 94.982 100.000
REALISASI MINGGUAN
REALISASI MINGGUAN KOMULATIF