ANALSYS OF RATES FOR 3 legged Gantries of18x2 meter spane

1.1 Earth Work in Excavation by mechanical means (hydraulic excavator) / manual means over areas (exceeding 30cm in
1.1 a All kind of soil
No. L B D or H Qty. Unit Rate Amount
For Gantry(3 Legged) 3 4.15 1.65 2.60 53.41 Cum
Total = 53.41 Cum 53.41 119.3 Rs. 6,371.87
2.1 Providing and laying in position cement concrete of specified grade excluding the cost of centering and

1:4:8 (1 cement , 4 coarse sand, graded stona


2.1.B aggregate 40mm nominal size) with Volumetric
No. L B D or H Qty. Unit
For Gantry(3 Legged) 3 4.15 1.65 0.10 2.05 Cum
Total = 2.05 Cum 2.05 2,545.28 Rs. 5,228.63

3.1 Centering and shuttering including strutting propping etc and removal of form for
foundations footings, bases of columns etc. for mass
3.1 a concrete
No. L B D or H Qty. Unit
For Gantry Raft (3 Legged) footing 6 4.150 …….. 0.100 2.49 Sqm
6 1.650 …….. 0.100 0.99 Sqm
For Gantry Col.(3 Legged) 6 3.850 …….. 0.500 11.55 Sqm
For Gantry Col.(3 Legged) 6 1.325 …….. 0.500 3.98 Sqm
6 2.100 …….. 2.100 26.46 Sqm
6 0.900 …….. 2.100 11.34 Sqm
56.81
Total = Sqm 56.81 150.00 Rs. 8,520.75

3.2 Steel reinforcement for R.C.C work including straighting, cutting, bending, placing , position and binding
3.2.A Thermo-Mechanically Treated bars
Dia Side No. L B D or H Qty. Unit
(3 Legged) Gantry
For Gantry Raft (Bottam) 12mm 2x1 8 4.20 67.20 mtr
12mm 2x1 20 1.70 68.00 mtr
Total = 135.20 mtr

(A) Wt. Per Mtr. @ 0.888 X 135.2 = (A) 120.0576 KG


(3 Legged) Gantry
For Gantry (Upper) 10MM 2x1 11 4.20 92.40
For Gantry (Upper) 10MM 2x1 27 1.70 91.80
Total 184.20 Mtr

(B) Wt. Per Mtr. @ 0.617 X 184.2 = (B) 113.6514 KG


(3 Legged) Gantry
For Gantry Col. 12 MM 2x1 36 3.50 252.00
Total 252.00 Mtr

(C) Wt. Per Mtr. @ 0.888 X 252 = (C) 223.776 KG


For chair for Raft
(3 Legged) Gantry 12mm 2x1 11 4.26 93.72
Total 93.72 Mtr

(D) Wt. Per Mtr. @ 0.888 X 93.72 = (D) 83.22336 KG


(3 Legged) Gantry
For Gentry (Main Rings) 8mm 2x1 13 10.70 278.20
Total 278.20 Mtr

(E) Wt. Per Mtr. @ 0.395 X 278.2 = (E) 109.889 KG


(3 Legged) Gantry
For Gentry (Both Internal) 10mm 2x3 (600 + 13 2.50 195.00
920)x2 (11x2)
For Gentry (Both Internal) 10mm 2x1 (300 + 13 4.70 122.20
920) x 2 (11x2)
Total 317.20 Mtr

(F) Wt. Per Mtr. @ 0.617 X 317.2 = (F) 195.7124 KG


Total (A+B+C+D+E+F) = 846.31 /2 423.155
423.155 3 1269.465 Kg 12.69 Qtl. 5154.00 Rs. 65,404.26

Providing and laying in position ready mixed M-25


3.3 grade concrete for reinforced cement concrete work,
(3 Legged) Gantry No L B D or H qty. unit
for Gantry RCC M-25 3 4.00 1.50 0.50 9.00 Cum
Col 3 2.10 0.90 2.10 11.91 Cum
Total 20.91 Cum 20.91 4191.95 Rs. 87,641.07

Filling available excavated earth exluding rock in


trenches, plinth , sites of foundatiom etc. in layers not
exceeding 20cm in depth , consolidating each
deposted layer by ramming & watering , lead up to
4.1 50mtr & lift upto 1.5mtr
For Gantry(3 Legged) 3 4.15 1.65 2.6 53.41 cum

deduct Qty of Item No. 2.1-b & 3.3 -22.96


1.37+13.94 Net Qty 30.45 cum 30.45 90.00 Rs. 2,740.50

4.2 Providing & fabricating structrual steel work welded & bolted in built up tublar section with ms base 30.45
4.2A Hot Finished welded type tubes
For Gantry(3 Legged)
For Gantry
Vertical Post 350mm Pipe 3 6.95 ……… ………. 20.85 Mtr
horizontal Member 2 18 ………… ……….. 36 Mtr
add 5% wastage 2.84 Mtr
Total = 59.69 Mtr
Wt. per Mtr. 85.22 kg x 59.69 = 5086.7818 KG (A)
For vertical post 250 mm Pipe 3x2 6 6.00 ……….. …….. 36.00
3x2 6 0.125 ……….. …….. 2.25
38.25
38.25 Mtrs@61.75 Kg/mtr = 2361.9375 KG (B)
For Gantry(3 Legged)
sleve for gentry 300mm pipe 5x3 15 1 ……….. ……. 15 mtr
15 mtr@76.92 kg per mtr = 1153.8 KG (C)

For Gantry(3 Legged)

Base plate 32mm thick for gantry (1900 x 700 mm) for
b gantry (3 legged) 1x3 3 1.90 0.70 3.99 sqm
3.99 mtr@251.22 kg per mtr = 1002.37 KG (D)

for gantry (3 legged)


c template plate 8mm thick for gantry (1900*700 mm) sqm
for gantry (3 legged) 1x3x2 6 1.9 0.1 1.14
1x3x2 6 0.5 0.1 0.3 sqm
total 1.44 sqm
1.44 mtr@62.80 kg per SQM = 90.43 kg (E)
for gantry (3 legged)
d stiffner 8mm thick for gantry (300*100) 36x1x3 108 0.3 0.075 ….. 2.43 sqm
2.43 mtr@62.80 kg per SQM = 152.60 kg (F)
for gantry (3 legged)
e Anchor bolt 36 mm dia of 1000 mm long 20x1x3 60 1 60.00 mtr
60 mtr@7.99 kg per Mtr = 479.4 kg (G)

Total (a+b+c+d+e +f+g) = 10327.32 kg 103.27 QTL. 7634 Rs. 788,387.86


5.1 finishing with epoxy paint (two or more coats)at all locations prepared and applied as per manufecturer's
5.1 a on steel work
for gantry (3 legged + gantry) no. L B D OR H QTY. UNIT
For gantry(350 dia pipe) 1 56.85 1.10 62.535 sqm
for gantry (250 dia pipe) 1 38.25 0.79 30.2175 sqm
for base plate of 1.90m*0.70 m 3 1.9 0.7 3.99 sqm
for stiffner 108 0.3 0.075 4.86 sqm
total 101.6 101.6 350 Rs. 35,560.00
6.1 Disposal of building rubbish/malba/similar unserviceable,dismantled or waste materials by mechanical
NO. L B D or H QTY. UNIT

Disposal of malba for gantry,cantilever & DSM same


as qty on item no 2.1. B and 3.3 22.96 cum 100 Rs. 2,296.13

7.1 providing installing and fixing with nesessary clamps etc. retro-reflective single sided overhead gantry signboard/cantilever signboards
comprising of customised modular pu epoxy coated MS hollow section frame work,aluminium composite panel (ACP)mill finished or
PVDF coated or as specified as base board micro prismatic retro reflective sheet and electro cut coloured overlay film the horizontal and
vertical members of the MS frame module shall be made of MS hollow section of size 50*50*4.5 mm as per approved drawing and each
panel shall be braced diagonally(one way only) with same section. The aluminium composite panel (ACP) shall have a thickness of 4mm with
0.5mm thick provided throughout the length and breadth of the frame including riveting at the right angle face of frame with pop riveting or
with self taping ss screws 5 mm dia spaced not more than 300mm center to center ensuring that no riveting is seen on either face of the frame.
On the front face of ACP,micro prismatic retro reflective sheet conforming to type-IX of ASTM : D 4956-09 shallbe pressure fixed in the similar
manner as described above.The edges of the board shall be covered allround with powder coated dia size extruded aluminium channel of
required color and shade of 68*12*2 mm. The channel shall be fixed using two rows of double sided VHB tape of above description.The channel
shall further be secured by pop rivets having ss screws of 5mm dia at junctions and corners.The rate shall included all materials labour,equipments,
fabrication transportation,erection,installation and incidents all complete as per direction of engineer in charge.only front area of board shall be
measured for payment.(All structural steel work shall be paid for seprately under the relevant agreement item,except MS hollow section frame work
and fixing arrangement with clamps for the sign boards.)

for gantry 2 18.00 2.10 75.6 sqm


75.60 28112.00 Rs. 2,125,267.20
Total Amounts = Rs. 3,127,418.00

Certified that
The rates of material are prevailing lowest market rate and labour is as per actual observed at site.
The work will be executed as per the relevant specifications.
The item is required as per site Requirement

JE / AE (C-III) SDE (C-III) DE (C-III )


GMADA Mohali GMADA Mohali GMADA Mohali
ANALSYS OF RATES FOR 3 legged Gantries of 26 x 2 meter spane
1.1 Earth Work in Excavation by mechanical means (hydraulic excavator) / manual means over areas (exceeding 30cm in
1.1 a All kind of soil
No. L B D or H Qty. Unit Rate Amount
For Gantry(3 Legged) 3 4.15 1.65 2.60 53.41 Cum 66.28+80%
Total = 53.41 Cum 53.41 Rs. 119.30 Rs. 6,372.09
1.3 Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material
1.3 a All kind of soil
No. L B D or H Qty. Unit
For Gantry(3 Legged) 3 4.15 1.65 1.10 22.60 Cum
Total = 22.60 Cum 22.60 Rs. 150.00 Rs. 3,389.51

2.1 Providing and laying in position cement concrete of specified grade excluding the cost of centering and

1:4:8 (1 cement , 4 coarse sand, graded stona


2.1.B aggregate 40mm nominal size) with Volumetric
No. L B D or H Qty. Unit
For Gantry(3 Legged) 3 4.15 1.65 0.10 2.05 Cum
Total = 2.05 Cum 2.05 Rs. 2,545.28 Rs. 5,228.63

3.1 Centering and shuttering including strutting propping etc and removal of form for
foundations footings, bases of columns etc. for mass
3.1 a concrete
No. L B D or H Qty. Unit
For Gantry Raft (3 Legged) footing 6 4.150 …….. 0.100 2.49 Sqm
6 1.650 …….. 0.100 0.99 Sqm
For Gantry Col.(3 Legged) 6 3.850 …….. 0.500 11.55 Sqm
For Gantry Col.(3 Legged) 6 1.325 …….. 0.500 3.98 Sqm
6 2.100 …….. 2.100 26.46 Sqm
6 0.900 …….. 2.100 11.34 Sqm
56.81 (117 + 35% )
Total = Sqm 56.81 Rs. 157.95 Rs. 8,972.35

3.2 Steel reinforcement for R.C.C work including straighting, cutting, bending, placing , position and binding
3.2.A Thermo-Mechanically Treated bars
Dia Side No. L B D or H Qty. Unit
(3 Legged) Gantry
For Gantry Raft (Bottam) 12mm 2x1 8 4.20 67.20 mtr
12mm 2x1 20 1.70 68.00 mtr
Total = 135.20 mtr

(A) Wt. Per Mtr. @ 0.888 X 135.2 = (A) 120.0576 KG


(3 Legged) Gantry
For Gantry (Upper) 10MM 2x1 11 4.20 92.40
For Gantry (Upper) 10MM 2x1 27 1.70 91.80
Total 184.20 Mtr

(B) Wt. Per Mtr. @ 0.617 X 184.2 = (B) 113.6514 KG


(3 Legged) Gantry
For Gantry Col. 12 MM 2x1 36 3.50 252.00
Total 252.00 Mtr

(C) Wt. Per Mtr. @ 0.888 X 252 = (C) 223.776 KG


For chair for Raft
(3 Legged) Gantry 12mm 2x1 11 4.26 93.72
Total 93.72 Mtr

(D) Wt. Per Mtr. @ 0.888 X 93.72 = (D) 83.22336 KG


(3 Legged) Gantry
For Gentry (Main Rings) 8mm 2x1 13 10.70 278.20
Total 278.20 Mtr
(E) Wt. Per Mtr. @ 0.395 X 278.2 = (E) 109.889 KG
(3 Legged) Gantry
For Gentry (Both Internal) 10mm 2x3 (600 +
920)x2 (11x2) 13 2.50 195.00

For Gentry (Both Internal) 10mm 2x1 (300 +


920) x 2 (11x2) 13 4.70 122.20

Total 317.20 Mtr

(F) Wt. Per Mtr. @ 0.617 X 317.2 = (F) 195.7124 KG

Total (A+B+C+D+E+F) = 846.31 /2 423.155


423.155 3 1269.465 Kg 12.69 Qtl. Rs. 5,154.00 Rs. 65,404.26

Providing and laying in position ready mixed M-25


3.3 grade concrete for reinforced cement concrete work,
(3 Legged) Gantry No L B D or H qty. unit
for Gantry RCC M-25 3 4.00 1.50 0.50 9.00 Cum
Col 3 2.10 0.90 2.10 11.91 Cum 3274.96 + 28%
Total 20.91 Cum 20.91 Rs. 4,191.95 Rs. 87,641.07

Filling available excavated earth exluding rock in


trenches, plinth , sites of foundatiom etc. in layers not
exceeding 20cm in depth , consolidating each
deposted layer by ramming & watering , lead up to
4.1 50mtr & lift upto 1.5mtr
For Gantry(3 Legged) 3 4.15 1.65 2.6 53.41 cum

deduct Qty of Item No. 2.1-b & 3.3 -22.96 (42.35+80%)


1.37+13.94 Net Qty 30.45 cum 30.45 Rs. 76.23 Rs. 2,321.20
4.2 Providing & fabricating structrual steel work welded & bolted in built up tublar section with ms base 30.45
4.2A Hot Finished welded type tubes
For Gantry(3 Legged)
For Gantry
Vertical Post 350mm Pipe 3 6.95 ……… ………. 20.85 Mtr
horizontal Member 2 26 ………… ……….. 52 Mtr
Diagnal Braces 4 2.2 8.8 Mtr
add 5% wastage 4.08 Mtr
Total = 85.73 Mtr
Wt. per Mtr. 85.22 kg x 85.73 = 7305.9106 KG (A)
For vertical post 250 mm Pipe 3x2 6 6.00 ……….. …….. 36.00
3x2 6 0.125 ……….. …….. 2.25
Hzl Braces 3x2x4 24 0.315 7.56
add 5% wastage 2.29 Mtr
48.10
48.1 Mtrs@61.75 Kg/mtr = 2970.175 KG (B)
For Gantry(3 Legged)
sleve for gentry 300mm pipe 5x3 15 1 ……….. ……. 15 mtr
15 mtr@76.92 kg per mtr = 1153.8 KG (C)

For Gantry(3 Legged)

Base plate 32mm thick for gantry (1900 x 700 mm) for
b gantry (3 legged) 1x3 3 1.90 0.70 3.99 sqm
add 5% wastage 0.2 Mtr
4.19
4.19 mtr@251.22 kg per mtr = 1052.61 KG (D)

for gantry (3 legged)


c template plate 8mm thick for gantry (1900*700 mm) sqm
for gantry (3 legged) 1x3x2 6 1.9 0.1 1.14
1x3x2 6 0.5 0.1 0.3 sqm
add 5% wastage 0.07 Mtr
total 1.51 sqm
1.51 mtr@62.80 kg per SQM = 94.83 kg (E)
for gantry (3 legged)
d stiffner 8mm thick for gantry (300*100) 36x1x3 108 0.3 0.075 ….. 2.43 sqm
add 5% wastage 0.12 Mtr
total 2.55 sqm
2.55 mtr@62.80 kg per SQM = 160.14 kg (F)
for gantry (3 legged)
e Anchor bolt 36 mm dia of 1000 mm long 20x1x3 60 1 60.00 mtr
60 mtr@7.99 kg per Mtr = 479.4 kg (G)

Total (a+b+c+d+e +f+g) = 13216.87 kg 132.17 Qtl. Rs. 7,634.00 Rs. 1,008,975.52
5.1 finishing with epoxy paint (two or more coats)at all locations prepared and applied as per manufecturer's
5.1 a on steel work
for gantry (3 legged + gantry) no. L B D OR H QTY. UNIT
For gantry(350 dia pipe) 1 81.65 1.10 89.815 sqm
for gantry (250 dia pipe) 1 38.25 0.79 30.2175 sqm
for base plate of 1.90m*0.70 m 3 1.9 0.7 3.99 sqm
for stiffner 108 0.3 0.075 4.86 sqm
total 128.88 128.88 Rs. 350.00 Rs. 45,108.00
6.1 Disposal of building rubbish/malba/similar unserviceable,dismantled or waste materials by mechanical
NO. L B D or H QTY. UNIT

Disposal of malba for gantry,cantilever & DSM same


as qty on item no 2.1. B and 3.3 22.96 cum Rs. 100.00 Rs. 2,296.13

7.1
Providing installing and fixing with nesessary clamps etc. retro-reflective single sided overhead gantry signboard/cantilever signboardscomprising of
customised modular pu epoxy coated MS hollow section frame work,aluminium composite panel (ACP)mill finished orPVDF coated or as specified as base
board micro prismatic retro reflective sheet and electro cut coloured overlay film the horizontal and vertical members of the MS frame module shall be
made of MS hollow section of size 50*50*4.5 mm as per approved drawing and each panel shall be braced diagonally(one way only) with same section.
The aluminium composite panel (ACP) shall have a thickness of 4mm with0.5mm thick provided throughout the length and breadth of the frame including
riveting at the right angle face of frame with pop riveting or with self taping ss screws 5 mm dia spaced not more than 300mm center to center ensuring
that no riveting is seen on either face of the frame.On the front face of ACP,micro prismatic retro reflective sheet conforming to type-IX of ASTM : D 4956-
09 shallbe pressure fixed in the similarmanner as described above.The edges of the board shall be covered allround with powder coated dia size extruded
aluminium channel of required color and shade of 68*12*2 mm. The channel shall be fixed using two rows of double sided VHB tape of above
description.The channelshall further be secured by pop rivets having ss screws of 5mm dia at junctions and corners.The rate shall included all materials
labour,equipments,fabrication transportation,erection,installation and incidents all complete as per direction of engineer in charge.only front area of
board shall bemeasured for payment.(All structural steel work shall be paid for seprately under the relevant agreement item,except MS hollow section
frame workand fixing arrangement with clamps for the sign boards.)

for gantry 2 23.18 2.10 97.356 sqm


97.36 Rs. 28,112.00 Rs. 2,736,871.87
Total Amounts = Rs. 3,972,581.00

Certified that
The rates of material are prevailing lowest market rate and labour is as per actual observed at site.
The work will be executed as per the relevant specifications.
The item is required as per site Requirement

JE / AE (C-III) SDE (C-III) DE (C-III )


GMADA Mohali GMADA Mohali GMADA Mohali
ANALSYS OF RATES FOR 18 m span overhead gantry
1.1 Earth Work in Excavation by mechanical means (hydraulic excavator) / manual means over areas (exceeding 30cm in
1.1 a All kind of soil
No. L B D or H Qty. Unit Rate Amount
For Gantry(2 Legged) 2 4.15 1.65 2.60 35.61 Cum
Total = 35.61 Cum 35.61 100 Rs. 3,560.70
1.3 Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material
1.3 a All kind of soil
No. L B D or H Qty. Unit
For Gantry(2 Legged) 2 4.15 1.65 1.10 15.06 Cum
Total = 15.06 Cum 15.06 150.00 Rs. 2,259.68

2.1 Providing and laying in position cement concrete of specified grade excluding the cost of centering and

1:4:8 (1 cement , 4 coarse sand, graded stona aggregate


2.1.B 40mm nominal size)
No. L B D or H Qty. Unit
For Gantry(2 Legged) 2 4.15 1.65 0.10 1.37 Cum
Total = 1.37 Cum 1.37 2,545.28 Rs. 3,485.76

3.1 Centering and shuttering including strutting propping etc and removal of form for
foundations footings, bases of columns etc. for mass
3.1 a concrete
No. L B D or H Qty. Unit
For Gantry Raft (2 Legged) footing 4 4.000 …….. 0.500 8.00 Sqm
1*2*2 = 4 4 1.500 …….. 0.500 3.00 Sqm
For Gantry Col.(2 Legged) 4 2.100 …….. 2.100 17.64 Sqm
For Gantry Col.(2 Legged) 4 0.900 …….. 2.100 7.56 Sqm
36.20
Total = Sqm 36.20 80.00 Rs. 2,896.00

3.2 Steel reinforcement for R.C.C work including straighting, cutting, bending, placing , position and binding
3.2.A Thermo-Mechanically Treated bars
Dia Side No. L B D or H Qty. Unit
(2 Legged) Gantry
For Gantry Raft (Bottam) 12mm 2x1 8 4.20 67.20 mtr
12mm 2x1 20 1.70 68.00 mtr
Total = 135.20 mtr

(A) Wt. Per Mtr. @ 0.888 X 135.2 = (A) 120.06 KG


(2 Legged) Gantry
For Gantry (Upper) 10MM 2x1 11 4.20 92.40
For Gantry (Upper) 10MM 2x1 27 1.70 91.80
Total 184.20 Mtr

(B) Wt. Per Mtr. @ 0.617 X 184.2 = (B) 113.6514 KG


(2 Legged) Gantry
For Gantry Col. 12 MM 2x1 36 3.50 252.00
Total 252.00 Mtr

(C) Wt. Per Mtr. @ 0.888 X 252 = (C) 223.776 KG


For chair for Raft
(2 Legged) Gantry 12mm 2x1 11 4.26 93.72
Total 93.72 Mtr

(D) Wt. Per Mtr. @ 0.888 X 93.72 = (D) 83.22336 KG


(2 Legged) Gantry
For Gentry (Main Rings) 8mm 2x1 13 10.70 278.20
Total 278.20 Mtr

(E) Wt. Per Mtr. @ 0.395 X 278.2 = (E) 109.889 KG


(2 Legged) Gantry
For Gentry (Both Internal) 10mm 2x3 (600 + 920)x2 13 2.50 195.00
(11x2)
For Gentry (Both Internal) 10mm 2x1 (300 + 920) x 13 4.70 122.20
2 (11x2)
Total 317.20 Mtr
(F) Wt. Per Mtr. @ 0.617 X 317.2 = (F) 195.7124 KG

Total (A+B+C+D+E+F) = 846.31 /1 846.31


Add 5 % Wastage = 42.3155
Total QTY, = 888.63
888.63 1 888.63 Kg 8.89 Qtl. 5154.00 Rs. 45,819.06

Providing and laying in position ready mixed M-25 grade


3.3 concrete for reinforced cement concrete work,
(2 Legged) Gantry No L B D or H qty. unit
for Gantry RCC M-25 2 4.00 1.50 0.50 6.00 Cum
Col 2 2.10 0.90 2.10 7.94 Cum
Total 13.94 Cum 13.94 4191.95 Rs. 58,427.38

Filling available excavated earth exluding rock in trenches,


plinth , sites of foundatiom etc. in layers not exceeding
20cm in depth , consolidating each deposted layer by
4.1 ramming & watering , lead up to 50mtr & lift upto 1.5mtr
For Gantry(2 Legged) 2 4.15 1.65 2.6 35.61 cum

deduct Qty of Item No. 2.1-b & 3.3 -15.31


1.37+13.94 Net Qty 20.30 cum 20.30 90.00 Rs. 1,827.00

4.2 Providing & fabricating structrual steel work welded & bolted in built up tublar section with ms base 20.3
4.2A Hot Finished welded type tubes
For Gantry( 2 Legged)
For Gantry
Vertical Post 350mm Pipe 2 6.95 ……… ………. 13.9 Mtr
horizontal Member 1 18 ………… ……….. 18 Mtr
Total = 31.9 Mtr
Wt. per Mtr. 85.22 kg x 31.9 = 2718.518 KG (A)
For Gantry (Near Yamuna Vihar )
Vertical Post 250 mm Pipe 2x2 4 6.00 ……….. …….. 24.00
Spot for Jointing 2x6 12 0.125 ……….. …….. 1.5
25.50
25.5 Mtrs@61.75 Kg/mtr = 1574.625 KG (B)
For Gantry(2 Legged)
sleve for gentry 300mm pipe 5x2 10 1 ……….. ……. 10 mtr
10 mtr@76.92 kg per mtr = 769.2 KG (C)

For Gantry(2 Legged)


Base plate 32mm thick for gantry (1900 x 700 mm) for
b gantry (2 legged) 1x2 2 1.90 0.70 2.66 sqm
2.66 mtr@251.22 kg per mtr = 668.25 KG (D)

for gantry (2 legged)


c template plate 8mm thick for gantry (1900*700 mm) sqm
for gantry (2 legged) 1x2x2 4 1.9 0.1 0.76
1x2x2 4 0.5 0.1 0.2 sqm
total 0.96 sqm
0.96 mtr@62.80 kg per SQM = 60.29 kg (E)
for gantry (2 legged)
d stiffner 8mm thick for gantry (300*100) 36x1x2 72 0.3 0.075 ….. 1.62 sqm
1.62 mtr@62.80 kg per SQM = 101.74 kg (F)
for gantry (2 legged)
e Anchor bolt 36 mm dia of 1000 mm long 20x1x2 40 1 40.00 mtr
40 mtr@7.99 kg per Mtr = 319.6 kg (G)
Add 5% Wastage = 310.61
Total (a+b+c+d+e +f+g) = 6522.83 kg 6522.83 90 Rs. 587,054.70
5.1 finishing with epoxy paint (two or more coats)at all locations prepared and applied as per manufecturer's
5.1 a on steel work
for gantry (2 legged + gantry) no. L B D OR H QTY. UNIT
For gantry(350 dia pipe) 1 31.9 1.10 35.09 sqm
for gantry (250 dia pipe) 1 25.5 0.79 20.145 sqm
for base plate of 1.90m*0.70 m 2 1.9 0.7 2.66 sqm
for stiffner 36 X 1 X 2 = 72 0.3 0.075 3.24 sqm
total 61.14 61.14 350 Rs. 21,399.00
6.1 Disposal of building rubbish/malba/similar unserviceable,dismantled or waste materials by mechanical
NO. L B D or H QTY. UNIT

Disposal of malba for gantry,cantilever & DSM same


as qty on item no 2.1. B and 3.3 15.31 cum 100 Rs. 1,530.75

7.1
Providing installing and fixing with nesessary clamps etc. retro-reflective single sided overhead gantry signboard/cantilever signboardscomprising of
customised modular pu epoxy coated MS hollow section frame work,aluminium composite panel (ACP)mill finished orPVDF coated or as specified as base
board micro prismatic retro reflective sheet and electro cut coloured overlay film the horizontal and vertical members of the MS frame module shall be made
of MS hollow section of size 50*50*4.5 mm as per approved drawing and each panel shall be braced diagonally(one way only) with same section. The
aluminium composite panel (ACP) shall have a thickness of 4mm with0.5mm thick provided throughout the length and breadth of the frame including riveting
at the right angle face of frame with pop riveting or with self taping ss screws 5 mm dia spaced not more than 300mm center to center ensuring that no
riveting is seen on either face of the frame.On the front face of ACP,micro prismatic retro reflective sheet conforming to type-IX of ASTM : D 4956-09 shallbe
pressure fixed in the similarmanner as described above.The edges of the board shall be covered allround with powder coated dia size extruded aluminium
channel of required color and shade of 68*12*2 mm. The channel shall be fixed using two rows of double sided VHB tape of above description.The
channelshall further be secured by pop rivets having ss screws of 5mm dia at junctions and corners.The rate shall included all materials
labour,equipments,fabrication transportation,erection,installation and incidents all complete as per direction of engineer in charge.only front area of board
shall bemeasured for payment.(All structural steel work shall be paid for seprately under the relevant agreement item,except MS hollow section frame
workand fixing arrangement with clamps for the sign boards.)

for gantry 1 18.00 2.10 37.8 sqm


37.80 28112.00 Rs. 1,062,633.60
Total Amounts = Rs. 1,790,894.00

Certified that
The rates of material are prevailing lowest market rate and labour is as per actual observed at site.
The work will be executed as per the relevant specifications.
The item is required as per site Requirement

JE / AE (C-III) SDE (C-III) DE (C-III )


GMADA Mohali GMADA Mohali GMADA Mohali
Analysis of rate of providing & fixing of informatory board Of size 1800x1200 mm
Sr No Discription Weight/Mtr Rate Amount

1/Ns Providing and fixing of 3" dia SS Pipe


2830+800 1 3050 3.65 3.650 Rmt
2250+800 1 3050 3.65 3.650 Rmt
7.300 4.79
7.3Rmt @ 4.79 kg per Rmtr = 34.967 kg
1.5 dia SS pipe
Rmt
1220+1830+1220+1830 = 6100 6.100 1.228

6.1Rmt @ 1.228 kg per Rmtr = 7.4908 kg


Internal frame 25x12.5 mm SS squar pipe
(5.74+(4x1220))/1000 = 4.89

2x2.16 2x1.8 2x1.2 = 10.32 Rmt


15.21 15.21 0.89
15.21Rmt @ 0.89 kg per Rmtr = 13.5369 kg
Total QTY .= 55.9947 kg
Add 10% wastage = 5.59947 kg
Net Total Qty. = 61.5942 kg
Cost of Stainless steel including welding, grinding, buffing, polishing and making curvature but
excluding the cost of stainless steel nuts and bolts complete, accessories, dash fastners, ss 61.594 kg 450.00 27717.38
bolts etc.

2/NS Supply of Retro refiective sheeting of high intensity microprismatic grade type X1
1.00 1.80 1.2 2.16 Sqm 2.16 7500.00 16200.00
Supply of overlay electrocut film /every denssion and 3 M INDIA used on high density
rectoreflective front with border words and design layout on board grade type X1

3/NS 2.16 Sqm 2.16 4000.00 8640.00

4/6.6 Earth work in excavation in all kind of soil in foundation 66.28+80%


2 2 2 2.5 20 cft or 0.566 cum 119.30 67.53

5/10.12 C. Cone 1:2:4 in stone ballast 2723.85+26%


2 2 2 2.5 20 cft or 0.566 cum 3432.051 1942.54
6/10.13 Extra for small quantity 36+70%
0.566 cum 61.20 34.64
7/MR Carrige of material from workshop to site LS 100.00
Add contactor profit 10% 54702 x 10% 5470.21

Total Rate for coutionarry /mandatory Board = 60172.29


Certified that
The rates of material are prevailing lowest market rate and labour is as per actual observed at site.
The work will be executed as per the relevant specifications.
The item is required as per site Requirement

JE/ AE (C-III) SDE (C-III) DE (C-III)


GMADA Mohali GMADA Mohali GMADA Mohali
Analysis of rate of providing & fixing of Cautionary board Of size 1800x900 mm
Sr No Discription Weight/Mtr Rate Amount

1/Ns Providing and fixing of 3" dia SS Pipe


1 3.75 3.75 3.750 Rmt
3.750 4.79
3.75Rmt @ 4.79 kg per Rmtr = 17.9625 kg
1.5 dia SS pipe
Rmt
1.2+0.9 2 2.10 4.200 1.228

4.2Rmt @ 1.228 kg per Rmtr = 5.1576 kg


Internal frame 25x25 mm SS squar pipe
1 4.2 = 4.20 Rmt
2 1.5 3.00
7.20 7.20 0.87
7.2Rmt @ 0.87 kg per Rmtr = 6.264 kg
Total QTY .= 29.3841 kg
Add 10% wastage = 2.93841 kg
Net Total Qty. = 32.3225 kg
Cost of Stainless steel including welding, grinding, buffing, polishing and making
curvature but excluding the cost of stainless steel nuts and bolts complete, accessories, 32.323 kg 450.00 14545.13
dash fastners, ss bolts etc.

2/NS Supply of Retro refiective sheeting of high intensity microprismatic grade type X1

1.00 1.20 0.9 1.08 Sqm 1.08 7500.00 8100.00


Supply of overlay electrocut film /every denssion and 3 M INDIA used on high density
rectoreflective front with border words and design layout on board grade type X1

3/NS 1.08 Sqm 1.08 4000.00 4320.00

4/6.6 Earth work in excavation in all kind of soil in foundation 66.28+80%


1 2 2 2.5 10 cft or 0.283 cum 119.30 33.76

5/10.12 C. Cone 1:2:4 in stone ballast 2723.85+26%


1 2 2 2.5 10 cft or 0.283 cum 3432.051 971.27
6/10.13 Extra for small quantity 36+70%
0.283 cum 61.20 17.32
7/MR Carrige of material from workshop to site LS 100.00
Add contactor profit 10% 28087 x 10% 2808.75

Total Rate for coutionarry /mandatory Board = 30896.23


Certified that
The rates of material are prevailing lowest market rate and labour is as per actual observed at site.
The work will be executed as per the relevant specifications.
The item is required as per site Requirement

JE/ AE (C-III) SDE (C-III) DE (C-III)


GMADA Mohali GMADA Mohali GMADA Mohali